OPERADOR Semana dia/Sem Sal/dia Sal/Jor. Sal/Jor. F.S.R. Sal.real Eq. Seg Comida Salario
56 Hrs. 10 hrs. 8 hrs. Redond
Retroexcavadora $3,200 ÷ 7 = $457.14 = 391.8367 390 1.6550 = $645 + $0.00 = 0.00 $645.45
Excavadora Cat 320 $4,000 ÷ 7 = $571.43 = 489.7959 490.00 1.6469 = $807 + $0.00 = 0.00 $806.98
Tractor D-8 $4,000 ÷ 7 = $571.43 = 489.7959 490.00 1.6469 = $807 + $0.00 = 0.00 $806.98
Tractor D-7 $4,000 ÷ 7 = $571.43 = 489.7959 490.00 1.6469 = $807 + $0.00 = 0.00 $806.98
Cargador Frontal (Payloader ) $3,800 ÷ 7 = $542.86 = 465.3061 470 1.6475 = $774 + $0.00 = 0.00 $774.33
Motoconformadora $4,000 ÷ 7 = $571.43 = 489.7959 490 1.6469 = $807 + $0.00 = 0.00 $806.98
Pipa de Agua de 10000 lts $2,600 ÷ 7 = $371.43 = 318.3673 320 1.6638 = $532 + $0.00 = 0.00 $532.42
Camión de Volteo $2,500 ÷ 7 = $357.14 = 306.1224 310 1.6638 = $516 + $0.00 = 0.00 $515.78
Oficial Obra Civil $1,900 ÷ 7 = $271.43 = 232.6531 235 1.6814 = $395 + $0.00 = 0.00 $395.13
Ayudante General $1,400 ÷ 7 = $200.00 = 171.4286 172 1.7082 = $294 + $0.00 = 0.00 $293.81
Cabo $3,200 ÷ 7 = $457.14 = 391.8367 390 1.6550 = $645 + $0.00 = 0.00 $645.45
Sobrestante $4,200 ÷ 7 = $600.00 = 514.2857 515 1.6453 = $847 + $0.00 = 0.00 $847.33
Topografo $3,500 ÷ 7 = $500.00 = 428.5714 430 1.6543 = $711 + $0.00 = 0.00 $711.35
Oficial Obra Electrica $3,500 ÷ 7 = $500.00 = 428.5714 430 1.6513 = $710 + $0.00 = 0.00 $710.06
Bodeguero $1,700 ÷ 7 = $242.86 = 208.1633 210 1.6886 = $355 + $0.00 = 0.00 $354.61
Velador 1500 ÷ 7 = $214.29 = 183.6735 190 1.6979 = $323 + $0.00 = 0.00 $322.60
Relleno con material de banco compactado con vibrocompactador al 95% del pvsm en
capas de 20 cm. Adicionando la humedad necesaria para lograr la compactación. En la
formación del terraplén de desvío para el trafico vehicular y Peatonal.
MATERIALES
AGUA M3 $10.00 0.200000 $2.00
Material de Banco M3 $18.38 1.300000 $23.89
Subtotal: MATERIALES $25.89
MANO DE OBRA
AYUDANTE DE OFICIAL JOR $313.69 2.000000 $627.38
CABO DE OFICIOS JOR $936.74 0.100000 $93.67
Cuadrilla de Topografía JOR $3,395.35 0.100000 $339.54
Importe: $1,060.59
Rendimiento: 96.15 M3./ Hr. 120.000000 $8.84
Subtotal: MANO DE OBRA $8.84
EQUIPO Y HERRAMIENTA
%MO HERRAMIENTA MENOR % $1,060.59 0.050000 $53.03
Moroconformadora HR $517.99 1.000000 $517.99
Vibrocompactador de 10 a 12 Ton. HR $380.89 1.000000 $380.89
CAMION PIPA DE 10000 LTS 140 HP HR $299.22 1.000000 $299.22
Importe: $1,251.13
Rendimiento: 120.000000 $10.43
Subtotal: EQUIPO Y HERRAMIENTA $10.43
Costo directo $45.16
INDIRECTOS 12.500% $5.64
SUBTOTAL $50.80
FINANCIAMIENTO 0% $0.00
SUBTOTAL $50.80
UTILIDAD 7.954% $4.04
PRECIO UNITARIO $54.84
(* SETENTA PESOS 39/100 M.N. *)
44. x1.12500x1.07954=
23-May-2011
SOLUCIONES DE INGENIERIA APLICADA S. A. DE C. V.
Cliente : INFRAESTRUCTURA COMPLEMENTARIA DE LA SECRETARIA DE COMUNICACIONES, GOBIERNO DEL ESTADO
DE VERACRUZ.
Concurso No.
MATERIALES
Derecho de Banco M3 $4.00 1.000000 $4.00
Subtotal: MATERIALES $4.00
MANO DE OBRA
AYUDANTE DE OFICIAL JOR $313.69 0.500000 $156.85
CABO DE OFICIOS JOR $936.74 0.100000 $93.67
Importe: $250.52
Rendimiento: 100.000000 $2.51
Subtotal: MANO DE OBRA $2.51
EQUIPO Y HERRAMIENTA
%MO HERRAMIENTA MENOR % $250.52 0.050000 $12.53
Tractor D-6 HR $850.00 1.000000 $850.00
Importe: $862.53
Rendimiento: 67.50 m3 / Hr. 100.000000 $8.63
Subtotal: EQUIPO Y HERRAMIENTA $8.63
Costo directo $15.13
INDIRECTOS 12.500% $1.89
SUBTOTAL $17.02
FINANCIAMIENTO 0% $0.00
SUBTOTAL $17.02
UTILIDAD 7.954% $1.35
PRECIO UNITARIO $18.38
(* SETENTA PESOS 39/100 M.N. *)
23-May-2011
SOLUCIONES DE INGENIERIA APLICADA S. A. DE C. V.
Cliente : INFRAESTRUCTURA COMPLEMENTARIA DE LA SECRETARIA DE COMUNICACIONES, GOBIERNO DEL ESTADO
DE VERACRUZ.
Concurso No.
Carga con maquinaria a camión con acarreo 1er. km, de Material Producto de la
excavación: material tipo B. Incluye: carga y acarreo 1er. km. Volumen medido en Banco.
EQUIPO Y HERRAMIENTA
CARGADOR FRONTAL CAT 950 SOBRE HR $434.51 / 70.000000 $6.21
NEUMATICOS
Rend : 10 Viaje de 7 m3 / Hr.
CAMION VOLTEO DE 7 M3 DE CAPACIDAD HR $296.44 / 18.000000 $16.47
Rend: Se apega a Tarifa
Subtotal: EQUIPO Y HERRAMIENTA $22.68
Costo directo $22.68
INDIRECTOS 12.500% $2.83
SUBTOTAL $25.51
FINANCIAMIENTO 0% $0.00
SUBTOTAL $25.51
UTILIDAD 7.954% $2.03
PRECIO UNITARIO $27.54
(* TREINTA Y DOS PESOS 55/100 M.N. *)
23-May-2011
SOLUCIONES DE INGENIERIA APLICADA S. A. DE C. V.
Cliente : INFRAESTRUCTURA COMPLEMENTARIA DE LA SECRETARIA DE COMUNICACIONES, GOBIERNO DEL ESTADO
DE VERACRUZ.
Concurso No.
EQUIPO Y HERRAMIENTA
CAMION VOLTEO DE 7 M3 DE CAPACIDAD HR $296.44 / 43.149900 $6.87
Rend: Se apega a Tarifa
Subtotal: EQUIPO Y HERRAMIENTA $6.87
Costo directo $6.87
INDIRECTOS 12.500% $0.86
SUBTOTAL $7.73
FINANCIAMIENTO 0% $0.00
SUBTOTAL $7.73
UTILIDAD 7.954% $0.61
PRECIO UNITARIO $8.34
(* TREINTA Y DOS PESOS 55/100 M.N. *)
Trazo y nivelación con equipo topográfico, estableciendo ejes de referencia y bancos de nivel,
incluye: Materiales, mano de obra, equipo y herramienta para la localización de Pilas.
MATERIALES
MADERA DE PINO DE 3A. EN BARROTE DE 2" PT $9.38 0.006000 $0.06
X4"X8'
CLAVO DE 2 1/2" A 3 1/2" KG $15.30 0.002500 $0.04
PINTURA ESMALTE COMEX 100 LT $99.50 0.000400 $0.04
CALHIDRA EN SACO TON $1,241.38 0.000050 $0.06
HILO PLASTICO CAL. 10 ROLLO $70.00 0.001000 $0.07
Subtotal: MATERIALES $0.27
MANO DE OBRA
TOPOGRAFO JOR $821.00 1.000000 $821.00
CADENEROS JOR $313.69 2.000000 $627.38
CABO DE OFICIOS JOR $936.74 0.100000 $93.67
Importe: $1,542.05
Rendimiento: 600.000000 $2.57
Subtotal: MANO DE OBRA $2.57
EQUIPO Y HERRAMIENTA
%MO HERRAMIENTA MENOR % $2.57 0.050000 $0.13
ESTACION TOTAL MARCA SOKIA HR $35.00 / 50.000000 $0.70
Subtotal: EQUIPO Y HERRAMIENTA $0.83
Costo directo $3.66
INDIRECTOS 12.500% $0.46
SUBTOTAL $4.12
FINANCIAMIENTO 0% $0.00
SUBTOTAL $4.12
UTILIDAD 7.954% $0.33
PRECIO UNITARIO $4.45
(* CINCO PESOS 38/100 M.N. *)
23-May-2011
SOLUCIONES DE INGENIERIA APLICADA S. A. DE C. V.
