FINANCE DEPARTMENT

MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)


DISTRICT GUJRANWALA
Prepared & Compiled by Haroon Tahir
haroon.aro.fd@gmail.com
TABLE OF CONTENTS
Ch.No. Chapter Page No.
1 Carriage 3 to 23
2 Loading, Unloading & Stacking 24 to 26
3 Earthwork (Excavation & Embankment) 27 to 33
4 Dismantling (Demolition) 34 to 38
5 Mortar. 39 to 40
6 Concrete 41 to 51
7 Brickwork 52 to 57
8 Stone Masonry 58 to 60
9 Roofing 61 to 67
10 Flooring. 68 to 74
11 Surface Rendering 75 to 79
12 Wood Work 80 to 91
13 Painting & Varnishing. 92 to 98
14 Lining of Canals 99 to 100
15 Sheet Piling 101 to 102
16 Protection & Diversion Work 103 to 112
17 Outlets 113 to 114
18 Road & Road Structure 115 to 124
19 Plumbing, Sanitary Installation & Gas Fittings 125 to 133
20 Surface Drainage. 134 to 135
21 Sewerage 136 to 140
22 Sinking of Wells 141 to 143
23 Tubewell & Water Supply 144 to 165
24 Electric Installation 166 to 202
25 Iron Work 203 to 211
26 Miscellaneous 212 to 216
27 Heating Ventilation & Air Conditioning 217 to 224
1. CARRIAGE
Note: 1 The rates are applicable to carriage of material on pacca roads only.
For kacha roads an allowance of 25% extra shall be allowed for 2nd and subsequent mileage (Km) rates. Rate
upto 1st mile (1st Km) is however common to both kacha and pacca roads.

Note: 2 For hilly areas 80% above the rates in the plain areas shall be allowed for total mileage (Km) covered.

Note: 3 In case of articles longer than 15 ft. (4.6 m) carried in trucks, the following rates shall be allowed:-

i) Above 15 ft. to 25 ft. (4.6 to 7.6 m) :- Total rates to be paid for 15 ft. to 25 ft. (4.6 to 7.6 m) length will be 1.5 times of the
rate given in the Composite Schedule of Rates.

ii) Above 25 ft. (7.6 m) :- The total rate to be paid for above 25 ft. (7.6 m) length will be 2 times of the rate given in the
Composite Schedule of Rates.

The length measured shall not be the actual length, but the length of the form of consignment as actually
received.

Note: 4 The term 'mile' (Km) whenever used is to mean statute mile (Km).

Note: 5 The rates include loading and unloading of material from the conveyance and stacking as directed.

Note: 6 The rates for carriage by boat or steamer shall be the same as by any other mechanical means on land.
MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. Unit of Unit of No.
M /ment Labour Composite M /ment Labour Composite
1 Carriage of 100 Cft. (2.83 cu.m) of all materials like stone 16.1 Add 20% extra for the item
aggregate, spawl, kankar lime (unslaked), surkhi, etc. or "Recouping of Reserve Stock of stone
150 Cft. (4.25 cu.m) of timber, by truck or by any other for Flood Protection Work in
means owned by the contractor. Irrigation Department".
1st chain (1st 30 m) Chain 280.45 30M 280.45
2nd chain (2nd 30 m) " 51.40 30M 51.40
3rd to 10th chain (60 to 300 m) " 32.10 30M 32.10
1000 to 3000 ft. (300 to 900 m) 1000 ft. 314.85 300 M 314.85
1st Km Km 299.80
2nd Km Km 145.45
3rd Km Km 117.00
4th Km Km 85.40
5th Km Km 80.25
6th Km Km 79.10
7th Km Km 74.30
8th Km Km 73.60
9th Km Km 69.60
10th Km Km 65.75
11th Kms to 200Kms Km 57.30
201 Kms to 250 Kms Km 3.25
251 Kms & susequent Kms Km 2.00

Chap-1 (Carriage) Page 3


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. Unit of Unit of No.
M /ment Labour Composite M /ment Labour Composite
2 Carriage of 5 tons of all material like coal, stone lime 16.1 Cement carried in containers other
(unslaked), etc. B.G. Rail fastenings, points and crossing, than bags will be paid according to
Bridge Girders, pipes, sheets, Rail, M.S. bars, etc. etc. this item. The word "pipes" covers
by truck or any other means owned by the contractor. G.I,C.I,R.C.C. and P.C.C.

1st chain (1st 30 m) Chain 280.45 30M 280.45


2nd chain (2nd 30 m) " 51.40 30M 51.40
3rd to 10th chain (60 to 300 m) " 32.10 30M 32.10
1000 to 3000 ft. (300 to 900 m) 1000 Ft. 314.85 300M 314.85
1st Km Km 299.80
2nd Km Km 145.45
3rd Km Km 117.00
4th Km Km 85.40
1st mile Mile 482.45
5th Km Km 80.25
2nd mile " 135.50
6th Km Km 79.10
3rd mile Mile 125.30
7th Km Km 74.30
4th mile " 116.25
8th Km Km 73.60
5th mile 108.90
9th Km Km 69.60
6th mile 103.15
10th Km Km 65.75
1 " 75.95
11th Kms to 200Kms Km 57.30
201 Kms to 250 Kms Km 3.25
251 Kms & susequent Kms Km 2.00
3 Carriage of 100 maunds of fuel wood by truck 16.1
or any other means owned by the contractor:
1st chain (1st 30 m) Chain 280.45 30 M 280.45
2nd chain (2nd 30 m) " 51.40 30 M 51.40
3rd to 10th chain (60 to 300 m) " 32.10 30 M 32.10
1000 to 3000 ft. (300 to 900 m) 1000 ft 314.85 300 M 314.85
1st Km Km 299.80
2nd Km Km 145.45
3rd Km Km 117.00
4th Km Km 85.40
1st mile Mile 482.45
5th Km Km 80.25
2nd mile " 135.50
6th Km Km 79.10
3rd mile " 125.30
7th Km Km 74.30
4th mile " 116.25
8th Km Km 73.60
5th mile " 108.90
9th Km Km 69.60
6th mile " 103.15

Chap-1 (Carriage) Page 4


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. Unit of Unit of No.
M /ment Labour Composite M /ment Labour Composite
10th Km Km 65.75
7th mile and subsequent miles " 75.95
11th & subsequent Kms Km 57.30
4 Carriage of 1000 Nos. bricks 10"x5"x3" (250x125x75 mm) ditto Reduce the rate by 33% in case of
or 1000 Nos. tiles 12"x6"x2" (300x150x50 mm) by truck or carriage of 1000 Nos. tiles size
any other means owned by the contractor :- 12"x6"x1¼" (300 x 150 x 30 mm).
1st chain (1st 30 m) Chain 280.45 30 M 280.45
2nd chain (2nd 30 m) " 51.40 30 M 51.40
3rd to 10th chain (60 to 300 m) " 32.10 30 M 32.10
1000 to 3000 ft. (300 to 900 m) 1000 Ft 314.85 300 M 314.85
1st Km Km 299.80
2nd Km Km 145.45
3rd Km Km 117.00
4th Km Km 85.40
1st mile Mile 482.45
5th Km Km 80.25
2nd mile " 135.50
6th Km Km 79.10
3rd mile " 125.30
7th Km Km 74.30
4th mile " 116.25
8th Km Km 73.60
5th mile " 108.90
9th Km Km 69.60
6th mile " 103.15
10th Km Km 65.75
7th mile and subsequent miles " 75.95
11th & subsequent Kms Km 57.30
5 Carriage of 100 cft. (2.83 cu.m) of all material like stone, 16.1 Material trolly to be supplied by the
aggregate, spawl, kankar lime(unslaked), surkhi, etc. or Government and maintained and run
150 cft. (4.25 cu.m) of timber, by means of material trolly. by the contractor.
1st chain (1st 30 m) Chain 280.45 30 M 280.45
2nd chain to 10th chain (2nd 30 m to 300 m) " 51.40 30 M 51.40
1000 to 3000 ft. (300 to 900 m) 1000 Ft. 314.85 300 M 314.85
1st Km Km 245.90
2nd Km Km 193.55
3rd Km Km 111.05
4th Km
1st mile Mile 395.70 Km 90.20
5th
2ndKm
mile 162.60 Km 80.50
6th Km
3rd mile 141.50 Km 77.50
7th Km Km 66.25
8th Km Km 65.60
9th
6th Km
mile 103.15 Km 62.05
10thmile
7th Km and subsequent miles 75.95 Km 58.60
11th Kms to 200Kms Km 52.90
201 Kms to 250 Kms Km 3.25
251 Kms & susequent Kms Km 2.00

Chap-1 (Carriage) Page 5


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. Unit of Unit of No.
M /ment Labour Composite M /ment Labour Composite
6 Carriage of 5 tons of all material like coal, stone lime 16.1 Material trolly to be supplied by the
(unslaked), etc. B.G. Rail fastening, points and crossing, Government and maintained and run
Bridge girders, pipes, sheets, Rail, M.S. bars, etc. etc. by by the contractor.
means of material trolly.
1st chain (1st 30 m) Chain 280.45 30 M 280.45
2nd chain (2nd 30 m) " 51.40 30 M 51.40
1000 to 3000 ft. (300 to 900 m) 0/00 Ft. 314.85 300 M 314.85
1st Km Km 245.90
2nd Km Km 193.55
3rd Km Km 111.05
4th Km Km 90.20
5th Km Km 80.50
6th
3rd Km
mile and subsequent miles 141.5 Km 77.50
7th
4th Km
mile 116.25 Km 66.25
8th Km Km 65.60
9th Km Km 62.05
10th Km q Km 58.60
11th Kms to 200Kms Km 52.90
201 Kms to 250 Kms Km 3.25
251 Kms & susequent Kms Km 2.00
7 Carriage of 100 maunds of fuel wood, by means of ditto Material trolly to be supplied
material trolly. by the Government and
1st chain (1st 30 m) Chain 280.45 30 M 280.45 maintained and run by the
2nd chain (2nd 30 m) " 51.4 30 M 51.40 contractor.
1000 to 3000 ft. (300 to 900 m) 1000 Ft 314.85 300 M 314.85
1st Km Km 245.90
2nd Km Km 193.55
3rd Km Km 111.05
4th Km Km 90.20
1st mile Mile 395.70
5th Km Km 80.50
2nd mile " 162.60
6th Km Km 77.50
3rd mile subsequent miles " 141.50
7th Km Km 66.25
4th mile 116.25
8th Km Km 65.60
5th mile 108.90
9th Km Km 62.05
6th mile 103.15
10th Km Km 58.60
7th mile and subsequent miles 75.95
11th & subsequent Kms Km 52.90
8 Carriage of 1000 Nos. tiles 12"x6"x2" (300x150x50 mm), ditto Material trolly to be supplied by the
by means of material trolly. Government and maintained and run
1st chain (1st 30 m) Chain 280.45 30 M 280.45 by the contractor.
2nd chain (2nd 30 m) " 51.40 30 M 51.40
1000 to 3000 ft. (300 to 900 m) 0/00 Ft. 314.85 300 M 314.85
1st Km Km 245.90

Chap-1 (Carriage) Page 6


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. Unit of Unit of No.
M /ment Labour Composite M /ment Labour Composite
2nd Km Km 193.55 16.1
3rd Km Km 111.05
4th Km Km 90.20
1st mile Mile 395.70
5th Km Km 80.50
2nd mile " 162.60
6th Km Km 77.50
3rd mile subsequent miles " 141.50
7th Km Km 66.25
4th mile 116.25
8th. Km 65.60
5th mile 108.90
9th Km Km 62.05
6th mile 103.15
10th Km Km 58.60
7th mile and subsequent miles 75.95
11th & subsequent Kms Km 52.90
9 Carriage of 1000 No. bricks, 9"x4½"x3" ditto
(225x113x75 mm) or 8"x4"x4" (200x100x100
mm) (nominal)
1st chain (1st 30 m) Chain 229.78 30 M 229.78
2nd chain (2nd 30 m) " 49.95 30 M 49.95
3rd to 10th chain (60 to 300 m) " 26.35 30 M 26.35
1000 to 3000 ft. (300 to 900 m) 0/00 Ft. 257.77 300 M 257.77
1st Km Km 245.75
2nd Km Km 118.95
3rd Km Km 95.80
4th Km Km 70.45
1st mile Mile 395.50
5th Km Km 67.75
2nd mile " 111.05
6th Km Km 66.35
3rd mile " 106.00
7th Km Km 60.85
4th mile " 95.30
8th Km Km 60.25
5th mile " 89.20
9th Km Km 56.95
6th mile " 84.50
10th Km Km 53.85
7th mile and subsequent miles " 62.30
11th & subsequent Kms Km 46.80
10 Carriage of 1000 No. tiles 9"x4½"x1½" 16.1
(225x113x38 mm).
1st chain (1st 30 m) Chain 138.68 30 M 138.68
2nd chain (2nd 30 m) " 25.39 30 M 25.39 16.1
3rd to 10th chain (60 to 300 m) " 15.75 30 M 15.75
1000 to 3000 ft. (300 to 900 m) 0/00 Ft. 155.72 300 M 155.72
1st Km Km 148.35

Chap-1 (Carriage) Page 7


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. Unit of Unit of No.
M /ment Labour Composite M /ment Labour Composite
2nd Km Km 72.00
3rd Km Km 57.90
4th Km Km 42.20
1st mile Mile 238.70
5th Km Km 39.45
2nd mile " 67.10
6th Km Km 38.90
3rd mile " 61.55
7th Km Km 36.80
4th mile " 57.55
8th Km Km 36.40
5th mile " 53.85
9th Km Km 34.40
6th mile " 51.10
10th Km Km 32.60
7th mile and subsequent miles " 37.50
11th & subsequent Kms Km 28.35
11 Carriage of 1 Cwt. (50 Kg) cement in bags. ditto

1st chain (1st 30 m) Chain 5.29 30 M 5.29


2nd chain (2nd 30 m) " 0.63 30 M 0.63
3rd to 10th chain (60 to 300 m) " 0.30 30 M 0.30

1000 to 3000 ft. (300 to 900 m) 0/00 Ft. 3.10 300 M 3.10

1st Km Km 3.70
1st mile Mile 5.95
2nd Km Km 2.55
2nd mile " 2.10
3rd Km Km 1.20
3rd mile subsequent miles " 1.10
4th Km and subsequent kilometers. Km 0.75
12 Carriage of 100 Nos. empty cement bags including 16.1
bundling.

1st 1000 (300 m) ft. 0/00 Ft. 77.24 300 M 77.24


1000 to 3000 (300 to 900 m) ft. " 9.62 300 M 9.62

1st Km Km 9.00
1st mile Mile 14.50
2nd Km Km 11.15
2nd mile to 6th mile Mile 1.95
3rd Km Km 4.65
7th mile and subsequent miles " 9.25
4th Km & subsequent Kms Km 4.70
13 Carriage of 100 (2.83 cu.m) cft. of Sarkanda or pilchi, frash ditto Previous lead of collection not
or brushwood, by boat or road :- to be deducted from the next
lead of carriage.

1st chain (1st 30 m) Chain 114.74 30 M 114.74

Chap-1 (Carriage) Page 8


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. Unit of Unit of No.
M /ment Labour Composite M /ment Labour Composite
2nd chain (2nd 30 m) " 51.40 30 M 51.40
3rd to 10th chain (60 to 300 m) " 15.75 30 M 15.75

1000 to 3000 ft. (300 to 900 m) 0/00 Ft. 129.35 300 M 129.35

1st Km Km 142.35
1st mile Mile 212.25
2nd Km Km 72.00
2nd mile " 189.45
3rd Km Km 57.90
3rd mile " 162.80
4th Km Km 42.20
4th mile " 122.15
5th Km Km 39.45
5th mile " 103.35
6th Km Km 38.90
6th mile 84.50
7th Km Km 36.80
7th mile and subsequent miles 62.30
8th Km Km 36.40
9th Km Km 34.40
10th Km Km 32.60
11th Km & subsequent Km 28.35

14 Carriage of light machinery weighing upto 3 tonne Ton Tonne ditto


upto 1000 ft. (300 metre) 0/00 ft. 935.86 300 M 935.86
Exceeding 1000 to 5000 ft (300 to 1500metre) 1000 ft. 226.75 " 226.75

1st Km Km 294.95
1st mile Mile 474.65
2nd Km Km 141.50
2nd mile " 107.10
3rd Km Km 100.95
3rd mile " 104.05
4th Km Km 68.95
4th mile " 85.55
5th Km Km 66.60
5th mile " 88.60
6th Km Km 64.10
6th mile " 70.10
7th Km Km 55.75
7th mile and subsequent miles " 59.40
8th Km Km 55.60
9th Km Km 55.40
10th Km Km 44.70
11th Km & susequent Km 41.00

Chap-1 (Carriage) Page 9


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. Unit of Unit of No.
M /ment Labour Composite M /ment Labour Composite
15 Carriage of small consignments weighing upto 5 maunds 16.1 For consignment weighing 5 to 10
(job rates) : maunds, rate be increased by 25%;
and for consignments weighing 10
Consig- to 20 maunds, rate be increased by
Upto 1000 ft. (300 metre) ment/ 76.00 Consign- 76.00 100%.
1000 ft. ment/
Exceeding 1000 to 3000 ft. (300 to 900 1000 ft. 52.12 300 M 52.12
metre)

1st Km Consign- 46.15


1st mile Consign- 74.30 ment/ Km
2nd Km ment/Mile 29.80
2nd mile and subsequent miles " 16.60 "
3rd Km & subsequent " 10.90
16 Carriage of consignments job.

i) Cooly load for distance:-


Each Each
a) Upto 5 Km Consignment 98.90 Consignment 98.90
b) Above 5 to 13 Km " 274.50 " 274.50

ii) Carriage of consignments odd jobs. Each Each


a) Donkey load for distance upto 500 feet. Consignment 10.85 Consignment 10.85
b) Upto 1000 feet. " 16.45 " 16.45
c) Upto ½ Mile/ 0.8 Km " 20.80 " 20.80
d) Upto one Mile/ 1.6 Km " 26.00 " 26.00
e) Upto three Miles/ 4.8 Km " 45.95 " 45.95
f) Exceeding 3 Miles/ 16 km " 82.25 " 82.25

Each Each
iii) Cart load for a distance :- Consign- Consig-
ment nment
a) upto 4 Miles/ 6.4 Km " 89.85 " 89.85
b) Exceeding 4 Miles(6.4 Km) to10 Miles(16 Km) " 163.55 " 163.55

iv) Camel load for a distance:-

a) upto 4 Miles/ 6.4 Km.) " 66.45 " 66.45


b) exceeding 4 to 12 mills (6.4 Km to 19.2 Km) " 100.75 " 100.75

17 Hire charges of:- 1. This item will be allowed with


prior concurrence of Superintending
i) truck (10 Ton Capacity) Per 4000.00 Per 4,000.00 Engineer.
day day 2. The rate includes pay of driver
ii) tractor with trolly " 12920.00 " 1,000.00 and cleaner only. The repairs shall
be the responsibility of the owner
iii) tractor without trolly " 12920.00 " 800.00 and the cost of lubrication, fuel,

Chap-1 (Carriage) Page 10


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. Unit of Unit of No.
M /ment Labour Composite M /ment Labour Composite
loading and unloading shall be paid
by the borrower.

18 Carriage of bitumen, tar or other lubricants, in drums: 16.1


0 Kilometer to 100 Kilometers P.Ton 1,274.20
0 Kilometer to 200 Kilometers P.Ton 1,665.80
0 Kilometer to 250 Kilometers Per 79.15 P.Ton 1,935.80
251 to susequent Kilometers Ton P.Ton 15.70
2nd mile " 15.80
"
3rd mile 26.00
19 Carriage of Asbestos cement pipes BSS Class 'B" with
comet joint and rubber ring, including loading, unloading
and stacking (rate per 100 Rft. (30 m pipes):-

i) 3" (75 mm) i/d pipes:-


1st chain (1st 30 m) Chain 11.05 30 M 11.05
2nd chain (2nd 30 m) " 2.05 30 M 2.05
3rd to 10th chain (60 to 300 m) " 1.25 30 M 1.25
1000 to 3000 ft. (300 to 900 m) 0/00 Ft. 12.45 300 M 12.45
1st Km Km 11.85
2nd Km Km 5.70
3rd Km Km 4.60
1st mile Mile 19.05
4th Km Km 3.35
2nd mile " 5.35
5th Km Km 3.15
3rd mile " 4.95
6th Km Km 3.05
4th mile " 4.60
7th Km Km 2.90
5th mile " 4.30
8th Km Km 2.85
6th mile " 4.05
9th Km Km 2.70
7th mile and subsequent miles " 3.00
10th Km Km 2.55

11th Km & Susequent Km 2.50

ii) 4" (100 mm) i/d pipes:-

1st chain (1st 30 m) Chain 14.50 30 M 14.50


2nd chain (2nd 30 m) " 2.65 30 M 2.65
3rd to 10th chain (60 to 300 m) " 1.65 30 M 1.65

1000 to 9000 ft. (300 to 900 m) 0/00 Ft. 16.30 300 M 16.30

Chap-1 (Carriage) Page 11


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. Unit of Unit of No.
M /ment Labour Composite M /ment Labour Composite
1st Km Km 15.50
1st mile Mile 24.95
2nd Km Km 7.50
2nd mile " 7.00
3rd Km Km 6.00
3rd mile " 6.50
4th Km Km 4.40
4th mile " 6.00
5th Km Km 4.15
5th mile " 5.65
6th Km Km 4.00
6th mile " 5.35
7th Km Km 3.80
7th mile and subsequent miles " 3.95
8th Km Km 3.70
9th Km Km 3.60
10th Km Km 3.40
11th Km & subsequent Km Km 3.30
iii) 6" (150 mm) i/d pipes:-
1st chain (1st 30 m) Chain 21.75 30 M 21.75
2nd chain (2nd 30 m) " 4.00 30 M 4.00
3rd to 10th chain (60 to 300 m) " 2.50 30 M 2.50
1000 to 9000 ft. (300 to 900 m) 0/00 Ft. 24.45 300 M 24.45
1st Km Km 23.25
2nd Km Km 11.30
3rd Km Km 9.05
1st mile Mile 37.45
4th Km Km 6.60
2nd mile " 10.50
5th Km Km 6.20
3rd mile " 9.70
6th Km Km 6.10
4th mile " 9.00
7th Km Km 5.75
5th mile " 8.45
8th Km Km 5.60
6th mile " 8.00
9th Km Km 5.40
7th mile and subsequent miles " 5.90
10th Km Km 5.05
11th Km & subsequent Km Km 4.65
iv) 8" (200 mm) i/d pipes:

1st chain (1st 30 m) Chain 36.80 30 M 36.80


2nd chain (2nd 30 m) " 6.75 30 M 6.75
3rd to 10th chain (60 to 300 m) " 4.20 30 M 4.20
1000 to 3000 ft. (300 to 900 m) 0/00 Ft. 41.30 300 M 41.30
1st Km Km 39.35

Chap-1 (Carriage) Page 12


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. Unit of Unit of No.
M /ment Labour Composite M /ment Labour Composite
2nd Km Km 20.10
3rd Km Km 15.70
1st mile Mile 63.30
4th Km Km 11.40
2nd mile " 17.80
5th Km Km 10.70
3rd mile " 16.45
6th Km Km 10.55
4th mile " 15.25
7th Km Km 9.90
5th mile " 14.30
8th Km Km 9.70
6th mile " 13.55
9th Km Km 8.50
7th mile and subsequent miles " 9.95
10th Km Km 2.65
11th Km & subsequent Km Km 2.35

v) 10" (250 mm) i/d pipes:-


1st chain (1st 30 m) Chain 49.45 30 M 49.45
2nd chain (2nd 30 m) " 9.05 30 M 9.05
3rd to 10th chain (60 to 300 m) " 5.65 30 M 5.65
1000 to 3000 ft. (300 to 900 m) 0/00 Ft. 55.55 300 M 55.55
1st Km Km 52.90
2nd Km Km 25.55
3rd Km Km 20.50
1st mile Mile 85.10
4th Km Km 14.95
2nd mile " 23.90
5th Km Km 14.05
3rd mile " 22.10
6th Km Km 13.85
4th mile Mile 20.50
7th Km Km 13.25
5th mile " 19.20
8th Km Km 13.10
6th mile " 18.20
9th Km Km 12.40
7th mile and subsequent miles " 13.40
10th Km Km 11.75
11th Km & subsequent Kms Km 10.15

vi) 12" (300 mm) i/d pipes:


1st chain (1st 30 m) Chain 64.30 30 M 64.30
2nd chain (2nd 30 m) " 11.80 30 M 11.80
3rd to 10th chain (60 to 300 m) " 7.35 30 M 7.35
1000 to 3000 ft. (300 to 900 m) 0/00 Ft. 72.20 300 M 72.20
1st Km Km 68.75
2nd Km Km 34.20
3rd Km Km 27.05

Chap-1 (Carriage) Page 13


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. Unit of Unit of No.
M /ment Labour Composite M /ment Labour Composite
4th Km Km 19.40
1st mile Mile 110.65
5th Km Km 18.25
2nd mile " 31.05
6th Km Km 18.00
3rd mile " 28.75
7th Km Km 16.90
4th mile " 26.65
8th Km Km 16.70
5th mile " 25.00
9th Km Km 15.80
6th mile " 23.65
10th Km Km 14.90
7th mile and subsequent miles " 17.40
11th Km & subsequent Kms Km 13.10
vii) 16" (400 mm) i/d pipes:-
1st chain (1st 30 m) Chain 105.45 30 M 105.45
2nd chain (2nd 30 m) " 19.30 30 M 19.30
3rd to 10th chain (60 to 300 m) " 12.05 30 M 12.05
1000 to 3000 ft. (300 to 900 m) 0/00 Ft. 118.35 300 M 118.35
1st Km Km 112.70
2nd Km Km 54.90
3rd Km Km 43.95
1st mile Mile 181.35
4th Km Km 32.10
2nd mile " 50.95
5th Km Km 30.15
3rd mile " 47.10
6th Km Km 29.70
4th mile " 43.70
7th Km Km 27.90
5th mile " 40.95
8th Km Km 27.65
6th mile " 38.80
9th Km Km 26.15
7th mile and subsequent miles " 28.55
10th Km Km 24.70
11th Km & subsequent Kms Km 21.55
viii) 18" (450 mm) i/d pipes:-

1st chain (1st 30 m) Chain 135.50 30 M 135.50


2nd chain (2nd 30 m) " 24.85 30 M 24.85
3rd to 10th chain (60 to 300 m) " 15.50 30 M 15.50
1000 to 3000 ft. (300 to 900 m) 0/00 Ft. 152.10 300 M 152.10
1st Km Km 144.80
2nd Km Km 70.30
3rd Km Km 56.50
1st mile Mile 233.05

Chap-1 (Carriage) Page 14


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. Unit of Unit of No.
M /ment Labour Composite M /ment Labour Composite
4th Km Km 41.25
2nd mile " 65.45
5th Km Km 38.80
3rd mile " 60.55
6th Km Km 38.20
4th mile " 56.15
7th Km Km 35.90
5th mile " 52.60
8th Km Km 35.55
6th mile " 49.85
9th Km Km 33.65
7th mile and subsequent miles " 36.70
10th Km Km 31.80
11th Km & subsequent Kms Km 27.60
ix) 20" (500 mm) i/d pipes:-
1st chain (1st 30 m) Chain 143.80 30 M 143.80
2nd chain (2nd 30 m) " 26.35 30 M 26.35
3rd to 10th chain (60 to 300 m) " 16.45 30 M 16.45
1000 to 3000 ft. (300 to 900 m) 0/00 Ft. 161.45 300 M 161.45
1st Km Km 153.75
2nd Km Km 74.60
3rd Km Km 60.00
1st mile Mile 247.40
4th Km Km 43.80
2nd mile " 69.50
5th Km Km 41.15
3rd mile " 64.25
6th Km Km 40.55
4th mile " 59.60
7th Km Km 38.10
5th mile " 55.85
8th Km Km 37.70
6th mile " 52.90
9th Km Km 35.70
7th mile and subsequent miles " 38.95
10th Km Km 33.70
11th Km & subsequent Kms Km 29.50
x) 24" (600 mm) i/d pipes:-
1st chain (1st 30 m) Chain 159.35 30 M 159.35
2nd chain (2nd 30 m) " 29.20 30 M 29.20
3rd to 10th chain (60 to 300 m) " 18.25 30 M 18.25
1000 to 5000 ft. (300 to 1500 m) 0/00 Ft. 178.90 300 M 178.90
1st Km Km 170.35
2nd Km Km 82.60
3rd Km Km 66.40
1st mile Mile 274.10
4th Km Km 49.00

Chap-1 (Carriage) Page 15


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. Unit of Unit of No.
M /ment Labour Composite M /ment Labour Composite
2nd mile " 77.00
5th Km Km 45.55
3rd mile " 71.20
6th Km Km 44.90
4th mile Mile 66.05
7th Km Km 42.15
5th mile " 61.85
8th Km Km 41.75
6th mile " 58.60
9th Km Km 39.50
7th mile and subsequent miles " 43.15
10th Km Km 37.30
11th Km & subsequent Kms Km 32.45
20 Carriage of PVC pipes B.S.S. Class 'B' including loading,
unloading and stacking (Rate per 1000 ft.) (300 metre) :-

i) 3" (75 mm) i/d pipes:-

1st chain (1st 30 m) Chain 21.70 30 M 21.70


2nd chain (2nd 30 m) " 4.00 30 M 4.00
3rd to 10th chain (60 to 300 m) " 2.50 30 M 2.50
1000 to 3000 ft. (300 to 900 m) 0/00 Ft. 24.35 300 M 24.35
1st Km Km 23.20
2nd Km Km 11.25
3rd Km Km 9.05
1st mile Mile 37.35
4th Km Km 6.60
2nd mile " 10.50
5th Km Km 6.20
3rd mile " 9.70
6th Km Km. 6.10
4th mile " 9.00
7th Km Km 5.75
5th mile Mile 8.45
8th Km Km 5.65
6th mile " 8.00
9th Km Km 5.35
7th mile and subsequent miles " 5.90
10th Km Km 5.05
11th Km & subsequent Kms Km 4.60
ii) 4" (100 mm) i/d pipes:-

1st chain (1st 30 m) Chain 33.45 30 M 33.45


2nd chain (2nd 30 m) " 6.15 30 M 6.15
3rd to 10th chain (60 to 300 m) " 3.85 30 M 3.85
1000 to 3000 ft. (300 to 900 m) 0/00 Ft. 37.55 300 M 37.55
1st Km Km 35.75
2nd Km Km 17.50

Chap-1 (Carriage) Page 16


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. Unit of Unit of No.
M /ment Labour Composite M /ment Labour Composite
3rd Km Km 13.95
1st mile Mile 57.50
4th Km Km 10.10
2nd mile " 16.15
5th Km Km 9.50
3rd mile " 14.95
6th Km Km 9.35
4th mile " 13.85
7th Km Km 8.75
5th mile " 13.00
8th Km Km 8.70
6th mile " 12.30
9th Km Km 8.25
7th mile and subsequent miles " 9.05
10th Km Km 7.75
11th Km & subsequent Kms Km 7.20
iii) 5" (125 mm) i/d pipes:-

1st chain (1st 30 m) Chain 45.60 30 M 45.60


2nd chain (2nd 30 m) " 8.35 " 8.35
3rd to 10th chain (60 to 300 m) " 5.20 " 5.20
1000 to 3000 ft. (300 to 900 m) 0/00 Ft. 51.20 300 M 51.20
1st Km Km 48.75
2nd Km " 23.80
3rd Km " 19.15
1st mile Mile 78.45
4th Km " 14.05
2nd mile " 22.05
5th Km Km. 13.00
3rd mile " 20.40
6th Km " 12.80
4th mile Mile 18.90
7th Km " 12.00
5th mile " 17.70
8th Km 11.90
6th mile " 16.80
9th Km 11.25
7th mile and subsequent miles " 12.35
10th Km 10.65
11th Km & subsequent Kms 9.30
iv) 6" (150 mm) i/d pipes:
1st chain (1st 30 m) Chain 62.90 30 M 62.90
2nd chain (2nd 30 m) " 11.55 30 M 11.55
3rd to 10th chain (60 to 300 m) " 7.20 30 M 7.20
1000 to 3000 ft. (300 to 300 m) 0/00 Ft. 70.60 300 M 70.60
1st Km. Km. 67.20
2nd Km Km. 32.60

Chap-1 (Carriage) Page 17


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. Unit of Unit of No.
M /ment Labour Composite M /ment Labour Composite
3rd Km Km. 26.25
1st mile Mile 108.15
4th Km Km. 19.15
2nd mile " 30.40
5th Km Km. 18.00
3rd mile " 28.10
6th Km Km. 17.75
4th mile " 26.05
7th Km Km. 16.65
5th mile " 24.40
8th Km Km. 16.50
6th mile " 23.15
9th Km Km. 15.60
7th mile and subsequent miles " 17.05
10th Km Km. 14.75
11th Km & subsequent Kms Km. 12.85
v) 8" (200 mm) i/d pipes:-

1st chain (1st 30 m) Chain 110.30 30 M 110.30


2nd chain (2nd 30 m) " 20.20 30 M 20.20
3rd to 10th chain (60 to 300 m) " 12.60 30 M 12.60
1000 to 3000 ft. (300 to 900 m) 0/00 Ft. 123.80 300 M 123.80
1st Km Km 117.90
2nd Km Km 57.20
3rd Km Km 46.00
1st mile Mile 189.70
4th Km Km 33.60
2nd mile " 53.30
5th Km Km 31.55
3rd mile Mile 49.25
6th Km Km 31.10
4th mile " 45.70
7th Km Km 29.20
5th mile " 42.80
8th Km Km 28.95
6th mile " 40.55
9th Km Km 27.35
7th mile and subsequent miles " 29.85
10th Km Km 25.85
11th Km & subsequent Kms Km 22.50
vi) 10" (250 mm) i/d pipes:-
1st chain (1st 30 m) Chain 171.00 30 M 171.00
2nd chain (2nd 30 m) " 31.35 30 M 31.35
3rd to 10th chain (60 to 300 m) " 19.55 30 M 19.55
1000 to 3000 ft. (300 to 900 m) 0/00 Ft. 192.00 300 M 192.00
1st Km Km 182.80
2nd Km Km 88.70

Chap-1 (Carriage) Page 18


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. Unit of Unit of No.
M /ment Labour Composite M /ment Labour Composite
3rd Km Km 71.30
1st mile Mile 294.20
4th Km Km 52.05
2nd mile " 82.60
5th Km Km 48.95
3rd mile " 76.40
6th Km Km 48.20
4th mile " 70.85
7th Km Km 45.30
5th mile " 66.40
8th Km Km 44.85
6th mile " 62.90
9th Km Km 42.45
7th mile and subsequent miles " 46.30
10th Km Km 40.10
11th Km & subsequent Kms Km 35.00
vii) 12" (300 mm) i/d pipes:-

1st chain (1st 30 m) Chain 240.70 30 M 240.70


2nd chain (2nd 30 m) " 44.10 30 M 44.10
3rd to 10th chain (60 to 300 m) " 27.55 30 M 27.55
1000 to 3000 ft. (300 to 900 m) 0/00 Ft. 270.30 300 M 270.30
1st Km Km 257.30
2nd Km Km 124.85
3rd Km Km 100.40
1st mile Mile 414.10
4th Km Km 73.30
2nd mile Mile 116.30
5th Km Km 68.90
3rd mile " 107.55
6th Km Km 67.85
4th mile " 99.75
7th Km Km 63.75
5th mile " 93.50
8th Km Km 63.15
6th mile " 88.55
9th Km Km 59.75
7th mile and subsequent miles " 65.20
10th Km Km 56.40
11th Km & subsequent Kms Km 49.25
viii) 14" (350 mm) i/d pipes:-
1st chain (1st 30 m) Chain 313.35 30 M 313.35
2nd chain (2nd 30 m) " 57.45 30 M 57.45
3rd to 10th chain (60 to 300 m) " 35.85 30 M 35.85
1000 to 3000 ft. (300 to 900 m) 0/00 Ft. 351.80 300 M 351.80
1st Km Km 334.95
2nd Km Km 162.50

