You are on page 1of 26

Work Permit Receiver’s Guess question is only the idea that

what type of question Can come.

Prepared by:-

S.M.NEMATULLAH
1) What type of permit is needed when opening a
line or drainage a vessel?

•Hot & Cold

•Hot & Confined Space

Correct •Release & Cold Permit

•Release & Confined Space


2) What type of permit is required when working on
or in the close proximity to live Electrical
apparatus or vehicle entry into a plant ?

•Cold & Confined Space Permit

•Hot & Confined Space Permit

•Release & Cold Permit

Correct •Hot Work Permit


3) Hold Tags and locks are primarily intended to
protect the individual doing the work from ?

•Leaving until the work is completed

Correct •Being injured in case of accidental start up

•To work safely

•None of the above


4) What type of work permit is for sealed radioactive
sources ?

•Hot Work Permit

Correct •Cold Work Permit

•Hot / Release Work Permit

•Release & Cold Work Permit


5) After the Hold Tag / Lock out system has been
installed. What the issuer will do?

•Proceed to work

•Stop the Job

Correct •To check by manual switch

•Issue the permit


6) Can you work even without a work permit ?

•No

•Obtain a Work Permit first

•In the Restricted area only

Correct •Yes, in case of Emergency


7) In Lock out system, how many pad locks required
if 4 different contractors ?

•3 Pad Locks

•2 Pad Locks

Correct •5 Pad Locks


•4 Pad Locks
8) If there is one machine who is uses by welder and
electrician, how many work permit require ?

•1 work permit

Correct •2 work permit


•Each job require permit

•All of the above


9) After the completion of work ?

•The receiver will leave the area

•Extend the permit

•Put barricade

Correct •Close the permit


10) When operations install a lock out device, what
should you do before starting work ?

Correct •Check the switches again to make sure it is isolated

•Work Safely

•Visually ensure the lock is on the right breaker

•None of the Above


11) A work permit can be approved for ?

•8 hours

•16 hours

•30 days

Correct •All of the above


12) When operations determine a joint job site
visit is not required, they must ?

Correct •Explain on the permit Why not ?

•Advise their Superintendent

•Involve Loss Prevention

•Issue a cold work permit


13) Who is responsible for specifying
precautions so the work can be done
without incident ?

•Foreman

•Receiver

Correct •Issuer

•Department Manager
14) Who is responsible for performing the
work in accordance with the conditions
and requirement agreed upon with the
issuer?
•Safety Department

Correct •Receiver
•Issuer

•SAPMT
15) What type of permit needed when erecting
a scaffold inside the tank ?

•Cold and Release

•Hot and Cold

•Release

Correct •Hot or Cold & Confined Space


16) Who can forcefully remove an isolation
lock when the owner of the lock can not be
found ?

•Shift Superintendent

•Shift Foreman

Correct •Shift Superintendent or Shift Foreman


•None of Them
17) When the maintenance or construction
groups are working on de-energized
equipment, who will be the first person to
install a lock out lock ?
•Receiver

Correct •Operation Person

•Craftsman

•None of These
18) When the work permit is extended into a
second operation shift, which is required
to sign ?

•Receiver only

•Issuer only

Correct •Both Receiver & Issuer


•Superintendent
19) When does a joint site inspection not
required ?

•Low Risk Job

•When first arriving to the plant

Correct •In case of emergencies however, work permit


should be issued as soon as possible.
•All of the above
20) Work that develops sparks, flames or heat
sufficient to cause ignition, what type of
permit required ?

•Cold & Confined Space

•Release only

•Hot or Release work permit

Correct •Hot work Permit


21) When you smell H2S gas at the job site,
what should you do ?

•Contact Loss Prevention

•Continue working and conduct a gas test yourself

Correct •Stop work and inform the issuer to conduct a gas


test.
•Use gas mask
22) What is the type of permit is required for
sand blasting ?

Correct •Hot Work Permit


•Cold Work Permit

•Confined Space Permit

•Cold & Release permit


23) Within how many feet of a power line is a
work permit required ?

•100 feet

Correct •200 feet


•Between goal post

•100 meters
24) During welding operation where’s your fire
extinguishers located at ?

•Welding Truck

•Down wind position

•Crane or any equipment

Correct •Upwind position


25) In H2S breathing apparatus not required or
safe work condition ?

•15 PPM

•100 PPM

Correct •10 PPM below


•10 PPM