Cliente : INFRAESTRUCTURA COMPLEMENTARIA DE LA SECRETARIA DE COMUNICACIONES, GOBIERNO DEL ESTADO
DE VERACRUZ.
Concurso No.
Suministro, habilitado y colocación de acero de refuerzo fy=4200 kg/cm2 del Nº4 (1/2"),y
No.5 (5/8") incluye: dobleces, ganchos y traslapes en Estribos helicoidales de Pilas de
Cimentación.
MATERIALES
VARILLA No. 4 (1/2") FY=4200 KG/CM2 TON $13,200.00 1.050000 $13,860.00
ALAMBRE RECOCIDO CAL. 18 KG $15.00 38.000000 $570.00
Subtotal: MATERIALES $14,430.00
MANO DE OBRA
OFICIAL de Obra Civil JOR $580.31 1.000000 $580.31
AYUDANTE DE OFICIAL JOR $313.69 1.000000 $313.69
CABO DE OFICIOS JOR $1,041.74 0.100000 $104.17
Importe: $998.17
Rendimiento: 0.17 a 0.25 Tn. / Jor. 0.210000 $4,753.21
Subtotal: MANO DE OBRA $4,753.21
EQUIPO Y HERRAMIENTA
HERRAMIENTA MENOR % $4,753.21 0.050000 $237.66
Subtotal: EQUIPO Y HERRAMIENTA $237.66
Costo directo $19,420.87
INDIRECTOS 12.500% $2,427.61
SUBTOTAL $21,848.48
FINANCIAMIENTO 0% $0.00
SUBTOTAL $21,848.48
UTILIDAD 7.954% $1,737.83
PRECIO UNITARIO $23,586.31
(* QUINCE MIL OCHENTA Y UN PESOS 93/100 M.N. *)
23-May-2011
SOLUCIONES DE INGENIERIA APLICADA S. A. DE C. V.
Cliente : INFRAESTRUCTURA COMPLEMENTARIA DE LA SECRETARIA DE COMUNICACIONES, GOBIERNO DEL ESTADO
DE VERACRUZ.
Concurso No.
Suministro, habilitado y colocación de acero de refuerzo fy=4200 kg/cm2 del Nº6 (3/4"),
incluye: dobleces, ganchos y traslapes en Estribos helicoidales de Pilas de Cimentación.
MATERIALES
VARILLA No. 6 (3/4") FY=4200 KG/CM2 TON $13,200.00 1.050000 $13,860.00
ALAMBRE RECOCIDO CAL. 18 KG $15.00 38.000000 $570.00
Subtotal: MATERIALES $14,430.00
MANO DE OBRA
OFICIAL de Obra Civil JOR $475.31 1.000000 $475.31
AYUDANTE DE OFICIAL JOR $313.69 1.000000 $313.69
CABO DE OFICIOS JOR $936.74 0.100000 $93.67
Importe: $882.67
Rendimiento: 0.204 a 0.306 Tn/ Jor. 0.255000 $3,461.47
Subtotal: MANO DE OBRA $3,461.47
EQUIPO Y HERRAMIENTA
HERRAMIENTA MENOR % $3,461.47 0.050000 $173.07
Subtotal: EQUIPO Y HERRAMIENTA $173.07
Costo directo $18,064.54
INDIRECTOS 12.500% $2,258.07
SUBTOTAL $20,322.61
FINANCIAMIENTO 0% $0.00
SUBTOTAL $20,322.61
UTILIDAD 7.954% $1,616.46
PRECIO UNITARIO $21,939.07
(* QUINCE MIL OCHENTA Y UN PESOS 93/100 M.N. *)
23-May-2011
SOLUCIONES DE INGENIERIA APLICADA S. A. DE C. V.
Cliente : INFRAESTRUCTURA COMPLEMENTARIA DE LA SECRETARIA DE COMUNICACIONES, GOBIERNO DEL ESTADO
DE VERACRUZ.
Concurso No.
Suministro, habilitado y colocación de acero de refuerzo fy=4200 kg/cm2 del Nº8 ( 1" ),
incluye: dobleces, ganchos y traslapes en Refuerzo Principal de Pilas de Cimentación.
MATERIALES
VARILLA No. 8 (1") FY=4200 KG/CM2 TON $13,200.00 1.060000 $13,992.00
ALAMBRE RECOCIDO CAL. 18 KG $15.00 40.000000 $600.00
Subtotal: MATERIALES $14,592.00
MANO DE OBRA
OFICIAL de Obra Civil JOR $475.31 1.000000 $475.31
AYUDANTE DE OFICIAL JOR $313.69 1.000000 $313.69
CABO DE OFICIOS JOR $936.74 0.100000 $93.67
Importe: $882.67
Rendimiento: 0.220 a 0.320 Ton / Jor. 0.270000 $3,269.16
Subtotal: MANO DE OBRA $3,269.16
EQUIPO Y HERRAMIENTA
HERRAMIENTA MENOR % $3,269.16 0.050000 $163.46
Subtotal: EQUIPO Y HERRAMIENTA $163.46
Costo directo $18,024.62
INDIRECTOS 12.500% $2,253.08
SUBTOTAL $20,277.70
FINANCIAMIENTO 0% $0.00
SUBTOTAL $20,277.70
UTILIDAD 7.954% $1,612.89
PRECIO UNITARIO $21,890.59
(* QUINCE MIL OCHENTA Y UN PESOS 93/100 M.N. *)
23-May-2011
SOLUCIONES DE INGENIERIA APLICADA S. A. DE C. V.
Cliente : INFRAESTRUCTURA COMPLEMENTARIA DE LA SECRETARIA DE COMUNICACIONES, GOBIERNO DEL ESTADO
DE VERACRUZ.
Concurso No.
Equipo, Mano de Obra para la Perforación previa en un diámetro máximo de 120 cm y profundidad
promedio de 17 m en material tipo "B".Incluye el suministro, dosificación y colocación de lodo
bentonitico al 5% sin recuperación, así también el retiro del excedente de la perforación etc. para Pilas
de Cimentación 17 m de longitud y 120 cm. Ø.
MATERIALES
AGUA M3 $10.00 0.200000 $2.00
Bentonita Sodica Ton. $1,650.00 0.021600 $35.64
Subtotal: MATERIALES $37.64
MANO DE OBRA
AYUDANTE DE OFICIAL JOR $313.69 7.000000 $2,195.83
OFICIAL de Obra Civil JOR $475.31 1.000000 $475.31
CABO DE OFICIOS JOR $936.74 0.100000 $93.67
Cuadrilla de Topografía JOR $3,395.35 0.150000 $509.30
Importe: $739.01
Rendimiento: 15.000000 $49.27
Subtotal: MANO DE OBRA $49.27
EQUIPO Y HERRAMIENTA
%MO HERRAMIENTA MENOR % $739.01 0.050000 $36.95
Grua de 40 Ton. HR 0.000000 1.000000 $0.00
Perforadora Watson Mod.5000 o Soilmec RTC/S 148 HR 0.000000 1.000000 $0.00
HP de 45/13280 o 32/11000 m/kg-m
Mezcladora de Bentonita Soilmec HR 0.000000 0.500000 $0.00
Desarenador HR 0.000000 0.500000 $0.00
Importe: $36.95
Rendimiento: 4.000000 $9.24
Subtotal: EQUIPO Y HERRAMIENTA $9.24
23-May-2011
SOLUCIONES DE INGENIERIA APLICADA S. A. DE C. V.
Cliente : INFRAESTRUCTURA COMPLEMENTARIA DE LA SECRETARIA DE COMUNICACIONES, GOBIERNO DEL ESTADO
DE VERACRUZ.
Concurso No.
Equipo, Mano de Obra para el Izaje y colocación de Estructura Habilitada en Acero de refuerzo del No.4
y No.8 en perforación previa de Pilas de Cimentación para una longitud de 10.00 ml y 80 cms de
diámetro.
MATERIALES
Subtotal: MATERIALES $0.00
MANO DE OBRA
AYUDANTE DE OFICIAL JOR $313.69 3.000000 $941.07
OFICIAL de Obra Civil JOR $475.31 1.000000 $475.31
CABO DE OFICIOS JOR $936.74 0.100000 $93.67
Cuadrilla de Topografía JOR $3,395.35 0.150000 $509.30
Importe: $739.01
Rendimiento: 15.000000 $49.27
Subtotal: MANO DE OBRA $49.27
EQUIPO Y HERRAMIENTA
%MO HERRAMIENTA MENOR % $739.01 0.050000 $36.95
Grua de 40 Ton. HR $0.00 1.000000 $0.00
Importe: $36.95
Rendimiento: 5.000000 $7.39
Subtotal: EQUIPO Y HERRAMIENTA $7.39
Costo directo $56.66
INDIRECTOS 12.500% $7.08
SUBTOTAL $63.74
23-May-2011
SOLUCIONES DE INGENIERIA APLICADA S. A. DE C. V.
Cliente : INFRAESTRUCTURA COMPLEMENTARIA DE LA SECRETARIA DE COMUNICACIONES, GOBIERNO DEL ESTADO
DE VERACRUZ.
Concurso No.