Chap-1 (Carriage) Page 19


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. Unit of Unit of No.
M /ment Labour Composite M /ment Labour Composite
3rd Km Km 130.70
1st mile Mile 539.05
4th Km Km 95.40
2nd mile " 151.40
5th Km Km 89.65
3rd mile " 140.00
6th Km Km 88.35
4th mile Mile 129.85
7th Km Km 83.00
5th mile " 121.65
8th Km Km 82.15
6th mile " 115.25
9th Km Km 77.75
7th mile and subsequent miles " 84.85
10th Km Km 73.50
11th Km & subsequent Kms Km 64.10
21 Carriage of PVC pipes B.S.S. Class 'D' including loading,
unloading and stacking (Rates per 1000 ft.):-

i) 2" (50 mm) i/d pipes:-


1st chain (1st 30 m) Chain 15.85 30 M 15.85
2nd chain (2nd 30 m) " 2.90 30 M 2.90
3rd to 10th chain (60 to 300 m) " 1.80 30 M 1.80
1000 to 3000 ft. (300 to 900 m) 0/00 Ft. 17.80 300 M 17.80
1st Km Km 16.95
2nd Km Km 8.25
3rd Km Km 6.60
1st mile Mile 27.30
4th Km Km 4.80
2nd mile " 7.65
5th Km Km 4.55
3rd mile " 7.10
6th Km Km 4.45
4th mile " 6.60
7th Km Km 4.25
5th mile " 6.15
8th Km Km 4.15
6th mile " 5.85
9th Km Km 3.90
7th mile and subsequent miles " 4.30
10Km Km 3.70
11th Km & subsequent Kms Km 3.30
ii) 2½" (63 mm) i/d pipes:-
1st chain (1st 30 m) Chain 24.70 30 M 24.70
2nd chain (2nd 30 m) " 4.50 30 M 4.50
3rd to 10th chain (60 to 300 m) " 2.80 30 M 2.80
1000 to 3000 ft. (300 to 900 m) 0/00 Ft. 27.70 300 M 27.70

Chap-1 (Carriage) Page 20


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. Unit of Unit of No.
M /ment Labour Composite M /ment Labour Composite
1st Km Km 26.40
2nd Km Km 12.85
3rd Km Km 10.30
1st mile Mile 42.45
4th Km Km 7.55
2nd mile " 11.90
5th Km Km 7.10
3rd mile " 11.05
6th Km Km 7.00
4th mile " 10.25
7th Km Km 6.60
5th mile " 9.60
8th Km Km 6.35
6th mile " 9.10
9th Km Km 6.10
7th mile and subsequent miles " 6.70
10Km Km 5.75
11th Km & subsequent Kms Km 5.10
iii) 3" (75 mm) i/d pipes:-
1st chain (1st 30 m) Chain 34.20 30 M 34.20
2nd chain (2nd 30 m) " 6.25 30 M 6.25
3rd to 10th chain (60 to 300 m) " 3.90 30 M 3.90
1000 to 3000 ft. (300 to 900 m) 0/00 Ft. 38.40 300 M 38.40
1st Km Km 36.55
2nd Km Km 17.75
3rd Km Km 14.30
1st mile Mile 58.85
4th Km Km 10.45
2nd mile " 16.55
5th Km Km 9.80
3rd mile " 15.30
6th Km Km 9.65
4th mile " 14.20
7th Km Km 9.10
5th mile Mile 13.30
8th Km Km 9.00
6th mile " 12.60
9th Km Km 8.40
7th mile and subsequent miles " 9.25
10th Km Km 7.95
11th Km & subsequent Kms Km 7.05
iv) 4" (100 mm) i/d pipes:-
1st chain (1st 30 m) Chain 56.60 30 M 56.60
2nd chain (2nd 30 m) " 10.40 30 M 10.40
3rd to 10th chain (60 to 300 m) " 6.50 30 M 6.50
1000 to 3000 ft. (300 to 900 m) 0/00 Ft. 63.55 300 M 63.55
1st Km Km 60.55
2nd Km Km 29.35

Chap-1 (Carriage) Page 21


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. Unit of Unit of No.
M /ment Labour Composite M /ment Labour Composite
3rd Km Km 23.60
1st mile Mile 97.40
4th Km Km 17.25
2nd mile " 27.35
5th Km Km 16.20
3rd mile " 25.30
6th Km Km 15.95
4th mile " 23.45
7th Km Km 15.05
5th mile " 22.00
8th Km Km 14.80
6th mile " 20.85
9th Km Km 14.05
7th mile and subsequent miles " 15.35
10th Km Km 13.20
11th Km & subsequent Kms Km 11.70

v) 5" (125 mm) i/d pipes:-

1st chain (1st 30 m) Chain 84.60 30 M 84.60


2nd chain (2nd 30 m) " 15.50 30 M 15.50
3rd to 10th chain (60 to 300 m) " 9.70 30 M 9.70
1000 to 3000 ft. (300 to 900 m) 0/00 Ft. 95.00 300 M 95.00
1st Km Km 90.50
2nd Km Km 43.90
3rd Km Km 35.30
1st mile Mile 145.60
4th Km Km 25.75
2nd mile " 40.90
5th Km Km 24.20
3rd mile " 37.80
6th Km Km 23.85
4th mile " 35.05
7th Km Km 22.40
5th mile " 32.85
8th Km Km 22.20
6th mile 31.10
9th Km Km 21.00
7th mile and subsequent miles 22.90
10th Km Km 19.70
11th Km & subsequent Kms Km 17.40
vi) 6" (150 mm) i/d pipes:-
1st chain (1st 30 m) Chain 121.95 30 M 121.95
2nd chain (2nd 30 m) " 22.35 30 M 22.35
3rd to 10th chain (60 to 300 m) " 13.95 30 M 13.95
1000 to 3000 ft. (300 to 900 m) 0/00 Ft. 136.90 300 M 136.90
1st Km Km 130.35
2nd Km Km 63.25

Chap-1 (Carriage) Page 22


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. Unit of Unit of No.
M /ment Labour Composite M /ment Labour Composite
3rd Km
1st mile Mile 209.75 Km 50.85
4th
2ndKm
mile 58.90 Km 37.10
5th
3rd Km
mile 54.45 Km 34.85
6th Km
4th mile 50.55 Km 34.35
7th
5th Km
mile 47.35 Km 32.30
8th
6th Km
mile 44.85 Km 32.00
9th
7th Km
mile and subsequent miles 33.00 Km 30.25
10th Km Km 28.55
11th Km & subsequent Kms Km 25.00
22 Hand shunting loaded Railway wagons or
trucks:-
a) upto ¼ mile / ¼ Km Each 440.75 Each 275.45
b) upto ½ mile / ½ Km No 797.90 No 498.70
c) upto ¾ mile / ¾ Km " 1077.20 " 673.25
d) upto 1 (1.6 Km) mile " 1281.80 " 801.15
e) 2nd mile and subsequent miles/ Each Each
2nd and subsequent kilometres No/Mile 905.10 No/Km 565.70
23 Hand shunting empty Railway wagons or trucks.

a) upto ¼ mile / ¼ Km Each 255.65 Each 159.80


b) upto ½ mile / ½ Km No. 423.60 No. 264.75
c) upto ¾ mile / ¾ Km " 558.60 " 349.15
d) upto 1 mile / 1 Km " 670.50 " 419.05
e) 2nd mile and subsequent miles/ Each Each
2nd and subsequent kilometres No/Mile 444.40 No/Km 277.75

Chap-1 (Carriage) Page 23


2. LOADING, UNLOADING & STACKING
1 The rate for loading into and unloading from mobile trucks, trollies and boats, etc. will be the same as for Railway wagons.

MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

1 Loading or unloading into or from Railway wagons, lead 100 Cft. 1019.05 cu.m 359.95
within one chain, (30m) shingle, sand, ballast, surkhi, ashes,
kankar, brick bats, coal, lime or 1,000 Nos. tiles size
12"x6"x2" (300x150x50 mm) or 9"x4½"x1½"
(225x113x37mm) properly laid & stacked.

2 Loading or unloading bricks into or from Railway wagons


laid and stacked, lead within one chain:-

a) Bricks 10" (250 mm) size. 1000 Nos. 1273.80 1000 Nos. 1273.80

b) Bricks 9" (225 mm) or smaller size. ditto 1019.05 ditto 1019.05

3 Loading or unloading into or from Railway wagons cement 100 Bags 1273.80 100 Bags 1273.80
in bags (from inside or outside the godown) and stacking
within one chain (30 m)

4 Loading or unloading into or from Railway wagons empty 100 Nos. 122.30 100 Nos. 122.30
cement bags (from inside or outside the godown) and
stacking.

5 Loading or unloading into or from Railway wagons (from 100 Mds. 764.30 100 Kg 20.50
inside or outside the godown) and stacking, white lime in
bags.

6 Loading or unloading into or from Railway wagons Per 611.40 Per 601.75
Structural Steel, R.S. joists, broad, narrow or meter gauge Tonne Tonne
rail and rail fastenings, etc.

7 Loading or unloading 45 gallon (204.57 Litres) drums full Each 76.45 Each 76.45
into or from Railway wagons, lead upto one chain.

8 Loading or unloading packages of all sorts, upto one Cwt Each 38.20 Each 38.20 Except cement in jute or
(50 Kg). paper bags.
9 Loading or unloading sleepers other than wooden,
including stacking lead within one chain:-

a) Broad gauge sleepers 100 Nos. 2547.60 100 Nos. 2547.60

b) Metre gauge and narrow gauge sleepers. ditto 1273.80 ditto 1273.80

Chap-2 (Loading/Unloading) Page 24


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

10 Loading or unloading timber logs or timber for shuttering, Per 318.45 Per 313.4
into or from Railway wagons of any gauge, including Ton Tonne
stacking lead within one chain (30 m)

11 Loading or unloading bhoosa in Railway wagons lead upto 100 Mds. 3057.1 100 Kg 81.9
150 ft. (45 m)

12 Loading or unloading timber scrap or wooden plugs, into or Per 509.50 Per 501.45
from Railway wagons, and stacking within one chain lead. Ton Tonne

13 Loading or unloading pitching stone or spawl from Railway 100 Cft. 377.05 cu.m 133.15
wagons of any gauge (including clearing 5 ft. (1500 mm)
away from the rail).

14 Loading or unloading building stone (including clearing 5 ft. 100 Cft. 489.15 cu.m 172.75
(1.5 m) away from rails).

15 Unloading oil, bitumen tar, etc.

a) Crude oil (to be pumped from tank wagon into tank). 1000 1273.80 100 28.00
Gallon litres

b) Crude oil (drained by gravity). 1000 1273.80 100 28.00


Gallon litres

c) Crude oil materials from railway wagons. 100 Cft. 163.05 cu.m 57.60

d) Fuel oil from tank into empty drums, including Per 452.90 Per 445.75
stacking within one chain (30 m). Ton Tonne

e) Petrol (2 gallon tin) 100 Nos. 642.00 100 Nos. 642.00 The rate includes checking
and weighing the tins.
f) Kerosene oil (4 gallon tin) 100 Nos. 1273.80 100 Nos. 1273.80
16 Removing and stacking within one chain
(30 m) lead:

a) Stone, spawl, brick bats, shingle, sand, lime, 100 Cft. 509.50 cu.m 179.95
surkhi, ashes, kankar and coat, etc.

b) Bricks. 1000 Nos. 1358.70 1000 Nos. 1358.70

c) Broad gauge wooden sleepers. 100 Nos. 815.25 100 Nos. 815.25

d) Metre gauge or narrow gauge wooden sleepers. 100 Nos. 485.25 100 Nos. 485.25

e) Rails girders, pipes, cement etc. Per 226.45 Per 222.90


Ton Tonne

Chap-2 (Loading/Unloading) Page 25


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

Sr. Description Rate (British System) Rate (Metric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

f) Bridge and crossing timbers, etc. 100 No. 2717.45 100 No. 2717.45

17 Loading into wagons girders, rails, permanent way Per 509.50 Per 501.45
material (except wooden sleepers) iron work, M.S. bars, Ton Tonne
pipes, etc. including lead one chain (30 M) and stacking
inside wagons.

18 Unloading from wagons girders, rails, permanent way Per 291.15 Per 286.55
material (except wooden sleepers) iron work, M.S. bars, Ton Tonne
pipes, etc. lead upto one chain (30 m) but excluding
stacking.

19 Loading into wagons wooden broad gauge sleepers, 100 Nos. 2038.10 100 Nos. 2038.10
including one chain (30 m) lead and stacking,.

20 Unloading wooden broad gauge sleepers from wagons, 100 Nos. 970.50 100 Nos. 970.50
including one chain (30 m) lead and stacking.

21 Loading metre gauge or narrow gauge wooden sleepers, 100 Nos. 1019.05 100 Nos. 1019.05
including one chain (30 m) lead and stacking inside
wagons.

22 Unloading metre gauge or narrow gauge wooden sleepers, 100 Nos. 536.35 100 Nos. 536.35
including one chain (30 m) lead but excluding stacking.

23 Loading bridge and crossing timbers, including one chain 100 Nos. 4076.15 100 Nos. 4076.15
(30 m) lead and stacking.
24 Unloading bridge and crossing timbers, including one 100 Nos. 2038.10 100 Nos. 2038.10
chain (30 m) lead but excluding stacking.

25 Loading or unloading bitumen, asphalt or tar in drums, into Per 305.70 Per 300.90
or from railway wagons, lead upto one chain (30 m). Ton Tonne

Chap-2 (Loading/Unloading) Page 26


3. EARTHWORK (EXCAVATION & EMBANKMENT)
1 Special allowances for the hardness, wetness and slush:-
The grant of allowances for hard, very hard, wet and slush will be subject to Superinteding Engineer's approval. Specific instructions regarding grant of such
allowances may be issued by the various Administrative Departments and Statutory Bodies. The earth requiring repeated blows of Kassi to break it and of
which dry bulk density is not less than 1.5, will be treated as hard.

2 Deduction for shrinkage from bank measurements:-


The following allowances should be provided for material which is not rammed, or equally consolidated:-
a) Deduction for shrinkage from the bank measurements when the earthwork is done by manual labour.......... 10%
b) Deduction for settlement from the bank measurement when the earthwork is done by machines................... 3 to 6%

Before the work is let out to be done by tractors, scrapers, etc. deduction ranging between 3% to 6% should be agreed to with the contractors.
MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. Unit of Unit of No.
M /ment Labour Composite M /ment Labour Composite

1 Earthwork excavation undressed lead upto a single throw 17.1 to 17.5


of Kassi, phaorah or shovel:-

a) In ashes, sand, soft soil or silt clearance. 1000 Cft. 3,821.40 -- cu.m 134.95 --
b) In ordinary soil. 1000 Cft. 4,585.70 -- cu.m 161.95 --

2 Earthwork excavation in ashes, sand and soft soil or silt 1000 Cft. 5,604.70 -- cu.m 197.95 -- ditto
clearance, undressed lead upto 50 ft (15 metre).

3 Bed clearance and dressing slopes of drains to required ditto The rate is applicable where the earth
sections including the removal of weeds, roots, etc. of the bed to be removed is of the
disposal of excavated materials within 50 ft. (15 metre) lead. type of ordinary soil. When it is silt or
a) Excavated material undressed. 1000 Cft. 7,133.30 -- cu.m 251.95 -- 1 or 2 above, whichever is applicable.
b) Excavated material dressed in the specified manner. 1000 Cft. 7,698.40 -- cu.m 271.90 -- the drains of each category.
4 Borrowpit excavation undressed lead upto 100 ft (30 metre).
a) Ordinary soil 1000 Cft. 7,133.30 - cu.m 251.95 -
b) Hard soil 1000 Cft. 8,763.75 - cu.m 309.55 -
5 Earthowrk in ordinary soil for embankments lead upto 100 * 411-1 to The rate includes hire charges of
ft. (30 m), including ploughing and mixing with blade grade 411-13 and machinery, cost of fuel, lubricants, pay
or disc harrow or other suitable equipment, and 301-1 & of driver and cleaner. The rate also
compaction by mechanical means at optimum moisture 202-3 includes clearing and grubbing
content and dressing to designed section, complete in all where necessary.
respects:-
i) 95% to 100% maximum modified AASHO dry density. 1000 Cft. 7,769.30 9,552.55 cu.m 274.40 337.40
ii) 90% maximum modified AASHO dry density. 1000 Cft. 7,769.30 9,276.30 cu.m 274.40 327.65
iii) 85% maximum modified AASHO dry density. 1000 Cft. 7,769.30 9,000.05 cu.m 274.40 317.90
6 Regular excavation dressed. 1000 Cft. 5,264.15 -- cu.m 185.95 -- * 411-2
7 Earthwork excavation in open cutting upto 5'-0" (1.5 m) 17.1 to
depth for storm water channels, drains, sullage drains in 17.5
open areas, roads, streets, lanes, including under pinning of
walls and shoring to protect existing works, shuttering and
timbering the trenches, dressed to designed level and
dimensions, trimming, removal of surface water from

Chap-3 (Earthwork) Page 27


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. Unit of Unit of No.
M /ment Labour Composite M /ment Labour Composite

trenches, back filling and surplus excavated material


disposed of and dressed within 50 ft. (15 m) lead:-
i) ordinary 1000 Cft. 8,944.85 9,055.25 cu.m 315.95 319.85
ii) hard 1000 Cft. 10,575.30 10,685.70 cu.m 373.50 377.40
iii) very hard 1000 Cft. 12,307.70 12,418.10 cu.m 434.70 438.60
iv) gravel & shingle 1000 Cft. 20,672.25 20,782.65 cu.m 730.15 734.05
8 Earthwork excavation in open cutting 5.01 ft. (1.5 m) to ditto
10.0 ft. (3.0 mm) depth for storm water channels, drains,
sullage drains in open areas, roads, streets, lanes, including
under pinning of walls and shoring to protect existing works,
shuttering and timbering the trenches, dressed to designed
level and dimensions, trimming, removal of surface water
from trenches, back filling and surplus excavated material
disposed of and dressed within 100 ft. (30 m) lead:-
i) ordinary 1000 Cft. 9,689.35 9,908.95 cu.m 342.25 350.00
ii) hard 1000 Cft. 11,319.80 11,539.40 cu.m 399.80 407.55
iii) very hard 1000 Cft. 13,052.15 13,271.75 cu.m 461.00 468.75
iv) gravel & shingle 1000 Cft. 22,435.80 22,655.40 cu.m 792.45 800.20
9 Excavation in shingle or gravel formation and rock, not 17.1 to 17.5
requiring blasting, undressed lead upto 100 ft (30 m).
i) Dry 1000 Cft. 19,361.75 -- cu.m 683.85 --
ii) Wet 1000 Cft. 22,418.90 -- cu.m 791.85 --
iii) In flowing water 1000 Cft. 28,533.10 -- cu.m 1,007.80 --
10 Earthwork excavation in irrigation channels, drains, etc. to
designed section, grades and profiles, excavated material ditto
disposed off and dressed within 50 ft. (15 m) lead:-
i) ordinary 1000 Cft. 8,160.75 -- cu.m 288.25 --
ii) hard 1000 Cft. 9,791.25 -- cu.m 345.85 --
iii) very hard 1000 Cft. 11,523.60 -- cu.m 407.00 --
iv) gravel & shingle 1000 Cft. 20,397.70 -- cu.m 720.45 --
11 Excavation in rock dressed to designed section, grades and
profiles, excavated material disposed off within 100 ft. (30 m) 17.1 to 17.5 Tools and plants shall be the liability
and lift upto 5'-0" (1.5 m). of the contractor.
a) Soft rock, slate, shale, schist laterite work, with pick and 1000 Cft. 19,404.00 -- cu.m 685.35 --
crow bar.
b) Medium hard rock, requiring occasional blasting. 1000 Cft. 31,857.40 32,447.80 cu.m 1,125.20 1,146.05
12 a) Excavation in hard rock requiring blasting and disposal
of excavated material (blasted material) upto 50 ft. (15 17.1 to 17.5 1) Tools and plants required shall be
m) lead, (including dressing and leveling to designed the liability of the Contractor
section,e tc. complete).
i) Grade I 1000 Cft. 18,616.75 19,207.15 cu.m 657.55 678.40 2) Reduce the rate by 8% if the
ii) Grade II 1000 Cft. 20,271.50 21,255.50 cu.m 716.00 750.75 excavated section is not dressed or
iii) Grade III 1000 Cft. 24,284.55 25,465.35 cu.m 857.75 899.45 levelled to designed section.
iv) Grade IV 1000 Cft. 27,021.70 28,399.30 cu.m 954.40 1,003.05
v) Grade V 1000 Cft. 29,838.85 31,413.25 cu.m 1,053.90 1,109.50
vi) Grade VI 1000 Cft. 32,066.50 33,837.70 cu.m 1,132.60 1,195.15

Chap-3 (Earthwork) Page 28


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. Unit of Unit of No.
M /ment Labour Composite M /ment Labour Composite

b) Excavation in hard rock requiring blasting, but blasting


prohibited, and disposal of excavated material within 50 17.1 to 17.5 1) Tools and plants required shall be
ft. (15 m) lead (including dressing and levelling to the liability of the contractor.
designed section, etc. complete):-
i) Grade I 1000 Cft. 37,233.50 38,414.30 cu.m 1,315.10 1,356.80 2) Reduce the rate by 8% if the
ii) Grade II 1000 Cft. 40,543.00 42,511.00 cu.m 1,432.00 1,501.50 excavated section is not dressed or
iii) Grade III 1000 Cft. 48,569.15 50,930.75 cu.m 1,715.45 1,798.85 levelled to designed section.
iv) Grade IV 1000 Cft. 54,043.45 56,798.65 cu.m 1,908.80 2,006.15
v) Grade V 1000 Cft. 59,677.75 62,826.55 cu.m 2,107.80 2,219.05
vi) Grade VI 1000 Cft. 64,133.00 67,675.40 cu.m 2,265.20 2,390.30

13 Rehandling of earthwork:

a) Lead upto a single throw of Kassi, phaorah or shovel 1000 Cft. 2,547.60 -- cu.m 90.00 -- ditto
b) Upto a lead of 50 ft. (15 m). 1000 Cft. 3,566.65 -- cu.m 125.95 --

14 Rehandling of gravel work or excavated rock, 1000 Cft. 10,190.40 -- cu.m 359.95 -- 17.1 to 17.5
lead upto 50 ft.( 15 m)

15 Filling, watering and ramming earth under floors:- ditto

i)with surplus earth from foundation, etc. 1000 Cft. 5,107.85 -- cu.m 180.40 --
ii)
with new earth excavated from outside, 1000 Cft. 11,190.10 -- cu.m 395.25 --
lead upto one chain (30 m).
16 Extra for every 50 ft. (15 m) additional lead or part thereof :- This rate shall be applicable upto
1000 ft. total distance, including the
i) for earhtwork soft, ordinary, hard and very hard. 1000 Cft. 97.70 -- cu.m 3.45 -- lead covered in the item of earthwork
ii) for gravel, shingle or rock. 1000 Cft. 116.25 -- cu.m 4.10 --

17 Transportation of earth all types when the total distance, This rate will be paid inaddition to the
including the lead covered in the item of work, is more than rate of earthwork, without deducting
1000 ft. (300 m) the lead covered in the item of
a) upto ¼ mile (400 m). 1000 Cft. 4,341.40 -- cu.m 153.35 -- earthwork
b) for every 330 ft. (100 m) additional lead or part thereof,
beyond ¼ mile (400 m) upto one mile. (1.6 Km.) 1000 Cft. 40.25 -- cu.m 1.40 --
c) for every ¼ mile (400 m) additional lead or part thereof,
beyond one mile (1.6 Km.) upto 5 mile (8 Km). 1000 Cft. 338.75 -- cu.m 11.95 --
d) for every ½ mile (800 m) additional lead
or part thereof, beyond 5 miles (8 Km). 1000 Cft. 320.70 -- cu.m 11.35 --

18 Dressing and levelling of earhtwork to designed section, etc. 17.10 to 17.5


complete:-
a) Ashes, sand, silt or soft soil. 1000 Cft. 327.80 -- cu.m 11.60 --
b) Ordinary or hard soil. 1000 Cft. 636.05 -- cu.m 22.45 --
c) Gravel work or soft rock not requiring 1000 Cft. 1,537.00 -- cu.m 54.30 --
blasting.

19 Dowel dressing. Per 299.00 -- Metre 9.80 -- ditto This rate is in addition to payment for
Chain dressed earhtwork.

Chap-3 (Earthwork) Page 29


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. Unit of Unit of No.
M /ment Labour Composite M /ment Labour Composite

20 a) Dressing slopes of banks or ground surface. 100Sft. 133.30 -- sq.m 14.35 -- ditto To be paid only when exclusively
dressing is done and no earthwork is
carried out in embankment or cutting.

b) Dressing of earthwork (done by machinery or otherwise 100Sft. 239.50 -- sq.m 25.75 -- i) The surface area dressed is to be
and left undressed) to designed section. taken for measurement.

ii) The item is applicable where the


dressing is done by the contractor
other than the one who executed the
work.
21 Excavation in foundation of building, bridges and other
structures, including dagbelling, dressing, refilling around 17.1 to 17.5 If refilling is not required, reduce labor and
structure with excavated earth, watering and ramming lead composite rate by Rs 720/- P.%0 Cft or
upto one chain (30 m) and lift upto 5 ft. (1.5 m) Rs 25.50/- P.Cu.m and surplus earth will
a) By M anual be adjusted accordingly.
i) in sand, ashes or loose soil 1000 Cft. 9,179.80 -- cu.m 324.25 --
ii) in ordinary soil. 1000 Cft. 10,712.60 -- cu.m 378.35 --
iii) in hard soil or soft murum. 1000 Cft. 11,988.50 -- cu.m 423.45 --
b) By Excavator
i) Sand,ashes or loose soil Per %0Cft 3,057.10 5,375.90 Cu.m 107.85 189.65
ii) Ordinary soil Per %0Cft 5,604.70 8,062.80 Cu.m 197.75 284.45
iii) Hard soil or Soft murum Per %0Cft 5,859.50 8,997.65 Cu.m 206.70 317.45
22 Cutting hard rock such as granite, ballast, hard lime stone or 1000 Cft. 83,950.95 92,774.30 cu.m 2,965.15 3,276.80 17.1 to 17.5 Tools and plants required shall be the
sand stone, etc. with chisels and hammers, for small liability of the contractor.
foundations.

23 Extra for excavation requiring shoring. 1000 Cft. 1,362.25 1,731.85 cu.m 48.10 61.15 17.1 to 17.5 Composite rate includes materials,
i.e. plank, etc.
24 Compaction of earthwork (soft, ordinary or hard soil) :- ditto

a) Mixing, moistening earth to optimum moisture content 1000 Cft. 1,201.15 -- cu.m 42.45 --
in layers for compaction, etc. complete.

b) Compaction by rolling with animal driven


roller/hand rammed:

i) soft or sandy soil 1000 Cft. 1,528.55 -- cu.m 54.00 --


1) The rate does not include hire
ii) ordinary soil 1000 Cft. 1,783.30 -- cu.m 63.00 -- charges of the roller.
2) Roller to be 'supplied by
iii) hard soil 1000 Cft. 2,038.10 -- cu.m 72.00 -- Government

iv) admixture of shingle 1000 Cft. 2,292.85 -- cu.m 81.00 --

c) Ramming earthwork (all types of soil). 1000 Cft. 1,528.55 -- cu.m 54.00 --

d) Ramming earhtwork behind retaining walls. 1000 Cft. 2,038.10 -- cu.m 72.00 --

Chap-3 (Earthwork) Page 30


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. Unit of Unit of No.
M /ment Labour Composite M /ment Labour Composite

25 Compaction of earthwork with power road roller, including 17.1 (a)


ploughing, mixing, moistening earth to optimum moisture * 411-5 and The rate also includes hire charges of
content in layers, etc. complete: 202-3 machinery, cost of fuel, lubricant, pay
of driver and cleaner, etc.
i) 95% to 100% maximum modified AASHO dry density. 1000 Cft. -- 1,783.25 cu.m - 63.00

ii) 90% maximum modified AASHO dry density. 1000 Cft. -- 1,507.00 cu.m - 53.25

iiii) 85% maximum modified AASHO dry density. 1000 Cft. -- 1,230.75 cu.m - 43.45

26 Extra for wet earthwork. 1000 Cft. 3,566.65 -- cu.m 125.95 - 17.1 to 17.5 That will support a man's weight.

27 Extra for slush or Daldal including dewatering. 1000 Cft. 8,152.30 -- cu.m 287.95 - 17.1 to 17.5 That will not support a man's weight.

28 Extra for puddling. 1000 Cft. 6,381.65 -- cu.m 225.40 - ditto

29 Earthwork on small rain water drains, along canal banks, 100 Rft. 968.10 -- Metre 31.75 - ditto
roads and plantation drains, dressed, etc. complete.

30 Filling and compacting soil, earth and boulders behind 1000 Cft. 9,171.35 -- cu.m 323.95 -- 17.1 to 17.5
retaining walls (including excavation of soil and lead upto 50
ft.( 15 m).

31 Dag bailing 3" (75 mm) deep. Per mile 3,797.60 -- Per 2,360.20 -- ditto Dag bailing for layout of borrow pit, to
Km be done by contractors at their own
cost.
32 Turfing slopes of banks or lawns with grass sods including 100Sft. 1,698.40 -- sq.m 182.75 -- ditto
ploughing, laying, setting and watering (Turf got from within a
distance of 5 miles (8 Km.) and maintenance for 15 days).

33 Berm cutting:- 17.1 to 17.5

a) lead upto a single throw of Kassi, phaora or shovel 1000 Cft. 4,585.70 -- cu.m 161.95 --
(without dressing).
b) upto 50 ft(15 m)lead (including dressing). 1000 Cft. 8,160.75 -- cu.m 288.25 --

34 Berm trimming both sides of channels:- 17.1 to 17.5

a) upto 3½ ft. (1.06 m) depth. Per Mile 11,902.90 -- Per Km. 7,439.30 --
b) exceeding 3½ ft. to 5 ft. (1.06 to 1.5 m) depth. Per Mile 16,875.30 -- Per Km. 10,547.05 --
c) exceeding 5 ft. to 8 ft. (1.5 to 2.4 m) depth Per Mile 26,223.55 -- Per Km. 16,389.70 --

35 Ploughing and levelling borrowpits. ditto Area ploughed to be measured.

i) upto 3 ft. (0.9 m) depth. Per Acre 2,547.60 -- Per Hect. 6,295.25 --
ii) above 3 ft. (0.9 m) depth. Per Acre 5,095.20 -- Per Hect. 12,590.50 --

Chap-3 (Earthwork) Page 31


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. Unit of Unit of No.
M /ment Labour Composite M /ment Labour Composite

36 Making boundary or service roads, including dag-belling, ditto


leveling and dressing:

i) in unploughed land:

a) from 10.0 ft. to 20.0 ft. (3 to 6 m) wide. Per Chain 1,277.30 -- Metre 41.90 --
b) from 20.1 ft. to 40.0 ft. (6.10 to 12 m) wide. Per Chain 1,705.45 -- Metre 55.95 --

ii) in ploughed land:

a) from 10.0 ft. to 20.0 ft. (3 to 6 m) wide. Per Chain 1,310.60 -- Metre 43.00 --
b) from 20.1 ft. to 40.0 ft. (6.10 to 12 m) wide. Per Chain 1,738.70 -- Metre 57.05 --

37 Earthwork by boats, including hire of boats:- 17.1 to 17.5 For ordinary soil.

i) Digging and loading into boats, upto 50 ft. (15 m) lead. 1000 Cft. 7,642.80 -- cu.m 269.95 --
ii) Carriage by boats upto 10 chains (300 m). 1000 Cft. 1,905.80 -- cu.m 67.30 --
iii) Extra for every additional one chain (30 m) or part 1000 Cft. 203.80 -- cu.m 7.20 --
thereof beyond 10 chains (300 m).
iv) Unloading earth from boats. 1000 Cft. 3,566.65 -- cu.m 125.95 --

38 Unloading earth from B.G. trucks and clearing 5 ft. (1.5 m) 1000 Cft. 3,057.10 -- cu.m 108.00 -- 17.1 to 17.5
from rail.

39 Earthwork by tramway, digging and loading in trucks, upto 50 1000 Cft. 7,133.30 -- cu.m 251.95 -- 17.1 to 17.5
ft. (15 m) lead.

40 Unloading earth from B.G. trucks and spreading upto 1000 Cft. 5,732.10 -- cu.m 202.45 -- ditto
15 ft. (4.5 m) from rail.

41 Supplying clean and screened river or pit sand within 5 100Cft. 963.70 986.70 cu.m 340.40 348.50 ditto The rate incudes:-
chains (150 m). i) removal of top crust of earth
over burden
ii) royalty to the government or cost
to the private owner.

42 Earth work excavation in open cutting for sewers and manholes as 17.1 to 17.5 The rate does not include back filling
shown in drawing including shuttering of wooden vertical planks, struts * * 13.1 & 13.4 after laying of sewer, which is payable
and beams, dressing to correct section and dimension separately.
according to templates and levels and removing surface water in all
types of soil except shingle, gravel and rock.
If wooden planks, beams and struts are not
i) 0 ft. to 7.0 ft. (0 to 2.10 m) depth 1000 Cft. 8,026.15 11,770.45 cu.m 283.50 415.75 used at site, the composite rates may be
ii) 7-01 ft. to 15.0 ft. (2.15 to 4.5 m) depth 1000 Cft. 12,558.20 16,932.30 cu.m 443.55 598.05 reduced by 31.5%, 25.7% & 23.2%,
iii) above 15.0 ft. (4.5 m) depth 1000 Cft. 13,782.10 17,915.05 cu.m 486.80 632.75 respectively for i), ii) & iii).

43 Earthwork excavation of trenches in open cutting for sewers 17.1 to 17.5 The rate does not include back filling
and manhole chambers, etc. below sub-soil water level to * * 13.3 & after laying of sewer, which is payable
correct section and dimensions according to templates and 13.5 separately.
levels, including shoring, timbering and shuttering of M.S.
sheets on both sides of the trenches:

Chap-3 (Earthwork) Page 32


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. Unit of Unit of No.
M /ment Labour Composite M /ment Labour Composite

i) 0 ft. to 4.0 ft. (0 to 1.20 m) depth below SSWL. 1000 Cft. 12,108.35 17,270.80 cu.m 427.65 610.00
ii) 4.01 ft. to 8.0 ft. (1.22 to 2.4 m) depth below SSWL. 1000 Cft. 15,136.85 22,407.00 cu.m 534.65 791.40
iii) Exceeding 8 ft. (2.4 m) depth below SSWL. 1000 Cft. 22,705.25 30,817.80 cu.m 801.95 1,088.50

44 Excavation of trenches in all kinds of soil, except cutting 1000 Cft. 7,647.00 -- cu.m 270.10 -- 17.1 to 17.5 The rate does not include back filling
rock, for watersupply pipelines upto 5 ft. (1.5 m) depth * * 8.1 after laying of pipe line, which is
from ground level, including trimming, dressing sides, payable separately.
leveling the beds of trenches to correct grade and cutting
pits for joints, etc. complete in all respects.

45 Cutting and removing trees within a distance of 100 ft. (30 m)

a) upto 2½ ft. (760 mm) girth. Each 1,531.20 -- Each 1,531.20


b) above 2½ ft. to 6 ft. (760 to 1800 mm) girth. Each 2,976.60 -- Each 2,976.60

46 Uprooting stump and removing within 100 ft. (30 m) from 2 ft. Each 1,910.70 -- Each 1,910.70
to 6 ft. (600 to 1800 mm) girth.

47 Jungle clearance and removing within 100 ft. (30 m).


The compaction of area will be restored to its
a) light 1000 Sft. 254.75 -- sq.m 2.75 -- original value without any extra payment.
b) thick 1000 Sft. 509.50 -- sq.m 5.50 --

48 Uprooting Sarkanda growth and disposal within 100 ft. (30 m) 100Sft. 122.30 -- sq.m 13.15 --

49 Ploughing 3 times. Per 1,034.95 -- Per Hect. 2,557.45 --


Acre

50 Leveling, dressing and making lawns. 100Sft. 509.50 -- sq.m 54.80 --

51 Turfing lawns (excluding cost of turf). 100Sft. 428.10 -- sq.m 46.05 --

52 Earthwork in excavation of drains, irrigation channels through


excavator / drag lines in all kind of soil and conditions(dry,wet
slush,daldal and under water) including its disposal and
preparation of working pad for operation of machinery.
(Rates includes 100 ft lead) 1000 Cft. -- 4,938.00 cu.m -- 174.40

* Specification number correspond to Book of "Specification for Road & Bridge Construction, 1971".
** Specification number correspond to Book of "Building & Roads Department Specification Vol. II, 1966 (Public Health Works).

Chap-3 (Earthwork) Page 33


4. DISMANTLING (DEMOLITION)
1 Rates for all finished works include the removal of surplus debris, unused material and byproducts.

2 The rates for dismantling roofs or upper storey floor, include the dismantling of all materials, except roof
supports such as beams and trusses.
MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

Stone Work

1 Dismantling dry stone masonry. 100Cft. 866.20 Cu.m 305.95 18.1

2 Dismantling stone masonry in mud mortar. 100Cft. 1,273.80 Cu.m 449.90 ditto

3 Dismantling stone masonry in lime or cement mortar. 100Cft. 3,057.10 Cu.m 1,079.75 ditto Add extra 13%, 32% and 51% on
labour rates only for 2nd, 3rd, 4th
and subsequent floors respectively.

4 a) Dismantling dry stone or spawl pitching. 100Cft. 1,528.55 Cu.m 539.90 ditto

b) Dismantling stone or spawl pitching (mud grouted). 100Cft. 1,936.20 Cu.m 683.85 ditto

5 Dismantling stone or spawl pitching and apron in silted 100Cft. 2,547.60 Cu.m 899.80 ditto
condition.

6 Dismantling stone pitching, cement or lime grouted. 100Cft. 4,076.15 Cu.m 1,439.70 ditto

7 Dismantling stone in crates:

a) wooden crates 100Cft. 2,038.10 Cu.m 719.85

b) wire crates 100Cft. 2,547.60 Cu.m 899.80

8 Dismantling stone ware drain including base concrete. 100Cft. 1,426.65 Cu.m 503.90 ditto

Brick Work

9 Dismantling mud/pise walling. 100Cft. 509.50 Cu.m 179.95 18.1

10 Dismantling sun dried brick masonry. 100Cft. 1,273.80 Cu.m 449.90 ditto

11 Dismantling dry brick masonry. 100Cft. 866.20 Cu.m 305.95 ditto

12 Dismantling brick work in mud mortar. 100Cft. 1,783.30 Cu.m 629.85 18.1 Add extra 13%, 32% and 51% on
labour rates only for 2nd, 3rd, 4th
13 Dismantling brick work in lime or cement mortar. 100Cft. 4,330.90 Cu.m 1,529.65 ditto and subsequent floors respectively
against item No. 12, 13, 14 & 15.

14 Dismantling cement block masonry. 100Cft. 3,821.40 Cu.m 1,349.70 ditto

Chap-4 (Dismantling) Page 34


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

15 Dismantling Dhajji walling. 100Cft. 1,019.05 Cu.m 359.95 ditto

Concrete

16 Dismantling mud concrete. 100Cft. 2,038.10 Cu.m 719.85 ditto

17 Dismantling lime concrete. 100Cft. 2,802.35 Cu.m 989.80 Add extra 13%, 32% and 51% on
labour rates only for 2nd, 3rd, 4th
18 Dismantling lime or cement concrete, under water. 100Cft. 10,699.90 Cu.m 3,779.20 and subsequent floors respectively
against item No. 17, 19 & 20.

19 a) Dismantling cement concrete plain 100Cft. 5,604.70 Cu.m 1,979.60 ditto


1:4:8.
b) Dismantling cement concrete plain 100Cft. 9,171.35 Cu.m 3,239.30
1:3:6.
c) Dismantling cement concrete 1:2:4 100Cft. 11,209.45 Cu.m 3,959.20
plain.
d) Dismantling cement concrete with brick 100Cft. 3,057.10 Cu.m 1,079.75
aggregate.
e) Dismantling D.P.C. of cement concrete 100Cft. 1,528.55 Cu.m 539.90
1½" thick (40 mm) and clearing the site.

20 Dismantling cement concrete reinforced, 100Cft. 18,342.70 Cu.m 6,478.65 ditto


separating reinforcement from concrete,
cleaning and straightening the same.

Roofing

21 Dismantling sirki sarkanda or thatched 100Sft. 611.40 Sq.m 65.80 18.1


roofing, supported on battens or bellies.

22 a) Dismantling 1st class tile roofing. 100Sft. 1,528.55 Sq.m 164.45 Add extra 13%, 32 and 51% on
labour rate only for 2nd, 3rd, 4th
b) Dismantling 2nd class tile roofing. 100Sft. 1,273.80 Sq.m 137.05 ditto and subsequent floors respectively
against items No. 22, 25, 26 and 28.

23 Dismantling from any height, asbestos sheets and ridge 100Sft. 852.70 Sq.m 91.75 18.1
coping.

24 a) Dismantling roof of wooden planks and battens, from 100Sft. 682.20 Sq.m 73.40 ditto
any height.

b) Dismantling wooden ceiling above 20' (6.0 m) height 100Sft. 2,657.95 Sq.m 286.00 ditto
in difficult position, including lifting with care and
special scaffolding along live electric wires and with
machines underneath.

Chap-4 (Dismantling) Page 35


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

25 Dismantling jack arch roofing, including removal of joists. 100Sft. 2,038.10 Sq.m 219.30 ditto

26 Dismantling R.B. roof complete with mud and plaster, 100Sft. 2,547.60 Sq.m 274.10 ditto
including separating reinforcement, cleaning and
straightening the same.

27 a) Stripping and stacking slate or tiles from the truss 100Sft. 1,273.80 Sq.m 137.05
roofing.

b) Stripping and stacking C.I. sheet roof. 100Sft. 1,183.80 Sq.m 127.40

c) Extra for dismantling C.I. sheet roof above 20 ft. (6m) 100Sft. 1,627.55 Sq.m 175.10
in difficult position, including lifting with special
scaffolding along live electric wire with machine
underneath.

28 Dismantling slates or tiles including battens, purlins and 100Sft. 2,038.10 Sq.m 219.30 18.1
planking.

Flooring

29 Dismantling brick or flagged flooring without 100Sft. 866.20 Sq.m 93.20 18.1 Add extra 13%, 32% and 51% on
concrete foundation. labour rates only for 2nd, 3rd, 4th
and subsequent floors respectively
30 Dismantling plank or wooden block flooring, 100Sft. 1,273.80 Sq.m 137.05 ditto against items No. 29 and 30.
etc.

31 Disjoining R.C.C. pipes inside the trench and dismantling i) The rate does not include the
and removing the pipes from the trench and stacking them cost of excavation and refilling of
outside:- trench, or the demolition of any
masonry or brick work.
a) 6" to 12" (150 to 300 mm) diameter Per Rft 34.10 Metre 111.85
b) 13" to 24" (325 to 600 mm) diameter Per Rft 54.50 Metre 178.75 ii) Bends, elbows, sluice valves,
c) 25" to 36" (625 to 900 mm) diameter Per Rft 63.85 Metre 209.45 etc. should not be paid for extra if
d) Above 36" (Above 900 mm) diameter Per Rft 90.80 Metre 297.80 fixed in the length of pipe line that
is being dismantled.

WOOD WORK
32 a) Removing door with chowkat. Per 448.45 Per 448.45 18.1 Add extra 13%, 32% and 51% on
No. No. labour rates only for 2nd, 3rd, 4th
b) Removing windows and sky lights with chowkat. ditto 350.45 ditto 350.45 and subsequent floors respectively
against items No. 32, 33, 34, 35 &
36.
33 Removing ventilators and wooden sunshade, etc. Per No. 183.80 Per No. 183.80 ditto

34 a) Dismantling wooden beams upto 12' (3.65m) Per No. 318.45 Per No. 318.45 ditto
length.

Chap-4 (Dismantling) Page 36


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

b) Dismantling wooden beams from 12.1' to 23' Per No. 509.50 Per No. 509.50
(3.65 to 7.0 m) length.

35 a) Dismantling wooden partition Jaffry work etc. 100Sft. 609.10 Sq.m 65.55 ditto

b) Dismantling wooden trusses. 100Kg 1,812.40 %Kg 1,812.40

36 Dismantling wooden palisade fencing. Per Lft. 49.85 Metre 163.50 ditto

I ron work

37 Dismantling iron work of trusses, sheds, water tanks, etc. 100Kg 1,816.65 %Kg 1,816.65 18.1 Add extra 13%, 32% and 51% on
excluding cutting of rivets. labour rates only for 2nd, 3rd, 4th
and subsequent floors respectively
against items No. 37 and 38.

38 Dismantling rolled steel beams or iron rails, etc. 100Kg 836.25 %Kg 836.25 ditto

39 Dismantling iron latrine. Per Unit/ 1,960.20 Per Unit/ 1,960.20 ditto
2 Seats 2 Seats

40 Dismantling tees, bends or sluice valves upto 12" Each per 41.55 Each per 16.60 ditto
(300 mm) bore. inch bore cm bore

41 a) Dismantling B.G. water column. Each 12,764.40 Each 12,764.40 ditto

b) Dismantling M.G. or N.G. water column. Each 8,514.00 Each 8,514.00 ditto

42 Dismantling all type of wire fencing, including rolling wire 100Lft. 866.20 Metre 28.40 18.1
into bundles and collecting material.

M iscellaneous

43 Dismantling wire netting of tennis courts and frame work. 100Sft. 407.60 Sq.m 43.85 18.1

44 Dismantling cloth ceiling and supporting timber. 100Sft. 764.30 Sq.m 82.25 ditto

45 Dismantling and removing road metalling. 100Cft. 2,038.10 Cu.m 719.85 ditto

46 Dismantling and removing road pavement, etc., including 100Cft. 2,720.85 Cu.m 961.00 ditto
screening and stacking of byproducts upto one chain lead
(30 metre).

47 Removing mud plaster from walls. 100Sft. 212.30 Sq.m 22.85 ditto Add extra 13%, 32% and 51% on
labour rates only for 2nd, 3rd, 4th
48 Removing cement or lime plaster. 100Sft. 424.60 Sq.m 45.70 ditto and subsequent floors against item
No. 47, 48, 49, & 50 respectively

Chap-4 (Dismantling) Page 37


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

49 Scraping:- 18.1

a) White wash or colour wash. 100Sft. 254.75 Sq.m 27.40

b) Ordinary distemper, oil bound distemper, ditto 764.30 Sq.m 82.25


or paint of wall.

50 Dismantling glazed or encaustic tiles, etc. 100Sft. 2,391.85 Sq.m 257.35 18.1

51 Scraping boulders. 100Cft. 3,566.65 Cu.m 1,259.75 18.1

52 Cleaning lime or cement mortar of old stones 100Cft. 1,783.30 Cu.m 629.85 18.1
to be used in masonry.

Electric Wiring

53 Dismantling light, fan and call bell point Per 78.45 79.35 Per 78.45 79.35
including casing and capping/strip open type, point point
and making good damaged surface (building
portion).

54 Dismantling plug point and making good Per 67.25 68.00 Per 67.25 68.00
damaged surface (building portion). point point

55 Dismantling G.I./M.S. conduit/G.I. flexible/PVC pipes or


conduit wiring, etc. of all sizes including making good
damaged surface (building portion):-

i) on surface Per foot 14.35 14.50 P.Mtr 47.05 47.55


ii) recessed in wall Per foot 30.40 30.65 P.Mtr 99.70 100.55

Chap-4 (Dismantling) Page 38


5. MORTAR
MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA
Dry Material Required for Dry Material Required for
100 Cft. Wet (Ready) Mortar One Cum Wet (Ready) Mortar
S. No. Ratio of Mortar Cement Lime Cement Lime Sand
(50 Kg) Putty Sand (50 Kg.) Putty Cum.
Bag Cft. Cft. Bag. Cum
1 2 3 4 5 6 7 8
1 Cement : Sand
1 : 2 33.48 82 11.83 0.82
1 : 3 23.11 85 8.16 0.85
1 : 4 18.37 90 6.49 0.90
1 : 5 14.70 90 5.19 0.90
1 : 6 13.61 100 4.81 1.00
1 : 7 11.68 100 4.12 1.00
1 : 8 10.21 100 3.61 1.00

2 Cement : Lime : Sand


1 : 1 : 6 12.25 15.0 90 4.33 0.15 0.90
1 : 1 : 7 10.70 13.1 92 3.78 0.13 0.92
1 : 1 : 8 9.39 11.5 92 3.32 0.12 0.92
1 : 1 : 9 8.52 10.44 94 3.00 0.10 0.94
1 : 1 : 10 7.67 9.4 94 2.71 0.09 0.94
1 : 2 : 8 9.19 22.5 90 3.25 0.23 0.90
1 : 2 : 9 8.16 20.0 90 2.88 0.20 0.90
1 : 2 : 10 7.67 18.8 94 2.71 0.19 0.94
1 : 2 : 12 6.39 15.66 94 2.26 0.16 0.94
1 : 3 : 12 6.26 23.0 92 2.21 0.23 0.92
1 : 3 : 14 5.47 20.1 94 1.93 0.20 0.94
1 : 3 : 16 4.82 17.7 94 1.70 0.18 0.94
1 : ¼ : 3 23.11 7.0 85 8.16 0.07 0.85

3 Lime : Sand
1 : 2 43 86 0.43 0.86
1 : 3 31 93 0.31 0.93

Chap-5 (Mortar) Page 39


5. MORTAR
MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA
Dry Material Required for 100 Cft. Dry Material Required for
Wet (Ready) Mortar one M 3 Wet (Ready) Mortar
S. Ratio of Mortar Clay Lime Sand Surkhi Cinder Clay Lime Sand Surkhi Cinder
No. (Putty) (Putty)
Cft. Cft. Cft. Cft. Cft. M3 M3 M3 M3 M3
1 2 3 4 5 6 7 3 4 5 6 7

4 Mud 135 1.35

5 Lime : Surkhi
2 : 3 49.00 - 73.5 - 0.49 - 0.74 -
1 : 2 40.75 - 81.5 - 0.41 - 0.82 -
1 : 3 30.30 - 91.0 - 0.30 - 0.91 -

6 Lime : Sand : Surkhi


1 : 1 : 1 40.50 40.5 40.5 - 0.41 0.41 0.41

7 Lime : Cinder
1 : 1 57.0 - 57.0 - 0.57 - - 0.57

Wet material required for 100 Cft. Wet material required for 1M³ (35.32 Cft)
masonry (including wastage): masonry ( including wastage) :

1 Brick M asonry :
a) Mud Mortar 35.00 Cft 0.35 M3
b) Cement, Sand 25.00 Cft 0.25 M3
c) Cement, Lime (Putty) Sand 25.00 Cft 0.25 M3
d) Lime (Putty) Sand 25.00 Cft 0.25 M3

2 Stone M asonry :
a) Random rubble, uncoursed
i) Foundation and Plinth 45.00 Cft 0.45 M3
ii) Superstructure 40.00 Cft 0.40 M3
iii) Coursed 35.00 Cft 0.35 M3
b) Ashlar Block in course or Scabled masonry 30.00 Cft 0.30 M3
c) Ashlar fine masonry 20.00 Cft 0.20 M3

(1) Cement 1 Cft. = 40.8233 Kg


Notes : (2) Unslaked lime 1.7 Cft. = 37.3242 Kg
(3) Slaked lime 2.5 Cft. = 37.3242 Kg
(4) Quick lime 40 Kg Will yield 2.6 Cft. lime putty.

Chap-5 (Mortar) Page 40


6. CONCRETE
1. Rates for all finished works include the removal of surplus debris, unused material and by products.
2. If concrete mixer or high frequency vibrator, etc. is supplied by the Government, all charges including depreciation will be recovered from the contractor.
3. Subsequent carriage of crushed stone aggregate and bajri will be paid according to the following:
a) The carriage for the whole distance to the site of work shall be calculated on the basis of the rates of the actual means of transport used in carriage, i.e. road and / or rail, as the case may be.
b) It shall be payable from the nearest approved quarry to site of work.
MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

1 Mud concrete in foundation including watering and ramming, 100Cft 5,639.35 10,889.35 cu.m 1,991.80 3,846.10
The stone ballast, crushed bajri, round shingle
using brick or stone ballast 1½" (40 mm) gauge.
from nallah, or brick ballast may be used
according to site requirement or as directed by
2 Dry rammed brick or stone ballast, 1½" to 2"( 40 mm to 50 100Cft 3,821.40 9,167.40 cu.m 1,349.70 3,237.95
the engineer incharge.
mm) gauge.

3 Cement concrete brick or stone ballast 1½ " to 2" (40 mm to 20.1 -do-
50 mm) gauge, in foundation and plinth:-

(a) Ratio 1: 3: 6 100Cft 7,440.20 28,982.60 Cu.m 2,627.90 10,236.65


(b) Ratio 1: 4: 8 100Cft 7,440.20 25,065.80 Cu.m 2,627.90 8,853.25
(c) Ratio 1:5:10 100Cft 7,440.20 22,985.00 Cu.m 2,627.90 8,118.30
(d) Ratio 1: 6:12 100Cft 7,440.20 21,393.80 Cu.m 2,627.90 7,556.30
(e) Ratio 1: 6: 18 100Cft 7,440.20 19,935.80 Cu.m 2,627.90 7,041.35
(f) Ratio 1: 7:20 100Cft 7,440.20 19,142.00 Cu.m 2,627.90 6,760.95

4 Extra on item No. 3 above, for sedimentation tank or filter


beds of Public Health Engineering Works: The stone ballast, crushed bajri,
round shingle from nallah, or brick
(a) in bed 100Cft 2,431.85 - Cu.m 858.95 - ballast may be used according to
their comparative cheaper rates in
(b) on slope 100Cft 3,627.75 - Cu.m 1,281.30 - various areas of the Province.
5 Cement concrete plain including placing, 20.1
compacting, finishing and curing
complete (including screening and
washing of stone aggregate):

(a) Ratio 1: 1:2 100Cft 10,129.40 54,535.40 Cu.m 3,577.70 19,261.90


(b) Ratio 1: 1½: 1½ 100Cft 10,129.40 53,766.20 Cu.m 3,577.70 18,990.20
(c) Ratio 1: 1½: 3 100Cft 10,129.40 43,969.40 Cu.m 3,577.70 15,530.00
(d) Ratio 1: 2: 3 100Cft 10,129.40 42,011.00 Cu.m 3,577.70 14,838.30
(e) Ratio 1: 3: 3 100Cft 10,129.40 37,453.40 Cu.m 3,577.70 13,228.55
(f) Ratio 1: 2: 4 100Cft 10,129.40 38,271.80 Cu.m 3,577.70 13,517.60
(g) Ratio 1: 2: 6 100Cft 10,129.40 34,119.80 Cu.m 3,577.70 12,051.10
(h) Ratio 1: 3: 6 100Cft 10,129.40 32,941.40 Cu.m 3,577.70 11,634.90
(i) Ratio 1: 4: 8 100Cft 10,129.40 29,079.80 Cu.m 3,577.70 10,271.00

Chap-6 (Concrete) Page 41


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

6 Providing and laying reinforced cement concrete (including 20.4 1) The rate includes rendering floor
prestressed concrete), using coarse sand and screened surface smooth, and the plastering
graded and washed aggregate, in required shape and design, done for making up all surfaces
including forms, moulds, shuttering, lifting, compacting, after removing centring.
curing, rendering and finishing exposed surface, complete
(but excluding the cost of steel reinforcement, its fabrication 2) Plastering done under soffit of
and placing in position, etc.):- R.C.C. roof slab meant for human
habitation buildings shall be paid
(a) (i) Reinforced cement concrete in roof slab, beams, extra.
columns lintels, girders and other structural members laid in
situ or precast laid in position, or prestressed members cast 3) This item shall not be applicable
in situ, complete in all respects:- to factory made units.
(1) Type A (nominal mix 1:1:2) Per Cft 187.65 716.20 Cu.m 6,627.80 25,296.20 4) Composite rate shall be reduced by Rs:
(2) Type B (nominal mix 1: 1½: 3) Per Cft 187.65 612.05 Cu.m 6,627.80 21,617.60 20.00 P.Cft & Rs: 25.00 P.Cft if chenab sand
(3) Type C (nominal mix 1: 2: 4) Per Cft 187.65 556.05 Cu.m 6,627.80 19,639.70 and local sand is used respectively.
(a) (ii) Reinforced cement concrete in retaining/ Shear walls laid in situ or
precast laid in position, or prestressed members cast in situ ( Formwork on
both sides) , complete in all respects:
(a) Type A (nominal mix 1:1:2)
(i) Upto 9" thick (Avg) Per Cft 238.60 774.90 Cu.m 8,417.90 27,338.70
(ii) More Than 9" thick (Avg) Per Cft 219.41 733.10 Cu.m 7,741.03 25,862.95
(b) Type B (nominal mix 1:1-1/2:3)
(i) Upto 9" thick (Avg) Per Cft 238.60 668.40 Cu.m 8,417.90 23,581.40
(ii) More Than 9" thick (Avg) Per Cft 219.41 626.60 Cu.m 7,741.03 22,105.61
(c) Type C (nominal mix 1:2:4)
(i) Upto 9" thick (Avg) Per Cft 238.60 613.95 Cu.m 8,417.90 21,659.35
(ii) More Than 9" thick (Avg) Per Cft 219.40 572.10 Cu.m 7,741.05 20,183.55
(a)(iii) Reinforced cement concrete in slab of rafts / strip
foundation, base slab of column and retaining walls; etc and
footing beams, other structural members other than those mentioned in
6(a) (i)&(ii) above not requiring form work (i.e. horizontal
shuttering) complete in all respects:-
(1) Type A (nominal mix 1: 1: 2) Per Cft 140.75 622.45 Cu.m 4,971.30 21,984.95
(2) Type B (nominal mix 1: 1½: 3) Per Cft 140.75 512.90 Cu.m 4,971.30 18,115.65
(3) Type C (nominal mix 1: 2: 4) Per Cft 140.75 456.85 Cu.m 4,971.30 16,135.95

(b) Precast reinforced cement concrete and prestressed


reinforced cement concrete in columns, beams, lintels, stair
cases, shelves, etc.
(1) Type A (nominal mix 1: 1: 2) Per Cft 183.40 696.00 Cu.m 6,477.70 24,582.70
(2) Type B (nominal mix 1:1½: 3) Per Cft 183.40 591.05 Cu.m 6,477.70 20,875.90
(3) Type C (nominal mix 1: 2: 4) Per Cft 183.40 535.85 Cu.m 6,477.70 18,926.20
(c) Erecting and fixing in position, precast cement concrete
or stone slab in roofs or lintels, etc. lift unto 20 ft., (6m) Per Cft 80.85 103.45 Cu.m 2,855.60 3,653.85
including all charges.
(d) Add extra labour for R.C. concrete in Per Cft 38.20 -- Cu.m 1,349.20 -
2nd and subsequent storeys.

Chap-6 (Concrete) Page 42


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

7 Providing and casting in situ bored reinforced concrete piles * 851-1 4) Composite rate shall be reduced by Rs:
with type C concrete (nominal mix 1: 2: 4 ) , using 10% extra to 20.00 P.Cft & Rs: 25.00 P.Cft if chenab sand
cement in dry mix, and course sand, including all labour and 851-10 and local sand is used respectively.
material (except the cost of steel reinforcement and its
labour for bending and laying in position, etc. which will be
paid separately, including, screening & washing of shingle
and curing:-
i) 18 " (450 mm) dia pile Per Rft 1,146.35 1,739.95 Metre 3,760.05 5,707.05
ii) 20" (500 mm) dia pile Per Rft 1,390.90 2,123.15 Metre 4,562.15 6,963.95
iii) 22" (550 mm) dia pile Per Rft 1,743.35 2,604.45 Metre 5,718.20 8,542.60
iv) 24" (600 mm) dia pile Per Rft 2,219.50 3,273.60 Metre 7,279.95 10,737.45

8 Providing and casting in situ bored premixed reinforced concrete piles with i. Composite rate shall be reduced by Rs:
specified type of concrete using coarse sand, including all labour and 20.00 P.Cft & Rs: 25.00 P.Cft if chenab sand
materials, boring, rig machine, crane, excavator, batching plant, transit and local sand is used respectively.
mixer, I-Land etc (except the cost of steel reinforcement, its labor for
bending and laying in position and boat plateform etc) which will be paid ii. If percussion boring is used based on the
separately, including screening & washing of shingle and curing as bore log/strata, derive rate accordingly with
approved by Engineer Incharge:- In Ordinary Soil the permission of Superintending Engineer.
(a) Type-C Concrete (1:2:4)
(i) 0.46 m / 18 inch Per Rft. 1,013.45 1,560.40 Meter 3,324.10 5,118.15
(ii) 0.51 m / 20 inch Per Rft. 1,095.50 1,770.55 Meter 3,593.20 5,807.40
(iii) 0.56 m / 22 inch Per Rft. 1,240.60 2,057.40 Meter 4,069.20 6,748.20
(iv) 0.61 m / 24 inch Per Rft. 1,380.45 2,352.45 Meter 4,527.80 7,716.10
(iii) 0.76 m / 30 inch Per Rft. 1,839.10 3,358.50 Meter 6,032.25 11,015.90
(iv) 0.91 m / 36 inch Per Rft. 2,545.80 4,733.75 Meter 8,350.25 15,526.75
(v) 1.07 m / 42 inch Per Rft. 3,341.05 6,319.10 Meter 10,958.60 20,726.65
(vi) 1.22 m / 48 inch Per Rft. 3,563.35 7,453.05 Meter 11,687.75 24,445.95
(vii) 1.37 m / 54 inch Per Rft. 3,803.60 8,726.50 Meter 12,475.90 28,623.00
(viii) 1.52 m / 60 inch Per Rft. 5,236.60 11,314.25 Meter 17,176.00 37,110.75
(ix) 1.68 m / 66 inch Per Rft. 6,046.10 13,400.10 Meter 19,831.25 43,952.30
(x) 1.83 m / 72 inch Per Rft. 6,617.80 15,369.65 Meter 21,706.40 50,412.40
(xi) 1.98 m / 78 inch Per Rft. 7,213.90 17,484.20 Meter 23,661.65 57,348.25
(xii) 2.13 m / 84 inch Per Rft. 8,324.95 20,237.15 Meter 27,305.85 66,377.90
(b) Type-B Concrete (1:1-1/2:3)
(i) 0.46 m / 18 inch Per Rft. 1,013.45 1,656.75 Meter 3,324.10 5,434.05
(ii) 0.51 m / 20 inch Per Rft. 1,095.50 1,889.40 Meter 3,593.20 6,197.15
(iii) 0.56 m / 22 inch Per Rft. 1,240.60 2,204.85 Meter 4,069.20 7,231.90
(iv) 0.61 m / 24 inch Per Rft. 1,385.70 2,528.90 Meter 4,545.15 8,294.80
(iii) 0.76 m / 30 inch Per Rft. 1,843.85 3,630.80 Meter 6,047.85 11,909.00
(iv) 0.91 m / 36 inch Per Rft. 2,545.80 5,119.00 Meter 8,350.25 16,790.35
(v) 1.07 m / 42 inch Per Rft. 3,219.95 6,722.35 Meter 10,561.35 22,049.30
(vi) 1.22 m / 48 inch Per Rft. 3,563.35 8,137.90 Meter 11,687.75 26,692.40
(vii) 1.37 m / 54 inch Per Rft. 3,803.60 9,593.35 Meter 12,475.90 31,466.15
(viii) 1.52 m / 60 inch Per Rft. 5,236.60 12,384.40 Meter 17,176.00 40,620.85
(ix) 1.68 m / 66 inch Per Rft. 6,046.10 14,694.95 Meter 19,831.25 48,199.50
(x) 1.83 m / 72 inch Per Rft. 6,617.80 16,910.65 Meter 21,706.40 55,466.90
(xi) 1.98 m / 78 inch Per Rft. 7,213.90 17,484.20 Meter 23,661.65 57,348.25
(xii) 2.13 m / 84 inch Per Rft. 8,324.95 22,334.65 Meter 27,305.85 73,257.65

Chap-6 (Concrete) Page 43


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

Strength Based Concrete


9
Placing, compacting, finishing and curing of concrete using Ordinary
Portland Cement / Sulphate resisting cement / Slag cement as may be
required; including screening, washing of aggregates and mixing of
constituents using batching plant, admixture, Transportation by transit
mixer, pouring with pump in the required proportions to achieve a
nominal cylindrical strength in the field as per ACI 214, with the specified
consistency. i/c the cost of shuttering, compaction with Viberator, cost of
Admixture, as approved and directed by the Engineer Incharge.

(a) Superstructure (Slabs, Beams, Columns and others requiring


formwork)
(i) 7000 PSI Per Cft 110.00 769.25 Cu.m 3,881.25 27,139.30
(ii) 6000 PSI Per Cft 110.00 741.45 Cu.m 3,881.25 26,159.00
(iii) 5000 PSI Per Cft 110.00 711.80 Cu.m 3,881.25 25,111.45
(iv) 4000 PSI Per Cft 110.00 685.35 Cu.m 3,881.25 24,179.90
(vi) 3000 PSI Per Cft 110.00 604.35 Cu.m 3,881.25 21,320.90
(b) Retaining/ Shear walls laid in situ or precast laid in position, or
prestressed members cast ( Formwork on both sides)
i) 7000 PSI
(i) Upto 9" thick Per Cft 105.75 755.65 Cu.m 3,731.70 26,659.65
(ii) More Than 9" Thick Per Cft 105.75 743.00 Cu.m 3,731.70 26,212.60
ii) 6000 PSI
(i) Upto 9" thick Per Cft 105.75 727.85 Cu.m 3,731.70 25,679.35
(ii) More Than 9" Thick Per Cft 105.75 715.20 Cu.m 3,731.70 25,232.25
iii) 5000 PSI
(i) Upto 9" thick Per Cft 105.75 698.20 Cu.m 3,731.70 24,631.80
(ii) More Than 9" Thick Per Cft 105.75 685.55 Cu.m 3,731.70 24,184.75
iv) 4000 PSI
(i) Upto 9" thick Per Cft 105.75 671.80 Cu.m 3,731.70 23,700.25
(ii) More Than 9" Thick Per Cft 105.75 659.15 Cu.m 3,731.70 23,253.15
v). 3000 PSI
(i) Upto 9" thick Per Cft 105.75 590.75 Cu.m 3,731.70 20,841.25
(ii) More Than 9" Thick Per Cft 105.75 578.10 Cu.m 3,731.70 20,394.15
( c) Substructure (Foundations, Raft, Strip and Footing Beams)
(i) 7000 PSI Per Cft 59.90 657.15 Cu.m 2,113.35 23,184.90
(ii) 6000 PSI Per Cft 59.90 630.40 Cu.m 2,113.35 22,240.20
(iii) 5000 PSI Per Cft 59.90 601.80 Cu.m 2,113.35 21,231.65
(iv) 4000 PSI Per Cft 59.90 564.55 Cu.m 2,113.35 19,917.25
(vi) 3000 PSI Per Cft 59.90 500.95 Cu.m 2,113.35 17,674.05

Chap-6 (Concrete) Page 44


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

10 Providing ,laying,compacting and curing Cyclopean/plum/rubble concrete


in (40:60) ratio (plum:Concrete) using pre-mixed Cement Concrete of
specified ratio by using Ordinary Portland Cement including screening
washing of aggregate ;mixing of constituents by using batching
plant,transported by transit mixer and pouring under gravity,with specified
consistency i/c the cost of compaction with Viberator but excluding the
cost of Admixture and carriage charges, as approved and directed by the
Engineer Incharge.
i. 1:3:6 P.Cft 53.10 260.00 Cu.m 1,873.40 9,173.25
ii. 1:2:4 P.Cft 53.10 295.95 Cu.m 1,873.40 10,441.80
11 Fabrication of mild steel reinforcement deformed bar cage of specified * 851.5 The overlap will be paid extra vide FD
yield strength for R.C.C bored piles including cutting bending, lowering of Notification No.RO(TECH)FD2-11/2010
cage with crane in position, welding and fastening, including the cost of dated 08.03.2010.
binding wire, Crane machine (also includes removal of rust from the bars)
as approved and directed by the Engineer Incharge.
i) Deformed Bars Grade-40 Per Cwt. 115.35 14,532.90 100 Kg 227.10 28,608.05
ii) Deformed Bars Grade-60 Per Cwt. 115.35 14,716.10 100 Kg 227.10 28,968.75
12 Fabrication of mild steel reinforcement for cement concrete, * 821 The rate includes wastage, overlaps
including cutting, bending, laying in position, making joints and steel chairs, etc. complete in all respect.
and fastenings, including cost of binding wire and labour
charges for binding of steel reinforcement (also includes
removal of rust from bars):-
(a) Plain bars Per Cwt. 747.45 12,990.60 100 kg 1,471.35 25,572.05
(b) Deformed bars (Grade-40) ditto 747.45 15,960.60 100 kg 1,471.35 31,418.50
('c) Deformed bars (Grade-60) ditto 747.45 16,158.60 100 kg 1,471.35 31,808.25

13 Precast cement concrete solid or face blocks (1:2:4), Per Cft 144.20 409.80 Cu.m 5,093.15 14,474.15 20.2 The cost includes mortar (1:5) and labour for
including cost of templates. fixing at any height.

14 Precast cement concrete hollow blocks (1: 2: 4) , including Per Cft 146.90 324.10 Cu.m 5,188.50 11,447.20 20.2 The cost includes mortar (1:5) and labour for
cost of templates and constructing walls thereof. fixing at any height.

15 Providing and fixing ornamental cement jali 2" (50 mm) thick Per Sft 59.80 106.90 Sq.m 643.45 1,150.25 20.1 to
(1: 2: 4), without steel. 20.4

16 Extra labour for laying concrete plain or reinforced:

(a) above 20' (6 m) upto 40'(12 m) height 100Cft 4,076.15 - Cu.m 1,439.70 -
(b) for every additional 10'(3 m) height. 100Cft 2,547.60 - Cu.m 899.80 -

17 Extra labour for work of weirs, rail or road bridges, syphons, and 100Cft 1,019.05 - Cu.m 359.95 -
concreting in superstructure

18 Making reinforced cement concrete spout, including fixing in Each 747.45 1,088.40 Each 747.45 1,088.40 20.4
position (2½' x 6" x5") (760 mmx150 mm x 125 mm)

19 Making holes upto 3"(75 mm) dia 18"(450 mm) depth in cement Per hole 1,793.90 - Each 1,793.90 - 20.1
concrete or stone masonry walls and repairing.

Chap-6 (Concrete) Page 45


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

20 Extra labour for skipping concrete in wells. 100Cft 6,239.20 - Cu.m 2,203.70 - 20.1

21 Nicking concrete surface:


(a) Cement concrete surface 100Sft 686.40 - Sq.m 73.85 -
(b) Lime concrete surface 100Sft 226.50 - Sq.m 24.35 -

22 Preparing, watering and ramming surface for laying concrete


(for Headworks only):-
(a) Horizontal floor 100Sft 639.15 - Sq.m 68.75 -
(b) Glacis and crest 100Sft 941.15 - Sq.m 101.25 -
(c) Inverted filters 100Sft 299.00 - Sq.m 32.15 -

23 Fabrication of high tensile steel prestressing cables for 100 Kg. 9,177.60 72,482.65 100 Kg. 9,177.60 72,482.65 * 811-1 The rate includes wastage in
prestressed (post tensioned) concrete, including assembling by to cutting and breakage in stressing,
drawing the H.T. wire through metal spacer plate, inserting in helix 811-11 etc.
core and taping or tying, sheathing in longitudinally welded metal
corrugated sheath, positioning , anchorage with male and female
set of anchorage cone, forming ducts for transverse cable,
stressing cables with jack at both ends as per stressing schedule,
maintaining stressing record and supply the same in the approved
proforma to the Engineer-in-charge, making loop at blind end,
including all materials required for it, grouting the cable ducts with
cement, cutting projected ends and making good recesses, etc.,
complete in all respects.
24 Fabrication of High Tensile steel reinforcement for prestressed 100kg 5,398.80 69,353.75 100kg 5,398.80 69,353.75 1) The rate includes wastage in
(pretension) concrete work, including inserting wire in moulds, cutting and breakage in stressing,etc.
providing M.S. shear bars, spacers and lift hooks, male and
female anchorage, tie down, struts, stressing cables, maintaining 2) Quantity of H. T. wire will form
stress record and supply the same in approved proforma to the basis of payment.
Engineer-in-charge, cutting wires and projecting ends and making 3) This item shall not be applicable
good recesses, etc., complete in all respects. to factory made units.

25 Lifting, transporting and placing precast prestressed concrete * 811-1


B eam, Girder and other members (excluding battens) etc. in to
Position on the bridge to correct alignment and level, etc. 811-11
complete

i) Beam upto 50 ft. (15 m) length 100Cft -- 2,920.85 Cu.m -- 1,031.65


ii) Beam above 50 ft. (15m) upto 75 ft. (22.5m) length 100Cft -- 4,053.05 Cu.m -- 1,431.55
iii) Beam above 75ft. (22.5m) upto 100ft. (30m) length 100Cft -- 5,683.15 Cu.m -- 2,007.30
iv) Beam above 100ft. (30m) upto 150ft.(45m) length 100Cft -- 7,453.20 Cu.m -- 2,632.45
v) Beam above 150ft. (45m) length 100Cft -- 9,354.25 Cu.m -- 3,303.90

26 Providing and laying foam concrete 3 inch (75 mm) thick, Per Sft. 57.60 128.25 Sq.m. 619.80 1,379.95
using cement sand in the ratio of 1:2 and aluminium powder
at the rate of 0.2% of the cement, sand mix,

Chap-6 (Concrete) Page 46


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

27 Providing and fixing 6 in(150 mm). wide curved sheet of


required shape fixed on face of the construction joint with G.I.
screw,1.5 in (40 mm) long to cover construction joints
vertically:-

i) aluminium sheet 1/16 in(1.5 mm) thick Per Rft. 31.30 151.10 Metre 102.65 495.60
ii) G.I. sheet, 18 SWG Per Rft. 32.05 234.70 Metre 105.10 769.80

28 Providing and fixing 1/8" (3 mm) thick 3" (75 mm) wide aluminium
strip on horizontal and vertical expansion joints in walls, columns,
ceilings and floors etc., including cost of clips/screws etc.,
complete in all respects:-

a) On interior surface (without mastic strip) Per Rft. 28.60 148.40 Metre 93.80 486.75
b) On exterior surface (with mastic strip) Per Rft. 28.60 156.80 Metre 93.80 514.30

29 Providing and fixing 1/16" (1.5 mm) thick copper flashing on Per Sft. 29.90 160.70 Sq.m 321.70 1,729.15
expansion joints complete in all respects.