$1,148.88
Costo ML de Pila Terminada = $6000.37 $6,000.37 $143.61
Perforación y Lodo Bentonitico 40.00% $2,400.15 $1,292.49
Izaje y Colocación de Acero de Refuerzo 15.00% $900.06 x 1.20 $102.80
Vaciado de concreto Sistema Tremie 45.00% $2,700.17 $1,395.29
100.00% $6,000.37
Trazo y nivelación con equipo topográfico, estableciendo ejes de referencia y bancos de nivel,
incluye: Materiales, mano de obra, equipo y herramienta para la localización de Zapatas.
MATERIALES
MADERA DE PINO DE 3A. EN BARROTE DE 2" PT $9.38 0.006000 $0.06
X4"X8'
CLAVO DE 2 1/2" A 3 1/2" KG $15.30 0.002500 $0.04
PINTURA ESMALTE COMEX 100 LT $99.50 0.000400 $0.04
CALHIDRA EN SACO TON $1,241.38 0.000050 $0.06
HILO PLASTICO CAL. 10 ROLLO $70.00 0.001000 $0.07
Subtotal: MATERIALES $0.27
MANO DE OBRA
TOPOGRAFO JOR $821.00 1.000000 $821.00
CADENEROS JOR $313.69 2.000000 $627.38
CABO DE OFICIOS JOR $936.74 0.100000 $93.67
Importe: $1,542.05
Rendimiento: 600.000000 $2.57
Subtotal: MANO DE OBRA $2.57
EQUIPO Y HERRAMIENTA
%MO HERRAMIENTA MENOR % $2.57 0.050000 $0.13
23-May-2011
SOLUCIONES DE INGENIERIA APLICADA S. A. DE C. V.
Cliente : INFRAESTRUCTURA COMPLEMENTARIA DE LA SECRETARIA DE COMUNICACIONES, GOBIERNO DEL ESTADO
DE VERACRUZ.
Concurso No.
MATERIALES
Barrote de 3.5" x 2.5" Madera de Pino PT $9.38 4.860000 $45.59
Triplay de 3/4" M2. $137.50 0.200000 $27.50
CLAVO DE 2 1/2" A 3 1/2" KG $15.30 0.170000 $2.60
Alambre Recocido KG $13.36 0.170000 $2.27
Alambron KG $11.64 2.500000 $29.10
Montenes de 6 y 8" Kg. $8.50 2.840000 $24.14
Tubería Usada de 3" diametro KG. $8.50 4.340000 $36.89
Equipo menor y Mano de Obra para el descabece de Pilas de Cimentación de 80 cm.Ø, Incluye el
desmantelamiento de estribos y dobles de 12 Vrs. Del No.8 en forma de Flor. Para el desplante de
Zapatas.
MATERIALES
Equipo y Mano de Obra para el Control del Nivel Freático durante el desplante de cimentación para
Estribos y Aleros. Mediante el uso del Sistema WellPoint ( 6 Puyones )
MATERIALES
MATERIALES
AGUA M3 $10.00 0.200000 $2.00
GRAVA 3/4" M3 $275.86 0.650000 $179.31
GRAVILLA M3 $228.45 0.550000 $125.65
CEMENTO GRIS TIPO I TON $1,965.52 0.280000 $550.35
SUBTOTAL: MATERIALES $857.30
MANO DE OBRA
Ayudante General JOR $290.78 5.000000 $1,453.90
CABO DE OFICIOS JOR $892.00 0.100000 $89.20
Importe: $1,543.10
Rendimiento: M3/JOR 15.000000 $102.87
SUBTOTAL: MANO DE OBRA $102.87
EQUIPO Y HERRAMIENTA
%MO HERRAMIENTA MENOR % $102.87 0.060000 $6.17
REVOLVEDORA PARA CONCRETO HR $87.50 12.000000 $7.29
23-May-2011
SOLUCIONES DE INGENIERIA APLICADA S. A. DE C. V.
Cliente : INFRAESTRUCTURA COMPLEMENTARIA DE LA SECRETARIA DE COMUNICACIONES, GOBIERNO DEL ESTADO
DE VERACRUZ.
Concurso No.
MATERIALES
MATAGU01 Polietileno negro M2. $25.00 1.200000 $30.00
Subtotal: MATERIALES $30.00
MANO DE OBRA
MO02 OFICIAL DE 1A. JOR $453.00 1.000000 $453.00
MO03 AYUDANTE DE OFICIAL JOR $290.78 1.000000 $290.78
MO06 CABO DE OFICIOS JOR $892.00 0.100000 $89.20
Importe: $832.98
Rendimiento: 80 m2/ Jor. 600.000000 $1.39
Subtotal: MANO DE OBRA $1.39
EQUIPO Y HERRAMIENTA
%MO HERRAMIENTA MENOR % $1.39 0.030000 $0.04
23-May-2011
SOLUCIONES DE INGENIERIA APLICADA S. A. DE C. V.
Cliente : INFRAESTRUCTURA COMPLEMENTARIA DE LA SECRETARIA DE COMUNICACIONES, GOBIERNO DEL ESTADO
DE VERACRUZ.
Concurso No.
Suministro, habilitado y colocación de acero de refuerzo fy=4200 kg/cm2 del Nº4 (1/2"),y
No.5 (5/8") incluye: dobleces, ganchos y traslapes en Zapatas
MATERIALES
VARILLA No. 4 (1/2") FY=4200 KG/CM2 TON $13,200.00 1.050000 $13,860.00
ALAMBRE RECOCIDO CAL. 18 KG $15.00 38.000000 $570.00
Subtotal: MATERIALES $14,430.00
MANO DE OBRA
OFICIAL de Obra Civil JOR $475.31 1.000000 $475.31
AYUDANTE DE OFICIAL JOR $313.69 1.000000 $313.69
CABO DE OFICIOS JOR $936.74 0.100000 $93.67
23-May-2011
SOLUCIONES DE INGENIERIA APLICADA S. A. DE C. V.
Cliente : INFRAESTRUCTURA COMPLEMENTARIA DE LA SECRETARIA DE COMUNICACIONES, GOBIERNO DEL ESTADO
DE VERACRUZ.
Concurso No.
Suministro, habilitado y colocación de acero de refuerzo fy=4200 kg/cm2 del Nº6 (3/4"),
incluye: dobleces, ganchos y traslapes en Zapatas
MATERIALES
VARILLA No. 6 (3/4") FY=4200 KG/CM2 TON $13,200.00 1.050000 $13,860.00
ALAMBRE RECOCIDO CAL. 18 KG $15.00 38.000000 $570.00
Subtotal: MATERIALES $14,430.00
MANO DE OBRA
OFICIAL de Obra Civil JOR $475.31 1.000000 $475.31
23-May-2011
SOLUCIONES DE INGENIERIA APLICADA S. A. DE C. V.
Cliente : INFRAESTRUCTURA COMPLEMENTARIA DE LA SECRETARIA DE COMUNICACIONES, GOBIERNO DEL ESTADO
DE VERACRUZ.
Concurso No.
Suministro, habilitado y colocación de acero de refuerzo fy=4200 kg/cm2 del Nº8 ( 1" ),
incluye: dobleces, ganchos y traslapes en Zapatas.
MATERIALES
VARILLA No. 8 (1") FY=4200 KG/CM2 TON $13,200.00 1.060000 $13,992.00
ALAMBRE RECOCIDO CAL. 18 KG $15.00 40.000000 $600.00
Subtotal: MATERIALES $14,592.00
23-May-2011
SOLUCIONES DE INGENIERIA APLICADA S. A. DE C. V.
Cliente : INFRAESTRUCTURA COMPLEMENTARIA DE LA SECRETARIA DE COMUNICACIONES, GOBIERNO DEL ESTADO
DE VERACRUZ.
Concurso No.
MATERIALES
BARROTE 1 1/2" X 4" X 8' DE 2A. PT $9.50 3.250000 $30.88
23-May-2011
SOLUCIONES DE INGENIERIA APLICADA S. A. DE C. V.
Cliente : INFRAESTRUCTURA COMPLEMENTARIA DE LA SECRETARIA DE COMUNICACIONES, GOBIERNO DEL ESTADO
DE VERACRUZ.
Concurso No.
MATERIALES
Material de Banco M3 $18.38 1.350000 $24.81
Subtotal: MATERIALES $24.81
MANO DE OBRA
MO01 AYUDANTE DE OFICIAL JOR $313.69 2.000000 $627.38
MO06 CABO DE OFICIOS JOR $936.74 0.100000 $93.67
Importe: $721.05
Rendimiento: 15.000000 $48.07
Subtotal: MANO DE OBRA $48.07
EQUIPO Y HERRAMIENTA
%MO HERRAMIENTA MENOR % $48.07 0.060000 $2.88
EQACMVB1 COMPACTADOR VIBRATORIO BAILARINA 4 H.P. HR $37.50 / 15.000000 $2.50
Subtotal: EQUIPO Y HERRAMIENTA $5.38
Costo directo $78.27
INDIRECTOS 12.500% $9.78
SUBTOTAL $88.05
FINANCIAMIENTO 0% $0.00
SUBTOTAL $88.05
UTILIDAD 7.954% $7.00
PRECIO UNITARIO $95.05
(* CINCO PESOS 88/100 M.N. *)
Rendimiento:
Relleno Manual: 5.2 a 7.8 M3/Jor.
Carga con maquinaria a camión con acarreo 1er. km, de Material Producto de la
excavación: material tipo B. Incluye: carga y acarreo 1er. km. Volumen medido en Banco.
EQUIPO Y HERRAMIENTA
CARGADOR FRONTAL CAT 950 SOBRE HR $434.51 / 70.000000 $6.21
NEUMATICOS
Rend : 10 Viaje de 7 m3 / Hr.
CAMION VOLTEO DE 7 M3 DE CAPACIDAD HR $296.44 / 18.000000 $16.47
Rend: Se apega a Tarifa
Subtotal: EQUIPO Y HERRAMIENTA $22.68
Costo directo $22.68
INDIRECTOS 12.500% $2.83
SUBTOTAL $25.51
FINANCIAMIENTO 0% $0.00
SUBTOTAL $25.51
UTILIDAD 7.954% $2.03
PRECIO UNITARIO $27.54
23-May-2011
SOLUCIONES DE INGENIERIA APLICADA S. A. DE C. V.
Cliente : INFRAESTRUCTURA COMPLEMENTARIA DE LA SECRETARIA DE COMUNICACIONES, GOBIERNO DEL ESTADO
DE VERACRUZ.
Concurso No.
MATERIALES
MADERA DE PINO DE 3A. EN BARROTE DE 2" PT $9.38 0.006000 $0.06
X4"X8'
CLAVO DE 2 1/2" A 3 1/2" KG $15.30 0.002500 $0.04
PINTURA ESMALTE COMEX 100 LT $99.50 0.000400 $0.04
CALHIDRA EN SACO TON $1,241.38 0.000050 $0.06
HILO PLASTICO CAL. 10 ROLLO $70.00 0.001000 $0.07
Subtotal: MATERIALES $0.27
MANO DE OBRA
TOPOGRAFO JOR $821.00 1.000000 $821.00
CADENEROS JOR $313.69 2.000000 $627.38
CABO DE OFICIOS JOR $936.74 0.100000 $93.67
Importe: $1,542.05
Rendimiento: 600.000000 $2.57
Subtotal: MANO DE OBRA $2.57
EQUIPO Y HERRAMIENTA
%MO HERRAMIENTA MENOR % $2.57 0.050000 $0.13
ESTACION TOTAL MARCA SOKIA HR $35.00 / 50.000000 $0.70
Subtotal: EQUIPO Y HERRAMIENTA $0.83
Costo directo $3.66
INDIRECTOS 12.500% $0.46
SUBTOTAL $4.12
FINANCIAMIENTO 0% $0.00
SUBTOTAL $4.12
UTILIDAD 7.954% $0.33
PRECIO UNITARIO $4.45
(* CINCO PESOS 38/100 M.N. *)
23-May-2011
SOLUCIONES DE INGENIERIA APLICADA S. A. DE C. V.
Cliente : INFRAESTRUCTURA COMPLEMENTARIA DE LA SECRETARIA DE COMUNICACIONES, GOBIERNO DEL ESTADO
DE VERACRUZ.
Concurso No.
Equipo y Mano de Obra para el Control del Nivel Freático durante el desplante de cimentación para
Estribos y Aleros. Mediante el uso del Sistema WellPoint ( 6 Puyones )
MATERIALES
Suministro, habilitado y colocación de acero de refuerzo fy=4200 kg/cm2 del Nº4 (1/2"), y
Nº 5 ( 5/8" ) Incluye: dobleces, ganchos y traslapes en Estribos, Aleros, Apoyos, Topes
Sísmico, etc. Para una altura de 0.00 a 8.50 m.
MATERIALES
VARILLA No. 4 (1/2") FY=4200 KG/CM2 TON $13,200.00 1.060000 $13,992.00
ALAMBRE RECOCIDO CAL. 18 KG $14.66 38.000000 $557.08
Alambrom KG $14.66 15.410000 $225.91
Subtotal: MATERIALES $14,774.99
MANO DE OBRA
OFICIAL de Obra Civil JOR $821.00 1.000000 $821.00
AYUDANTE DE OFICIAL JOR $313.69 1.000000 $313.69
CABO DE OFICIOS JOR $936.74 0.100000 $93.67
Importe: $1,228.36
Rendimiento: 0.151 a 0.227 Ton / Jor. 0.190000 $6,465.07
Subtotal: MANO DE OBRA $6,465.07
EQUIPO Y HERRAMIENTA
HERRAMIENTA MENOR % $6,465.07 0.050000 $323.25
Subtotal: EQUIPO Y HERRAMIENTA $323.25
Costo directo $21,563.32
INDIRECTOS 12.500% $2,695.41
SUBTOTAL $24,258.73
FINANCIAMIENTO 0% $0.00
SUBTOTAL $24,258.73
UTILIDAD 7.954% $1,929.54
PRECIO UNITARIO $26,188.27
(* QUINCE MIL OCHENTA Y UN PESOS 93/100 M.N. *)
23-May-2011
SOLUCIONES DE INGENIERIA APLICADA S. A. DE C. V.
Cliente : INFRAESTRUCTURA COMPLEMENTARIA DE LA SECRETARIA DE COMUNICACIONES, GOBIERNO DEL ESTADO
DE VERACRUZ.
Concurso No.
Suministro, habilitado y colocación de acero de refuerzo y=4200 kg/cm2 del Nº6 (3/4"),
incluye: dobleces, ganchos y traslapes en Estribos, Aleros, Apoyos, Topes Sísmico etc.
Para una altura de 0.00 a 8.50 m.
MATERIALES
VARILLA No. 4 (1/2") FY=4200 KG/CM2 TON $13,200.00 1.070000 $14,124.00
ALAMBRE RECOCIDO CAL. 18 KG $14.66 38.000000 $557.08
Alambrom KG $14.66 15.410000 $225.91
Subtotal: MATERIALES $14,906.99
MANO DE OBRA
OFICIAL de Obra Civil JOR $821.00 1.000000 $821.00
AYUDANTE DE OFICIAL JOR $313.69 1.000000 $313.69
CABO DE OFICIOS JOR $936.74 0.100000 $93.67
Importe: $1,228.36
Rendimiento: 0.168 a 0.252 Ton /Jor 0.190000 $6,465.07
Subtotal: MANO DE OBRA $6,465.07
EQUIPO Y HERRAMIENTA
HERRAMIENTA MENOR % $6,465.07 0.050000 $323.25
Subtotal: EQUIPO Y HERRAMIENTA $323.25
Costo directo $21,695.32
INDIRECTOS 12.500% $2,711.91
SUBTOTAL $24,407.23
FINANCIAMIENTO 0% $0.00
SUBTOTAL $24,407.23
UTILIDAD 7.954% $1,941.35
PRECIO UNITARIO $26,348.58
(* QUINCE MIL OCHENTA Y UN PESOS 93/100 M.N. *)
23-May-2011
SOLUCIONES DE INGENIERIA APLICADA S. A. DE C. V.
Cliente : INFRAESTRUCTURA COMPLEMENTARIA DE LA SECRETARIA DE COMUNICACIONES, GOBIERNO DEL ESTADO
DE VERACRUZ.
Concurso No.
Suministro, habilitado y colocación de acero de refuerzo fy=4200 kg/cm2 del Nº8 (1"),
incluye: dobleces, ganchos y traslapes en Estribos , Aleros, Apoyos, Topes Sísmico etc.
Para una altura de 0.00 a 8.50 m.
MATERIALES
VARILLA No. 4 (1/2") FY=4200 KG/CM2 TON $13,200.00 1.120000 $14,784.00
ALAMBRE RECOCIDO CAL. 18 KG $14.66 40.000000 $586.40
Alambrom KG $13.00 15.410000 $200.33
Subtotal: MATERIALES $15,570.73
MANO DE OBRA
OFICIAL de Obra Civil JOR $821.00 1.000000 $821.00
AYUDANTE DE OFICIAL JOR $313.69 1.000000 $313.69
CABO DE OFICIOS JOR $936.74 0.100000 $93.67
Importe: $1,228.36
Rendimiento:0.172 a 0.258 Ton/Jor. 0.215000 $5,713.32
Subtotal: MANO DE OBRA $5,713.32
EQUIPO Y HERRAMIENTA
HERRAMIENTA MENOR % $5,713.32 0.050000 $285.67
Subtotal: EQUIPO Y HERRAMIENTA $285.67
Costo directo $21,569.72
INDIRECTOS 12.500% $2,696.21
SUBTOTAL $24,265.93
FINANCIAMIENTO 0% $0.00
SUBTOTAL $24,265.93
UTILIDAD 7.954% $1,930.11
PRECIO UNITARIO $26,196.04
(* QUINCE MIL OCHENTA Y UN PESOS 93/100 M.N. *)
23-May-2011
SOLUCIONES DE INGENIERIA APLICADA S. A. DE C. V.
Cliente : INFRAESTRUCTURA COMPLEMENTARIA DE LA SECRETARIA DE COMUNICACIONES, GOBIERNO DEL ESTADO
DE VERACRUZ.
Concurso No.