30 Providing and fixing 6 in (150 mm). wideG.I. sheet 18SWG. Per Rft. 10.60 196.10 Metre 34.75 643.20
stopper to expansion joint.

31 Providing embeding 10" (250 mm) wide ¼" (6 mm) thick Per Rft. 42.90 282.90 Metre 140.70 927.85
rubber water stopper in expansion joints of R.C.C. roof
slab complete in all respects.

32 Filling expansion joints with bitumen. sand & saw dust in Per Rft P.Metre/
ratio 1:2:2. per inch 6.35 35.55 Per 25 mm 20.85 116.60
width Width

33 Filling expansion joints with bitumen. Per Rft. 111.55 - Metre 365.90 -

34 Laying asphaltic mixture in expansion joints. Per Rft. 89.15 - Metre 292.40 - Material to be paid on actuals.

35 Providing and fixing theremopore (foamed polythene)


sheet in horizontal and vertical expansion joints:

a) 1" (25 mm) thick thermopore sheet Per Sft. 11.95 18.40 Sq.m 128.60 198.00
b) 1½" (40 mm) thick thermopore sheet ditto 11.95 24.85 " 128.60 267.40

36 Providing and laying damp proof course of cement concrete


1:2: 4(using cement, sand and shingle), including bitumen
coating :-

(a) with one coat bitumen and one coat polythene sheet
500gauge

i) 1½" thick (40 mm) 100Sft 2,656.05 8,702.95 Sq.m 285.80 936.45
ii) 2" thick (50 mm) 100Sft 2,656.05 9,788.15 Sq.m 285.80 1,053.20
iii) 3" thick (75 mm) 100Sft 2,770.45 12,265.25 Sq.m 298.10 1,319.75

Chap-6 (Concrete) Page 47


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

(b) with 2 coats of bitumen:

i) 1½" thick (40 mm) 100Sft 2,656.05 9,336.75 Sq.m 285.80 1,004.65
ii) 2" thick (50 mm) 100Sft 2,656.05 10,420.75 Sq.m 285.80 1,121.25
iii) 3" thick (75 mm) 100Sft 2,770.45 12,897.85 Sq.m 298.10 1,387.80

37 Providing and laying damp proof course with cement sand


plaster and bitumen coating:-

(a) with one coat of bitumen and one coat of polythene sheet
500 gauge :-

i) Ratio 1: 4
a) ½" thick (13 mm) 100Sft 2,484.45 5,757.35 Sq.m 267.35 619.50
b) ¾" thick (20 mm) 100Sft 2,484.45 6,306.35 Sq.m 267.35 678.55

ii) Ratio 1:3


a) ½ " thick (13 mm) 100Sft 2,484.45 5,935.20 Sq.m 267.35 638.65
b) ¾ " thick (20mm) 100Sft 2,484.45 6,516.60 Sq.m 267.35 701.20

iii) Ratio 1:2


a) ½ " thick (13 mm) 100Sft 2,484.45 6,160.60 Sq.m 267.35 662.90
b) ¾ " thick (20 mm) 100Sft 2,484.45 6,980.70 Sq.m 267.35 751.10

(b) with 2 coats of bitumen:-

i) Ratio 1: 4
a) ½" thick (13 mm) 100Sft 2,484.45 6,078.30 Sq.m 267.35 654.05
b) ¾" thick (20 mm) 100Sft 2,484.45 6,627.50 Sq.m 267.35 713.10

ii) Ratio 1:3


a) ½ " thick (13 mm) 100Sft 2,484.45 6,259.35 Sq.m 267.35 673.50
b) ¾ " thick (20 mm) 100Sft 2,484.45 6,840.75 Sq.m 267.35 736.05

iii) Ratio 1:2


a) ½ " thick (13 mm) 100Sft 2,484.45 6,702.15 Sq.m 267.35 721.15
b) ¾ " thick (20 mm) 100Sft 2,484.45 7,572.60 Sq.m 267.35 814.80

38 Providing and laying vertical damp proof course with cement


sand plaster and bitumen coating:-

(a) with one coat of bitumen and one coat of polythene sheet
500 gauge:

i) Ratio 1: 4
a) ½" thick (13 mm) 100Sft 2,484.45 5,538.85 Sq.m 267.35 596.00
b) ¾" thick (20 mm) 100Sft 2,484.45 6,089.00 Sq.m 267.35 655.20

Chap-6 (Concrete) Page 48


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

ii) Ratio 1:3


a) ½ " thick (13 mm) 100Sft 2,484.45 5,717.80 Sq.m 267.35 615.25
b) ¾ " thick (20 mm) 100Sft 2,484.45 6,299.20 Sq.m 267.35 677.80

iii) Ratio 1:2


a) ½ " thick (13 mm) 100Sft 2,484.45 6,160.60 Sq.m 267.35 662.90
b) ¾ " thick (20 mm) 100Sft 2,484.45 7,031.10 Sq.m 267.35 756.55

(b) with 2 coats of bitumen:-

i) Ratio 1: 4
a) ½" thick (13 mm) 100Sft 2,484.45 6,077.80 Sq.m 267.35 653.95
b) ¾" thick (20 mm) 100Sft 2,484.45 6,627.50 Sq.m 267.35 713.10

ii) Ratio 1:3


a) ½ " thick (13 mm) 100Sft 2,484.45 6,256.35 Sq.m 267.35 673.20
b) ¾ " thick (20 mm) 100Sft 2,484.45 6,837.75 Sq.m 267.35 735.75

iii) Ratio 1:2


a) ½ " thick (13 mm) 100Sft 2,484.45 6,699.40 Sq.m 267.35 720.85
b) ¾ " thick (20 mm) 100Sft 2,484.45 7,569.60 Sq.m 267.35 814.50

39 Grouting concrete between, the grooves of gates, including 100Cft 11,943.35 - Cu.m. 4,218.40 -
shuttering.

40 Chiesel dressing concrete surface on sides of grooves. 100Sft 377.50 - Sq.m 40.60 -

41 Laying and ramming dry ballast or kankar. 100Cft 4,139.85 - Cu.m 1,462.20 -

42 Hoisting and placing in position R.C.C. shelves. per No. 133.25 - per No. 133.25 -

43 Breaking brick ballast, screening and stacking:-


(a) 2"(50 mm) ring 100Cft. 3,184.50 - Cu.m 1,124.75 -
(b) 1½ "(40 mm) ring 100Cft. 3,566.65 - Cu.m 1,259.75 -
(c) 1" (25 mm) ring 100Cft. 4,139.85 - Cu.m 1,462.20 -
(d) Jhama ballast ¾"(20 mm) ring 100Cft. 4,776.75 - Cu.m 1,687.15 -

44 Supplying and fixing broken glasses on court yard walls, Per Rft 99.65 179.50 metre 326.85 588.75
including 1:3: 6 cement concrete coping.

45 Crushing stone ballast by machine. 100Cft 3,184.50 - Cu.m. 1,124.75 -


This does not include the charges for working
of crushers, but includes manual labour for
carriageof stone to crusher within three chains
(90 m) and also stacking the product after
crushing within three chains (90 m).
46 Breaking stone ballast screened and stacked:-
(a) 2" ring (50 mm) 100Cft. 3,566.65 - Cu.m. 1,259.75 -
(b) 1½ " ring (40 mm) 100Cft. 4,139.85 - Cu.m. 1,462.20 -

Chap-6 (Concrete) Page 49


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

(c) 1" ring (25 mm) 100Cft. 4,776.75 - Cu.m. 1,687.15 -


d) ½ " ring (13 mm) 100Cft. 6,369.00 - Cu.m. 2,249.55 -
(e)1/8" to ¼" ring (3 mm to 6 mm) 100Cft. 10,827.30 - Cu.m. 3,824.20 -
47 Screening and stacking stone ballast shingle or bajri, etc. 100Cft. 1,019.05 - Cu.m. 359.95 -
48 Washing ballast, bajri or shingle. 100Cft. 1,019.05 - Cu.m. 359.95 -
49 Erecting and carting sun shades of precast R.C. concrete
upto 5' x 2½' (1.50 m x 0.76 m) Each 579.20 - Each 579.20 -
50 Extra for Kentledge and loading arangements for test pile to ensure Per Cwt. 1.00 23.95 Per M.Ton 22.40 527.50
structural and Geotechnical soundness of pile upto a maximum test load
applying in stages i/c the hiring of machinary required for complete job
and furnishing a report in this regard by a qualified/authorized Geo
Technical Engineer by studying the data of at least seven days as approved
and directed by the Engineer Incharge.
51 Making Temporary floating plateform comprising of required Nos. of Each 8,969.40 81,279.40 Each 8,969.40 81,279.40
unifloats in running water / pond to place machinery, manpower and
proper access complete in all respect as approved and directed by the
Engineer Incharge.
52 Providing and fixing precast Edge Kerb Stone (4"to 6" thick), of 3500 PSI * 1203-1
Compressive Strength, embeded in PCC 1:2:4 over lean concrete 1:4:8 etc to
complete in all respect. 1203-3
a) Without Painting
(i) 14" high Per Rft 108.35 465.45 Meter 355.40 1,526.60
(ii) 18" high Per Rft 111.70 478.00 Meter 366.30 1,567.80
b) With Painting
(i) 14" high Per Rft 138.05 518.90 Meter 452.85 1,701.95
(ii) 18" high Per Rft 141.40 531.45 Meter 463.75 1,743.10
53 Providing & fixing precast Edge Kerb Stone (4" to 6" thick) and 14" high
of Compressive Strength of 3500 PSI laid in cement sand mortar (1:3) over
pre-laid brick masonary for drain cum footpath etc complete in all respect.

(i) Without painting Per Rft 90.85 361.60 Meter 298.05 1,186.10
(ii) With painting Per Rft 120.60 415.05 Meter 395.50 1,361.40
54 Providing and laying Kerb Block / RCC Barrier of Concrete having
compressive strength of 4000 PSI ratio (1:1.25:2.25) of required size, over
Lean Concrete of (1:4:8), with Slip form Paver / power kerber machine,
batching plant, excluding the cost of additive / super plasticizer, steel
reinforcement and its labour for bending and laying in position as specified
etc complete in all respect. If batching plant is not used, reduce rate:-
a) Kerb Block Per Cft 106.55 527.70 Cu.m 3,763.00 18,637.65 a) Rs.23.85 P.Cft or Rs.843.10 P.CUM
b) R.C.C Barrier
(i) Single Face Per Cft 84.30 505.45 Cu.m 2,978.20 17,852.85 b-i) Rs. 18.05 P.Cft or Rs. 638.25 P.CUM
(ii) Double Face Per Cft 86.75 507.90 Cu.m 3,063.65 17,938.30 b-ii) Rs. 18.80 P.Cft or Rs. 665.10 P.CUM

Chap-6 (Concrete) Page 50


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

55 Providing and mixing super plasticizer (water reducing admixture) as


i. The use of Super Plasticizer will be subject
defined in ASTM C-94 in order to achieve the required consistancy /
to the permission of Superintending Engineer.
workablility measured by the slump or to acheive specified strenth in the Per Gallon 13.60 613.65 Per Ltr. 3.00 135.00
ii. Used in the ratio of (0.05% to 1.00%) by
ratio as proposed by the designer in the concrete mix design etc. complete
weight of cement.
in all respect as appprved and directed by Engineer incharge.

Specification numbers correspond to book of standard specification of Road and Bridge Construction, "1971"

Chap-6 (Concrete) Page 51


7. BRICK WORK
1 Rates for all finsihed works include the removal of surplus debris, unused material and byproducts.
2 The rates apply to all sizes of bricks, including the modular bricks of size 8"x4"x4" (200x100x100 mm) nominal.

MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

1 Pacca brick work in mud mortar in buildings: 21.1 Masonry of boundary wall to be
to considered as masonry other than
i) in foundation and plinth 100Cft. 5,252.70 24,965.70 Cu.m 1,855.25 8,817.90 21.4 building.
ii) in ground floor 100Cft. 6,958.10 26,671.10 Cu.m 2,457.60 9,420.25
The composite rate is to be
reduced by 7% and 14%, if 2nd or
3rd class bricks are used.
2 Add extra labour on item No. 1 for brick work in:-

i) first floor 100Cft. 1,362.25 -- Cu.m 481.15 -


ii) second floor 100Cft. 3,067.70 -- Cu.m 1,083.50 -
iii) third floor 100Cft. 4,773.10 -- Cu.m 1,685.85 -
iv) fourth & subsequent floors 100Cft. 7,674.50 -- Cu.m 2,710.65 -

3 Pacca brick work in mud mortar other than building:- 21.1 to Same remarks as against
21.4 item No. 1 above
i) upto 20 ft. (6.1 m) height 100Cft. 7,160.85 26,873.85 Cu.m 2,529.20 9,491.85
ii) extra labour for every 5 ft. (1.5 m) 100Cft. 1,362.25 -- Cu.m 481.15 -
additional height, or part thereof.

4 Pacca brick work in foundation and plinth in:- ditto Same remarks as against
item No. 1 above.
i) Cement, sand mortar:-

Ratio 1:2 100Cft. 6,909.60 36,645.60 Cu.m 2,440.40 12,943.25


Ratio 1:3 100Cft. 6,909.60 34,260.60 Cu.m 2,440.40 12,100.85
Ratio 1:4 100Cft. 6,909.60 32,829.60 Cu.m 2,440.40 11,595.40
Ratio 1:5 100Cft. 6,909.60 31,875.60 Cu.m 2,440.40 11,258.45
Ratio 1:6 100Cft. 6,909.60 31,158.85 Cu.m 2,440.40 11,005.30
Ratio 1:7 100Cft. 6,909.60 30,689.40 Cu.m 2,440.40 10,839.50
Ratio 1:8 100Cft. 6,909.60 30,277.55 Cu.m 2,440.40 10,694.05

ii) lime, cement sand mortar:- 21.1 The rate of lime mortar also
includes grinding of mortar.
Ratio 1:1:6 100Cft. 6,909.60 31,946.20 Cu.m 2,440.40 11,283.40
Ratio 1:1:7 100Cft. 6,909.60 31,416.50 Cu.m 2,440.40 11,096.30
Ratio 1:1:8 100Cft. 6,909.60 30,988.20 Cu.m 2,440.40 10,945.05
Ratio 1:1:9 100Cft. 6,909.60 30,628.95 Cu.m 2,440.40 10,818.15
Ratio 1:1:10 100Cft. 6,909.60 30,359.75 Cu.m 2,440.40 10,723.05

iii) lime, sand mortar 1:2 100Cft. 6,909.60 30,074.95 Cu.m 2,440.40 10,622.45 ditto ditto

chapter-7(Brickwork).xls Page 52
MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

5 Pacca brick work in ground floor:- ditto i) The composite rate is to


be reduced by 7% and 14%,
i) cement, sand mortar:- if 2nd or 3rd class bricks are
used.
Ratio 1:2 100Cft. 9,124.60 38,860.60 Cu.m 3,222.80 13,725.55 ii) Masonry of boundary wall
Ratio 1:3 100Cft. 9,124.60 36,475.60 Cu.m 3,222.80 12,883.20 to be considered as masonry
Ratio 1:4 100Cft. 9,124.60 35,044.60 Cu.m 3,222.80 12,377.75 other than building.
Ratio 1:5 100Cft. 9,124.60 34,090.60 Cu.m 3,222.80 12,040.80
Ratio 1:6 100Cft. 9,124.60 33,373.80 Cu.m 3,222.80 11,787.65
Ratio 1:7 100Cft. 9,124.60 32,904.40 Cu.m 3,222.80 11,621.85
Ratio 1:8 100Cft. 9,124.60 32,490.00 Cu.m 3,222.80 11,475.45
ii) lime, cement, sand mortar:- The rate of lime mortar also
includes grinding of mortar.
Ratio 1:1:6 100Cft. 9,124.60 34,161.15 Cu.m 3,222.80 12,065.70
Ratio 1:1:7 100Cft. 9,124.60 33,638.10 Cu.m 3,222.80 11,881.00
Ratio 1:1:8 100Cft. 9,124.60 33,203.20 Cu.m 3,222.80 11,727.35
Ratio 1:1:9 100Cft. 9,124.60 32,843.90 Cu.m 3,222.80 11,600.45
Ratio 1:1:10 100Cft. 9,124.60 32,575.75 Cu.m 3,222.80 11,505.75
iii) lime, sand mortar 1:2 100Cft. 9,124.60 32,289.90 Cu.m 3,222.80 11,404.80 The rate of lime mortar also
includes grinding of mortar.
6 Add extra labour on item No. 5 for brickwork
in:-
i) first floor 100Cft. 1,362.25 -- Cu.m 481.15 -
ii) second floor 100Cft. 3,067.70 -- Cu.m 1,083.50 -
iii) third floor 100Cft. 4,773.10 -- Cu.m 1,685.85 -
iv) fourth & subsequent floors 100Cft. 7,674.50 -- Cu.m 2,710.65 -

7 Pacca brick work other than building upto 10ft. (3 m) 21.1 i) The composite rate is to be
height. to reduced by 7% and 14%, if 2nd or
21.5 3rd class bricks are used.
i) cement, sand mortar:-
ii) Workshops, godowns,, bins,
Ratio 1:2 100Cft. 8,021.90 37,757.90 Cu.m 2,833.35 13,336.10 house type godowns, reservoirs,
Ratio 1:3 100Cft. 8,021.90 35,372.90 Cu.m 2,833.35 12,493.70 filter beds, storage tanks, wells,
Ratio 1:4 100Cft. 8,021.90 33,941.90 Cu.m 2,833.35 11,988.30 screening chambers, collecting
Ratio 1:5 100Cft. 8,021.90 32,987.90 Cu.m 2,833.35 11,651.35 tanks, manholes etc. are to be
Ratio 1:6 100Cft. 8,021.90 32,271.15 Cu.m 2,833.35 11,398.15 treated as masonry other than
Ratio 1:7 100Cft. 8,021.90 31,801.70 Cu.m 2,833.35 11,232.35 buildings.
Ratio 1:8 100Cft. 8,021.90 31,389.85 Cu.m 2,833.35 11,086.90
ii) lime, cement, sand mortar:- The rate of lime mortar also
includes grinding of mortar.
Ratio 1:1:6 100Cft. 8,021.90 33,058.45 Cu.m 2,833.35 11,676.25
Ratio 1:1:7 100Cft. 8,021.90 32,528.75 Cu.m 2,833.35 11,489.15
Ratio 1:1:8 100Cft. 8,021.90 32,100.50 Cu.m 2,833.35 11,337.90
Ratio 1:1:9 100Cft. 8,021.90 31,741.05 Cu.m 2,833.35 11,210.95
Ratio 1:1:10 100Cft. 8,021.90 31,472.00 Cu.m 2,833.35 11,115.90

iii) lime, sand mortar 1:2 100Cft. 8,021.90 31,187.20 Cu.m 2,833.35 11,015.30 ditto

chapter-7(Brickwork).xls Page 53
MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

8 Add extra labour on item No. 7, for every 10ft.(3 m) 100Cft. 1,362.25 -- Cu.m 481.15 -
additional height, or part thereof.

9 Extra labour for arch work in brick masonry, including 100Cft. 2,568.70 -- Cu.m 907.25 - 21.5
labour for centring and decentring.

10 Extra for pacca brick work in steining of wells or any other 100Cft. 1,716.00 2,896.80 Cu.m 606.10 1,023.15 21.1 The composite rate is to be
circular masonry. to reduced by 7% and 14%, if 2nd or
21.4 3rd class bricks are used.

11 Extra labour for profile and flared walls. 100Cft. 590.30 -- Cu.m 208.50 -

12 Extra labour for pacca brick work in piers and abutment:-

i) from 10ft. to 20ft. (3 m to 6 m) height 100Cft. 674.25 -- Cu.m 238.15 -


ii) above 20 ft. (6 m) height. 100Cft. 1,362.25 -- Cu.m 481.15 -

13 Extra for face work (half brick thick) using special bricks 100Cft. 7,892.65 Cu.m 2,787.70 This item is to be executed only
instead of first class bricks. under the written permission of
Superintending Engineer.

14 Reinforced brick work in lintel of openings, laid in 1:3 Per Cft. 227.70 522.45 Cu.m 8,042.50 18,452.95
cement mortar, including all labour, material, forms,
moulds, lifting & shuttering, etc, (but excluding cost and
labour of steel reinforcement which shall be paid for
separately).

15 Extra for dressing or chamfering bricks for:-

a) special architectural bricks 100 Nos. 4,464.85 - 100 Nos. 4,464.85 -


b) all other purposes 100 Nos. 2,232.45 - 100 Nos. 2,232.45 -

16 Perforated pacca brick walling half brick thick, in ground 21.1 The composite rate is to be
floors:- to reduced by 7% and 14%, if 2nd or
21.4 3rd class bricks are used.
i) mud mortar 100 Sft. 3,473.95 8,409.40 Sqm. 373.80 904.85

ii) cement, sand mortar:-

Ratio 1:2 100 Sft. 4,572.50 12,013.70 Sqm. 492.00 1,292.65


Ratio 1:3 100 Sft. 4,572.50 11,416.85 Sqm. 492.00 1,228.45
Ratio 1:4 100 Sft. 4,572.50 11,059.70 Sqm. 492.00 1,190.00
Ratio 1:5 100 Sft. 4,572.50 10,821.20 Sqm. 492.00 1,164.35
Ratio 1:6 100 Sft. 4,572.50 10,653.65 Sqm. 492.00 1,146.35
Ratio 1:7 100 Sft. 4,572.50 10,523.55 Sqm. 492.00 1,132.35
Ratio 1:8 100 Sft. 4,572.50 10,427.90 Sqm. 492.00 1,122.05
iii) lime, cement sand mortar The rate of lime mortar also
includes grinding of mortar.

chapter-7(Brickwork).xls Page 54
MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

Ratio 1:1:6 100Sft. 4,572.50 10,838.85 Sqm. 492.00 1,166.25


Ratio 1:1:7 100Sft. 4,572.50 10,705.15 Sqm. 492.00 1,151.85
Ratio 1:1:8 100Sft. 4,572.50 10,606.10 Sqm. 492.00 1,141.20
Ratio 1:1:9 100Sft. 4,572.50 10,508.20 Sqm. 492.00 1,130.70
Ratio 1:1:10 100Sft. 4,572.50 10,450.95 Sqm. 492.00 1,124.50

iv) lime, sand mortar 1:2 100Sft. 4,572.50 10,366.40 Sqm. 492.00 1,115.45 ditto

17 Add extra labour on item No. 16 for pacca brick work in:-

i) first floor 100Sft. 688.00 - Sqm. 74.05 -


ii) second floor 100 Sft. 1,527.00 - Sqm. 164.30 -
iii) third floor 100 Sft. 2,393.40 - Sqm. 257.55 -
iv) fourth & subsequent floors 100 Sft. 3,697.90 - Sqm. 397.90 -

18 Perforated pacca brick walling one brick thick, in ground 21.1 The composite rate is to be
floor: to reduced by 7% and 14%, if 2nd or
21.4 3rd class bricks are used.
i) mud mortar 100Sft. 4,878.00 14,734.50 Sqm. 524.85 1,585.45

ii) cement, sand mortar:-

Ratio 1:2 100 Sft. 6,872.55 21,740.55 Sqm. 739.50 2,339.30


Ratio 1:3 100 Sft. 6,872.55 20,548.05 Sqm. 739.50 2,210.95
Ratio 1:4 100 Sft. 6,872.55 19,832.55 Sqm. 739.50 2,134.00
Ratio 1:5 100 Sft. 6,872.55 19,355.55 Sqm. 739.50 2,082.65
Ratio 1:6 100 Sft. 6,872.55 19,020.40 Sqm. 739.50 2,046.60
Ratio 1:7 100 Sft. 6,872.55 18,759.45 Sqm. 739.50 2,018.50
Ratio 1:8 100 Sft. 6,872.55 18,556.65 Sqm. 739.50 1,996.70

iii) lime, cement, sand mortar:- The rate of lime mortar also
Ratio 1:1:6 100Sft. 6,872.55 19,390.85 Sqm. 739.50 2,086.45 includes grinding of mortar
Ratio 1:1:7 100 Sft. 6,872.55 19,119.85 Sqm. 739.50 2,057.30
Ratio 1:1:8 100 Sft. 6,872.55 18,912.05 Sqm. 739.50 2,034.95
Ratio 1:1:9 100 Sft. 6,872.55 18,732.20 Sqm. 739.50 2,015.60
Ratio 1:1:10 100 Sft. 6,872.55 18,601.05 Sqm. 739.50 2,001.45

iv) lime, sand mortar 1:2 100Sft. 6,872.55 18,452.10 Sqm. 739.50 1,985.45 ditto

19 Add extra labour on item No. 18 for perforated pacca brick


work in:-

i) first floor 100Sft. 1,021.70 -- Sqm. 360.85 -


ii) second floor 100 Sft. 2,300.75 -- Sqm. 812.65 -
iii) third floor 100 Sft. 3,579.85 -- Sqm. 1,264.40 -
iv) fourth & subsequent floors 100 Sft. 5,755.90 -- Sqm. 2,033.00 -

chapter-7(Brickwork).xls Page 55
MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

20 Fire brick masonry in fireclay mortar:- 21.1


to
i) upto 20 ft. (6.10 m) height including all charges. Per Cft. 87.10 983.15 Cu.m 3,075.75 34,724.75 21.2

ii) Extra for every 5 ft. (1.5 m) additional height, or part 100Cft. 1,362.25 -- Cu.m 481.15 - A&C No.I dated 2.9.1998
thereof.

21 First class brick walling laid in 1:3 cement sand mortar,


reinforced with 1" (25 mm) wide 18 gauge hoop iron:- 21.19

i) 4½" (113 mm) thick walling with hoop iron, bonding 6" 100Sft. 3,886.75 17,060.35 Sq.m 418.20 1,835.70
(150 mm) apart.
ii) 4½" (113 mm) thick walling with hoop iron, bonding 100Sft. 3,482.50 15,430.90 Sq.m 374.70 1,660.35
12" (300 mm) apart.
iii) 3" (75 mm) thick walling with hoop iron, bonding 6" 100 Sft. 3,075.05 12,931.25 Sq.m 330.90 1,391.40
(150 mm) apart.
iv) 3" (75 mm) thick walling with hoop iron, bonding 12" 100 Sft. 2,460.05 10,955.45 Sq.m 264.70 1,178.80
(300 mm) apart.

22 Ghilafi work (1½ brick thick wall) 100Cft. 6,999.20 17,802.20 Cu.m 2,472.10 6,287.75 21.18

23 Dry brick pitching 100Cft. 4,263.60 23,703.60 Cu.m 1,505.90 8,372.10 21.1

24 Sun dried bricks in mud mortar 100Cft. 5,882.70 7,775.70 Cu.m 2,077.75 2,746.40 21.16

25 Pise wall (mud walling) 100Cft. 3,415.10 -- Cu.m 1,206.20 - 21.17

26 Eave brick moulded, weathered and throated with back 21.1 to 21.2
brick or drip course cornice, in 1:3 cement mortar:-

i) 3" (75 mm) thick drip course cornice Rft. 44.45 111.10 Metre 145.80 364.40 correction vide A&C No.I
ii) 4½" (113 mm) thick drip course cornice. Rft. 50.40 204.40 ditto 165.30 670.45 dated 2.9.98
iii) 4½" (113 mm) thick eave brick with back brick. Rft. 34.10 228.60 ditto 111.85 749.80

27 Laying dressed or moulded brick cornices in 1:6 cement 21.1 to 21.2


mortar, plastering or painting complete:-

i) 1 brick Rft. 50.40 80.15 Metre 165.30 262.90


ii) 2 bricks Rft. 74.30 165.25 ditto 243.70 542.00
iii) 3 bricks Rft. 99.15 251.10 ditto 325.20 823.60
iv) 4 bricks Rft. 124.75 339.95 ditto 409.20 1,115.05

28 Cleaning bricks dismantled from kacha pacca masonry 1,000 1,783.30 -- 1,000 1,783.30 -
Nos Nos

29 Scraping bricks dismantled from pacca masonry 1,000 3,362.85 -- 1,000 3,362.85 -
Nos Nos

chapter-7(Brickwork).xls Page 56
MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

30 Supplying and filling sand under floor; or plugging in wells. 100Cft. 424.60 2,944.60 Cu.m 149.95 1,040.05

31 Providing and laying 2" (50 mm) thick and 15" (375 mm) Rft. 186.85 327.55 Metre 612.85 1,074.35
projected tile band, laid in 1:2 cement sand mortar, with
hoop iron 1" (25 mm) wide 18 gauge flat iron sheet 9"
apart.

32 First class brick tiles clad by laying tiles in stretcher This item is to be executed only
course in cement sand mortar reinforced with 18 SWG under the written permission of the
hoop iron strips bonding placed at 2.0' (600 mm) apart Superintending Engineer.
horizontally, and at 1.0' (300 mm) interval vertically.

i) 1:3 100Sft. 3,482.50 17,592.10 Sq.m 374.70 1,892.90


ii) 1:4 100Sft. 3,482.50 17,019.70 Sq.m 374.70 1,831.30

33 Chamfering sides of head regulators and masonry walls to Per Sft. 99.65 -- Sq.m 1,072.25 -
increase width.

34 Replacing kallar eaten bricks Each No. 78.45 90.55 Each 78.45 90.55

35 Repairing corners of bridges and other hydraulic masonry Each No. 498.30 668.60 Each 498.30 668.60
works

36 Extra labour for drains of bath rooms, etc. Per Lft. 42.90 -- Metre 140.70

37 Maroo corners Each 274.55 -- Each 274.55 Payable in addition to brick work
Corner Corner
38 Providing and laying fair face Gutka cladding laid in (1:2) cement / red Carriage charges of Gutka shall be paid
posso mortar having 1/4" thick groove finish i/c cost of 8 SWG wire in seprately
shape of 8 placed horizontally and vertically at 36" and 18" c/c
respectively i/c cutting charges as per approved drawing , complete in all
respect as approved and directed by the Engineer Incharge.
i. 2-1/4" x 2-1/4" x 9" Per Sft 73.70 183.05 P.Sqm 792.95 1,969.40
ii. 2-1/4" x 3" x 9" Per Sft 66.20 156.55 P.Sqm 712.50 1,684.40

39 Providing and laying 4-1/2" thick fair face Special brick Cladding Per Sft 61.40 215.45 P.Sqm 660.50 2,318.10 21.1
(9"x4-1/2"x3") laid in (1:3) cement / red posso mortar having 1/4" thick
groove finish i/c the cost of 8 SWG wire in shape of 8 placed horizontally
and vertically at 36" and 18" c/c respectively i/c cutting charges as per
approved drawing, complete in all respect as approved and directed by the
Engineer Incharge.

chapter-7(Brickwork).xls Page 57
8. STONE MASONRY
1 The composite rates do not include the carriage of stone or spawl which will be paid separately by road and/or rail whichever means of
transport is adopted. The supply and carriage to site of work of all other materials is included in the composite rates.

2 The payment of carriage of stone or spawl will be made on the basis of the actual stack measurement (without any reduction factor) of the
stone or spawl carried.

3 Where the stone or spawl is issued from stock and the contractor is paid for its carriage and/or labour only; or where the stone or spawl is
supplied, carried or handled by the contractor in which no laying is required, the actual stack measurement (without any reduction factor)
shall form the basis of the payment of supply or carriage of stone or spawl. The quantity of finished and completed item of work shall form
the basis of laying.

4 Rates for all finished work include the removal of surplus debris, unused material and byproducts.

MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

1 Random, rubble masonry (uncoursed), in foundation and 22.10,


plinth: 22.11

a) dry masonry 100 Cft. 7,253.40 8,753.40 Cu.m 2,561.90 3,091.70


b) in mud mortar 100 Cft. 9,069.40 10,920.40 Cu.m 3,203.30 3,857.10
c) in lime, sand mortar 1:2 100 Cft. 13,875.20 20,163.20 Cu.m 4,900.70 7,121.65
d) in cement, sand mortar
i) ratio 1:3 100 Cft. 13,875.20 27,241.70 Cu.m 4,900.70 9,621.75
ii) ratio 1:4 100 Cft. 13,875.20 25,095.20 Cu.m 4,900.70 8,863.65
iii) ratio 1:6 100 Cft. 13,875.20 22,638.50 Cu.m 4,900.70 7,995.90
iv) ratio 1:8 100 Cft. 13,875.20 21,279.20 Cu.m 4,900.70 7,515.80

2 Coursed rubble masonry hammer dressed, in foundation 22.8


and plinth:

a) dry masonry 100 Cft. 8,969.40 10,469.40 Cu.m 3,168.00 3,697.80


b) in mud mortar 100 Cft. 12,601.40 14,452.40 Cu.m 4,450.80 5,104.60
c) in lime, sand mortar 1:2 100 Cft. 15,483.25 21,237.35 Cu.m 5,468.70 7,501.05
d) in cement, sand mortar:
i) ratio 1:3 100 Cft. 15,483.25 28,161.25 Cu.m 5,468.70 9,946.55
ii) ratio 1:4 100 Cft. 15,483.25 26,253.25 Cu.m 5,468.70 9,272.65
iii) ratio 1:6 100 Cft. 15,483.25 24,068.80 Cu.m 5,468.70 8,501.10
iv) ratio 1:8 100 Cft. 15,483.25 22,867.85 Cu.m 5,468.70 8,076.95

3 Random rubble masonry (uncoursed) in 22.10


ground floor or 20 ft.(6 m) height, building/other
than building.

a) dry masonry 100 Cft. 8,111.40 9,611.40 Cu.m 2,864.95 3,394.75


b) in mud mortar 100 Cft. 10,885.40 12,736.40 Cu.m 3,844.70 4,498.50

chapter-8(Stone masonary).xls Page 58


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

c) in lime, sand mortar 1:2 100 Cft. 15,054.25 21,342.25 Cu.m 5,317.15 7,538.10
d) in cement, sand mortar:
i) ratio 1:3 100 Cft. 15,054.25 28,420.75 Cu.m 5,317.15 10,038.20
ii) ratio 1:4 100 Cft. 15,054.25 26,274.25 Cu.m 5,317.15 9,280.05
iii) ratio 1:6 100 Cft. 15,054.25 23,817.60 Cu.m 5,317.15 8,412.40
iv) ratio 1:8 100 Cft. 15,054.25 22,458.25 Cu.m 5,317.15 7,932.25

4 Coursed rubble masonry hammer dressed, in ground floor 22.8


or 20 ft. (6 m) height, building/other than building.

a) dry masonry 100 Cft. 10,464.30 11,964.30 Cu.m 3,696.00 4,225.80


b) in mud mortar 100 Cft. 15,591.20 17,426.60 Cu.m 5,506.80 6,155.10
c) in lime, sand mortar 1:2 100 Cft. 17,407.15 23,161.25 Cu.m 6,148.20 8,180.55
d) in cement, sand mortar:
i) ratio 1:3 100 Cft. 17,407.15 30,085.15 Cu.m 6,148.20 10,626.10
ii) ratio 1:4 100 Cft. 17,407.15 28,177.15 Cu.m 6,148.20 9,952.15
iii) ratio 1:6 100 Cft. 17,407.15 25,992.70 Cu.m 6,148.20 9,180.60
iv) ratio 1:8 100 Cft. 17,407.15 24,791.75 Cu.m 6,148.20 8,756.45

5 Ashlar block in course or scabbled masonry (including 22.5


dressing, etc.,) in ground floor or 20 ft. (6 m) height, &
building/other than building. 22.6

a) in lime, sand mortar 1:2 100 Cft. 46,184.15 51,388.00 Cu.m 16,312.25 18,150.25
b) in cement, sand mortar:
i) ratio 1:3 100 Cft. 46,184.15 56,107.60 Cu.m 16,312.25 19,817.20
ii) ratio 1:4 100 Cft. 46,184.15 54,676.60 Cu.m 16,312.25 19,311.80
iii) ratio 1:6 100 Cft. 46,184.15 53,054.80 Cu.m 16,312.25 18,738.95

6 Ashlar fine masonry (including dressing, etc.) in ground 22.3


floor or 20 ft. 6 m) height, building/other than building. (A) to
(C) &
a) in lime, sand mortar 1:2 100 Cft. 84,599.45 88,968.75 Cu.m 29,880.55 31,423.75 22.4
b) in cement, sand mortar:
i) ratio 1:3 100 Cft. 84,599.45 91,328.55 Cu.m 29,880.55 32,257.25
ii) ratio 1:4 100 Cft. 84,599.45 90,612.25 Cu.m 29,880.55 32,004.25
iii) ratio 1:6 100 Cft. 84,599.45 89,817.35 Cu.m 29,880.55 31,723.50

7 Extra labour on items 3, 4, 5 & 6 above for work in:-

i) first floor 100 Cft. 1,924.85 - Cu.m 679.85 -


ii) second floor 100 Cft. 4,296.85 - Cu.m 1,517.65 -
iii) third floor 100 Cft. 6,719.85 - Cu.m 2,373.45 -
iv) fourth floor 100 Cft. 10,648.70 - Cu.m 3,761.10 -

8 Extra labour on items 3,4,5 & 6 above for every 5 ft.(1.5 m) 100 Cft. 1,705.45 - Cu.m 602.35 -
additional height, other than building, or part thereof.

chapter-8(Stone masonary).xls Page 59


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

9 Extra labour for arch work in stone masonry, including 100 Cft. 5,042.10 - Cu.m 1,780.85 - 22.12
centering and decentring, etc.