MATERIALES
BARROTE 1 1/2" X 4" X 8' DE 2A. PT $9.50 3.900000 $37.05
TRIPLAY DE PINO 1 CARA 19 MM 1.22 X 2.44 M. M2 $120.00 0.250000 $30.00
POLIN DE4" X 4" X 8' DE 2A. PT $9.50 5.500000 $52.25
DESMOLDANTE BASE AGUA LT $10.50 0.250000 $2.63
CLAVO DE 2 1/2" A 3 1/2" KG $15.94 0.170000 $2.71
ALAMBRE RECOCIDO CAL. 18 KG $14.66 0.070000 $1.03
ALAMBROM KG $13.00 3.250000 $42.25
Subtotal: MATERIALES $167.91
MANO DE OBRA
OFICIAL DE 1A. JOR $821.00 1.000000 $821.00
AYUDANTE DE OFICIAL JOR $313.69 2.000000 $627.38
CABO DE OFICIOS JOR $936.74 0.100000 $93.67
Importe: $1,542.05
Rendimiento: 12.000000 $128.50
Subtotal: MANO DE OBRA $128.50
EQUIPO Y HERRAMIENTA
%MO HERRAMIENTA MENOR % $1,542.05 0.060000 $92.52
Importe: $92.52
Rendimiento: 12.000000 $7.71
Subtotal: EQUIPO Y HERRAMIENTA $7.71
Costo directo $304.13
INDIRECTOS 12.500% $38.02
23-May-2011
SOLUCIONES DE INGENIERIA APLICADA S. A. DE C. V.
Cliente : INFRAESTRUCTURA COMPLEMENTARIA DE LA SECRETARIA DE COMUNICACIONES, GOBIERNO DEL ESTADO
DE VERACRUZ.
Concurso No.
MATERIALES
MATAGU01 AGUA M3 $8.00 0.015000 $0.12
Material de Banco M3 $18.38 1.350000 $24.81
Subtotal: MATERIALES $24.93
MANO DE OBRA
MO01 AYUDANTE DE OFICIAL JOR $313.69 2.000000 $627.38
MO06 CABO DE OFICIOS JOR $936.74 0.100000 $93.67
Importe: $721.05
Rendimiento: 12.000000 $60.09
Subtotal: MANO DE OBRA $60.09
EQUIPO Y HERRAMIENTA
%MO HERRAMIENTA MENOR % $60.09 0.060000 $3.61
EQACMVB1 COMPACTADOR VIBRATORIO BAILARINA 4 H.P. HR $37.50 / 12.000000 $3.13
Subtotal: EQUIPO Y HERRAMIENTA $6.73
Costo directo $91.75
INDIRECTOS 12.500% $11.47
SUBTOTAL $103.22
FINANCIAMIENTO 0% $0.00
SUBTOTAL $103.22
UTILIDAD 7.954% $8.21
PRECIO UNITARIO $111.43
(* CINCO PESOS 88/100 M.N. *)
23-May-2011
SOLUCIONES DE INGENIERIA APLICADA S. A. DE C. V.
Cliente : INFRAESTRUCTURA COMPLEMENTARIA DE LA SECRETARIA DE COMUNICACIONES, GOBIERNO DEL ESTADO
DE VERACRUZ.
Concurso No.
Carga con maquinaria a camión con acarreo 1er. km, de Material Producto de la
excavación: material tipo B. Incluye: carga y acarreo 1er. km. Volumen medido en Banco.
EQUIPO Y HERRAMIENTA
CARGADOR FRONTAL CAT 950 SOBRE HR $434.51 / 70.000000 $6.21
NEUMATICOS
Rend : 10 Viaje de 7 m3 / Hr.
CAMION VOLTEO DE 7 M3 DE CAPACIDAD HR $296.44 / 18.000000 $16.47
Rend: Se apega a Tarifa
Subtotal: EQUIPO Y HERRAMIENTA $22.68
Costo directo $22.68
INDIRECTOS 12.500% $2.83
SUBTOTAL $25.51
FINANCIAMIENTO 0% $0.00
SUBTOTAL $25.51
UTILIDAD 7.954% $2.03
PRECIO UNITARIO $27.54
(* TREINTA Y DOS PESOS 55/100 M.N. *)
23-May-2011
SOLUCIONES DE INGENIERIA APLICADA S. A. DE C. V.
Cliente : INFRAESTRUCTURA COMPLEMENTARIA DE LA SECRETARIA DE COMUNICACIONES, GOBIERNO DEL ESTADO
DE VERACRUZ.
Concurso No.
EQUIPO Y HERRAMIENTA
CAMION VOLTEO DE 7 M3 DE CAPACIDAD HR $296.44 / 43.149900 $6.87
Subtotal: EQUIPO Y HERRAMIENTA $6.87
Costo directo $6.87
INDIRECTOS 12.500% $0.86
SUBTOTAL $7.73
FINANCIAMIENTO 0% $0.00
SUBTOTAL $7.73
UTILIDAD 7.954% $0.61
PRECIO UNITARIO $8.34
(* TREINTA Y DOS PESOS 55/100 M.N. *)
23-May-2011
SOLUCIONES DE INGENIERIA APLICADA S. A. DE C. V.
Cliente : INFRAESTRUCTURA COMPLEMENTARIA DE LA SECRETARIA DE COMUNICACIONES, GOBIERNO DEL ESTADO
DE VERACRUZ.
Concurso No.
Materiales y Mano de Obra para el Mejoramiento del Acceso para el trafico de la Vigas
Cajón 200/135 y una longitud de 30.50 m.
MATERIALES
MATAGU01 AGUA M3 $8.00 0.015000 $0.12
Material de Banco M3 $18.38 1.350000 $24.81
Subtotal: MATERIALES $24.93
MANO DE OBRA
MO02 OFICIAL DE 1A. JOR $475.31 2.000000 $950.62
MO03 AYUDANTE DE OFICIAL JOR $313.69 6.000000 $1,882.14
MO06 CABO DE OFICIOS JOR $936.74 0.400000 $374.70
Importe: $3,207.46
Rendimiento: 2.000000 $1,603.73
Subtotal: MANO DE OBRA $1,603.73
EQUIPO Y HERRAMIENTA
%MO HERRAMIENTA MENOR % $1,603.73 0.060000 $96.22
Retroexcavadora HR. $313.19 2.000000 $626.38
Camión de Volteo HR. $299.22 5.000000 $1,496.10
Vibrocompactador 10 Ton HR. $380.99 2.000000 $761.98
Motoconformadora HR. $517.99 2.000000 $1,035.98
Subtotal: EQUIPO Y HERRAMIENTA $4,016.66
23-May-2011
SOLUCIONES DE INGENIERIA APLICADA S. A. DE C. V.
Cliente : INFRAESTRUCTURA COMPLEMENTARIA DE LA SECRETARIA DE COMUNICACIONES, GOBIERNO DEL ESTADO
DE VERACRUZ.
Concurso No.
MATERIALES
Fabricación y Traslado de Viga tipo Cajón Pza $190,339.86 1.000000 $190,339.86
de 200/135 y 29.20 m.
Subtotal: MATERIALES $190,339.86
MANO DE OBRA
MO02 OFICIAL DE 1A. JOR $475.31 2.000000 $950.62
MO03 AYUDANTE DE OFICIAL JOR $313.69 8.000000 $2,509.52
MO06 CABO DE OFICIOS JOR $936.74 0.400000 $374.70
Importe: $3,834.84
Rendimiento: 4.000000 $958.71
Subtotal: MANO DE OBRA $958.71
EQUIPO Y HERRAMIENTA
%MO HERRAMIENTA MENOR % $958.71 0.060000 $57.52
Subtotal: EQUIPO Y HERRAMIENTA $57.52
Costo directo $191,356.10
23-May-2011
SOLUCIONES DE INGENIERIA APLICADA S. A. DE C. V.
Cliente : INFRAESTRUCTURA COMPLEMENTARIA DE LA SECRETARIA DE COMUNICACIONES, GOBIERNO DEL ESTADO
DE VERACRUZ.
Concurso No.
MATERIALES
Fabricación y Traslado de Viga tipo Cajón Pza $73,908.95 1.000000 $73,908.95
de 200/135 y 29.20 m.
Subtotal: MATERIALES $73,908.95
MANO DE OBRA
MO02 OFICIAL DE 1A. JOR $475.31 2.000000 $950.62
MO03 AYUDANTE DE OFICIAL JOR $313.69 8.000000 $2,509.52
MO06 CABO DE OFICIOS JOR $936.74 0.400000 $374.70
Importe: $3,834.84
Rendimiento: 4.000000 $958.71
Subtotal: MANO DE OBRA $958.71
EQUIPO Y HERRAMIENTA
%MO HERRAMIENTA MENOR % $958.71 0.060000 $57.52
Subtotal: EQUIPO Y HERRAMIENTA $57.52
23-May-2011
SOLUCIONES DE INGENIERIA APLICADA S. A. DE C. V.
Cliente : INFRAESTRUCTURA COMPLEMENTARIA DE LA SECRETARIA DE COMUNICACIONES, GOBIERNO DEL ESTADO
DE VERACRUZ.
Concurso No.
MATERIALES
MATAGU01 AGUA M3 $8.00 0.015000 $0.12
Material de Banco M3 $18.38 438.750000 $8,064.23
Subtotal: MATERIALES $8,064.35
MANO DE OBRA
MO02 OFICIAL DE 1A. JOR $475.31 2.000000 $950.62
MO03 AYUDANTE DE OFICIAL JOR $313.69 6.000000 $1,882.14
MO06 CABO DE OFICIOS JOR $936.74 0.400000 $374.70
Importe: $3,207.46
Rendimiento: 2.000000 $1,603.73
Subtotal: MANO DE OBRA $1,603.73
23-May-2011
SOLUCIONES DE INGENIERIA APLICADA S. A. DE C. V.
Cliente : INFRAESTRUCTURA COMPLEMENTARIA DE LA SECRETARIA DE COMUNICACIONES, GOBIERNO DEL ESTADO
DE VERACRUZ.
Concurso No.
MATERIALES
Grout N.M. Mca. Fester Saco $480.00 2.300000 $1,104.00
MATERIALES
Apoyo Neopreno de 30x40x4.10 cm.( Apoyo Fijo) Pza. $1,700.00 1.250000 $2,125.00
MATERIALES
Apoyo Neopreno de 30x40x 5.70 cm.( Apoyo Movil) Pza. $2,300.00 1.250000 $2,875.00
MATERIALES
Demolición por medios Mecánico de concreto Armado F'c= 300 lk/ cm2. Incluye el
desmantelamiento del acero de refuerzo, retiro del concreto a la zona de almacenamiento
para su carga y acarreo. Para una altura de 0.00 a 5.00 m. para Estribos, losa,
banquetas.
MATERIALES
Aceite Hidraulico Lt. $60.00 10.000000 $600.00
Punta de Pistola Rompedora de 1¼"Ø Pza. $785.00 1.500000 $1,177.50
23-May-2011
SOLUCIONES DE INGENIERIA APLICADA S. A. DE C. V.
Cliente : INFRAESTRUCTURA COMPLEMENTARIA DE LA SECRETARIA DE COMUNICACIONES, GOBIERNO DEL ESTADO
DE VERACRUZ.
Concurso No.
Demolición por medios Manuales de concreto Armado F'c= 300 lk/ cm2. Incluye el
desmantelamiento del acero de refuerzo, retiro del concreto a la zona de almacenamiento
para su carga y acarreo. Para una altura de 0.00 a 5.00 m. para LOSA CALZADA
MATERIALES
Seguetas Pza. $2.00 18.500000 $37.00
23-May-2011
SOLUCIONES DE INGENIERIA APLICADA S. A. DE C. V.
Cliente : INFRAESTRUCTURA COMPLEMENTARIA DE LA SECRETARIA DE COMUNICACIONES, GOBIERNO DEL ESTADO
DE VERACRUZ.
Concurso No.
MATERIALES
23-May-2011
SOLUCIONES DE INGENIERIA APLICADA S. A. DE C. V.
Cliente : INFRAESTRUCTURA COMPLEMENTARIA DE LA SECRETARIA DE COMUNICACIONES, GOBIERNO DEL ESTADO
DE VERACRUZ.
Concurso No.
EQUIPO Y HERRAMIENTA
CARGADOR FRONTAL CAT 950 SOBRE HR $434.51 / 70.000000 $6.21
NEUMATICOS
Rend : 10 Viaje de 7 m3 / Hr.
CAMION VOLTEO DE 7 M3 DE CAPACIDAD HR $296.44 / 18.000000 $16.47
Rend: Se apega a Tarifa
Subtotal: EQUIPO Y HERRAMIENTA $22.68
Costo directo $22.68
INDIRECTOS 12.500% $2.83
SUBTOTAL $25.51
FINANCIAMIENTO 0% $0.00
SUBTOTAL $25.51
UTILIDAD 7.954% $2.03
PRECIO UNITARIO $27.54
(* TREINTA Y DOS PESOS 55/100 M.N. *)
EQUIPO Y HERRAMIENTA
CAMION VOLTEO DE 7 M3 DE CAPACIDAD HR $296.44 / 43.149900 $6.87
Subtotal: EQUIPO Y HERRAMIENTA $6.87
Costo directo $6.87
INDIRECTOS 12.500% $0.86
SUBTOTAL $7.73
FINANCIAMIENTO 0% $0.00
SUBTOTAL $7.73
UTILIDAD 7.954% $0.61
PRECIO UNITARIO $8.34
(* TREINTA Y DOS PESOS 55/100 M.N. *)
MATERIALES
BARROTE 1 1/2" X 4" X 8' DE 2A. PT $9.50 2.150000 $20.43
TRIPLAY DE PINO 1 CARA 16 MM 1.22 X 2.44 M. M2 $117.00 0.200000 $23.40
DESMOLDANTE BASE AGUA LT $10.50 0.200000 $2.10
CLAVO DE 2 1/2" A 3 1/2" KG $16.00 0.150000 $2.40
ALAMBRE RECOCIDO CAL. 18 KG $14.70 0.050000 $0.74
Subtotal: MATERIALES $49.06
MANO DE OBRA
OFICIAL DE 1A. JOR $475.31 1.000000 $475.31
AYUDANTE DE OFICIAL JOR $313.69 1.500000 $470.54
CABO DE OFICIOS JOR $936.74 0.100000 $93.67
Importe: $1,039.52
Rendimiento: 9.500000 $109.42
Subtotal: MANO DE OBRA $109.42
EQUIPO Y HERRAMIENTA
%MO HERRAMIENTA MENOR % $1,039.52 0.060000 $62.37
Importe: $62.37
Rendimiento: 9.500000 $6.57
Subtotal: EQUIPO Y HERRAMIENTA $6.57
Costo directo $165.05
INDIRECTOS 12.500% $20.63
SUBTOTAL $185.68
FINANCIAMIENTO 0% $0.00
SUBTOTAL $185.68
UTILIDAD 7.954% $14.77
PRECIO UNITARIO $200.45
23-May-2011
SOLUCIONES DE INGENIERIA APLICADA S. A. DE C. V.
Cliente : INFRAESTRUCTURA COMPLEMENTARIA DE LA SECRETARIA DE COMUNICACIONES, GOBIERNO DEL ESTADO
DE VERACRUZ.
Concurso No.
Suministro, habilitado y colocación de acero de refuerzo fy=4200 kg/cm2 del Nº3 (3/8"),
incluye: dobleces, ganchos y traslapes. Para Losas, Paramentos, Banquetas y Lavadero
MATERIALES
VARILLA No. 3 (3/8") FY=4200 KG/CM2 TON $13,000.00 1.050000 $13,650.00
ALAMBRE RECOCIDO CAL. 18 KG $14.70 38.000000 $558.60
Subtotal: MATERIALES $14,208.60
MANO DE OBRA
OFICIAL de Obra Civil JOR $475.31 1.000000 $475.31
AYUDANTE DE OFICIAL JOR $313.69 1.000000 $313.69
CABO DE OFICIOS JOR $936.74 0.100000 $93.67
Importe: $882.67
Rendimiento: 0.17 a 0.25 Ton / Jor. 0.210000 $4,203.21
Subtotal: MANO DE OBRA $4,203.21
EQUIPO Y HERRAMIENTA
%MO HERRAMIENTA MENOR % $4,203.21 0.060000 $252.19
Subtotal: EQUIPO Y HERRAMIENTA $252.19
Costo directo $18,664.00
INDIRECTOS 12.500% $2,333.00
SUBTOTAL $20,997.00
FINANCIAMIENTO 0% $0.00
SUBTOTAL $20,997.00
UTILIDAD 7.954% $1,670.10
PRECIO UNITARIO $22,667.10
(* QUINCE MIL OCHENTA Y UN PESOS 93/100 M.N. *)
23-May-2011
SOLUCIONES DE INGENIERIA APLICADA S. A. DE C. V.
Cliente : INFRAESTRUCTURA COMPLEMENTARIA DE LA SECRETARIA DE COMUNICACIONES, GOBIERNO DEL ESTADO
DE VERACRUZ.
Concurso No.
Suministro, habilitado y colocación de acero de refuerzo fy=4200 kg/cm2 del Nº4 (1/2"),
incluye: dobleces, ganchos y traslapes. Para Losas, Paramentos, Banquetas y Lavadero.
MATERIALES
VARILLA No. 4 (1/2") FY=4200 KG/CM2 TON $13,000.00 1.060000 $13,780.00
ALAMBRE RECOCIDO CAL. 18 KG $14.70 36.000000 $529.20
Subtotal: MATERIALES $14,309.20
MANO DE OBRA
OFICIAL de Obra Civil JOR $475.31 1.000000 $475.31
AYUDANTE DE OFICIAL JOR $313.69 1.000000 $313.69
CABO DE OFICIOS JOR $936.74 0.100000 $93.67
Importe: $882.67
Rendimiento: 0.151 a 0.227 Kg./ Jor 0.195000 $4,526.53
Subtotal: MANO DE OBRA $4,526.53
EQUIPO Y HERRAMIENTA
HERRAMIENTA MENOR % $4,526.53 0.060000 $271.59
Subtotal: EQUIPO Y HERRAMIENTA $271.59
Costo directo $19,107.33
INDIRECTOS 12.500% $2,388.42
SUBTOTAL $21,495.74
FINANCIAMIENTO 0% $0.00
SUBTOTAL $21,495.74
UTILIDAD 7.954% $1,709.77
PRECIO UNITARIO $23,205.51
(* QUINCE MIL OCHENTA Y UN PESOS 93/100 M.N. *)
23-May-2011
SOLUCIONES DE INGENIERIA APLICADA S. A. DE C. V.
Cliente : INFRAESTRUCTURA COMPLEMENTARIA DE LA SECRETARIA DE COMUNICACIONES, GOBIERNO DEL ESTADO
DE VERACRUZ.
Concurso No.