10 Extra labour for:- 22.7

a) coping and caps, etc. 100 Cft. 24,710.40 - Cu.m 8,727.70 -


b) cornice & string course 100 Rft. 24,710.40 - Rm. 810.50 -

11 Dressing stones:- 22.2


i) This rate of dressing shall be paid
a) hammer dressed 100 Sft. 9,411.60 - Sq.m 1,012.70 - only when the supply of undressed
b) rough tooled dressed 100 Sft. 17,804.15 - Sq.m 1,915.75 - stone is made.
c) chisel dressed 100 Sft. 21,568.80 - Sq.m 2,320.80 - ii) In case of masonry, dressing is
d) fine dressed 100 Sft. 44,906.40 - Sq.m 4,831.95 - already included and this rate shall
not be added thereto.
iii) Only dressed surface of stone
shall be measured.

12 Dhajji walling 5"x5" (125 mmx125 mm) thick deodar 100 Sft. 18,549.10 38,819.85 Sq.m 1,995.90 4,177.00 22.13
framing with stone laid in 1:6 cement sand mortar, and 1:4
cement sand plaster on both sides.

13 Providing and fixing stone blocks from 2 Cft. Per Cft. 795.65 841.70 Cu.m 28,102.35 29,728.85
(0.6 cu.m) to 6 Cft (0.17 cu.m). each
including lift upto 20 ft. (6 m)

14 Providing and fixing stone blocks, under 2 Per Cft. 455.75 515.25 Cu.m 16,097.10 18,198.65
Cft. (06 cu.m) each including lift upto 20 ft.
(6 m)

chapter-8(Stone masonary).xls Page 60


9. ROOFING
Rates for all finished works include the removal of surplus debris unused material and byproducts.

MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

1 First class tile roofing, consisting of 4" (100 mm) earth 100Sft. 12,409.30 24,493.10 Sq.m 1,335.25 2,635.45 23.1 Add extra 13%, 32% & 51% on
and 1" (25 mm) mud plaster with Gobri leeping over ½" (13 labour rates only or 6%, 15% & 23%
mm) thick cement plaster 1:6 with 34 lbs. per %Sft or on composite rates for 2nd, 3rd, 4th
1.72 Kg/sq.m hot bitumen coating sand blinded, provided & sub- sequent floors, respectively.
over 2 layers of tiles 12"x6"x1¼" (300x150x30 mm) laid in
1:6 cement mortar with ½" (13 mm) thick sand wiched
layer of 1:6 cement mortar, including 1:2 cement pointing
underside of tiles, complete, including curing, etc.

2 Second class tile roofing consisting of 4" (100 mm) earth 100Sft. 9,554.70 17,793.75 Sq.m 1,028.10 1,914.60 23.2 ditto
and 1" (25 mm) mud plaster with Gobri leeping over ½" (13
mm) thick cement plaster 1:6 with 34 lbs. per %Sft or
1.72 Kg/sq.m of hot bitumen coating sand blinded,
provided over one layer of 12"x6"x2" (300x150x50 mm)
tiles laid in 1:6 cement mortar, including 1:2 cement
pointing underneath of tiles complete including curing, etc.

3 Covering mud roof with coal tar, and fine sand. 100Sft. 524.35 1,983.10 Sq.m 56.40 213.40 23.1 to 23.2 ditto

4 Filling spaces in between:-

a) Wooden battens over beams, filled with 100Sft. 996.60 6,443.10 Sq.m 107.25 693.30 Add extra 13%, 32% & 51% on
deodar wood pieces (spacers). roof area labour rates only or 6%, 15% &
b) RCC battens, filled with CC block 1:3:6. -ditto- 1,833.90 2,541.80 197.35 273.50 23% on composite rates for 2nd,
c) Spaces filled with bricks. -ditto- 509.35 1,421.05 54.80 152.90 3rd, 4th & sub- sequent floors,
respectively.

5 Single layer of tiles 9"x4½"x1½" (225x113x40 mm) laid 100Sft. 3,047.00 11,721.40 Sq.m 327.85 1,261.20 23.1 ditto
over 4"(100 mm) earth and 1" (25 mm) mud plaster without
Bhoosa, grouted with cement sand 1:3 on top of RCC roof
slab, provided with 34 lbs. per %Sft. or 1.72 Kg/Sq.m
bitumen coating sand blinded.

6 Jack arch roofing 4½" (113 mm) thick laid in 1:5 cement 23.3 to For steel part and its erection etc.
mortar, including an average depth of 4" (100 mm) cement 23.5 items 10 & 14 under Chapter IRON
concrete in haunches and over crown, with 3" (75 mm) WORK be referred.
earth and 1" (25 mm) plaster, soffits of arches cement
plaster 1:6 and ½" (13 mm) thick. The rate also includes Add extra 13%, 32% & 51% on
bitumen coating, centring, laying skew bricks in cement labour rates only or 6%, 15% & 23%
mortar (1:3), and encasing exposed flanges of the joints on composite rates for 2nd, 3rd, 4th
with fine cement concrete 1:2:4 using stone aggregate:- & sub- sequent floors, respectively.

chapter-9(Roofing).xls Page 61
MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

a) cement concrete in haunches 1:6:12. 100Sft. 13,651.95 35,496.35 Sq.m 1,468.95 3,819.40
b) cement concrete in haunches 1:3:6. ditto 13,651.95 37,984.90 Sq.m 1,468.95 4,087.20

7 Jack arch roofing 4½" (113 mm) thick laid in 1:5 cement 23.3 For steel part and its erection etc.
mortar, including an average depth of 4" (100 mm) cement to items 10 & 14 under Chapter IRON
concrete in haunches and over crown, with ½" (13 mm) 23.5 WORK be referred.
cement plaster 1:6 on top (except earth filling mud plaster
and gobri) soffit of arches cement plastered. The rate also Add extra 13%, 32% & 51% on
includes bitumen coating, centring, laying skew bricks in labour rates only or 6%, 15% & 23%
cement sand mortar (1:3), and encasing exposed flanges on composite rates for 2nd, 3rd, 4th
of the joints with fine cement concrete 1:2:4 using stone & sub- sequent floors, respectively.
aggregate:-

a) cement concrete in haunches 1:6:12. 100Sft. 11,093.80 36,048.85 Sq.m 1,193.70 3,878.85
b) cement concrete in haunches 1:3:6. ditto 11,093.80 35,048.15 Sq.m 1,193.70 3,771.20

8 Extra for vaulted jack arch roofing. 100Sft. 2,745.60 Sq.m 295.45 - ditto

9 Jack arch roofing of shingle and cement concrete 1:3:6, 100Sft. 15,322.55 29,887.90 Sq.m 1,648.70 3,215.95 23.3 ditto
4½" (113 mm) thick at crown, with ½" (13 mm) cement to
plaster including cost of supplying, erecting and 23.5
dismantling centring.

10 Earth filling over roof including watering, ramming with 1" 23.1 Add extra 13%, 32% & 51% on
(25 mm) mud plaster finished, with gobri leeping: to labour rates only or 6%, 15% & 23%
23.3 on composite rates for 2nd, 3rd, 4th
a) 3" (75 mm) thick earth filling and 1" (25 mm) mud 100Sft. 1,307.10 1,782.45 Sq.m 140.65 191.80 & sub- sequent floors, respectively.
plaster

b) 4" (100 mm) thick earth filling and 1" (25mm) 100Sft. 1,710.90 2,264.30 Sq.m 184.10 243.65
mud plaster

11 1/8" (3 mm) thick gobri leeping on roofs or floors. 100Sft. 188.65 235.90 Sq.m 20.30 25.40 ditto ditto

12 Two coats of bitumen laid hot using 34 lbs. per %Sft, or 100Sft. 1,019.05 3,921.35 Sq.m 109.65 421.95 23.1
1.72 Kg per square metre over roof and blinded with sand
at one Cft. per %Sft. (0.003 cu.m per sq.m)

13 Providing & Fixing corrugated galvanized iron sheets with G.I. bolts, 23.7 Add extra 13%, 32% & 51% on
nuts, limpet and bitumen washers, wind ties, complete in labour rates only or 6%, 15% & 23%
all respects without valleys and ridges:- on composite rates for 2nd, 3rd, 4th
& sub- sequent floors, respectively,
a) 20 BWG 100Sft. 1,993.20 42,299.95 Sq.m 214.45 4,551.50 on items 13 to 18.
b) 22 BWG 100Sft. 1,993.20 37,091.05 Sq.m 214.45 3,991.00
c) 24 BWG 100Sft. 1,993.20 29,848.20 Sq.m 214.45 3,211.65

chapter-9(Roofing).xls Page 62
MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

14 Khassi parnalas in cement, sand mortar 1:2, 12" (300 Rft. 141.25 183.90 Metre 463.30 603.20 23.10
mm) outside width finished smooth with a floating coat of
neat cement.

15 Khuras on roof 2'x2'x6" (600 x 600 x 150 mm) Each 529.75 866.40 Each 529.75 866.40 23.10

16 Bottom Khuras of brick masonry in cement mortar 1:6, Each 529.75 1,765.25 Each 529.75 1,765.25 23.10
4'x2'x4½" (1200x600x113 mm) over 3" (75 mm) cement
concrete 1:4:8.

17 Plain galvanized iron sheets 22 SWG rain water down pipe


including clamp and fixing in position.

a) 4" (100 mm) diameter down pipe Per Rft. 112.95 396.55 Metre 370.50 1,300.70
b) 5" (125 mm) diameter down pipe Per Rft. 112.95 465.70 Metre 370.50 1,527.50

18 Plain galvanized iron sheet flashing, 22 gauge. Per Sft. 112.95 337.80 sq.m 1,215.35 3,634.75 23.11

19 Providing and fixing 1/16" (1.5 mm) thick lead flashing over Per Sft. 34.30 133.90 Sq.m 369.05 1,440.75
roof expansion joint complete in all respects.

20 Cast iron rain water downpipe fixed in position, excluding Add extra 13%, 32% & 51% on
heads and shoes, but including painting and clamps, etc:- labour rates only or 6%, 15% & 23%
on composite rates for 2nd, 3rd, 4th
a) 4" dia (100 mm) cast iron down pipe. Per Rft. 99.65 328.35 Metre 326.85 1,077.00 & sub- sequent floors, respectively,
b) 3" (75 mm) cast iron down pipe. Per Rft. 99.65 293.90 Metre 326.85 964.00 on items 19 to 24

21 Rain water down pipe cast iron head fixed in place, Each 423.50 899.95 Each 423.50 899.95
including cost of clamp holdfast and painting.

22 Shoes, bends or offsets for cast iron rain water down pipe, Each 149.50 473.45 Each 149.50 473.45
including fixing and painting.

23 Plain GI sheet iron spouts fixed in position, including Each 470.60 800.30 Each 470.60 800.30 23.10
painting.

24 Laying ½" (13 mm) thick deodar ceiling complete, 100Sft. 10,685.40 52,752.10 Sq.m 1,149.75 5,676.15 26.1
including sawing, planing and fixing.

25 Flat sheet roof with galvanized iron plain sheets, including


battens, rolls, screws, clips etc. (Planking to be paid for
separately):-

a) 22 BWG sheets roofing 100Sft. 6,317.50 43,664.95 Sq.m 679.75 4,698.35 23.60
b) 24 BWG sheets roofing 100Sft. 6,317.50 39,182.55 Sq.m 679.75 4,216.05

26 Asbestos cement corrugated sheet roofing including 100Sft. 4,263.60 12,372.60 Sq.m 458.75 1,331.30 23.8
necessary overlaps, and GI hook bolts, nuts, screws,

chapter-9(Roofing).xls Page 63
MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

washers and bitumen washers, etc. (excluding valleys and


ridges, etc).

27 Extra labour for erection of GI sheets, flat sheet or 100Sft. 493.25 -- Sq.m 53.05 - 23.6
asbestos sheet roofing, above 20' (6.10 m) height in
difficult position, including lifting with care and special
scaffolding along live electric wires.

28 Fixing asbestos cement sheet ridges and valleys ¼" Per Rft. 51.20 121.05 Metre 167.95 397.05 23.8
(6 mm) thick.

29 Plain galvanized iron sheet ridging, including fixture, 23.6


timber for ridge roll and ridge sheeting:-

a) 6" (150 mm) lap and 18" (450 mm) Per Rft. 141.15 1,126.15 Per Metre 462.95 3,693.75
overall, of 22 gauge G.I sheet ridging.
b) 9" (225 mm) lap and 24" (600 mm) Per Rft. 179.40 1,096.90 Per Metre 588.45 3,597.85
overall, of 24 gauge G.I sheet ridging.
c) 12" (300 mm) lap and 30" (750 mm) Per Rft. 179.40 1,296.60 Per Metre 588.45 4,252.85
overall, of 22 gauge G.I sheet ridging.

30 Plain 22 gauge G.I sheet gutter semi circular Per Rft. 89.70 385.60 Per Metre 294.20 1,264.75 23.11
8" (200 mm) dia meter.

31 Making masonry ventilators in cement, sand Each 1,993.20 2,943.45 Each 1,993.20 2,943.45
mortar 1:4

32 Fixing water spouts or parnalas. Each 597.95 -- Each 597.95 - 23.10

33 Making drip course 2"x½" (50x13 mm) under RCC slab edges Per Rft. 25.05 27.65 Metre 82.15 90.70
in outer opening, in cement, sand mortar 1:2.

34 Supplying and laying of twin G.I sheet 20 SWG duly Per Sft. 72.45 809.35 Sq.m 779.55 8,708.60
painted with bitumen, with polythene film in between 300
gauge, to provide a sliding joint under the bearing of the
beams, including 3" (75 mm) long, 3/8" (10 mm) dia bar to
act as holdfast on wall and beam.

35 Providing and laying roof insulation, comprising of single


layer of tiles 9"x4½"x1½" (225x113x40 mm) grouted with
cement sand mortar 1:3 laid over 2" (50 mm) thick earth
(including mud plaster) over thermopore sheet, over
polythene sheet 300 gauge over a layer of bitumen,
complete in all respects:-

i) Thermopore sheet ½ " (13 mm) thick 100Sft. 4,697.90 14,504.60 Sq.m 505.50 1,560.70
ii) Thermopore sheet ¾ " (20 mm) thick 100Sft. 4,697.90 14,882.60 Sq.m 505.50 1,601.35
iii) Thermopore sheet 1" (25 mm) thick 100Sft. 4,706.45 15,269.20 Sq.m 506.40 1,642.95

chapter-9(Roofing).xls Page 64
MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

36 Providing and fixing AC rain water down pipe 4" (100 mm) Rft. 29.90 362.10 Metre 98.05 1,187.70
dia, with shoe, T-bend, clamp, etc.

37 Making jharries in existing brick masonry for providing Rate will be increased by 1.5 time
recesses for bearing of RCC roof slab, including repairing for stone masonry or plain; concrete;
the damaged face:- and 2 times for reinforced cement
concrete.
i) for slabs upto 6" (150 mm) thick Rft. 34.30 38.10 Metre 112.50 124.95
ii) for slabs exceeding 6" to 12" (150 to 300 mm) thick. Rft. 57.85 64.70 Metre 189.75 212.20

38 Making recess in existing brick masonry for bearing of Rates will be increased by 1.5 times
beam, girder, R.S. Joist, etc. including repairing damaged for stone masonry and plain
face:- cement concrete and two times
for reinforced cement concrete.
i) upto 1.0' (300 mm) height of girder or beam. Each 143.00 155.50 Each 143.00 155.50

ii) for every 6" (150 mm) additional height or part thereof. Each 68.65 74.65 Each 68.65 74.65

39 Hoisting RS. Beams and wooden beams and placing in Each 553.75 - Each 553.75 -
position.

40 Hoisting and placing in position sahl ballies, over roof. Each 85.40 - Each 85.40 -

41 Hoisting precast R.C.C/prestressed concrete


battens and placing in position.

a) 5' to 6' (1.50 to 1.83 m) long Each 79.10 - Each 79.10 -


b) 6' to 7' (1.83 to 2.13 m) long Each 110.75 - Each 110.75 -
c) 7' to 8' (2.13 to 2.44 m) long Each 138.45 - Each 138.45 -
d) 8' to 9' (2.44 to 2.74 m) long Each 184.60 - Each 184.60 -
e) above 9' (2.74 m) length Each 221.50 - Each 221.50 -

42 Hoisting and placing in position R.C. trough: Applicable only to roof trough
(inverted tees & trough) for height of
a) upto 10' (3 m) in length Each 221.50 - Each 221.50 - 1st storey only.
b) 10' to 11' (3 to 3.36 m) in length Each 276.85 - Each 276.85 -
c) 11' to 12' (3.36 to 3.66 m) in length Each 369.15 - Each 369.15 -
d) 12' to 13' (3.66 to 3.96 m) in length Each 425.95 - Each 425.95 -
e) 13' to 14' (3.96 to 4.26 m) in length Each 461.45 - Each 461.45 -
f) 14' to 15' (4.26 to 4.57 m) in length Each 503.40 - Each 503.40 -
g) 15' to 16' (4.57 to 4.88 m) in length Each 553.75 - Each 553.75 -
h) 16' to 17' (4.88 to 5.19 m) in length Each 615.25 - Each 615.25 -
i) 17' to 18' (5.19 to 5.49 m) in length Each 791.05 - Each 791.05 -
j) 18' to 19' (5.49 to 5.80 m) in length Each 851.90 - Each 851.90 -
k) 19' to 20' (5.80 to 6.10 m) in length Each 922.90 - Each 922.90 -

43 Hoisting and placing in position R.C. inverted battens:-

i) upto 10' (3.05 m) span Each 170.30 - Each 170.30 -


ii) from 10' to 12' (3.05 to 3.66 m) span Each 378.40 - Each 378.40 -

chapter-9(Roofing).xls Page 65
MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

iii) from 12' to 13' (3.66 to 3.96 m) span Each 454.10 - Each 454.10 -
iv) from 13' to 14' (3.96 to 4.26 m) span Each 567.60 - Each 567.60 -
v) from 14' to 15' (4.26 to 4.57 m) span Each 619.20 - Each 619.20 -
vi) from 15' to 16' (4.57 to 4.88 m) span Each 681.10 - Each 681.10 -
vii) from 16' to 18' (4.88 to 5.49 m) span Each 851.40 - Each 851.40 -
viii) from 18' to 20' (5.49 to 6.10 m) span Each 1,362.25 - Each 1,362.25 -

44 Reinforced cement concrete spout, including fixing in Each 797.30 1,292.90 Each 797.30 1,292.90
position, with top and bottom Khurras.

45 Providing and Laying Insulation material of Extruded Polystyrene XPS in


Rigid Insulation / Foam Board on roof or walls, Density 32-38Kg/M,
compressive strength 250-400 kpa, R-value 5 per inch thickness and water
obsorption (1% by volume, closed cell type structure) i/c cutting and
placing in position. complete in all respect.
a) 1" thick % Sft 642.20 6,942.20 P.Sqm 69.10 747.00
b) 1-1/2" thick % Sft 642.20 9,462.20 P.Sqm 69.10 1,018.15
c) 2" thick % Sft 642.20 11,982.20 P.Sqm 69.10 1,289.30
46 Providing and applying torch-on plain waterproofing bitumenous 23.1 If Aluminum Foiled membrane is
membrane of specified thickness (made of Roof-Grip/ Euro Bit) duly used,increase composite rate by Rs 7.00/-
lapped/connected by heating with Torch over ps-6 primer i/c Psft or Rs 75.00 P.Sq.mtr.
preparation/smoothen the surface complete in all respect as approved and
directed by the Engineer Incharge
i) 3 mm thick Per Sft 13.10 91.10 Sq.m 140.75 980.05
ii) 4 mm thick Per Sft 13.10 97.10 Sq.m 140.75 1,044.60
47 Providing and applying 15-20 micron thick high density (40 gm/m2) Per Sft 16.80 71.60 Sq.m 180.95 770.30
plain/self adhesive super polyshield combined reinforced (Polyster &
fiberglass) fabric memberane for water proofing, applied over a layer of
hot bitumen (grade 60/70) @ 8 kg/100 Sft and sandwiched with a 2nd
layer of bitumen @ 8 kg/100 sft (grade 60/70) duly sand blended i/c
preparation of surface complete in all respect as approved and directed by
the Engineer Incharge
48 Providing and fixing false ceiling comprises of Gypsum board laminated
sheet of size 2'x2'/2'x3'/ 3'x3'of specified design and thickness i/c cost of
fixtures i.e galvanized angle 1" x 1" at wall sides, galvanized tee 1¼" x
1"and 1 ½” x 1” both at 4’ c/c ( made of Taiwan CKM or equivalent),
hanging with G.I/Copper wire 16 SWG, G.I hook, Rawal Plug etc:
complete in all respects as approved and directed by the Engineer Incharge.

i) 6 mm thick Per Sft 18.70 85.60 Sq.m 201.05 921.10


ii) 7.5mm thick Per Sft 18.70 89.40 Sq.m 201.05 961.80
iii) 9 mm thick Per Sft 18.70 95.70 Sq.m 201.05 1,029.55
iv) 12 mm thick Per Sft 18.70 100.30 Sq.m 201.05 1,079.25

chapter-9(Roofing).xls Page 66
MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

49 P/L false ceiling comprising of 5/8" thick plaster of paris sheet of required Per Sft 36.35 134.30 Sq.m 390.95 1,444.80
size in approved design with one line of 6" wide niche all around , hanging
with Copper wire (16 SWG) duly enriched with POP and flaxen i/c the cost
of making space for rope light /screws/jute/making holes for lights and
rawal plugs complete in all respects as approved and directed by the
Incharge.(Measurement will be made as per carpet Area).

50 Per Sft 60.50 118.85 Sq.m 650.85 1,278.80 23.1


Providing and laying high density single profile spanish glazed tappered
barrel type of 4"- 5-1/2" dia Terra Cotta Khaprail Tile dipped or sealed
with a water repellent, with Terra Cotta base plate ( 10"x16"), resistant to
salt attack laid with laps and duly interlocked on slopping roof over 1/2"
thick (1:3) cement sand mortar i/c cost of all material and labour complete
in all respect as approved and directed by the Engineer Incharge.

chapter-9(Roofing).xls Page 67
10. FLOORING
Rates for all finished works include the removal of surplus debris, unused material and byproducts
MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

1 Laying Murum flooring, consisting of 1"(25 mm) layer of 100 Sft. 5,321.60 6,915.20 Sq.m 572.60 744.10
fine powdery or flakey variety of Murum, laid over 6"(150
mm) good hard layer of Murum spreaded over 9"(225 mm)
thick sub-base comprising of hand packed rubble or
broken bricks properly watered and rammed, provided over
well rammed earth.

2 Earth flooring, consisting of 6"(150 mm) thick consolidated 100 Sft. 1,809.40 2,199.40 Sq.m 194.70 236.65 24.1
layer of moistened earth, including ramming.

3 Providing, laying, watering and ramming brick ballast 1½" 100 Cft. 4,077.20 9,567.20 C.um 1,440.05 3,379.15
to 2"(40 mm to 50 mm) gauge mixed with 25% sand, for
floor foundation, complete in all respects.

4 Mud flooring, consisting of 6"(150 mm) thick consolidated 100 Sft. 3297.70 3,953.30 Sq.m 354.85 425.40 24.2
layer of moistened earth and finished off with 1"(25 mm)
mud plaster and gobri leeping.

5 Dry brick paving laid flat, sand grouted, including 100 Sft. 1756.80 6,969.60 Sq.m 189.05 749.95 24.12
preparation of bed by watering, ramming and bringing the
same to proper camber, by ½"(13 mm) thick mud plaster.

6 Dry brick on edge paving, sand grouted, including 100 Sft. 3163.15 10,921.15 Sq.m 340.35 1,175.10 24.12
preparation of bed by watering, ramming & bringing the
same to proper camber, by ½ "(13 mm) thick mud plaster.

7 Grouting 4½"(113 mm) dry brick work with cement mortar 100 Sft. 1709.65 2,679.85 Sq.m 183.95 288.35
ratio 1: 5

8 Flat brick flooring laid in 1:6 cement mortar, over a bed of 100 Sft. 3071.90 9,955.10 Sq.m 330.55 1,071.15 24.4
3/4" (20 mm) thick cement mortar, 1:6.

9 Brick on edge flooring, laid in 1:6 cement mortar, over a 100 Sft. 3,924.60 13,929.75 Sq.m 422.30 1,498.85 24.4
bed of ¾" (20 mm) thick cement mortar 1:6.

10 Brick tiles (12"x6"x2") (300x150x50mm) laid in 1:6 100 Sft. 3,839.90 8,563.10 Sq.m 413.15 921.40 ditto
cement mortar, over a bed of ¾" (20 mm) thick cement
mortar 1:6.
11 Brick ties (9"x4½"x1½")(225 mm x 113 mm x 40 mm) laid 100 Sft. 4,268.90 10,778.90 Sq.m 459.35 1,159.80 24.4
flat in 1:3 cement mortar, over a bed of 3/4"(20 mm) thick
cement mortar 1:6.

12 Cement tiles (8"x8"x¾")(200 x 200 x 20 mm) laid flat in 100 Sft. 2,564.65 13,611.95 Sq.m 275.95 1,464.65 24.7
1:2 cement mortar, over 3/4" (20 mm) thick bed of cement
mortar 1:2.

chapter-10(Flooring).xls Page 68
MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

13 Cement concrete tiles laid in 1:2 cement mortar, over 24.8


3/4" (20 mm) thick bed of cement mortar 1:2:-

(a) 12"x12"x1" (300 x 300 x 25 mm) 100 Sft. 2,564.65 9,986.75 Sq.m 275.95 1,074.55
(b) 9"x9"x¾" (225 x 225 x 20 mm) ditto 2,564.65 12,770.95 Sq.m 275.95 1,374.15
(c) 6"x6"x¾"(150 x 150 x 20 mm) ditto 2,564.65 17,609.70 Sq.m 275.95 1,894.80

14 Coloured cement tiles (8"x8"x¾")(200 x 200 x 20 mm) of 100 Sft. 2,564.65 13,658.75 Sq.m 275.95 1,469.70 24.7
approved dark shade laid flat in 1:2 cement mortar, over
¾" (20 mm) bedding mortar of 1:2.

15 Providing and laying topping of cement concrete 1:2:4, 24.9 If glass or marble strips are used
including surface finishing and dividing in panels:- for panelling, it will be paid extra as
per item No. 41 or 42.
(a) 1"(25 mm) thick 100 Sft. 2,910.35 5,315.45 Sq.m 313.15 571.95
(b) 1¼"(30 mm) thick ditto 2,910.35 5,857.25 Sq.m 313.15 630.25
(c) 1½"(40 mm) thick ditto 3,611.45 7,100.15 Sq.m 388.60 764.00
(d) 1¾"(45 mm) thick ditto 3,611.45 7,661.55 Sq.m 388.60 824.40
(e) 2"(50 mm) thick ditto 4,312.55 9,031.95 Sq.m 464.05 971.85
(f) 2¼"(56 mm) thick ditto 4,439.95 9,659.55 Sq.m 477.75 1,039.35
(g) 2½"(62 mm) thick ditto 5,013.70 10,615.90 Sq.m 539.45 1,142.25
(h)2¾"(70 mm) thick ditto 5,013.70 11,334.10 Sq.m 539.45 1,219.55
(i) 3"(75 mm) thick ditto 5,013.70 11,956.90 Sq.m 539.45 1,286.55

16 Providing and laying conglomerate flooring (two coat work) 24.10 If glass or marble strips are used
with top layer of ½"(13mm) thick wearing surface, for panelling, it will be paid extra as
consisting of one part of cement and 2 parts of stone per item No. 41 or 42.
chips passing 3/16"(6 mm) sieve, over bottom layer of
cement concrete 1:3:6, including surface finishing and
dividing in panels:-

(a) 1½"(40 mm) thick 100 Sft. 4,301.00 7,711.65 Sq.m 462.80 829.75
(b) 1¾"(45 mm) thick ditto 4,301.00 8,070.60 Sq.m 462.80 868.40
(c) 2"(50 mm) thick ditto 5,431.15 9,756.35 Sq.m 584.40 1,049.80

17 Add extra in cement concrete floor topping, if finished with 100 Sft. 996.60 1,923.10 Sq.m 107.25 206.95
pigment and polishing.

18 Extra labour for each storey above ground, for mosaic, 100 Sft 764.30 - Sq.m 82.25 - On items 19-25 & 29-34
conglomerate, tiles, stone and wooden floor.

19 Flag stone flooring in lime mortar 1:2, over ¾"(20 mm) 24.5
bedding mortar, in platforms and floors, etc.

(a) 2"(50 mm) thick 100 Sft. 8,564.50 13,379.45 Sq.m 921.55 1,439.65
(b) 3"(75 mm) thick ditto 8,564.50 13,695.25 Sq.m 921.55 1,473.60

chapter-10(Flooring).xls Page 69
MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

20 Asphalt flooring , including preparation of proper base 24.10


remelting, setting out, and finishing complete:-

(a) 1"(25 mm) thick topping 100 Sft. 3,405.60 29,287.50 Sq.m 366.45 3,151.35
(b) ½"(13 mm) thick topping ditto 2,682.90 15,879.90 Sq.m 288.70 1,708.70
(c) ¼"(6 mm) thick topping ditto 1,994.50 8,847.75 Sq.m 214.60 952.00

3
21 1 /8"(35 mm) thick mosaic flooring, consisting of 3/8"(10 If glass or marble strips are used
mm) mosaic topping of one part of cement and marble for panelling, it will be paid extra as
powder in the ratio of 3:1 and two parts of marble chips, per item No. 41 or 42.
laid over 1"(25 mm) thick flooring of 1:2:4 cement concrete
including rubbing and polishing complete :-

(a) using grey cement 100 Sft. 13,295.90 19,693.95 Sq.m 1,430.65 2,119.05
(b) using white cement ditto 13,295.90 20,291.85 Sq.m 1,430.65 2,183.40

22 1½"(40 mm) thick mosaic flooring, consisting of ½ "(13 If glass or marble strips are used
mm) mosaic topping of one part of cement and marble for panelling, it will be paid extra as
powder in the ratio of 3:1 and two parts of marble chips, per item No. 41 or 42.
laid over 1"(25 mm) thick floor of 1:2:4 cement concrete,
including rubbing and polishing complete with finishing :-

(a) using grey cement 100 Sft. 13,295.90 19,991.35 Sq.m 1,430.65 2,151.05
(b) using white cement ditto 13,295.90 21,791.65 Sq.m 1,430.65 2,344.80

23 Providing and laying floor of mosaic marble chips tiles 100 Sft. 7,160.75 22,149.10 Sq.m 770.50 2,383.25 24.8
1"(25 mm) thick of approved quality and shade, laid in
white cement and pigment, over ¾"(20 mm) thick bedding
of cement sand mortar 1:2, including finishing and
polishing, complete.
24 Providing and laying superb quality Ceramic tile floors of Master
brand of specified size,Glossy/Matt/Texture of approved Color and
Shade as per approved design with adhesive bond, over 3/4" thick
(1;2) cement sand plaster i/c the cost of sealer for finishing the joints
i/c cutting grinding complete in all respects and as approved and
directed by the Engineer Incharge. 24.7
i) 12"x18"/12"x24"/10"x24" /8"x24"/12"x36" Per Sft 66.20 241.40 Sq.m 712.50 2,597.55
ii) 10"x13" Per Sft 66.20 215.00 Sq.m 712.50 2,313.50
iii) 6"x6" Per Sft 66.20 200.95 Sq.m 712.50 2,162.25
iv) 4"x4" Per Sft 66.20 200.95 Sq.m 712.50 2,162.25
25 Providing and laying superb quality Ceramic tiles dado of Master ditto
brand of specified size,Glossy/Matt/Texture skirting/dado of approved
Color and Shade with adhesive bond over 1/2"thick (1:2) cement
plaster i/c the cost of sealer for finishing the joints i/c cutting grinding
complete in all respects as approved and directed by the Engineer
Incharge.
i) 12"x18"/12"x24"/10"x24" /8"x24"/12"x36" Per Sft 66.20 294.15 Sq.m 712.50 3,165.15
ii) 10"x13" Per Sft 66.20 282.20 Sq.m 712.50 3,036.35
iii) 6"x6" Per Sft 66.20 257.00 Sq.m 712.50 2,765.20

chapter-10(Flooring).xls Page 70
MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

iv) 4"x4" Per Sft 66.20 243.45 Sq.m 712.50 2,619.45


26 Rubbing and polishing old grit/ mosaic floor, including 100 Sft. 2,648.70 2,868.55 Sq.m 285.00 308.65 The composite rate will be reduced
repairing voids, uneven surface, complete in all respects. by Rs. 150.00 per % Sft or Rs.13.95 per
Sq. metre respectively, if no
polishing is done.

27 Rubbing and polishing grit floor, including repairing voids, 100 Sft. 2,802.85 3,052.75 Sq.m 301.60 328.50 The composite rate will be reduced
uneven surface, complete in all respects by Rs. 150.00 per % Sft or Rs.13.95 per
Sq. metre respectively, if no
polishing is done.

28 Cleaning and washing mosaic or marble floor with caustic 100 Sft. 388.75 459.30 Sq.m 41.85 49.40 24.6
soda mixture.

29 Shisham wood boarding or strip flooring 3/4" (20mm) thick 100 Sft. 8,580.00 142,377.05 Sq.m 923.20 15,319.75 24.13
(sawn to required size) tongued and grooved or splayed
rebated fixed with brass screws on deodar wood battens
1½ "x2"(40 x 50 mm),size placed at 12"(300 mm) centre
to centre, including two coats of bitumen laid hot on the
base.

30 Deodar wood boarding or strip flooring 3/4" (20 mm) thick 100 Sft. 8,969.40 123,182.75 Sq.m 965.10 13,254.45 ditto
(sawn to required size) tongued and grooved or splayed
rebated fixed with brass screws on deodar wood battens
1½"x2"(40 x 50 mm) size , placed at 12"(300 mm) centre,
to centre including two coats of bitumen laid hot on the
base.

31 Teak wood boarding or strip flooring ½" (13 mm) "thick 100 Sft. 7,843.00 198,333.15 Sq.m 843.90 21,340.65 ditto
(sawn to required size) to tongued and grooved screwed
on deodar wood battens 1½ " x2"(40 x 50 mm) size,
placed at 12"(300 mm) centre to centre, including 2 coats
of bitumen laid hot on base.

32 Shisham wood block flooring 1"(25 mm) thick cut to 100 Sft. 8,332.50 175,961.15 Sq.m 896.60 18,933.40 24.13
required size, fixed on a layer of asphalt bitumen laid on
base.

33 Teak wood block 1"(25 mm) thick cut to required size, 100 Sft. 7,843.00 365,156.70 Sq.m 843.90 39,290.85 ditto
fixed on a layer of asphalt bitumen laid on base.

34 Laying wooden paving of hard wood on edge in coal tar ditto


and asphalt:- 100 Sft. Sq.m
Per Inch per cm
(a) Shisham wood thickness 4,835.60 111,511.20 thickness 520.30 11,998.60
(b) Kikar wood ditto 4,835.60 38,733.60 ditto 520.30 4,167.75

35 Tile skirting laid in 1:2 cement mortar, over ¾"(20 mm)


thick cement mortar, 1:2 including cement washing and

chapter-10(Flooring).xls Page 71
MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

filling joints complete:-

(a) cement tiles 100 Sft. 4,198.75 16,058.95 Sq.m 451.80 1,727.95
(b) mosaic tiles ditto 6,937.60 23,016.75 Sq.m 746.50 2,476.60

36 Providing grey cement skirting or dado 3/8"(10 mm) thick


including rounding of corner and straight ening of top edge
and finishing to smooth surface afterplastering :-

(a) 1:2 cement, sand mortar 100 Sft. 5,309.90 6,547.95 Sq.m 571.35 704.55
(b) 1:3 cement, sand mortar ditto 5,309.90 6,182.00 Sq.m 571.35 665.20
(c) Extra if skirting or dado is finished ditto 318.45 742.75 Sq.m 34.25 79.90
with pigment of any colour.