MATERIALES
BARROTE 1 1/2" X 4" X 8' DE 2A. PT $9.50 2.500000 $23.75
TRIPLAY DE PINO 1 CARA 16 MM 1.22 X 2.44 M. M2 $117.00 0.200000 $23.40
DESMOLDANTE BASE AGUA LT $10.50 0.180000 $1.89
CLAVO DE 2 1/2" A 3 1/2" KG $16.00 0.150000 $2.40
ALAMBRE RECOCIDO CAL. 18 KG $14.70 0.050000 $0.74
Subtotal: MATERIALES $52.18
MANO DE OBRA
OFICIAL DE 1A. JOR $475.31 1.000000 $475.31
AYUDANTE DE OFICIAL JOR $313.69 1.000000 $313.69
CABO DE OFICIOS JOR $936.74 0.100000 $93.67
Importe: $882.67
Rendimiento: 10.000000 $88.27
Subtotal: MANO DE OBRA $88.27
EQUIPO Y HERRAMIENTA
%MO HERRAMIENTA MENOR % $882.67 0.060000 $52.96
Importe: $52.96
Rendimiento: 10.000000 $5.30
Subtotal: EQUIPO Y HERRAMIENTA $5.30
Costo directo $145.74
INDIRECTOS 12.500% $18.22
SUBTOTAL $163.96
FINANCIAMIENTO 0% $0.00
SUBTOTAL $163.96
UTILIDAD 7.954% $13.04
PRECIO UNITARIO $177.00
23-May-2011
SOLUCIONES DE INGENIERIA APLICADA S. A. DE C. V.
Cliente : INFRAESTRUCTURA COMPLEMENTARIA DE LA SECRETARIA DE COMUNICACIONES, GOBIERNO DEL ESTADO
DE VERACRUZ.
Concurso No.
MATERIALES
Tubería Hidraulica de 4" Ml. $70.00 0.250000 $17.50
Subtotal: MATERIALES $17.50
MANO DE OBRA
OFICIAL DE 1A. JOR $475.31 1.000000 $475.31
AYUDANTE DE OFICIAL JOR $313.69 1.000000 $313.69
CABO DE OFICIOS JOR $936.74 0.100000 $93.67
Importe: $882.67
Rendimiento: 16.000000 $55.17
Subtotal: MANO DE OBRA $55.17
EQUIPO Y HERRAMIENTA
%MO HERRAMIENTA MENOR % $882.67 0.060000 $52.96
Importe: $52.96
Rendimiento: 16.000000 $3.31
Subtotal: EQUIPO Y HERRAMIENTA $3.31
Costo directo $75.98
INDIRECTOS 12.500% $9.50
SUBTOTAL $85.47
FINANCIAMIENTO 0% $0.00
SUBTOTAL $85.47
UTILIDAD 7.954% $6.80
PRECIO UNITARIO $92.27
(* UN MIL SEISCIENTOS CUARENTA Y NUEVE PESOS 10/100 M.N. *)
23-May-2011
SOLUCIONES DE INGENIERIA APLICADA S. A. DE C. V.
Cliente : INFRAESTRUCTURA COMPLEMENTARIA DE LA SECRETARIA DE COMUNICACIONES, GOBIERNO DEL ESTADO
DE VERACRUZ.
Concurso No.
MATERIALES
Junta Calzada de 5 cm de separación Ml. $3,500.00 1.100000 $3,850.00
Subtotal: MATERIALES $3,850.00
MANO DE OBRA
OFICIAL DE 1A. JOR $453.00 1.000000 $453.00
AYUDANTE DE OFICIAL JOR $290.78 1.000000 $290.78
CABO DE OFICIOS JOR $892.00 0.100000 $89.20
Importe: $832.98
Rendimiento: 8.000000 $104.12
Subtotal: MANO DE OBRA $104.12
EQUIPO Y HERRAMIENTA
%MO HERRAMIENTA MENOR % $832.98 0.060000 $49.98
Importe: $49.98
Rendimiento: 8.000000 $6.25
Subtotal: EQUIPO Y HERRAMIENTA $6.25
Costo directo $3,960.37
INDIRECTOS 12.500% $495.05
SUBTOTAL $4,455.42
FINANCIAMIENTO 0% $0.00
SUBTOTAL $4,455.42
UTILIDAD 7.954% $354.38
PRECIO UNITARIO $4,809.80
(* UN MIL SEISCIENTOS CUARENTA Y NUEVE PESOS 10/100 M.N. *)
23-May-2011
SOLUCIONES DE INGENIERIA APLICADA S. A. DE C. V.
Cliente : INFRAESTRUCTURA COMPLEMENTARIA DE LA SECRETARIA DE COMUNICACIONES, GOBIERNO DEL ESTADO
DE VERACRUZ.
Concurso No.
Suministro e Instalación de Anclas Tipo Escuadra en Material Cold Rolled AISI 1018 de
1"Ø x 30 cm de desarrollo para el Montaje del Herraje del Paramento Metálico, de
acuerdo a Planos.
MATERIALES
Ancla Cold Rolle AISI 1018,1!Ø x 30 cm Pza $175.00 1.100000 $192.50
Subtotal: MATERIALES $192.50
MANO DE OBRA
OFICIAL DE 1A. JOR $453.00 1.000000 $453.00
AYUDANTE DE OFICIAL JOR $290.78 1.000000 $290.78
CABO DE OFICIOS JOR $892.00 0.100000 $89.20
Importe: $832.98
Rendimiento: 12.000000 $69.42
Subtotal: MANO DE OBRA $69.42
EQUIPO Y HERRAMIENTA
%MO HERRAMIENTA MENOR % $832.98 0.060000 $49.98
Importe: $49.98
Rendimiento: 12.000000 $4.16
Subtotal: EQUIPO Y HERRAMIENTA $4.16
Costo directo $266.08
INDIRECTOS 12.500% $33.26
SUBTOTAL $299.34
FINANCIAMIENTO 0% $0.00
SUBTOTAL $299.34
23-May-2011
SOLUCIONES DE INGENIERIA APLICADA S. A. DE C. V.
Cliente : INFRAESTRUCTURA COMPLEMENTARIA DE LA SECRETARIA DE COMUNICACIONES, GOBIERNO DEL ESTADO
DE VERACRUZ.
Concurso No.
MATERIALES
Placa Acero al Carbón Kg. $17.51 21.300000 $372.96
Oxigeno M3. $92.80 0.220000 $20.42
Acetileno Kg. $301.60 0.100000 $30.16
Disco abrasivo de 7"Ø y 1/4" de espesor Pza. $52.00 0.125000 $6.50
Soldadura 7018 Kg. $60.15 0.350000 $21.05
Cepillo de alambre Pza. $28.00 0.250000 $7.00
Subtotal: MATERIALES $458.09
MANO DE OBRA
Oficial Pailero JOR $498.97 1.000000 $498.97
Oficial Soldador JOR $498.97 1.000000 $498.97
Ayudante Obra Mecánica JOR $290.78 2.000000 $581.56
Cabo JOR $824.25 0.200000 $164.85
Importe: $1,579.50
Rendimiento: 200 Kg./ Jor. 8.000000 $197.44
Subtotal: MANO DE OBRA $197.44
EQUIPO Y HERRAMIENTA
23-May-2011
SOLUCIONES DE INGENIERIA APLICADA S. A. DE C. V.
Cliente : INFRAESTRUCTURA COMPLEMENTARIA DE LA SECRETARIA DE COMUNICACIONES, GOBIERNO DEL ESTADO
DE VERACRUZ.
Concurso No.
MATERIALES
Tubo Galvanizado 2"Ø ced.40 Ml. $149.66 1.080000 $161.63
Oxigeno M3. $92.80 0.105600 $9.80
Acetileno Kg. $301.60 0.038500 $11.61
Disco abrasivo de 7"Ø y 1/4" de espesor Pza. $52.00 0.027500 $1.43
Soldadura 7018 Kg. $60.15 0.160000 $9.62
Cepillo de alambre Pza. $28.00 0.055000 $1.54
Subtotal: MATERIALES $195.64
MANO DE OBRA
Oficial Pailero JOR $498.97 1.000000 $498.97
Oficial Soldador JOR $498.97 1.000000 $498.97
Ayudante Obra Mecánica JOR $290.78 2.000000 $581.56
Cabo JOR $824.25 0.200000 $164.85
Importe: $1,579.50
Rendimiento: 200 Kg./ Jor. 40.000000 $39.49
Subtotal: MANO DE OBRA $39.49
EQUIPO Y HERRAMIENTA
23-May-2011
SOLUCIONES DE INGENIERIA APLICADA S. A. DE C. V.
Cliente : INFRAESTRUCTURA COMPLEMENTARIA DE LA SECRETARIA DE COMUNICACIONES, GOBIERNO DEL ESTADO
DE VERACRUZ.
Concurso No.
Materiales y Mano de Obra para la Aplicación de Pintura Alquidalica Amarillo Trafico sobre superficie
metálica del parapeto. Incluye la Limpieza Mecánica.
MATERIALES
Pintura Alquidalica Amarillo Trafico Comex Lt. $102.32 0.250000 $25.58
Thiner Lt. $28.50 0.120000 $3.42
Brocha de 6" Pza $65.60 0.002752 $0.18
Trazo y nivelación con equipo topográfico, estableciendo ejes de referencia y bancos de nivel,
incluye: Materiales, mano de obra, equipo y herramienta.