37 Mosaic dado or skirting with one part of cement and


marble powder in the ratio of 3:1 and two parts of marble
chips, laid over ½"(13 mm) thick cement plaster 1:3,
including rubbing and polishing, complete with finishing:

(a) using grey cement:


i) 3/8"(10 mm) thick 100 Sft. 15,843.95 19,815.40 Sq.m 1704.80 2,132.15
ii) ½"(13 mm) thick ditto 15,843.95 21,441.10 Sq.m 1704.80 2,307.05

(b) using white cement :

'i) 3/8"(10 mm) thick 100 Sft. 15,843.95 21,614.90 Sq.m 1704.80 2,325.75
ii) ½"(13 mm) thick ditto 15,843.95 22,248.80 Sq.m 1704.80 2,393.95

38 Rubber flooring, consisting of 12"x12"x1/8" Per Sft. 36.25 148.15 Sq.m 390.05 1,594.10 24.14 The cost of base for rubber flooring
(300x300x3mm) rubber tiles, laid on firm foundation. is not included in the rate and is
payable separately.

39 Providing and fixing glass strip 5mm thick and 1½" Per Rft. - 5.55 Metre - 18.20 Labour for fixing already included in
(40 mm) wide, for dividing the mosaic flooring into panels. items No. 15, 16, 21and 22 of this
Chapter.

40 Providing and fixing marble strip of any shade for dividing


the mosaic flooring into panels

3
a) sSize 1½" x /8" (40 x 10 mm) Per Rft. - 19.80 Metre - 64.95
b) sSize 1½" x ¼" (40 x 6 mm) Per Rft. - 15.85 Metre - 52.00

41 Providing and laying Tuff pavers, having 7000 PSI, crushing strength
of approved manufacturer, over 2" to 3" sand cushion i/c grouting with
sand in joints i/c finishing to require slope . complete in all respect.
(50% Grey / 50% Coloured)
a) 50-mm thick P.Sft 24.80 139.80 Sq.m 267.05 1,504.20
b) 60-mm thick P.Sft 24.80 154.30 Sq.m 267.05 1,660.10

chapter-10(Flooring).xls Page 72
MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

c) 80-mm thick P.Sft 24.80 192.80 Sq.m 267.05 2,074.30


42 Providing and laying superb quality Porcelain glazed tiles flooring of 24.7 If matt tile will be used, reduce composite rate
MASTER brand of specified size in approved design,Color and Shade by Rs. 12/- Psft.
with adhesive/bond over 3/4"thick (1:3) cement plaster i/c the cost of
sealer for finishing the joints i/c cutting grinding complete in all
respect as approved and directed by the Engineer Incharge.
a) Full body Glazed tiles
(i) 400 mm x 400 mm Per Sft 66.20 279.65 Sq.m 712.50 3,009.20
(ii) 600mmx 600 mm Per Sft 66.20 341.95 Sq.m 712.50 3,679.65
(iii) 600mmx 1200 mm Per Sft 66.20 512.30 Sq.m 712.50 5,512.10
b) Half body Tile
(i) 400mmx400mm semi Glazed Per Sft 66.20 243.45 Sq.m 712.50 2,619.45
c) Semi glazed Tiles 300mmx300mm Per Sft 66.20 210.10 Sq.m 712.50 2,260.85
d) (Non-Skid Chequred Tiles) 300mmx300mm Per Sft 66.20 213.00 Sq.m 712.50 2,292.00
43 Providing and laying superb quality Porcelain glazed tiles of Master 24.7 If matt tile will be used, reduce composite rate
brand, skirting/dado of specified size, Color and Shade with adhesive/ by Rs. 12/- Psft.
bond over 1/2"thick (1:2) cement plaster i/c the cost of and sealer for
finishing the joints, cutting grinding complete in all respect as
approved and directed by the Engineer Incharge.
a) Full body Glazed Tile
(i) 400 mmX400 mm Per Sft 66.20 294.15 Sq.m 712.50 3,165.15
(ii) 600mm x600 mm Per Sft 66.20 341.95 Sq.m 712.50 3,679.65
(iii) 600mmx 1200 mm Per Sft 66.20 512.30 Sq.m 712.50 5,512.10
b) Half body Tile
(i) 400mm x400 mm Per Sft 66.20 373.15 Sq.m 712.50 4,015.30
(ii) 300mm x300 mm Per Sft 66.20 342.75 Sq.m 712.50 3,687.90
44 Providing and laying 3/8 inch thick superb class Multani tiles of Per Sft 78.95 936.90 Sq.m 849.55 3,073.00 24.7
specified size and design of approved Color and Shade with adhesive
bond, over 1/2"thick (1:2) cement plaster i/c the cost of sealer for
finishing the joints i/c cutting grinding complete in all respects and as
approved and directed by the Engineer Incharge.
45 Providing and laying flooring with China Verona Marble having 24.7
uniform texture (Spotless) of required size and specified thickness,
with adhesive bond over 3/4" thick bedding of (1:2) cement sand
mortor i/c the cost of matching sealer,cutting, grinding and chemical
polishing complete in all respect as approved and directed by the
Engineer Incharge.
i) 1/2" thick(12"x12"/12"x24") Per Sft 107.45 333.90 Sq.m 1,156.20 3,592.55
ii) 3/4" thick (12"x24"/12"x36") Per Sft 107.45 371.70 Sq.m 1,156.20 3,999.25
46 Providing and laying 3/8" thick Prepolished Marble skirting/risers 24.7
having uniform texture (spot less) of size 24"x6" of approved quality
and shade with adhesive bond over 3/4" thick (1:2) cement sand
mortor complete in all respect i/c the cost of matching sealer to finish
the joints as approved and directed by the Engineer Incharge.

i) China Verona Per Sft 66.20 206.05 Sq.m 712.50 2,216.95

chapter-10(Flooring).xls Page 73
MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

47 Providing and laying 3/4" thick full width Prepolished Marble slab for 24.7
Vanities / Shelves / Treads/Window Cills , having Uniform texture
(Spotless) with adhesive bond over 3/4" thick (1:2) cement sand
mortor i/c the cost of matching sealer complete in all respects as
approved and directed by the Engineer Incharge.
i) China Verona Per Sft 66.20 413.75 Sq.m 712.50 4,452.05
ii) Ziarat White Per Sft 66.20 1,232.75 Sq.m 712.50 13,264.50
48 Extra for Bevelling charges of marble edge in approved design Per Rft 25.75 25.90 P.Mtr 84.45 85.00
complete in all respects i/c the cost of Carborandam disc as approved
and directed by the Engineer Incharge.
49 Extra cost for making hole in Marble slab for fixtures, Sink,burners,
basin Vanities i/c cost of bevelling of internal edge as approved and
directed by the Engineer Incharge. Each 514.80 711.60
50 Providing and laying Prepolished Granite of specified thickness and 24.7
shade of full width of approved quality laid with adhesive bond over
3/4" thick (1:2) cement sand mortor bed , complete in all respect as
approved and directed by the Engineer Incharge.
(i) 3/4" thick Per Sft 81.15 1,310.75 Sq.m 873.35 14,103.80
(ii) 1/2" thick Per Sft 81.15 1,184.75 Sq.m 873.35 12,748.05

chapter-10(Flooring).xls Page 74
11. SURFACE RENDERING
1 PLASTERING, POINTING, WHITE WASHING, COLOUR WASHING AND DISTEMPERING, ETC.
2 Rates for all finished works include the removal of surplus debris, unused material and byproducts.
MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

1 Mud plaster on walls (excluding Gobri leeping) upto 20' 25.7


(6.00 m) height:-

a) ½" (13 mm) thick 100 Sft. 794.25 922.05 Sq.m 85.45 99.20
b) 1" (25 mm) thick 100 Sft. 1,110.75 1,366.35 Sq.m 119.50 147.00

2 Mud plaster on floor or roof (excluding Gobri leeping):- ditto Add extra 13%, 32% and 51% above
the labour rates only or 6%, 15% &
a) ½" (13 mm) thick 100 Sft. 715.85 843.65 Sq.m 77.05 90.80 23% on the composite rates for 2nd,
3rd, 4th and subsequenct floors,
b) 1" (25 mm) thick 100 Sft. 715.85 971.45 Sq.m 77.05 104.55 respectively.

3 Cement lime plaster 1:7:12 (cement, lime and sand) upto 25.1 to 25.6
20' (6.00 m) height.

a) ¼" (6 mm) thick 100 Sft. 2,305.50 2,691.80 Sq.m 248.05 289.65

b) ½" (13 mm) thick 100 Sft. 2,305.50 3,077.70 Sq.m 248.05 331.15

4 Cement Neru plaster 1:2 (cement and sand) upto 20' ditto
(6.00 m) height:-

a) ¼" (6 mm) thick 100 Sft. 2,305.50 3,247.90 Sq.m 248.05 349.45
b) ½" (13 mm) thick 100 Sft. 2,305.50 3,835.60 Sq.m 248.05 412.70

5 2" (50 mm) stucco cement plaster 1:2:4 (cement, sand 100 Sft. 5,757.20 11,228.50 Sq.m 619.50 1,208.20 ditto
and shingle) upto 20' (6.00 m) height.

6 Providing and laying machine sprayed plaster ½" (13 mm) ditto
thick, using cement and chips zero gauge, over the
existing plastered and roughened surface, upto 20' (6.00
m) height:-

i) ratio 1:1 100 Sft. 2,026.45 6,490.45 Sq.m 218.05 698.35


ii) ratio 1:1½ 100 Sft. 2,026.45 6,494.05 Sq.m 218.05 698.75
iii) ratio 1:2 100 Sft. 2,026.45 6,494.05 Sq.m 218.05 698.75

7 Cement plaster 1:2 upto 20' (6.00 m) height:- 25.1


to
a) 3/8" (10 mm) thick 100 Sft. 2,305.50 3,543.55 Sq.m 248.05 381.30 25.6
b) ½" (13 mm) thick 100 Sft. 2,305.50 3,911.10 Sq.m 248.05 420.85
c) ¾" (20 mm) thick 100 Sft. 2,903.45 5,379.55 Sq.m 312.40 578.85

chapter-11(Surface Rendering).xls Page 75


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

8 Cement plaster 1:3 upto 20' (6.00 m) height:- ditto

a) 3/8" (10 mm) thick 100 Sft. 2,305.50 3,177.60 Sq.m 248.05 341.90
b) ½" (13 mm) thick 100 Sft. 2,305.50 3,468.30 Sq.m 248.05 373.20
c) ¾" (20 mm) thick 100 Sft. 2,903.45 4,647.65 Sq.m 312.40 500.10

9 Cement plaster 1:4 upto 20' (6.00 m) height:- ditto

a) 3/8" (10 mm) thick 100 Sft. 2,305.50 3,078.80 Sq.m 248.05 331.30
b) ½" (13 mm) thick 100 Sft. 2,305.50 3,289.75 Sq.m 248.05 354.00
c) ¾" (20 mm) thick 100 Sft. 2,903.45 4,437.45 Sq.m 312.40 477.45

10 Cement plaster 3/8" (10 mm) thick under soffit of R.C.C. ditto i) This item shall be applicable to
roof slabs only, upto 20' height. buildings meant for human
habitation only, such as buildings
like residences, offices,
a) 1:2 100 Sft. 2,648.70 4,132.80 Sq.m 285.00 444.70 educational institutions and
b) 1:3 100 Sft. 2,648.70 3,765.60 Sq.m 285.00 405.20 hospitals, etc. It shall not be
c) 1:4 100 Sft. 2,648.70 3,666.80 Sq.m 285.00 394.55 admissible on godowns; bins;
agriculture, poultry and animal
sheds; cycle stands; garrages; etc.
ii) The thickness of the plaster will
not be more than 3/8" (10 mm)
thick.
11 Cement plaster 1:5 upto 20' (6.00 mm) height:- 25.1 to 25.6

a) 3/8" (10 mm) thick 100 Sft. 2,305.50 2,993.10 Sq.m 248.05 322.05
b) ½" (13 mm) thick 100 Sft. 2,305.50 3,140.70 Sq.m 248.05 337.95
c) ¾" (20 mm) thick 100 Sft. 2,903.45 4,278.65 Sq.m 312.40 460.40

12 Cement plaster 1:6 upto 20' (6.00 mm) ditto


height:-
a) 3/8" (10 mm) thick 100 Sft. 2,305.50 2,870.70 Sq.m 248.05 308.90
b) ½" (13 mm) thick 100 Sft. 2,305.50 3,055.05 Sq.m 248.05 328.70
c) ¾" (20 mm) thick 100 Sft. 2,903.45 4,033.85 Sq.m 312.40 434.05

13 Applying floating coat of cement 1/32" (0.8 mm) thick. 100 Sft. 1,387.10 1,876.70 Sq.m 149.25 201.95 25.4 to 25.6

14 Lime pointing flush upto 20' (6.00 m) height including 100 Sft. 1,707.55 1,994.85 Sq.m 183.75 214.65 25.8
raking joints, in lime, sand mortar 1:2.

15 Lime pointing struck joints on walls, upto 20' (6.00 m) 100 Sft. 2,648.70 2,936.00 Sq.m 285.00 315.90 ditto
height, including raking joints in lime sand mortar 1:2.

16 Cement pointing flush upto 20' (6.00 m) heihgt:- ditto

a) ratio 1:2 100 Sft. 2,305.50 3,232.15 Sq.m 248.05 347.80


b) ratio 1:3 100 Sft. 2,305.50 3,016.85 Sq.m 248.05 324.60

chapter-11(Surface Rendering).xls Page 76


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

17 Cement pointing 1:2 flush on floor. 100 Sft. 1,707.55 2,634.20 Sq.m 183.75 283.45 ditto

18 Cement pointing struck joints, on walls, upto


20' (6.00 m) hiehgt:-

a) ratio 1:2 100 Sft. 2,648.70 3,575.35 Sq.m 285.00 384.70


b) ratio 1:3 100 Sft. 2,648.70 3,360.05 Sq.m 285.00 361.55

19 Pointing flush on stone work, upto 20' (6.00 m) height. 25.8

a) in lime mortar 1:2 (lime, sand) 100 Sft. 2,139.20 2,525.45 Sq.m 230.20 271.75
b) in cement mortar 1:3 100 Sft. 2,139.20 2,850.55 Sq.m 230.20 306.70
c) on stone work raised:-
i) in lime mortar 1:2 100 Sft. 4,021.50 4,407.80 Sq.m 432.70 474.30
ii) in cement mortar 1:3 100 Sft. 4,021.50 4,732.85 Sq.m 432.70 509.25

20 Raking and washing joints of stone masonry 100 Sft. 1,372.80 - Sq.m 147.70 - ditto
(old work).

21 Raking and washing joints of brick masonry (old work). 100 Sft. 686.40 - Sq.m 73.85 - ditto

22 Priming coat of chalk under distemper. 100 Sft. 239.20 271.95 Sq.m 25.75 29.25 25.11

23 Distempering:- ditto

a) new surface:-
i) one coat 100 Sft. 262.40 747.00 Sq.m 28.25 80.40
ii) two coats 100 Sft. 387.90 1,028.45 Sq.m 41.75 110.65
iii) three coats 100 Sft. 513.40 1,309.95 Sq.m 55.25 140.95

b) old surface:-
i) one coat 100 Sft. 239.55 568.10 Sq.m 25.80 61.15
ii) two coats 100 Sft. 387.90 716.45 Sq.m 41.75 77.10

24 Colour washing:- 25.10

a) new surface:-
i) one coat 100 Sft. 225.90 353.00 Sq.m 24.30 38.00
ii) two coats 100 Sft. 338.80 524.05 Sq.m 36.45 56.40

b) old surface:-
i) one coat 100 Sft. 225.90 312.40 Sq.m 24.30 33.60
ii) two coats 100 Sft. 338.80 480.70 Sq.m 36.45 51.70

25 White washing:- 25.9

a) new surface:-
i) one coat 100 Sft. 225.90 327.55 Sq.m 24.30 35.25
ii) two coats 100 Sft. 338.80 491.05 Sq.m 36.45 52.85

chapter-11(Surface Rendering).xls Page 77


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

iii) three coats 100 Sft. 438.05 640.85 Sq.m 47.15 68.95

b) old surface:-
i) one coat 100 Sft. 225.90 302.05 Sq.m 24.30 32.50
ii) two coats 100 Sft. 338.80 465.55 Sq.m 36.45 50.10

26 Gobri leeping:- 25.7

a) on walls 100 Sft. 267.55 280.55 Sq.m 28.80 30.20


b) over roofs 100 Sft. 226.40 239.40 Sq.m 24.35 25.75

27 Striking joints of burnt bricks in lime or cement mortar. 100 Sft. 343.20 - Sq.m 36.95 - 25.8 Payable with fresh masonry, when
the face of the work is not to be
plastered/pointed.
28 Extra for lime, mud or cement plaster and pointing from 100 Sft. 419.50 - Sq.m 45.15 -
20' (6.00 m) and above for each additional 10' (3.00 m)
height or part thereof.

29 Caulking joints of sleeper wall, with sand and coaltar. 100 Sft. 1,195.90 2,081.90 Sq.m 128.70 224.00

30 Caulking joints of sleepers, withmud and chopped straw. 100 Sft. 1,195.90 1,241.50 Sq.m 128.70 133.60

31 Extra cost of labour and material for red oxide pigment in 100 Sft. 429.00 669.00 Sq.m 46.15 72.00
cement pointing to match with the colour of bricks.

32 Providing grooved cement sand plaster 1:3 over existing


plastered and roughened surface upto 20' (6.00 m) height.

i) 3/8" (10 mm) thick 100 Sft. 2,648.70 3,520.80 Sq.m 285.00 378.85
ii) ½" (13 mm) thick 100 Sft. 2,648.70 3,811.50 Sq.m 285.00 410.10

33 Providing and fitting expanded metal edge bead for Rft. 20.45 65.90 Metre 67.10 216.15
corners, with nails on both sides of edges.

34 Petty repairs to fire place.

i) Single Each 418.55 521.15 Each 418.55 521.15


ii) Double Each 837.15 1,042.25 Each 837.15 1,042.25

35 Petty repair to main rooms. Each 862.10 1,135.85 Each 862.10 1,135.85 Area above 100 Sft (10.76 sq.m)

36 Petty repair to small rooms. Each 431.05 567.85 Each 431.05 567.85 Area upto 100 Sft (10.76 sq.m)

37 Petty repair to verandah. Each 862.10 1,080.95 Each 862.10 1,080.95


The height will be taken from the
38 Extra labour for white washing, colour washing, priming coat 100 Sft. 37.65 - Sq.m 4.05 - floor, roof or ground uderneath as
and distempering, etc. from 20' (6.00 m) height and above, Per Per the case may be on the side
requiring scaffolding, for every additional 10' (3.00m) height coat coat towards which the work is to be
or part thereof. done.

chapter-11(Surface Rendering).xls Page 78


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

39 Preparing surface and applying Graffiato Weather Coating ( Per Sft 37.35 53.20 Sq.m 402.15 572.55 25.1&

25.6
Co-polymer emulsion) of approved colour & shade with weather resistant
pigment, highly water repellant with Metalic Spatula having top class
finish by smoothing with a plastic Spatula, on a base coat (Primer) over
well cleaned plastered surface complete in all respect as approved and
directed by the Engineer Incharge.
40 Providing & applying 1.5 mm thick fine textured high quality Sandtex Per Sft 37.35 53.70 Sq.m 402.15 578.05 25.1&

25.6
Coating formed of special Acrylic base protective decorative coating of
approved colour & shade with trowel having top class finish over well
cleaned plastered surface i/c preparation and cleaning the surface,
complete in all respect as approved and directed by the Engineer
Incharge.

chapter-11(Surface Rendering).xls Page 79


12. WOOD WORK
1 No extra rate is to be paid for sawing as the rates are inclusive of these.
2 Rates for all finished works include the removal of surplus debris, unused material and byproducts.

MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

1 Plain wood work sawn, wrought, planed and fixed 26.1


inposition, including cost of nails and screws etc.

a) Deodar wood Per Cft. 1,510.10 11,081.05 cu.m 53,336.75 391,382.70


b) Shisham wood ditto 1,716.00 12,805.80 ditto 60,609.10 452,300.85

2 Plain wood work for regulation karries or needles, etc. 26.1


including sawing, planning, wroughting wood and providing
and fixing steel parts of karries i.e. end strip and rods, etc.

a) Deodar wood Per Cft. 978.10 10,777.30 cu.m 34,546.50 380,654.25


b) Shisham wood ditto 978.10 12,255.70 ditto 34,546.50 432,871.30

3 First class teak wood wrought joinery in doors and 26.1


windows, etc. panelled, panelled and glazed or fully to
glazed and fixed in position, including chowkat, holdfast, 26.3
tower bolt, chocks, rubber stop, cleats/G.I. clamps, &
chords with hooks, nails, screws, etc. complete 26.7
(excluding sliding bolt and lock):-

i) 2" (50 mm) thick Per Sft. 249.65 6,706.25 sq.m 2,686.25 72,159.25
ii) 1¾" ( 45 mm) thick ditto 249.65 6,239.60 ditto 2,686.25 67,138.10
iii) 1½" (40 mm) thick ditto 249.65 5,784.05 ditto 2,686.25 62,236.40

4 First class teak wood wrought joinery in wire gauze doors 26.8 i) This also includes the cost of
and windows with frames 22 SWG galvanized iron wire to wood required for extra thickness of
2
gauze 12x12 meshes to square inch, (5x5 meshes in cm ) 26.10 chowkat.
including brass fittings, sash bars, etc. complete:- ii) If 24 SWG wire gauge is used,
the composite rate shall be
a) teak wood framing 1¾" (45 mm) thick with wire gauze reduced by Rs.4.70 per sft. and
fixed in position:- Rs.50.60 per sq.m.

i) without springs or spring hinges. Per Sft. 47.65 2,787.05 sq.m 512.70 29,988.65

ii) with springs or spring hinges. ditto 47.65 2,796.25 ditto 512.70 30,087.65

b) teak wood framing 1½" (40 mm) thick, with wire


gauze fixed in position:-
i) without springs or spring hinges. Per Sft. 47.65 2,564.80 sq.m 512.70 27,597.25
ii) with springs or spring hinges. ditto 47.65 2,575.50 ditto 512.70 27,712.40

chapter-12(Wood Work).xls Page 80


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

c) G.I. wire gauze 22 SWG, 12x12 meshes per square Per Sft. 85.80 742.30 sq.m 923.20 7,987.15
2
inch, (5x5 meshes per cm ) fixed to chowkat with ¾"
(20 mm) teak wood strips and screws.

d) G.I. wire gauze 22 SWG, 12x12 meshes per square Per Sft. 80.45 2,639.85 sq.m 865.65 28,404.80
2
inch (5x5 meshes per cm ) fixed with ½" (13 mm) strip
on separate frame of teak wood 2"x2" (50x50 mm),
for windows, etc.

5 P/F expanded metal ½" to ¾" (13 to 20 mm) mesh, 16 Per Sft. 107.25 1,224.75 sq.m 1,154.00 13,178.30
Guage, fixed to chowkat with 1" (25 mm) teak wood cover
strips and screw etc., complete.

6 Providing and fixing expanded metal ½" (13 mm) to ¾" Per Sft. 107.25 1,896.15 sq.m 1,154.00 20,402.55
20 mm), 16 gauge, fixed to chowkat with 1" (25 mm)cover
moulding and screws, including teak wood frame 2"x2"
(50 mm x 50 mm)

7 Providing and fixing 1st class solid wood wrought joinery in panelled or 26.1 to
panelled and glazed doors and windows of specified thickness with 1" 26.3 & 26.7
thick solid wood panels with step and 1-1/2"x2-1/2" beadings all around
the panels i/c the cost of Tower bolt and handles complete in all respect
(Excluding the cost of sliding bolt,lock and chowkats (frame), etc.) as
approved and directed by the Engineer Incharge
a) Deodar wood Door
(i) 2" thick (50 mm) Per Sft 317.80 2,656.05 Sq.m 3,419.30 28,578.85 For doors without beadings around the
(ii) 1-3/4" thick (45 mm) Per Sft 317.80 2,483.30 Sq.m 3,419.30 26,720.30 panels, Reduce Composite rate by Rs
(iii) 1-1/2" thick (40 mm) Per Sft 317.80 2,310.55 Sq.m 3,419.30 24,861.75 280.80 P.sft or Rs 3021.40 P.Sq Mtr.
b) Oak/Ash wood Door
(i) 2" thick (50 mm) Per Sft 381.35 2,333.35 Sq.m 4,103.15 25,106.95 For doors without beadings around the
(ii) 1-3/4" thick (45 mm) Per Sft 381.35 2,190.05 Sq.m 4,103.15 23,564.80 panels, Reduce Composite rate by Rs
(iii) 1-1/2" thick (40 mm) Per Sft 381.35 2,046.70 Sq.m 4,103.15 22,022.70 230.40 P.sft or Rs 2479.15 P.Sq Mtr.
c) Yellowpine wood Door
(i) 2" thick (50 mm) Per Sft 381.35 1,627.55 Sq.m 4,103.15 17,512.55 For doors without beadings around the
(ii) 1-3/4" thick (45 mm) Per Sft 381.35 1,538.00 Sq.m 4,103.15 16,548.75 panels, Reduce Composite rate by Rs
(iii) 1-1/2" thick (40 mm) Per Sft 381.35 1,448.40 Sq.m 4,103.15 15,584.95 144.00 P.sft or Rs 1549.40 P.Sq Mtr.

8 P/F 1½" (40mm) thick semi solid panelled or panelled and glazed doors 26.1 to
comprising of solid wood styles and rails of specfied width and panels of 26.3 & 26.7
2.5 mm thick veneer ply matching with wood used with grooves , pasted
on both sides of 1" thick Lasani wood panel with tapered edges i/c the
cost of tower bolt ,handles complete in all respect (Excluding the cost of
chowkat frame,sliding bolt and lock) as approved and directed by For doors without beadings around the
Engineer Incharge panels, Reduce the :-.
i) Composite rate by Rs 280.80 P.sft or Rs
(i) Deodar Wood Per Sft 221.45 1,696.90 Sq.m 2,383.00 18,258.75
3012.40 P.Sq Mtr

chapter-12(Wood Work).xls Page 81


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

ii) Composite rate by Rs 230.40 P.sft or Rs


(ii) Oak/Ash Wood Per Sft 221.45 1,474.50 Sq.m 2,383.00 15,865.80
2479.10 P.Sq Mtr
iii) Composite rate by Rs 144.00 P.sft or
(iii) Yellowpine Wood Per Sft 221.45 1,068.10 Sq.m 2,383.00 11,492.95
Rs 1549.45 P.Sq Mtr
9 Deodar wood framed, braced and battened doors and 26.1, 26.2
windows, complete with iron fittings and fixed in position, & 26.4
including chowkats:-

a) 2¼" (56 mm) thick, with 1¼" (30 mm) Per Sft. 286.00 2,053.15 sq.m 3,077.35 22,091.90
battens and 1" (25 mm) planks.
b) 1¾" (40 mm) thick with 1" (25 mm) ditto 264.00 1,754.05 ditto 2,840.65 18,873.60
battens and ¾" (20 mm) planks.

10 1" (25 mm) thick battneded doors and windows fitted in Per Sft. 326.05 1,120.25 sq.m 3,508.30 12,053.90
position, complete with iron fittings, without chowkats.

11 Deodar battened ledged and braced doors and windows 26.1, 26.2
2¼" (56 mm) thick (1¼" (30 mm) thick ledge braces and 26.4 to
1" (25 mm) thick battens complete with iron fittings, Per Sft. 308.00 1,978.90 sq.m 3,314.10 21,292.95 26.6
chowkats and fixed in position.

12 a) Deodar wood framed with braces and 22 SWG G.I. 26.1, 26.2 If 24 gauge G.I. sheet is used, the
sheet facing, including holdfast, wooden beadings, & 26.4 composite rate will be reduced by
hinges, and locking arrangements as directed by the Re.4.70 per Sft. (Rs. Per 50.60
Engineer incharge:- Sq.m) for G.I. facing on one side
and Rs.9.40 per Sft. (Rs.101.20
i) G.I. sheet facing on one side. Per Sft. 134.05 1,402.60 sq.m 1,442.40 15,092.00 per Sq.m) for G.I. sheet facing on
ii) G.I. sheet facing on both sides. ditto 147.45 1,489.70 ditto 1,586.55 16,029.15 both sides.

b) Partal wood framed with braces and 22 SWG G.I.


sheet facing, including holdfast, wooden beadings, -ditto-
hinges and locking arrangements, as directed by the
Engineer-in-charge:-

i) G.I. sheet facing on one side. Per Sft. 134.05 654.45 sq.m 1,442.40 7,041.90
ii) G.I. sheet facing on both sides. ditto 147.45 741.55 ditto 1,586.55 7,979.10

13 First class deodar wood wrought joinery work in wire 26.8 to i) This also includes the cost of
gauze doors and windows, with 22 SWG G.I. wire gauze, 26.10 wood required for extra thickness
2
12x12 meshes per square inches (5x5 per cm ) including of chowkat.
iron fittings etc. complete:-
ii) If 24 SWG wire gauze is used
a) deodar wood framing 1¾" (45 mm) thick with wire the composite rate shall be
gauze fixed in position:- reduced by Rs.4.70 per sft or
Rs.50.60 per sq.m.
i) without springs or spring hinges. Per Sft. 143.00 1,165.05 sq.m 1,538.70 12,535.95
ii) with springs or spring hinges. ditto 143.00 1,175.70 ditto 1,538.70 12,650.55

chapter-12(Wood Work).xls Page 82


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

b) deodar wood framing 1½" (40 mm) thick, with wire


gauze fixed in position:-
i) without springs or spring hinges Per Sft. 143.00 1,085.95 sq.m 1,538.70 11,684.80
ii) with springs or spring hinges ditto 143.00 1,092.65 ditto 1,538.70 11,756.90

c) G.I. wire gauze 22 SWG, 12x12 meshes per square


2
inch, (5x5 in cm ) fixed to chowkat, with ¾" Per Sft. 107.25 399.60 sq.m 1,154.00 4,299.70
('20 mm) thick deodar wood strip and screws.

d) G.I. wire gauze 22 SWG 12x12 meshes per square


2
inch, (5x5 meshes in cm ) fixed to chowkat, with ½" Per Sft. 160.90 1,030.90 sq.m 1,731.30 11,092.50
(13 mm) strip on separate frame of deodar wood 2" x
2" (50 mm x 50 mm).

14 Making and fixing trellis doors and windows of deodar Per Sft. 238.35 1,327.50 sq.m 2,564.65 14,283.90 26.1
wood, complete. 26.2

15 Providing and fixing mild steel chowkat of doors, windows,


C.window, etc. including holdfast, making and threading
holes for hinges, etc. complete:-

a) M.S. angle iron 1½"x 1½"x ¼" (40x40x6 mm) welded Per Sft. 57.15 404.70 sq.m 614.95 4,354.55
with M.S. flat 2"x ¼" (50 mm x 6 mm)

b) M.S. tee iron 1½"x 1½"x ¼" (40x40x6 mm) welded Per Sft. 57.15 305.95 sq.m 614.95 3,292.00
with M.S. flat 2"x ¼" (50 mm x 6 mm)

16 Providing and fixing M.S. sheet hollow pressed frame of


doors, windows, C. windows, etc. (chowkat only) of 20
SWG welded with M.S. flat 6"x 1¼" x 1/8" (150
mmx30mmx3mm) M.S. holdfast 9"x1"x1/8"
(225mmx25mmx3mm) welded/screwed 4" (100 mm) long
iron hinges, including filling chowkat with cement sand
mortar 1:8 and embedding holdfast in cement concrete
1:2:4, complete in all respects:

a) single rebate Per Sft. 84.05 378.20 sq.m 904.40 4,069.45


b) double rebate ditto 99.35 433.05 ditto 1,069.00 4,659.60

17 Providing and fixing 2" wide MS/ GI Chowkat singel/double rebate made
of 16 SWG MS sheet pressed/welded / supported with M.S. flat 1-
1/4"x1/8" i/c 6"long M.S. Flat 1"x1/8"hold fasts (6-Nos) welded/
screwed, punching of lock hole covered with MS Box,coating with
antirust paint including filling with cement sand mortar (1:8) and
embedding hold fast in cement concrete (1:2:4) ,complete in all respect as
approved and directed by Engineer Incharge.
(i) 15 " wide Per Sft 122.55 731.95 Sq.m 1,318.85 7,875.75

chapter-12(Wood Work).xls Page 83


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

(ii) 10.50 " wide Per Sft 122.55 626.60 Sq.m 1,318.85 6,742.15
(iii) 5.5 " wide Per Sft 122.55 434.65 Sq.m 1,318.85 4,676.70

18 Extra for providing and fixing iron double spring hinges, Per Sft. 8.15 78.75 sq.m 87.70 847.35 26.2
with brass fittings (it shall include brass finger plate, 6" door area door area
(150 mm) tower bolt).

19 Providing and fixing brass spring hinges to wire gauzed Each 171.60 483.60 Each 171.60 483.60
doors.

20 Extra for brass fittings to doors and windows, except for


hinges, which shall be of iron:-

i) deodar wood panelled or panelled and glazed or fully glazed. Per Sft. 4.90 59.70 sq.m 52.70 642.35
ii) deodar wood wire gauzed shutters. ditto 4.90 38.45 ditto 52.70 413.70

21 Extra for providing and fixing approved quality rim lock Each 514.80 1,018.80 Each 514.80 1,018.80
adjustable over the style surface.

22 Providing and fixing, approved quality mortice lock. Each 715.00 799.00 Each 715.00 799.00

23 Providing and fixing, expended metal ½" to ¾" (13 mm to


20 mm) mesh 16 gauge.

a) fixed to chowkat with 1" (25 mm) thick deodar wood Per Sft. 107.25 577.95 sq.m 1,154.00 6,218.75
strip and screws, etc.
b) fixed with 1" (25 mm) cover moulding and screws, ditto 107.25 814.65 ditto 1,154.00 8,765.65
including deodar wood frame 2"x2" (50 x 50 mm)

24 a) Providing and fixing deodar wood almirah 9" to 12" For hollow frame shutter with
(225 mm to 300 mm) depth, including boxing with Per Sft. 343.20 3,820.95 sq.m 3,692.85 41,113.50 commercial ply on one side, the
back, shelves, shutter and brass fittings, etc. composite rate shall be reduced by
complete. Rs.54.00 per Sft;or Rs.580.00
per Sqm and for hollow frame
shutter with commercial ply on
both sides, the composite rate
shall be reduced by Rs.22.80 per
Sft. or Rs.245.00 per Sq. metre.
b) Providing and fixing deodar wood almirah 9" to 12"
(225 mm to 300 mm)depth with shelves, shutters, Per Sft. 257.40 1,564.60 sq.m 2,769.60 16,835.10
brass fittings, etc., without boxing and back,
complete.
25 Providing and fixng class room almirah consiting of 1" (25 Per Sft. 189.85 836.80 Sq.m 2,042.55 9,004.15
mm) thick solid flush shutter with deodar wood lipping ¼" (6 mm)
thick all around (Approved Factory Manufactured) fixed in deodar
wood frame 3"x1" (75mm x 25mm) including full hinges
C.P. fittings with RCC (1:1½:3) shelves 1½" (40 mm) thick
including 3 coats of painting.
chapter-12(Wood Work).xls Page 84
MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

26 Providing and fixing wooden box type wardrobe 22" (550 If hollow flush door leaves 1" thick
mm) deep including ¾" (20 mm) thick boxing and shelves, (25 mm) with commercial ply
hanger rods, hard board back drawers, brass fittings, 3 ply) on both sides of deodar
locking arrangements, handles, internal bolts, shoe rods, wood frame and partal wood
etc. including three coats of enamel paint:- bracing and deodar wood lipping is
used, the composite rate will be
reduced by Rs.13.00 per Sft. or
i) Partal wood boxing and deodar wood shelves and leaves, etc. Per Sft. 396.00 2,143.50 sq.m 4,260.95 23,063.90 Rs.140.00 per Sq. metre.
ii) Deodar wood boxing, and deodar wood shelves and leaves, etc. ditto 386.10 2,769.45 ditto 4,154.45 29,799.20
27 Providing and fixing wardrobe 22" (550 mm) deep Per Sft. 153.60 1,258.75 Sq.m 1,653.00 13,544.10
consisting of RCC shelves 1½" (40 mm) thick including ½"
thick vinboard boxing and back (one side ply) vinboard
shutter ¾" (20 mm) thick including deodar wood lipping ¼"
(6 mm) on all edges, fixes including deodar wood frame
3"x1" (75mm x 25mm) with hanger rod in centre position
drawers at bottom and openable shutter on upper portion
including full hinges C.P. fitting and painting 3 coats
complete.

28 Providing and fixing 3"x4-1/2" chowkat for doors, windows and C.


windows, including holdfast, etc.

a) Teak wood Per Sft. 76.25 2,313.15 Sq.m 820.65 24,889.55


b) Deodar wood Per Sft. 47.65 873.20 Sq.m 512.90 9,395.85
c) Shisham wood Per Sft. 57.20 799.70 Sq.m 615.45 8,604.65
d) Oak/Ash Wood Per Sft. 52.55 756.55 Sq.m 565.50 8,140.55
e) Yellowpine Wood Per Sft. 52.55 497.55 Sq.m 565.50 5,353.70
29 Making and fixing deodar wood planking in eave boards, 26.1
etc. planed on both sides, rebated and fixed including 26.2
nails and screws, bolts and brackets:-

a) 1" (25 mm) thick Sft. 85.80 872.70 sq.m 923.20 9,390.40
b) ¾" (20 mm) thick ditto 85.80 675.65 ditto 923.20 7,269.95
c) ½" (13 mm) thick ditto 85.80 479.40 ditto 923.20 5,158.45

30 Making and fixing deodar wood shelves, including ditto


brackets:-

i) 1" (25 mm) thick Sft. 85.80 872.70 sq.m 923.20 9,390.40
ii) 1½" (40 mm) thick ditto 85.80 1,266.00 ditto 923.20 13,622.30
iii) 2" (50 mm) thick ditto 85.80 1,659.30 ditto 923.20 17,854.20

31 a) Making and fixing cleats for doors and windows, Each 102.95 333.95 Each 102.95 333.95 26.1 and
including hinges and screws. 26.2

chapter-12(Wood Work).xls Page 85


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

b) Making and fixing cleats with brass hooks for roof Each 137.30 293.30 Each 137.30 293.30
ventilators.

c) Providing and fixing door stops of 1½" (40 mm) dia Each 14.30 85.10 Each 14.30 85.10
rubber block.

d) Providing and fixing G.I. hook with clamps for doors. Each 4.60 23.75 Each 4.60 23.75

32 Hard wood railing of any shape and design, including ditto


bends and corners, fixed in position, including polishing
complete as directed.
a) Shisham wood Per Rft. 393.25 1,124.15 Metre 1,289.85 3,687.15
b) Teak wood ditto 291.70 3,004.75 ditto 956.85 9,855.65

33 Deodar wood dado or picture rail 3"x1½" (75x40 mm) as Per Rft. 145.85 650.15 Metre 478.40 2,132.50 26.1
per approved design including moulding and fixed in place, 26.2
cost of screws, nails, plugs, and painting complete.

34 Sawing wood by hand:-

a) Soft wood (deodar, kail or chir). 100Sft. 1,716.00 - sq.m 184.65 -


b) Hard wood (shisham, kikar, teak or ditto 2,288.00 - ditto 246.20 -
sahl).

35 Sawing wood by machine:

a) Soft wood 100Sft. 1,012.44 - sq.m 108.95 -


b) Hard wood ditto 1,521.50 - ditto 163.70 -

36 Making and fixing sun-shade of deodar wood including Per Sft. 120.10 1,056.70 sq.m 1,292.50 11,370.05 26.1
fixing brackets.

37 Making and fixing 1" (25 mm) thick kail or chir wooden ditto
notice board with frame. Per Sft. 143.00 315.70 sq.m 1,538.70 3,396.95

38 Making deodar punkha pole 10'x6"x6" Each 514.80 23,806.80 Each 514.80 23,806.80 ditto
(3.0 m x 150 mm x 150 mm)

39 Dismantling and refixing eave boards. Per Rft. 36.75 -- Metre 120.65 --

40 Making wooden stair-cases complete 2' to 3' (600 to 900 Per Rft. 557.60 6,574.75 Metre 1,828.95 21,565.25 26.1
mm) wide frame 1½" (40 mm) thick planks of deodar
wood, including hand rails.

41 Providing and fixing partition, including frame work:-

a) Sheets on one side of framework:-

i) Hard board 100Sft. 2,681.25 36,809.80 sq.m 288.50 3,960.75

chapter-12(Wood Work).xls Page 86


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

ii) Ply wood ¼" (6 mm) thick ditto 2,681.25 37,439.80 ditto 288.50 4,028.50
iii) Masonite ditto 2,681.25 36,179.80 ditto 288.50 3,892.95

b) Sheets on both sides of frame work:-

i) Hard board 100Sft. 3,217.50 42,437.80 sq.m 346.20 4,566.30


ii) Ply wood ¼" (6 mm) thick ditto 3,217.50 53,372.80 ditto 346.20 5,742.90
iii) Masonite ditto 3,217.50 41,177.80 ditto 346.20 4,430.75

42 Providing and fixing ceiling, including frame work:-

i) Hard board 100Sft. 5,132.20 25,675.65 sq.m 552.20 2,762.70


ii) Chip board ditto 5,132.20 28,675.65 ditto 552.20 3,085.50
iii) Ply wood ¼" (6 mm) thick ditto 5,132.20 26,875.65 ditto 552.20 2,891.80
iv) Masonite ditto 5,132.20 25,075.65 ditto 552.20 2,698.15

43 Providing and fixing thermopore false ceiling, including In case acoustic thermopore sheet is used,
wooden frame panelling, cost of M.S. clamps, making composite rate will be increased by
holes in walls and repairing damaged surface, complete in Rs.12.00 per Sft.
all respects:-

a) Deodar wood frame panelling:

i) ¾" (20 mm) thick 100Sft. 5,804.80 27,948.55 sq.m 624.60 3,007.25
ii) 1" (25 mm) thick ditto 5,804.80 28,227.40 ditto 624.60 3,037.25

b) Partal wood frame panelling:

i) ¾" (20 mm) thick 100Sft. 5,804.80 18,513.55 sq.m 624.60 1,992.05
ii) 1" (25 mm) thick ditto 5,804.80 18,891.55 ditto 624.60 2,032.75

44 a) Fixing door, including chowkats. Each 747.45 - Each 747.45 -


b) Fixing windows, including chowkats. ditto 373.75 - ditto 373.75 -
45 a) Glazing with panes (16 oz. to 18 oz.,) Per Sft. 61.30 115.20 sq.m 659.45 1,239.55 26.12
including cost of putty.

b) Glazing with panes (16 oz. to 18 oz.) Per Sft. 77.20 195.00 sq.m 830.90 2,098.10
using deodar wooden fillets and putty.

46 Glazing with panes (24 oz. to 26 oz.), using Per Sft. 112.85 212.05 sq.m 1,214.35 2,281.70 26.12
putty and deodar wooden fillets.

47 a) Cutting to required size and fixing glass Per Sft. 42.90 44.00 sq.m 461.60 473.60
panes with putty

b) Cutting to required size and fixing glass panes with Per Sft. 64.35 117.10 sq.m 692.40 1,259.75
wooden fillets and putty.

chapter-12(Wood Work).xls Page 87


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

48 Glazing with plate glass 1/4" (6 mm) thick including the cost
of deodar wood fillets and putty:-

a) Glazing upto 8 sft (0.75 sq.m) Per Sft. 98.65 297.55 sq.m 1,061.70 3,201.85

b) Glazing exceeding 8 Sft (0.75 sq.m) but not exceeding 24 sft Per Sft. 98.65 297.75 sq.m 1,061.70 3,203.95
(2.25 sq.m).

49 Providing and fixing 1½" (40 mm) thick deodar wood


panelled or panelled and glazed, doors and windows, with
mild steel chowkat (frame), etc. complete in all respects
(excluding sliding bolt or lock) with:-
i) M.S. angle iron 1½"x1½"x¼", welded Per Sft. 366.70 2,023.25 sq.m 3,945.85 21,770.05
(40 mmx 40 mmx 6mm) with M.S. flat
2"x¼" (50 mm x 6 mm)
ii) M.S. tee iron 1½"x1½"x¼", welded Per Sft. 366.70 1,881.65 sq.m 3,945.85 20,246.70
(40 mmx40 mmx 6mm) with M.S. flat
½"x¼" (13 mm x 6 mm)

50 Providing and fixing 1½" (40 mm) thick hollow flush doors Teak ply would be used under the
and windows with commercial ply (3 ply) on both faces of written permission of the
deodar wood shutter frame 1¼" (30 mm) thick and partal superintending Engineer, and the
wood braces at about 3" (75 mm) apart and deodar wood composite rate of using teak ply
lipping 1½"x3/8" (40 mmx10 mm) fixed with M.S. chowkat will be increased by Rs.20.00 per
(frame) including chromium plated fittings, etc. complete Sft. ( 216.00 per Sq.m)
in all respects (without sliding bolt or lock):-

i) M.S. angle iron 1½"x1½"x¼", welded Per Sft. 254.20 1,519.80 sq.m 2,735.45 16,352.90
(40 mmx40 mmx 6mm) with M.S. flat
2"x¼" (50 mm x 6 mm)
ii) M.S. tee iron 1½"x1½"x¼", welded Per Sft. 254.20 1,421.05 sq.m 2,735.45 15,290.45
(40 mmx40 mmx 6mm) with M.S. flat
½"x¼" (13 mm x 6 mm)
51 P/F 1-1/2" thick solid flush door comprising of 2.5 mm thick Commercial Per Sft 153.55 506.80 Sq.m 1,652.05 5,453.25 26.1 to It C.P. Finger plate and kick plate are not
ply compressed over 2.5 mm thick commercial ply over 1" thick packing 26.3 & 26.7 provided/ fixed, the composite rate will be
wood in style and rails under proper pressure i/c the cost of nails, tower reduced by Rs.15.20 P.Sft.
bolt , handles, glue, sawing charges, Painting charges, sand papering and
3/8" thick matching wooden lipping as approved and directed by the
Engineer Incharge.
52 P/F 1-1/2" thick solid flush door comprising of 2.5 mm thick Per Sft 220.10 685.75 Sq.m 2,368.25 7,378.45 26.1 to
Deodar/Ash/Oak ply with grooves , compressed over 2.5 mm thick 26.3 & 26.7
commercial ply over 1" thick packing wood in style and rails under proper
pressure i/c the cost of nails, tower bolt , handles, glue, sawing charges
and lacquar polishing to show the grains of ply properly, sand papering
and 3/8" thick matching wooden lipping as approved and directed by the
Engineer Incharge.
53 Providing and laying 24 SWG aluminum kick plate 4" (100 Per Rft. 51.50 72.00 Metre 168.85 236.15
mm) high, fixed with screws 4" (100 mm) centre to centre,
on bottom rail of flush doors only of commercial ply.
chapter-12(Wood Work).xls Page 88
MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

54 Providing and fitting curtain railing to doors and windows, Per Rft. 21.45 300.05 Metre 70.35 984.25
comprising of TOSO-elite Japan made superior type of
railing or equivalent, fixed over 4"x¾" (100mmx20mm)
deodar wood strip, including painting.

55 Providing and fixing G.I. wire gauze 22 SWG, 12x12 Per Sft. 43.70 172.95 sq.m 470.00 1,861.05 It 24 SWG wire gauze is used, the
2
meshes per square inch, (5x5 meshes in cm ) fixed to composite rate shall be reduced by
steel window, complete with flat iron patti ½"x 1/8" (13 Rs.4.70 per Sft. or Rs.50.60 P.SQM
mmx3 mm) and machine made screws.

56 Providing and fixing wooden moulding stopper 2½"x5/8"


(63 x 16 mm) on door frame fitted with ply of approved
quality complete in all respects.

a) Teak wood moulding Per Sft. 53.65 470.35 sq.m 577.00 5,060.95
b) Deodar wood moulding ditto 53.65 172.50 ditto 577.00 1,855.95

57 Providing and fixing deodar wood dolly frame having Rate shall be paid as per surface
1½"x1½" (40 x 40 mm) vertical and horizontal double post area of dolly frame
with 1½"x1½" (40 x 40 mm) full width of james braces at e-g 0.75' x (3.5' + (2 x 7))
12" (300 mm) including filling of the spaces in between
braces with 1:3:6 PCC fixing ply of approved quality
including holdfasts complete in all respects.

a) Teak wood ply Per Sft. 132.00 823.30 sq.m 1,420.30 8,858.45
b) With commercial ply ditto 132.00 807.05 ditto 1,420.30 8,683.65

58 Providing and fixing ornamental wooden architrave 3" x


(1½" tapered to ¼") all along the door frame complete in all
respect.

a) Teak wood architrave Per Sft. 23.05 305.80 sq.m 248.10 3,290.20
b) Deodar wood architrave ditto 23.05 102.95 ditto 248.10 1,108.00

59 Providing and fixing Vin board cabinet 3/4" thick with


drawers 3"deep in 'Kitchen including termite proofing and
polishing with synthetic enamel as specified, with handles
hinges,screws etc., complete in all respects.
i) 1-1/2' deep,without back Per Sft 260.40 1,111.00 sq.m 2,801.80 11,954.25
ii) 1-1/2' deep,with back Per Sft 260.40 1,195.00 sq.m 2,801.80 12,858.10
iii) 2' deep,without back Per Sft 260.40 1,192.90 sq.m 2,801.80 12,835.50
iv) 2' deep,with back Per Sft 260.40 1,276.90 sq.m 2,801.80 13,739.35

chapter-12(Wood Work).xls Page 89


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

60 P/F 1½" (40mm) thick wooden dolly Frame chowkat comprising of


1-1/2'x2" (40 mmx50 mm) vertical and (40 mmx50 mm) horizontal
bracings @ 12" c/c of yellowpine wood full width of Jamb, filling of
spaces with (1:3:6) PCC i/c the cost of 3/8 " thick specified wooden
cladding i/c the cost of holdfast complete in all respect as approved and
directed by Engineer Incharge. ( Surface area of chowkat will be made
basis for payment)
(i) Deodar Wood Cladding Per Sft 114.85 967.35 Sq.m 1,235.90 10,408.75
(ii) Oak/Ash Wood Claddding Per Sft 114.85 927.80 Sq.m 1,235.90 9,983.10
(ii) Yellowpine Wood Cladding Per Sft 114.85 795.95 Sq.m 1,235.90 8,564.35
61 P/F 3/4" dia heavy duty sliding bolt of specified material i/c the cost of
hardware complete in all respect as approved and directed by the Engineer
Incharge.
a) I ron
(i) 10" (250 mm) long Each 149.50 413.50 Each 149.50 413.50
ii) 12" (300 mm) long Each 149.50 473.50 Each 149.50 473.50
b) Brass
i) 10" (250 mm) long Each 149.50 649.50 Each 149.50 649.50
(ii) 12" (300 mm) long Each 149.50 929.50 Each 149.50 929.50
(iii) 18" (450 mm) long Each 149.50 1,229.50 Each 149.50 1,229.50
62 Providing and fixing almirah shutter comprising of 3/4" thick both side Per Sft 91.60 433.80 Sq.m 985.75 4,667.50 26.1 to
Laminated/Glossy MDF (Karachi) sheet with 1"x3/4"deodar wood golla 26.3 & 26.7
all around the leaf fixed on (3"x1") Kail wood frame i/c the cost of 1/2"
full brass hinges, C.P.handles, catchers, screws, and rawal plugs,
polishing/ paint ing 3 coat to gola & frame i/c the cost of locking
arrangement complete in all respect as approved and directed by Engineer
Incharge.
63 Providing and fixing 24" Deep Box type Wardrobe consisting of 3/4" Per Sft 205.90 1,250.10 Sq.m 2,215.70 13,451.30 26.1 to
thick UV coated MDF board(Medium density Fiber board) Sheet both 26.3 & 26.7
side glazed shutters and box comprising of 3/4" thick laminated MDF
sheet i/c the cost of 1mm thick PVC tape duly hot pressed on all edges of
the shutters / panels / drawers etc., with machine i/c the cost of self closing
box type hinges, handles, screws, Glue and rawal plugs, Drawers &
locking arrangement complete in all respect as approved and directed by
Engineer Incharge
64 Providing and fixing 1-1/2" thick G.I sheet forged door comprising of G.I Per Sft 416.95 1,895.50 Sq.m 4,486.55 20,395.45
pressed double skin pannelled sheet of 22 SWG in specified width of rails,
Styles and panels pressed on both sides of fillet (Honey Comb paper),
dully fixed in chowkat with Archtrative on one side, with heavy duty 4
No. steel hinges i/c M.S Tower bolt 9" long, M.S Sliding bolt 12" long,
Rowel bolt for Hold Fasts, duly powder coated paint and punching of
required holes as approved and directed by the Engineer Incharge .

66 P/F heavy duty self closing box type hinge having required degree of
opening i/c the cost of hardware complete in all respect as approved and
directed by the Engineer Incharge.
chapter-12(Wood Work).xls Page 90
MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

(i) CP coated Iron Each 149.50 347.50 Each 149.50 347.50


(ii) Stainless steel Each 149.50 545.50 Each 149.50 545.50
67 Providing and fixing auotomatic hydraulic operated door closer imported Each 299.00 2,939.00 Each 299.00 2,939.00
heavy duty complete in all respect as approved and directed by the
Engineer Incharge.

68 Providing and fixing heavy duty 3 mm thick SS Plate, die-cast metal Each 299.00 5,579.00 Each 299.00 5,579.00
auotomatic hydraulic operated door stopper (Concealed floor hinge )
embeded in floor i/c the cost of Top pivot hinge,hardware, cutting of floor
and making it good complete in all respect as approved and directed by
the Engineer Incharge.

chapter-12(Wood Work).xls Page 91


13. PAINTING AND VARNISHING
1 The rates include charges for scaffolding and other arrangements.
2 The rates for all finished works include the removal of surplus debris, unused material and by products
MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

1 a) Cleaning painted wood work with oil and water. 100 Sft. 254.75 333.95 sq.m 27.40 35.95

b) Oiling woodwork with boiled linseed oil. 100 Sft. 169.85 250.50 sq.m 18.30 26.95 27.7

2 Brushing and scraping blisters of old paints from 100 Sft. 509.50 -- sq.m 54.80 - 27.3
woodwork.

3 Scraping, brushing and removing old paint from metal 100 Sft. 2,038.10 -- sq.m 219.30 - 27.9
surface.

4 Painting old surfaces:- 27.1


27.3 &
a) Painting corrugated surfaces, patent roofing, etc. with 27.9
oil paint.

i) first coat 100 Sft. 657.75 954.40 sq.m 70.80 102.70


ii) each subsequent coat ditto 498.30 650.95 ditto 53.60 70.05

b) Painting sashes, fanlights, glazed or gauzed doors


and windows:-

i) first coat 100 Sft. 398.65 559.90 sq.m 42.90 60.25


ii) each subsequent coat ditto 338.85 471.30 ditto 36.45 50.70

c) Painting doors and windows, any type:

i) first coat 100 Sft. 657.75 963.05 sq.m 70.80 103.60


ii) each subsequent coat ditto 498.30 731.60 ditto 53.60 78.70

d) Painting guard bars, gates of iron bars, gratings,


railing (including standards, braces etc.) and similar
open work:-
i) first coat 100 Sft. 398.65 559.90 sq.m 42.90 60.25
ii) each subsequent coat ditto 338.85 471.30 ditto 36.45 50.70
e) Painting fillets, framings, skirtings, pipes, gutters and
similar linear work not exceeding 6" in girth:-

i) first coat 100 Lft. 338.85 500.10 Metre 11.10 16.40


ii) each subsequent coat ditto 239.20 371.65 ditto 7.85 12.20

chapter-13(Painting & Var).xls Page 92


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

f) Painting small detached articles, not exceeding one


square foot (Sq.m) of painted surface:-

i) first coat 100 Nos. 1,017.25 1,313.85 100 Nos. 1,017.25 1,313.85
ii) each subsequent coat ditto 917.40 1,078.70 ditto 917.40 1,078.70

g) Painting small detached articles, exceeding one


square foot (Sq.m) but not exceeding three square
feet (Sq.m) of painted surface:-

i) first coat 100 Nos 2,325.10 3,206.35 100 Nos 2,325.10 3,206.35
ii) each subsequent coat ditto 1,344.50 1,785.15 ditto 1,344.50 1,785.15

5 Painting new surface:- 27.1


27.2 &
a) Preparing surface and painting corrugated surface, 27.9
patent roofing, etc.

i) priming coat. 100 Sft. 1,010.85 1,334.15 sq.m 108.75 143.55


ii) each subsequent coat of paint. ditto 353.95 722.60 ditto 38.10 77.75

b) Preparing surface and painting sashes, fan light,


glazed or gauzed doors and windows etc. any type
(including edges):-

i) priming coat. 100 Sft. 424.70 694.00 sq.m 45.70 74.70


ii) each subsequent coat of paint. ditto 287.00 497.25 ditto 30.90 53.50

c) Preparing surface and painting of doors and windows


any type (including edges):-

i) priming coat. 100 Sft. 1,010.85 1,325.50 sq.m 108.75 142.60


ii) each subsequent coat of paint. ditto 353.95 722.60 ditto 38.10 77.75

d) Preparing surface and painting guard bars, gates of


iron bars, gratings, railing (including standards,
braces, etc.) and in similar open work:-
i) priming coat. 100 Sft. 645.55 841.35 sq.m 69.45 90.55
ii) each subsequent coat of paint. ditto 287.00 497.25 ditto 30.90 53.50

e) Preparing surface and painting of fillets, framing,


skirtings, pipes, gutters, and similar linear work not
exceeding 6" (150 mm) girth:-

i) priming coat. 100 Lft. 508.25 658.15 Metre 16.65 21.60


ii) each subsequent coat of paint. ditto 191.35 367.05 ditto 6.30 12.05

chapter-13(Painting & Var).xls Page 93


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

f) Preparing surface and painting of small detached


articles, not exceeding one sq. ft. (Sq.m) of painted
surface:-

i) priming coat. 100 Nos. 1,494.90 2,412.20 100 Nos. 1,494.90 2,412.20
ii) each subsequent coat of paint. ditto 737.85 1,466.50 ditto 737.85 1,466.50

g) Preparing surface and painting of small detached


articles, exceeding one Sft. but not exceeding 3 Sft.
(Sq.m) of painted surface:-

i) priming coat. 100 Nos. 4,276.80 5,518.10 100 Nos. 4,276.80 5,518.10
ii) each subsequent coat of paint. ditto 1,282.60 2,587.25 ditto 1,282.60 2,587.25

h) Extra for knotting and stopping to 100 Sft. 68.65 94.55 sq.m 7.40 10.20
priming coat on new surface of wood.

6 Applying Khanki Mixture hot to barrage 27.10


gates:-

i) first coat 100 Sft. 498.30 995.65 sq.m 53.60 107.15


ii) second coat ditto 395.35 713.55 ditto 42.55 76.80

7 French polishing complete:- 27.6

a) on new work 100 Sft. 5,140.45 5,281.95 sq.m 553.10 568.35


b) on old work ditto 2,689.05 2,765.70 ditto 289.35 297.60

8 Varnishing wood work, including cleaning and preparing


surface.

a) first coat 100 Sft. 398.65 613.90 sq.m 42.90 66.05


b) second coat ditto 149.50 313.05 ditto 16.10 33.70
c) third coat ditto 149.50 278.25 ditto 16.10 29.95

9 Bitumen coating to plastered or cement concrete surface:-

i) 20 lbs. per 100 Sft. (9.07 Kg per Sq.m) 100 Sft. 424.60 2,178.75 sq.m 45.70 234.45
ii) 14 lbs. per 100 Sft. (6.35 Kg per Sq.m) ditto 407.60 1,312.80 ditto 43.85 141.25
iii) 10 lbs. per 100 Sft. (4.54 Kg per Sq.m) ditto 336.30 1,241.50 ditto 36.20 133.60

10 Writing letters or figures, per letter, per inch (25 mm) Per No. 19.95 21.05 Per No. 19.95 21.05 27.1
height.

11 Writing letters or figures at any surface with reflective paint Per Letter 19.95 20.55 Per Letter 19.95 20.55 27.1
of approved quality and colour per letter per inch height. per inch per 25 mm
height height

chapter-13(Painting & Var).xls Page 94


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

12 Writing letters of figures on any surface with reflective tape ditto 23.55 24.95 ditto 23.55 24.95 ditto
of approved quality and colour per letter per inch (25 mm)
height.

13 Coaltar painting: 27.8


to
a) first coat, laid hot 100 Sft. 453.00 1,809.90 sq.m 48.75 194.75 27.11
b) second coat, laid hot ditto 274.55 1,147.40 ditto 29.55 123.45

14 Solignum painting:- 27.8

a) one coat, applied hot 100 Sft. 377.50 434.40 sq.m 40.60 46.75
b) two coats, applied hot ditto 572.00 662.35 ditto 61.55 71.25

15 Creosote painting:- ditto

a) one coat, applied hot 100 Sft. 453.00 614.30 sq.m 48.75 66.10
b) two coats, applied hot ditto 686.40 954.25 ditto 73.85 102.70

16 Burning off or rubbing down with pumice stone, old paint 100 Sft. 1,627.55 1,643.15 sq.m 175.15 176.80 27.3
from wood work.

17 Removing with caustic soda, old paint from wood work. 100 Sft. 509.50 520.55 sq.m 54.80 56.00 ditto

18 Painting distance marks for white ground and black Each 99.65 117.00 Each 99.65 117.00 27.1
lettering on both sides.

19 Painting two feet wide gauges, reading to 10th of a foot Per Rft. 199.30 233.45 per Metre 653.75 765.70 ditto
(metre).

20 Painting sounding rods and other gauges, reading to 10th Per Lft. 99.65 110.25 per Metre 326.90 361.60 27.1
of a foot (metre)

21 Painting leveling staves. Per Lft. 313.70 330.80 per Metre 1,029.00 1,084.95

22 a) Painting and lettering mile/Km stones, ditto


on both sides:
i) one coat Each 213.55 335.60 Each 213.55 335.60
ii) two coats ditto 373.75 571.00 ditto 373.75 571.00
b) Painting and lettering Furlong/½ Km 27.1
stones, on both sides:-
i) one coat Each 28.45 43.00 Each 28.45 43.00
ii) two coats ditto 49.85 75.20 ditto 49.85 75.20

chapter-13(Painting & Var).xls Page 95


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

c) Painting and lettering Sign posts:-

i) one coat Each 239.20 318.60 Each 239.20 318.60


ii) two coats ditto 394.65 530.00 ditto 394.65 530.00

23 Removing paint or varnish from wall. 100 Sft. 1,019.05 - sq.m 109.65 - 27.12

24 Scraping from hydraulic gates:- 27.1

a) Khanki paint 100 Sft. 2,038.10 - sq.m 219.30 -


b) Aluminium paint ditto 2,038.10 - ditto 219.30 -

25 Painting letters with shade. per letter 31.90 31.90 per letter 31.90 31.90 27.1
per inch per 25 mm
height height

26 Scraping rust from old rail or girders. 100 Sft. 1,528.55 1,618.55 sq.m 164.45 174.15 27.9
27.10

27 Chiselling old paint from brick work. 100 Sft. 2,038.10 2,080.10 sq.m 219.30 223.80 27.12

28 Cleaning glasses with chalk and spirit, etc. 100 Sft. 1,698.40 1,736.40 sq.m 182.75 186.85

29 Cleaning and oiling rafter or rolled steel 100 Sft. 509.50 617.50 sq.m 54.80 66.45 27.9
beams.

30 Cleaning and painting punkha poles, including fixing Each 429.00 442.90 Each 429.00 442.90 27.3
hooks.

31 Preparing surface and painting with emulsion paint:- 27.12

a) first coat 100 Sft. 514.15 1,169.20 sq.m 55.30 125.80


b) 2nd and each subsequent coat ditto 394.15 896.45 ditto 42.40 96.45

32 Preparing surface and painting with water proof coloured 27.12


cement finish, like duracem, buxcem or other finishes with
similar specifications, on walls, etc.

a) new surface:

i) 1st coat 100 Sft. 514.15 783.45 sq.m 55.30 84.30


ii) 2nd and subsequent coat ditto 394.15 626.55 ditto 42.40 67.40

b) old surface:

i) 1st coat 100 Sft. 514.15 624.35 sq.m 55.30 67.20


ii) 2nd and subsequent coat ditto 394.15 498.25 ditto 42.40 53.60

chapter-13(Painting & Var).xls Page 96


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

33 Providing and applying weather shield paint of approved


quality on external surface of building including preparation of
surface, application of primer complete in all respect:
a) new surface:
i) 1st coat %sft 1,705.45 3,349.45 sq.m 183.50 360.40
ii) 2nd coat %sft 938.50 1,943.50 sq.m 101.00 209.10
b) old surface: %sft 938.50 1,943.50 sq.m 101.00 209.10
34 Painting Traffic Lane 5" (125 mm) wide, with road marking Per Rft. 3.00 5.00 Metre 9.80 16.45
enamel.

35 Painting Traffic Lane 5" (125 mm) wide with reflective Per Rft. 4.00 15.05 Metre 13.15 49.30 AASHTO Rates shall be reduced by Rs.0.50
clorinated rubber (CR) paint including glass beads comlpete M248-91 P.Rft or Rs.1.65 P.Mtr.
in all respect. (2000) If glass beads are not used.
36 Painting Traffic Lane Marking of specified width (1.5mm thick), with *1205-1 Payment will be made as per actual
Thermoplastic (TP) Paint including Glass Beads, complete in all respect, to measurement.
as approved and directed by Engineer incharge. 1205-8
i) 5" wide Per Rft. 5.50 48.30 Metre 18.10 158.50
ii) 6" wide Per Rft 5.50 56.35 Meter 18.10 184.75
37 Repainting of ceiling fan (all sizes and types), including Per Job 122.55 183.05 Job 122.55 183.05
painting of blades, canopy, suspension rod and regulator,
with suitable enamel paint.
38 Repainting of iron poles with cross arms, with bitumen or Per Job 286.00 490.50 Job 286.00 490.50
other approved paint.
39 Repainting of pipes and specials of G.I., M.S. or conduit,
etc., fixed for on surface electric wiring, with approved
paint:
i) upto 40 mm (1½") dia Per Rft. 2.60 8.60 Metre 8.60 15.55
ii) above 40 mm (1½") to 50 mm (2") dia ditto 5.25 8.75 ditto 17.15 28.70
iii) above 50 mm (2") to 100 mm (4") dia ditto 8.70 14.00 ditto 28.60 45.90
40 Repainting main switches and branch distribution boards Per Job 56.65 143.05 Job 56.65 143.05
of all sizes and types, with approved paint (complete set).

41 Extra labour for painting, varnishing, etc. from 20' (6.10 m) 100 Sft. 163.05 - sq.m 17.55 - The height will be taken from the
height and above, for every additional 10' (3.05 m) height, per coat floor, roof or ground underneath, as
or part thereof, requiring scaffolding. the case may be on the side
towards which the work is to be
done.
42 Lettering and printing of signage / direction boards / road delineators of
any colour by machine i/c cost of Digital Lettering, Lamination & pasting
etc complete in all respect.
a) High Intensity Prismatic (HIP) Tape P.Sft 124.60 1,114.60 Sq.m 1,340.45 11,992.85
b) Diamond Grade Tape P.Sft 124.60 1,264.60 Sq.m 1,340.45 13,606.85

chapter-13(Painting & Var).xls Page 97


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

43 Providing and laying Rumble Strips with Thermoplastic Paint on pre-laid P.Rft 15.70 134.60 Meter 51.45 441.45
asphalt roads comprising of 8" wide yellow strip comprising of 03 Nos
humps and 6" wide chequered strip in white colour with machine of
specified thicknesses and pattern etc complete in all respect.

44 Preparing surface and Lacquar polish to reveal wooden grains by 27.6


application of multiple coats of wood sealer , sand papering with different
no of sandpapers and Lacquar to make glossy surface finish i/c the cost of
cotton, thinner, wood sealer complete in all respects as approved and
directed by the Engineer Incharge.
(i) Matt Finish Per Sft 122.05 173.40 Sq.m 1,313.05 1,865.80
(ii) Glossy Finish Per Sft 125.55 191.60 Sq.m 1,350.75 2,061.60
45 Preparing surface and painting with Matt/Glossy high chemical
resistant/hard wearing Polyurethane paint (Epoxy Paint) by sprayer/Brush
i/c the cost of Primer coat , all material and labour complete in all respects
as approved and directed by the Engineer Incharge.

(i)Priming Coat Per Sft 10.10 24.50 Sq.m 108.75 263.80


(ii) Each and subsequent Coat Per Sft 5.30 20.40 Sq.m 57.15 219.50

46 Providing and applying wall putty of 2mm thickness over plastered surface
(new surface) to prepare the surface even and smooth complete in all 100 Sft 239.20 376.65 Sq.m 25.75 40.55
respect.

chapter-13(Painting & Var).xls Page 98


14. LINING OF CANALS
1 Rates for all finished works include the removal of surplus debris, unused material and byproducts.
2 The rates also include curing for specified period wherever necessary.
3 Nominal dimension of tile or brick shall be taken for the purpose of measurement and payment.
MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

1 Formation, dressing and preparing sub-grade:- 28.1 to 28.3

a) in bed 100Sft. 1,123.75 - sq.m 120.90 -


b) on slope ditto 1,532.80 - ditto 164.95 -

2 Stabilized layer of cement, sand ratio 1:30, 2" (50 mm) 100Sft. 2,728.70 3,794.30 sq.m 293.60 408.25 ditto
thick on slope.

3 Cement plaster ½" (13 mm) thick ratio 1:10. ditto

a) in bed 100Sft. 1,985.80 2,507.80 sq.m 213.65 269.85


b) on slope ditto 2,473.95 2,995.95 ditto 266.20 322.35

4 Cement plaster 3/8" (10 mm) thick ratio 1:3. ditto

a) in bed 100Sft. 1,985.80 2,905.60 sq.m 213.65 312.65


b) on slope ditto 2,473.95 3,393.75 ditto 266.20 365.15

5 Cement plaster 1½" (40 mm) thick ratio 1:6. ditto

a) in bed 100Sft. 2,473.95 4,678.20 sq.m 266.20 503.40


b) on slope ditto 3,071.90 5,276.20 ditto 330.55 567.70

6 Tile lining 12"x6"x2" (300x 150x50 mm) in 1:6 cement, 28.2 to 28.3 The rates are only for laying tiles
sand mortar:- over 1/8" (3 mm) thick layer of 1:6
mortar. Items 1 to 5 above are
a) in bed 100Cft. 11,622.25 34,624.45 cu.m 4,105.00 12,229.35 payable separately.
b) on slope ditto 13,325.05 36,327.25 ditto 4,706.40 12,830.80

7 Tile lining 12"x6"x2" (300x150x50 mm) in 28.2 to 28.3 The rates are only for laying tiles
1:3 cement, sand mortar:- over 1/8" (3 mm) thick layer of 1:3
mortar. Items 1 to 5 above are
a) in bed 100Cft. 11,622.25 37,677.25 cu.m 4,105.00 13,307.60 payable separately.
b) on slope ditto 13,325.05 39,380.05 ditto 4,706.40 13,909.05

8 Brick lining 9"x4½"x3" (225x113x75 mm) in 1:6 cement, 28.2 The rates are only for laying bricks
sand mortar:- over 1/8" (3 mm) thick layer of 1:6
mortar. Items 1 to 5 above are
a) in bed 100Cft. 11,622.25 35,920.45 cu.m 4,105.00 12,687.10 payable separately.
b) on slope ditto 13,325.05 37,623.25 ditto 4,706.40 13,288.55

chapter-14(Lining of canal).xls Page 99


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

9 Brick lining 9"x4½"x3" (225x113x75 mm), in 1:3 cement, ditto The rates are only for laying
sand mortar:- bricks over 1/8" (3 mm) thick
layer of 1:3 mortar. Items 1 to
a) in bed 100Cft. 11,622.25 38,973.25 cu.m 4,105.00 13,765.35 5 above are payable
b) on slope ditto 13,325.05 40,676.05 ditto 4,706.40 14,366.80 separately.

10 Cement concrete lining, using washed screened and 20.1, 28.1


graded stone aggregate:- & 28.3

a) in bed:-

i) ratio 1:2:4 100Cft. 10,129.40 38,271.80 cu.m 3,577.70 13,517.60


ii) ratio 1:3:6 ditto 10,129.40 32,941.40 ditto 3,577.70 11,634.90
iii) ratio 1:4:8 ditto 10,129.40 29,079.80 ditto 3,577.70 10,271.00

b) on slope:-

i) ratio 1:2:4 100Cft. 11,703.80 39,846.20 cu.m 4,133.80 14,073.65


ii) ratio 1:3:6 ditto 11,703.80 34,515.80 ditto 4,133.80 12,190.95
iii) ratio 1:4:8 ditto 11,703.80 30,654.20 ditto 4,133.80 10,827.05

chapter-14(Lining of canal).xls Page 100


15. SHEET PILING
Rates for all finished works include the removal of surplus debris, unused material and by products.

MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

1 Cutting Ransome and Larson piles. Per 343.20 - Per 343.20 - 29.1-
cut cut 29.3

2 Cutting universal piles. Per cut 507.95 - Per cut 507.95 - ditto

3 Driving steel piles, 25' to 30'. (7.5 to 9.0 m) 100Sft. 7,872.50 - sq.m 847.10 - ditto 1) The rate includes laying and
removing of track and also carriage
of piles to machine, average
distance of 3 chains (90 metre).