MATERIALES
MADERA DE PINO DE 3A. EN BARROTE DE 2" PT $9.38 0.006000 $0.06
X4"X8'
CLAVO DE 2 1/2" A 3 1/2" KG $15.30 0.002500 $0.04
PINTURA ESMALTE COMEX 100 LT $99.50 0.000400 $0.04
CALHIDRA EN SACO TON $1,241.38 0.000050 $0.06
HILO PLASTICO CAL. 10 ROLLO $70.00 0.001000 $0.07
Subtotal: MATERIALES $0.27
MANO DE OBRA
TOPOGRAFO JOR $823.00 1.000000 $823.00
CADENEROS JOR $290.78 2.000000 $581.56
CABO DE OFICIOS JOR $892.00 0.100000 $89.20
Importe: $1,493.76
Rendimiento: 500.000000 $2.99
23-May-2011
SOLUCIONES DE INGENIERIA APLICADA S. A. DE C. V.
Cliente : INFRAESTRUCTURA COMPLEMENTARIA DE LA SECRETARIA DE COMUNICACIONES, GOBIERNO DEL ESTADO
DE VERACRUZ.
Concurso No.
Desmonte Tipo Mediano con Maquinaria sobre la franja donde se contruíra el cuerpo del
terraplén
MATERIALES
Subtotal: MATERIALES $0.00
MANO DE OBRA
AYUDANTE DE OFICIAL JOR $313.69 10.000000 $3,136.90
CABO DE OFICIOS JOR $936.74 0.100000 $93.67
Importe: $3,230.57
Rendimiento: 2.000000 $1,615.29
Subtotal: MANO DE OBRA $1,615.29
EQUIPO Y HERRAMIENTA
%MO HERRAMIENTA MENOR % $3,230.57 0.050000 $161.53
23-May-2011
SOLUCIONES DE INGENIERIA APLICADA S. A. DE C. V.
Cliente : INFRAESTRUCTURA COMPLEMENTARIA DE LA SECRETARIA DE COMUNICACIONES, GOBIERNO DEL ESTADO
DE VERACRUZ.
Concurso No.
MATERIALES
Subtotal: MATERIALES $0.00
MANO DE OBRA
AYUDANTE DE OFICIAL JOR $313.69 2.000000 $627.38
CABO DE OFICIOS JOR $936.74 0.100000 $93.67
Importe: $721.05
Rendimiento: 1,300.00 $0.55
Subtotal: MANO DE OBRA $0.55
23-May-2011
SOLUCIONES DE INGENIERIA APLICADA S. A. DE C. V.
Cliente : INFRAESTRUCTURA COMPLEMENTARIA DE LA SECRETARIA DE COMUNICACIONES, GOBIERNO DEL ESTADO
DE VERACRUZ.
Concurso No.
MATERIALES
AGUA M3 $10.00 0.200000 $2.00
Material de Banco M3 $18.38 1.300000 $23.89
Subtotal: MATERIALES $25.89
MANO DE OBRA
AYUDANTE DE OFICIAL JOR $313.69 2.000000 $627.38
23-May-2011
SOLUCIONES DE INGENIERIA APLICADA S. A. DE C. V.
Cliente : INFRAESTRUCTURA COMPLEMENTARIA DE LA SECRETARIA DE COMUNICACIONES, GOBIERNO DEL ESTADO
DE VERACRUZ.
Concurso No.
44. x1.12500x1.07954=
Material de Banco $25.89 1.2144825 $31.45
Formación terraplen $19.26 1.2144825 $23.40
$54.84
Corte con Maquinaria en Material Tipo II, Zona " B " hasta 40 cm. De Profundidad para
llegar al Nivel de Subrasante.
MATERIALES
Materiales y Equipo para la construcción de Base con Material de Banco ( Material Grava
en Greña y Material Arcilloso ), Mezclado, tendido y compactado con Maquinaria en
capas de 20 cm. Adicionando humedad necesaria para alcanzar el grado de
compactación del 95% del pvsm.
MATERIALES
AGUA M3 $10.00 0.200000 $2.00
23-May-2011
SOLUCIONES DE INGENIERIA APLICADA S. A. DE C. V.
Cliente : INFRAESTRUCTURA COMPLEMENTARIA DE LA SECRETARIA DE COMUNICACIONES, GOBIERNO DEL ESTADO
DE VERACRUZ.
Concurso No.
Suma 1553.05
1.125000
1.079540 1.214483
11.55
15.18
21.30 Kg,
1 ML =5.50 KG.
COSTO DE EQUIPO DE PROTECCIÓN
3.-Vacaciones
L.F.T. Articulo 76 : 6Dias
TOTALES
2015 MARAN
RO DE ENFERMEDADES Y MATERNIDAD
ASEGURADOS DE LAS PRESTACIONES EN DINERO DE LOS GASTOS MÉDICOS A PENSIONADOS
CANTIDAD PRIMA TOTAL DIARIA SALARIO BASE % QUE CORRESPONDE PRIMA TOTAL DIARIA SALARIO BASE % QUE CORRESPONDE PRIMA TOTAL DIARIA
QUE CORRESPONDEN DE COTIZACIÓN PAGAR AL PATRÓN. QUE CORRESPONDEN DE COTIZACIÓN PAGAR AL PATRÓN. QUE CORRESPONDEN
SALARIO BASE % QUE CORRESPONDE PRIMA TOTAL DIARIA CASO SALARIO BASE % QUE CORRESPONDE PRIMA TOTAL DIARIA
DE COTIZACIÓN PAGAR AL PATRÓN. QUE CORRESPONDEN DE COTIZACIÓN PAGAR AL PATRÓN. QUE CORRESPONDEN
86.940 49.419
DEL SEGURO DEL RETIRO ( SAR) DEL SEGURO DE CESANTÍA EN EDAD AVANZADA Y VEJEZ DEL SEGURO DE RIESGOS DE TRABAJO
SALARIO BASE % QUE CORRESPONDE PRIMA TOTAL DIARIA SALARIO BASE % QUE CORRESPONDE PRIMA TOTAL DIARIA SALARIO BASE % QUE CORRESPONDE
DE COTIZACIÓN PAGAR AL PATRÓN. QUE CORRESPONDEN DE COTIZACIÓN PAGAR AL PATRÓN. QUE CORRESPONDEN DE COTIZACIÓN PAGAR AL PATRÓN.
98.837 156.493
PRIMA TOTAL DIARIA SALARIO BASE % QUE CORRESPONDE CUOTA TOTAL DIARIA
375.025 247.093
EN RELACIÓN CON EL
SALARIO D. INTEGRADO
0.441315
0.417538
0.301934
0.294398
0.290797
0.289129
0.287540
0.287447
0.287920
0.287917
0.282191
0.269227
0.262794
0.260059
0.256793
0.255657
0.252502
0.3636
ANÁLISIS DE LAS PRESTACIONES DE SEGURIDAD SOCIAL PAGADAS POR EL TRABAJADOR.
DEL SEGURO DE ENFERMEDADES Y MA
DE LAS PRESTACIONES EN ESPECIE DE LOS ASEGURADOS
CASO CONSISTENTE EN SALARIO FACTOR SALARIO CANTIDAD DIF. ENTRE TRES P. PRESTAC.
CUOTA F. DE PRESTACIONES
TOTALES
L TRABAJADOR. 2012 ICA-FLUOR DANIELS, S.A.de C.V.
RO DE ENFERMEDADES Y MATERNIDAD
SEGURADOS DE LAS PRESTACIONES EN DINERO DE LOS GASTOS MÉDICOS A PENSIONADOS
CANTIDAD PRIMA TOTAL DIARIA SALARIO BASE % QUE CORRESPONDE PRIMA TOTAL DIARIA SALARIO BASE % QUE CORRESPONDE PRIMA TOTAL DIARIA
QUE CORRESPONDEN DE COTIZACIÓN PAGAR AL PATRÓN. QUE CORRESPONDEN DE COTIZACIÓN PAGAR AL PATRÓN. QUE CORRESPONDEN
SALARIO BASE % QUE CORRESPONDE PRIMA TOTAL DIARIA CASO SALARIO BASE % QUE CORRESPONDE PRIMA TOTAL DIARIA SALARIO BASE
DE COTIZACIÓN PAGAR AL PATRÓN. QUE CORRESPONDEN DE COTIZACIÓN PAGAR AL PATRÓN. QUE CORRESPONDEN DE COTIZACIÓN
22.393 0.000
2012
EL SEGURO DEL RETIRO ( SAR) DEL SEGURO DE CESANTÍA EN EDAD AVANZADA Y VEJEZ DEL SEGURO DE RIESGOS DE TRABAJO
% QUE CORRESPONDE PRIMA TOTAL DIARIA SALARIO BASE % QUE CORRESPONDE PRIMA TOTAL DIARIA SALARIO BASE % QUE CORRESPONDE PRIMA TOTAL DIARIA
PAGAR AL PATRÓN. QUE CORRESPONDEN DE COTIZACIÓN PAGAR AL PATRÓN. QUE CORRESPONDEN DE COTIZACIÓN PAGAR AL PATRÓN. QUE CORRESPONDEN
SALARIO FACTOR DE INTEGRACIÓN SALARIO TOTAL FACTOR QUE REPRES. FACTOR QUE REPRES.
CASO DIARIO SALARIO (INCLUYE PRIMA BASE DE DE EN RELACIÓN CON EL EN RELACIÓN CON EL
65.15 0.000
65.16 0.000
83.62 0.000
104.52 0.000
130.29 0.000
130.65 0.000
156.78 0.000
195.44 0.000
195.45 0.000
195.46 0.000
209.04 0.000
235.17 0.000
261.30 0.000
313.56 0.000
365.82 0.000
418.08 0.000
522.60 0.000
0.000
OBRA: Calle Casa Maran
Fecha:27 de Mayo,2015
C A T A L O G O DE S A L A R I O S.