2) The rates are for the tackle


gangs only supplied by the
contractor, Mechanical staff
on-machines will be supplied by
Government.

3) T-piles and adjustable junction


piles will be counted as two piles.

4 Driving steel piles,more than 15' (4.6 m) and less than 25' 100Sft. 7,529.30 - sq.m 810.15 - ditto ditto
(7.5 m).

5 Driving steel piles, 15' (4.5 m) and under. 100Sft. 5,470.10 - sq.m 588.60 - ditto ditto

6 Dolleying piles. Each 478.35 - Each 478.35 - ditto Upto 5' (1.5 m) dolleying.

7 Drilling holes in piles by hand. Each 47.20 - Each 47.20 - ditto

8 Raising and lowering machine. Per Ft. 7,418.40 - Metre 24,332.35 - ditto

o.
9 Turning Machine, 90 Per 10,586.40 - Per 10,586.40 - 29.1 to
Job Job 29.3
o
10 Turning Machine, 135 . Per 13,332.00 - Per 13,332.00 - ditto
Job Job
o
11 Turning Machine, 180 . Per 18,115.70 - Per 18,115.70 - 29.1 to
Job Job 29.3

12 Travelling machine (light). Per 21,360.25 - 30 M. 21,360.25 - ditto


Chain

chapter-15(Sheet piling).xls Page 101


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

13 Loading and unloading piles. Ton 377.05 - Tonne 371.10 - ditto To be done by hand carts or
ramps, including cost of ropes.

14 Dismantling piling machine. Each 45,819.40 - Each 45,819.40 - ditto

15 Erecting piling machine. Each 52,868.55 - Each 52,868.55 - ditto

16 Carriage of piling machine under different conditions. per 8,626.20 - 30 M 8,626.20 - ditto
chain

chapter-15(Sheet piling).xls Page 102


16. PROTECTION & DIVERSION WORKS
1 Rates for all finished works include the removal of surplus debris, unused material and byproducts.
2 The composite rates of the items in which stone, boulders, shingle spawl are used do not contain the carriage
of the these stone materials, which will be paid separately by road, and/or rail, whichever means of transport is
adopted. The supply and carriage to site of work of all other material required in the item, is included in the
composite rates.
3 The carriage of stone or spawl will be paid on the basis of actual stack measurement (without any reduction
factor) of the stone, boulders, shingle or spawl carried.
4 Where stone, boulder or spawl is issued from stock and contractor is paid for its carriage and/or labour only;
or where such stone product is supplied, carried or handled by the contractor in which no laying is required,
the actual stack measurement (without any reduction factor) shall from the basis of payment of supply or
carriage of the stone, boulder or spawl, etc. The quantity of finished and completed item of work shall form the
basis of laying.
5 In case of the items in which the rates include carriage of stakes, bushing, Pilchi, sarkanda or farash, etc. within
one mile (1.6 Km.)

i) the cost of the carriage within one mile (one Km) shall not be deducted from the carriage charges to follow thereafter
from the point of supply.

ii) if the site of work happens to be within one mile (one Km.) of the source of supply, the materials will be collected
and measured at site of work and no extra carriage would be admissible in such cases.

iii) where the site of the work is situated at more than one mile (one Km.) distance from the source of supply, the point
of supply will be fixed carefully by the Engineer-in-charge in such a way that the carriage charges would
be arrived at, most economically. Extra carriage will be admissible from the place of supply of the
material which will be considered its starting point. The demarcation of the place of supply will be
pre-determined before calling the tenders.

MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

1 Cutting pilchi frash or sarkanda inlcuidng carriage within 100Cft. 1,936.20 cu.m 683.75
one mile.

2 Weaving matresses. 100Cft. 3,668.55 cu.m 1,295.55

3 a) Supplying and filling jute bags 1.25 (o.o35 cum) Cft., Per 57.30 88.05 Per Baq 57.30 88.05 The rate does not include supply of
capacity, with sand or earth, sewing and stacking, in Bag sand or earth for filling bags, which
dry. will be paid extra.

b) Supply and filling jute bags 1.25 (0.35 ccum) Cft. ditto 89.15 119.90 Per Baq 89.15 119.90 -ditto-
capacity, with sand or earth, sewing and laying in
position, under water.

4 a) Supplying and filling jute bags 4 to 5 cft Per 137.20 203.10 Per 137.20 203.10 The rate does not include supply of
(0.11 to 0.14 cum) capacity, with sand or earth, Bag Bag sand or earth for filling bags, which
sewing and stacking, in dry. will be paid extra.

chapter-16(Protec & Div).xls Page 103


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

b) Supply and filling new jute bags 4 to 5 cft (0.11 to ditto 195.95 261.90 ditto 195.95 261.90 -ditto-
0.14 cu.m) capacity, with sand or earth, sewing and
laying in position, under water.

5 Carriage of jute bags 1.25 Cft. (0.035 cu m) capacity, filled


with sand or earth:-

a) 1st chain (30 m) 100 Nos 509.50 % Nos 509.50

b) 2nd to 4th chain (30 m to 120 m) Per chain 183.45 Per 30 m 183.45
per 100 Per 100 Nos/
Nos

c) 5th and subsequent chains ditto 71.35 ditto 71.35


(150 m and subsequent every 30 m)

6 Carriage of new jute bags 4 to 5 Cft.(0.11 to 0.14 cu.m)


capacity, filled with sand or earth:-

a) 1st chain (Ist 30 metre) 100 Nos 2,038.10 % Nos 2,038.10

b) 2nd to 4th chain (60 m to 120 m) per chain 713.35 Per 30 m 713.35
per 100Nos per %Nos

c) 5th and subsequent chains (150 m and ditto 275.15 ditto 275.15
subsequent every 30 m)

7 Rolling matresses to river edge and floating,


after unroling:-

a) area of matress upto 2,000 Sft. 100Sft. 1,146.40 sq.m 123.35


( 186 sq.m)

b) area of matress 2,000 to 2,500 Sft. 100Sft. 1,910.70 sq.m 205.60


(186 sq.m to 232 sq.m)

c) area of matress over 2,500 Sft. ditto 2,229.15 ditto 239.85


(232 sq.m)

8 Sewing empty cement bags in sheets. 100 Nos 1,783.30 1,839.30 % Nos 1,783.30 1,839.30

chapter-16(Protec & Div).xls Page 104


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

9 Making compact round pilchi, frash or sarkanda round 100Cft. 2,483.90 2,690.30 cu.m 877.30 950.20 Measured in the shape of compact
bundles of specified size for the work. round bundles and of size specified
for the work, before filling at site.

10 Launching the above and placing in position. 100Cft. 1,222.85 cu.m 431.85

11 Supply within 5 chains (150 m):-

a) Boulders 9" (225 mm) and above 100Cft. 3,688.95 cu.m 1,302.75

b) Over size shingle 3" to 9"(75 to 225 mm) ditto 2,466.10 ditto 870.90

c) Mixed graded shingle ditto 2,924.65 ditto 1,032.85

12 Supplying Munj or Patha Trungers 6" (150 mm) mesh to hold Each 159.25 249.00 Each 159.25 249.00
3 Cft. (0.085 cu.m)

13 Providing and weaving G.I. wire netting for wire crates, with
G.I. wire of approved size (including siding and partition to
make crate):-

a) 6" (150 mm) mesh

i) 15 SWG wire 100Sft. 2,092.85 2,942.95 sq.m 225.20 316.65


ii) 10 SWG wire ditto 2,242.35 5,002.35 ditto 241.30 538.25
iii) 8 SWG wire ditto 2,242.35 6,570.05 ditto 241.30 706.95

b) 4" (100 mm) mesh

i) 15 SWG wire 100Sft. 2,690.80 3,968.70 sq.m 289.55 427.05


ii) 10 SWG wire ditto 2,989.80 7,121.50 ditto 321.70 766.30
iii) 8 SWG wire ditto 2,989.80 9,467.50 ditto 321.70 1,018.70

14 Providing and laying shingle on top of bund, including 100Cft. 1,273.80 2,329.80 cu.m 449.85 822.80
handling of materials within three chains.

15 Supply and dumping at site, without boat, including


handling of materials within three chains (90 m)

a) stone or boulder 100Cft. 2,229.15 3,153.15 cu.m 787.20 1,113.55 The rate includes supply of brick
b) shingle or spawl ditto 2,229.15 3,285.15 ditto 787.20 1,160.15 bats to site of work.
c) brick bats ditto 1,719.65 7,263.65 ditto 607.35 2,565.50

16 Supply and dumping by boat, including loading into boat The rate includes supply of brick
within three chains (90 m) lead, and hire charges of boat and bats to site of work.
boatman.

a) stone or boulder 100Cft. 3,855.70 4,779.70 cu.m 1,361.85 1,688.20


b) shingle or spawl ditto 3,855.70 4,911.70 ditto 1,361.85 1,734.80
c) brick bats ditto 3,346.20 8,890.20 ditto 1,181.90 3,140.00

chapter-16(Protec & Div).xls Page 105


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

17 Providing and filling brick bats in crates 100Cft. 3,371.95 8,915.95 cu.m 1,190.95 3,149.10 The rate includes supply of brick
(excluding cost of crates). bats to site of work.

18 Supplying and filling bricks in crates and hand packing 100Cft. 4,008.85 25,608.85 cu.m 1,415.90 9,045.05 The rate includes supply of bricks
(excluding cost of crates). to site of work.

19 Supply and filling in wire crates, including sewing crates


(excluding cost of crates):-

i) stone or boulder 100Cft. 4,518.35 5,442.35 cu.m 1,595.90 1,922.25


ii) shingle or spawl ditto 4,518.35 5,574.35 ditto 1,595.90 1,968.85

20 Extra for anchoring boat, for dumping by boats or tipping 100Cft. 448.40 - cu.m 158.35 -
crates.

21 Extra for tipping crates (in addition to anchoring boats). 100Cft. 2,241.90 - cu.m 791.85 -

22 Pilchi reventment, including carriage upto one mile 100Sft. 1,273.80 1,913.80 sq.m 137.05 205.95 30.1
(1.6 km.)

23 Surface protection with pilchi matresses, carriage upto 100Sft. 3,184.50 3,248.50 sq.m 342.65 349.55 ditto
one mile (1.6 Km).

24 Pilchi, sarkanda or frash pitching on slopes, including The cost of placing earth between
supply of pilchi, sarkanda or frash within one mile, (1.6 km) 100Sft. 8,665.05 10,182.00 sq.m 932.35 1,095.60 rolls shall be paid separately, as
also supply and driving of pegs 1½' (460 mm) long earthwork.
sharpened at one end and, tying with wire or Munj Ban
(excluding cost of placing earth between rolls).

25 Constructing Groynes upto 5' (1.5 m) height, with single 100Sft. 2,732.40 2,918.65 sq.m 294.00 314.05 Measurement to be made of the
row of wooden vertical stakes 7" to 12" (175 to 300 mm) area of elevation on one face only.
dia, 1' (300 mm) apart, average lead one mile (1.6 km.)

26 Construction Groynes upto 10' (3.0 m) height, with double 100Sft. 4,606.80 4,828.55 sq.m 495.70 519.55
row of wooden vertical stakes 7" to 12" (175 to 300 mm)
dia, 2' (600 mm) apart, average lead one mile (1.6 Km).

27 Providing and laying stone pitching/filling, dry hand 100Cft. 2,989.80 4,933.80 cu.m 1,056.00 1,742.60
packed, as filling behind retaining walls or in pitching and
aprons.

28 Providing and laying stone pitching with hammer dressed 100Cft. 7,682.40 9,410.40 cu.m 2,713.40 3,323.75
stones on surface, laid in courses.

29 Providing and laying stone pitching, for top layer only:-

a) one slope 100Cft. 6,395.40 8,123.40 cu.m 2,258.85 2,869.20


b) on level ditto 5,758.50 7,486.50 ditto 2,033.90 2,644.25

chapter-16(Protec & Div).xls Page 106


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

30 Providing and laying stone or spawl filling:-

a) on level 100Cft. 1,702.80 2,662.80 cu.m 601.45 940.50


b) on slope ditto 2,097.50 3,057.50 ditto 740.85 1,079.90

31 Providing and laying stone pitching, hand packed, with


surface levelled off to the correct section and voids filled in
1:8 cement, sand mortar, in floors of bridges along banks
and in appons etc.

i) top layer on slope 100Cft. 8,473.35 14,171.40 cu.m 2,992.80 5,005.35


ii) top layer on level ditto 7,836.45 13,534.50 ditto 2,767.85 4,780.40
iii) stone pitching/filling on slope or on level ditto 4,530.90 10,445.00 ditto 1,600.30 3,689.15
(other than top layer).

32 Grouting stone pitching or apron, etc. in:-


a) cement, sand mortar 1:3 100Sft. 2,886.00 10,791.95 sq.m 310.55 1,161.20
b) cement, sand mortar 1:8 ditto 2,452.90 6,422.95 ditto 263.95 691.10

33 Sand grouting in stone apron, with high 100Sft. 980.10 2,240.10 sq.m 105.45 241.05
pressure hose.

34 Grouting stone filling or pitching, with bajri. 100Cft. 1,592.25 3,464.25 cu.m 562.40 1,223.55

35 Removing stone and repitching hand packed, on slopes or 100Cft. 5,982.50 - cu.m 2,113.00 -
level after making good damaged slope/portion.

36 Collecting and stacking boulders from nullah beds or loose 100Cft. 2,038.10 - cu.m 719.85 -
shale, or from any other site, within 3 chains (90 m) lead.

37 Levelling and dressing stone filling under blocks and 100Cft. 1,702.80 3,574.80 cu.m 601.45 1,262.60
grouting with shingle.

38 Grouting jharies between blocks with bajri. 100Cft. 1,702.80 2,950.80 cu.m 601.45 1,042.20

39 Breaking stone into spawls and stacking 100Cft. 1,528.55 - cu.m 539.90 -

Canal and Roads


40 Fixing floating spurs, with material from canal plantation
within one mile (1.6 Km) lead:-

a) upto 2.0' (600 mm) F.S. depth Each 54.90 - Each 54.90 -

b) above 2.0' to 3.0' (600 to 900 mm) F.S. depth ditto 61.75 - ditto 61.75 -

c) above 3.0' to 4.0' F.S. (900 mm to 1200mm) depth Each 82.30 - ditto 82.30 -

chapter-16(Protec & Div).xls Page 107


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

d) above 4.0' (1200 mm) F.S. depth ditto 205.80 - ditto 205.80 -

41 Staking and bushing from canal plantation, royalty to be


paid to Forest Department or cost to private owner, if and
when required:-

a) i) Cutting and supply unsharpened pegs 3.5' (1.07 100 Nos 2,547.60 2,589.60 % Nos 2,547.60 2,589.60
m) long, 3" to 6" (75 to 150 mm) dia, within one mile
(1.6 Km) lead.

ii) Sharpening one end of 3.5' (1.07 m) long pegs, 3" 100 Nos 1,195.90 - 100 Nos 1,195.90 -
to 6" (75 to 150 mm) dia.

iii) Driving pegs 3.5' (1.07 m) long, 3" to 6" (75 to 150 100 Nos 1,921.90 - 100 Nos 1,921.90 -
mm) dia (driven 1.0' (300 mm) below the available bed
or ground (average).
iv) Tying pegs with Munj, Patha ban (one line, Per Chain 127.40 189.80 Per 30 127.40 189.80
incuding tying around the pegs). of One Metre
Row of one
row

v) Cutting and supplying brush wood from canal ditto 1,939.35 2,164.95 ditto 1,939.35 2,164.95
plantation or private owners, lead within one mile
(1.6 Km) and wattling between stakes and intertwining
(thickness of wattled brushwood 1.0' (300 mm)
average).

b) i) Cutting and supplying unsharpened pegs 4.0' 100 Nos 93.60 141.40 100 Nos 93.60 141.40
(1.20 m) long, 3" to 6" (75 to 150 mm) dia, from canal
plantation, lead within one mile (1.6 Km).

ii) Sharpening one end of 4' (1.20 M) long pegs, 3" 100 Nos 1,195.90 - 100 Nos 1,195.90 -
to 6" (75 to 150 mm) dia.

iii) Driving pegs 4' (1.20 m) long, 3" to 6" (75 to 150 100 Nos 2,116.70 - 100 Nos 2,116.70 -
mm) dia (driven 1.0' (300 mm) below the available bed
or ground (average).

iv) Tying pegs with Munj, Patha ban (one line, Per 127.40 Per 127.40
incuding tying around the pegs). Chain of 30 M of
one row one row

chapter-16(Protec & Div).xls Page 108


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

v) Cutting and supplying brush wood from canal ditto 4,900.50 ditto 4,900.50
plantation or private source, lead within one mile
(1.6 Km). and wattling between stakes and intertwining
(thickness of wattled brushwood 1.0' (300 mm)
average).

c) i) Cutting and supplying unsharpened pegs 5.0' (1.5 100 Nos 117.10 176.85 100 Nos 117.10 176.85
m) long, 3" to 6" (75 to 150 mm) dia, from canal
plantation, lead within one mile (1.6 Km).

ii) Sharpening one end of 5' (1.5 m) long pegs, 3" to 100 Nos 1,264.55 - 100 Nos 1,264.55 -
6" (75 to 150 mm) dia.

iii) Driving pegs 5' (1.5 m) long, 3" to 6" (75 to 150 100 Nos 2,391.85 - 100 Nos 2,391.85 -
mm) dia (driven 1.5' (450 mm) below the available bed
or ground (average).

iv) Tying pegs with Munj, Patha ban (one line, Per 127.40 189.80 Per 127.40 189.80
incuding tying around the pegs). Chain of 30 M
one row of one
row

v) Cutting and supplying brush wood from canal Per chain 2,574.00 2,889.60 Per 30 M 2,574.00 2,889.60
plantation or private source, lead within one mile of one row of one row
(1.6 Km) and wattling between stakes and intertwining
(thickness of wattled brushwood 1.0' (300 mm)
average).

d) i) Cutting and supplying unsharpened 100 Nos 5,095.20 5,166.95 100 Nos 5,095.20 5,166.95
pegs 6.0' (1.8 m) long, 3" to 6" (75 to
150 mm) dia, from canal plantation, lead
within one mile (1.6 Km).

ii) Sharpening one end of 6' (1.8 m) long pegs, 3" to 100 Nos 1,503.75 - 100 Nos 1,503.75 -
6" (75 to 150 mm) dia.

iii) Driving pegs 6' (1.8 m) long, 3" to 6" (75 to 150 100 Nos 2,870.20 - 100 Nos 2,870.20 -
mm) dia (driven 1.75' (530 mm) below the available
bed or ground (average).

iv) Tying pegs with Munj, Patha ban (one line, Per Per Chain
incuding tying around the pegs). Chain of 127.40 189.80 of one row 127.40 189.80
one row

v) Cutting and supplying brush wood from canal ditto 5,537.40 5,920.70 ditto 5,537.40 5,920.70
plantation or private source, lead within one mile
(1.6 Km) and wattling between stakes and intertwining
(thickness of wattled brushwood 1.0' (300 mm) average).

chapter-16(Protec & Div).xls Page 109


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

e) i) Cutting and supplying unsharpened pegs 6'-1" to 100 Nos 3,821.40 3,970.20 100 Nos 3,821.40 3,970.20
8.0' long (1.85 to 2.45 m), 4" to 8" (100 to 200 mm)
dia, from canal plantation, lead within one mile
(1.6 Km).

ii) Sharpening one end of 6'-1" to 8.0' (1.85 to 2.45m) 100 Nos 1,913.45 - 100 Nos 1,913.45 -
long pegs, 4" to 8" (100 to 200 mm) dia.

iii) Driving pegs 6'-1" to 8.0' (1.85 to 2.45 m) long, 3" 100 Nos 3,160.35 - 100 Nos 3,160.35 -
to 6" (75 to 150 mm) dia driven 2' (600 mm) below
the available bed or ground (average).

iv) Tying pegs with Munj, Patha ban (one line, Per chain 127.40 161.95 Per 30 M 127.40 161.95
incuding tying around the pegs). of one row of one row

v) Cutting and supplying brush wood from canal Per 6,395.40 6,846.30 Per 30 M 6,395.40 6,846.30
plantation or private source, lead within one mile Chain of of one row
(1.6 Km) and wattling between stakes and intertwining one row
(thickness of wattled brushwood 1.0' (300 mm)
average).

42 Staking with Bamboo from market and bushing from canal


plantation or private source (royalty of brushwood to be
paid to Forest Department or cost to private owner, if and
when required):-

a) i) Supplying Bamboos 8'-1" to 10.0' (2.46 to 3.05 m) 100 Nos 60,000.00 100 Nos 60,000.00
long, 2½" to 5" (63 m to 125 mm) dia.

ii) Sharpening one end of 8'-1" to 10.0' (2.46 to 30.5 100 Nos 1,674.30 - 100 Nos 1,674.30 -
m) long Bomboos, 2½" to 5" (63 to 125 mm) dia.

iii) Driving Bamboos 8'-1" to 10.0' (2.46 to 3.05 m) 100 Nos 3,468.15 - 100 Nos 3,468.15 -
long 2½" to 5" (63 to 125 mm) dia, driven 2.5' (750
mm) below the available bed or ground (average).

iv) Tying Bamboos 2½" to 5" (63 to 125 mm) dia with Per Per 30 M
Munj, Patha Ban, two lines, including tying around Chain of 191.05 289.00 of one 191.05 289.00
the Bamboos. one row Row

v) Cutting and supplying brushwood from canal ditto 7,890.30 8,475.90 ditto 7,890.30 8,475.90
plantation or private source, lead within one mile
(1.6 Km), and wattling between stakes and
intertwining (thickness of wattled brushwood 1.0'
(300 mm) average).

chapter-16(Protec & Div).xls Page 110


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

b) i) Supplying Bamboos 10'-1" to 12.0' (3.07 to 3.66 100 Nos - 69,000.00 100 Nos - 69,000.00
m) long, 2½" to 5" (63 to 125 mm) dia.

ii) Sharpening one end of 10'-1" to 12.0' 100 Nos 1,913.45 - 100 Nos 1,913.45 -
(3.07 to 3.66 m) long Bamboos, 2½" to
5" (63 to 125 mm) dia.

iii) Driving Bamboos 10'-1" to 12.0' (3.07 to 3.66 m) 100 Nos 3,758.30 - 100 Nos 3,758.30 -
long 2½" to 5" (63 to 125 mm) dia, driven 2.75'
(840 mm) below the available bed or ground (average).

iv) Tying Bamboos 2½" to 5" (63 to 125 mm) dia with Per chain Per 30 M
S.W.G. No. 10 wire, two lines, including tying around of one 636.90 2,556.20 of one Row 636.90 2,556.20
the Bamboos and third tie around the top end only. row

v) Cutting and supplying brushwood from canal ditto 9,593.10 10,337.10 ditto 9,593.10 10,337.10
plantation or private source, lead within one mile
(1.6 Km) and wattling between stakes and intertwining
(thickness of wattled brushwood 1.0' ( 300 mm)
average).

c) i) Supplying Bamboos 12'-1" to 14.0' (3.68 to 4.27 100 Nos - 78,000.00 100 Nos - 78,000.00
m) long, 2½" to 5" (63 to 125 mm) dia.

ii) Sharpening one end of 12'-1" to 14.0' (3.68 to 4.27 100 Nos 2,152.65 - 100 Nos 2,152.65 -
m) long Bamboos, 2½" to 5" (63 to 125 mm) dia.

iii) Driving Bamboos 12'-1" to 14.0' (3.68 to 4.27 m) 100 Nos 4,305.30 - 100 Nos 4,305.30 -
long 2½" to 5" dia, driven 3.5' (1.07 mm) below the
available bed or ground (average).

iv) Tying Bamboos 2½" to 5" (63 to 125 mm) dia with Per chain Per 30 M
S.W.G. No. 10 wire, two lines, including tying around of one row 636.90 2,556.20 of one row 636.90 2,556.20
the Bamboos and third tie around the top end only.

v) Cutting and supplying brushwood from canal ditto 11,295.90 12,152.70 ditto 11,295.90 12,152.70
plantation or private source, lead within one mile
(1.6 Km) and wattling between stakes and intertwining
(thickness of wattled brushwood 1.0' (300 mm)
average).

d) i) Supplying Bamboos 14'-1" to 16.0' (4.30 to 4.90 m) 100 Nos - 93,000.00 100 Nos - 93,000.00
long, 2½" to 5" (63 to 125 mm) dia.

ii) Sharpening one end of 14'-1" to 16.0' (4.30 to 100 Nos 2,391.85 - 100 Nos 2,391.85 -
4.90 m) long Bamboos, 2½" to 5" (63 to 125 mm) dia.
iii) Driving Bamboos 14'-1" to 16.0' long (4.30 to 4.90m) 100 Nos 4,783.70 - 100 Nos 4,783.70 -
2½" to 5" (63 to 125 mm) dia, driven 4' (1.20 m)
below the available bed or ground (average).
chapter-16(Protec & Div).xls Page 111
MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

iv) Tying Bamboos 2½" to 5" (63 to 125 mm) dia with Per Chain Per 30 M
S.W.G. No. 10 wire, two lines, including tying around of one 636.90 2,556.20 of one 636.90 2,556.20
the Bamboos and third tie around the top end only. Row Row

v) Cutting and supplying brushwood from canal ditto 13,045.55 14,037.55 ditto 13,045.55 14,037.55
plantation or private source, lead within one mile
(1.6 Km) and wattling between stakes and intertwining
(thickness of wattled brushwood 1.0' (300 mm)
average).

e) i) Supplying Bamboos 16'-1" to 20' (4.9 to 6.10 m) 100 Nos - 120,000.00 100 Nos - 120,000.00
long, 2½" to 5" (63 to 125 mm) dia.

ii) Sharpening one end of 16'-1" to 20' (4.9 to 100 Nos 2,870.20 - 100 Nos 2,870.20 -
6.10 m) long Bamboos, 2½" to 5" (63 to 125 mm) dia.

iii) Driving Bamboos 16'-1" to 20' long (4.9 to 6.10 m) 100 Nos 5,740.40 - 100 Nos 5,740.40 -
2½" to 5" (63 to 125 mm) dia, driven 4' (1.20 m)
below the available bed or ground (average).

iv) Tying Bamboos 2½" to 5" (63 to 125 mm) dia with Per Chain Per 30 M
S.W.G. No. 10 wire, two lines, including tying around of one 636.90 2,556.20 of one 636.90 2,556.20
the Bamboos and third tie around the top end only. row row

v) Cutting and supplying brushwood from canal ditto 16,417.50 17,679.90 ditto 16,417.50 17,679.90
plantation or private source, lead within one mile
(1.6 Km) and wattling between stakes and intertwining
(thickness of wattled brushwood 1.0' (300 mm)
average).

43 Cutting and supplying brushwood from canal plantation or 100Cft. 636.90 726.90 cu.m 224.95 256.75 Royalty to be paid to the Forest
from any other source, within one mile (1.6 Km). Department or cost to the private
owner, if and when required.

44 Filling brush wood only, thoroughly packed. 100Cft. 509.50 - cu.m 179.95 - Measured in compacted and
packed shape before filling.

45 Covering road 10' to 12' (3.00 to 3.65 m) wide, with 3" Per 1,222.85 - Per 1,222.85 -
(75 mm) sarkanda or jungle upto one chain lead (30 m). Chain 30 M

46 a) Gachi pitching 1' (300 mm) thick. 100Sft. 6,623.75 - Sq.m 712.70 -
b) Gachi pitching done with silt clearance 100Sft. 5,604.70 - Sq.m 603.05 -
and berm dressing.

47 Providing, mixing and placing cement sand & Bituminious joint sealent P.Rft - 15.90 P.Meter - 52.10
Ratio 1:2:3, 1/2" wide- 1" deep (10' C/C) in construction control joints.

chapter-16(Protec & Div).xls Page 112


17. OUTLETS
Rates for all finished works include the removal of surplus debris, unused material and byproducts.

MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

1 Earthwork for outlets, excavation refilling, ramming and 17.1 Includes consolidation of earth after
puddling:- to refilling.
17.5
a) channels, discharge upto 50 cusecs. Job 2,123.00 - Job 2,123.00 -

b) channels, discharge from 51 to 100 cusecs. Job 2,802.35 - Job 2,802.35 -

c) channels, discharge from 101 to 200 cusecs. Job 4,246.00 - Job 4,246.00 -

d) channels, discharge from 201 to 350 cusecs. Job 5,732.10 - Job 5,732.10 -

e) channels, discharge over 350 cusecs. Job 8,492.00 - Job 8,492.00 -

2 Dismantling outlets:- 18.1 These rates are for total


dismantlement and removal
a) old types, such as K.G.O's orifices, etc. Each 2,123.00 - Each 2,123.00 - of material. The rates do not
include earth work for which
b) A.P.M. or O.F., "H" upto 2.0 ft. (600 mm) ditto 3,184.50 - ditto 3,184.50 - rates are given in item 1,
above.
c) A.P.M. or O.F., "H" from 2.1 ft. to 3.0'. ditto 4,246.00 - ditto 4,246.00 -
(630 mm to 900 mm)

d) A.P.M. or O.F., "H" above 3.0'. ditto 5,307.50 - ditto 5,307.50 -


(900 mm)

e) Tail cluster bifurcation ditto 3,184.50 - ditto 3,184.50 -

f) Tail cluster trifurcation ditto 4,246.00 - ditto 4,246.00 -

g) Tail cluster quardification ditto 5,307.50 - ditto 5,307.50 -

3 Making temporary A.P.M. bricks block and fixing at site. Each 986.65 1,605.85 Each 986.65 1,605.85 21.1 & 21.2

4 Dismantling walls, taking out temporary Job 2,048.65 - Job 2,048.65 - 18.1, 21.1
A.P.M. brick block, fixing iron block and & 21.2
rebuilding dismantled walls.

5 Dismantling walls and fitting iron block of O.F. outlet. Each 2,048.65 - Each 2,048.65 - 18.1, 21.1
& 21.2

6 Constructing, watching and removing bund for outlet built 17.1


in running water:- to
17.2

chapter-17(Outlet).xls Page 113


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

a) upto 3.0' (0.300 m) depth Each 5,095.20 - Each 5,095.20 -


b) above 3.0' (0.300 m) depth ditto 6,878.50 - ditto 6,878.50 -

7 Adjusting "B" of tail cluster by dismantling and rebuilding Each 1,094.50 1,944.10 Each 1,094.50 1,944.10 18.1, 21.1
throat walls. & 21.2

8 Adjusting "Y" of an A.P.M. outlet, including dismantling Each 2,131.80 3,514.20 Each 2,131.80 3,514.20 ditto
and rebuilding.

9 Extra labour in fixing A.P.M. and O.F. outlet blocks, 21.1 & 21.2 Rates to be Rs. 4.00 less in case
including dressing of bricks:- of O.F. outlets, where there is no
O.F. iron block.
a) for channel depth of 5.0'. (1.5 m) Each 2,391.85 2,661.85 Each 2,391.85 2,661.85
b) for channel depth of 4.0'. (1.2 m) ditto 1,793.90 2,063.90 ditto 1,793.90 2,063.90
c) for channel depth of 3.0'. (900 mm) ditto 1,435.10 1,705.10 ditto 1,435.10 1,705.10
d) for channel depth of 2.0'. (600 mm) ditto 1,195.90 1,404.70 ditto 1,195.90 1,404.70
e) for channel depth of less than 2.0'. (600 mm) ditto 956.75 1,104.35 ditto 956.75 1,104.35

10 Repairing damaged reducing collar of Hume pipe outlets. Each 986.65 1,380.25 Each 986.65 1,380.25

11 Laying iron pipes for outlets. Per Lft. 47.85 - Metre 156.95 - 21.1, 21.2
& 17.1 to
17.5

12 Water allowance for constructing outlets or culverts, when Each 1,036.00 Each 1,036.00 At the discretion of the
canal water is not flowing. to to Engineer-in-charge depending upon
2,123.00 2,123.00 the distance and source of supply.

13 Hoisting and placing R.C. slab or stone in position on Each 780.80 - Each 780.80 -
outlets or W.C. culverts.

14 Fixing pipe outlet, including back filling of earth and 17.1 to 17.5
puddling:- & 21.1 to
21.2
a) portion under bank. Rft. 198.45 216.45 Metre 651.05 710.10
b) portion under road, beyond bank. ditto 86.55 104.55 ditto 284.00 343.10

15 Removing pipe outlet, refilling earth and puddling. 17.1


to
a) portion under bank. Rft. 169.85 - Metre 557.20 - 17.5
b) portion under road, beyond bank. ditto 63.70 - ditto 208.95 -

16 Changing pipe outlets by removing one pipe and replacing


it at the same site with another pipe complete with earth
and puddling.

a) portion under bank. Rft. 235.20 253.20 Metre 771.60 830.65


b) portion under road, beyond bank. ditto 117.60 135.60 ditto 385.80 444.85

chapter-17(Outlet).xls Page 114


18. ROAD & ROAD STRUCTURE
1 Specification No. correspond to Book of "Standard Specification for Road and Bridge Construction 2022".
2 Rates for all finished works include the removal of surplus debris, unused material and byproducts.
3 The rates include the provision and maintenance of field test laboratory, pay of laboratory staff, cost of material for testing, etc.
4 Subsequent carriage of crushed stone aggregate and bajri will be paid according to the following:
a) The carriage for the whole distance to the site of work shall be calculated on the basis of the rates of the actual means of transport used in carriage, i.e. road and / or rail, as the case may be.
b) It shall be payable from the nearest approved quarry to site of work.
MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

Sub-base & base construction

1 Providing and laying sub-base course of brick on edge 100Cft. 6,735.60 27,450.00 cu.m 2,379.00 9,695.35 5-5 The nominal thickness of bricks
4½" (113 mm) thick, including compaction to required shall be taken for the purpose of
camber and grade. measurement and payment.

2 Providing and laying sub-base course of brick aggregate, 100Cft. 6,177.00 10,002.60 cu.m 2,181.70 3,532.90 5-2 To be used only when brick
including compaction of sub-base course material to aggregate is cheaper than stone
required depth, camber, grade & density. aggregate.

3 a) Providing and laying sub-base course of stone product 5-2


of approved quality and grade, including placing, mixing,
spreading and compaction of sub-base material to
required depth, camber, grade to achieve 100%
maximum modified AASHO dry density, including
carriage of all material to site of work except gravel and.
aggregate.
i) Pit run or bed run gravel. 100Cft. 6,177.00 7,545.00 cu.m 2,181.70 2,664.90
ii) Crushed stone aggregate. 100Cft. 6,177.00 9,345.00 cu.m 2,181.70 3,300.65

(b) Subsequent carriage of gravel and crushed stone 100Cft. of 1) The carriage of the whole distance
aggregate consoli- to the site of work shall be
dated calculated on the basis of the rates
sub-base of the actual means of transport
used in carriage, i.e. road and/or rail,
as the case may be.

2) It shall be payable from the


nearest approved quarry.
3) The quantity of pit run
or bed run gravel and crushed stone
aggregate for payment of carriage shall
be taken as per actual loose volume but
not more than 120 Cft.

chapter-18(R & Road Struc).xls Page 115


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

4 a) Providing and laying base course of crushed stone 100Cft. 7,035.00 14,122.50 cu.m 2,484.75 4,988.05 5-7
aggregate of approved quality and grade, and supply and
spreading of stone screening, including placing, mixing,
spreading and compaction of base course material to
required depth, camber and grade to achieve 100%
maximum modified AASHO dry density, including
carriage of all materials to site of work except gravel and.
aggregate.

b) Subsequent carriage of crushed stone aggregate. 100Cft. of 1) The carriage for the whole
console- distance to the site of work shall be
dated calculated on the basis of the rates
base of the actual means of transport
used in carriage, i.e. road and/or
rail, as the case may be.

2) It shall be payable from the


nearest approved quarry.
3) The quantity of crushed stone
aggregate for payment of carriage shall
be taken as per actual loose volume but
not more than 122 Cft.

5 Providing and laying road edging of 3" (75 mm) wide and Per Rft. 17.15 58.65 Metre 56.30 192.35 5-10
9" (225 mm) deep brick on end, complete in all respects.

Bituminous Work & Resurfacing.


6 Providing and laying bituminous priming coat, using 10 100Sft. 254.75 2,309.00 sq.m 27.40 248.45 6-1
lbs. kerosene oil and 10 lbs. binder per 100 Sft. or 0.5 Kg
kerosene and 0.5 Kg binder per square metre.
7 Providing and laying bituminous tack coat, using 10 lbs. of 100Sft. 254.75 1,055.15 sq.m 27.40 113.55 6-2
bitumen per 100 Sft (0.49 Kg of bitumen per sq.m.)

8 a) Providing surface treatment to roads, including supply 6-3


of bitumen and bajri/crushed stone aggregate of
approved quality, including cleaning of road surface,
heating and spraying bitumen, spreading bajri and rolling
with road roller (including its operation cost, fuel and
hire charges, etc.) etc. complete including carriage of all
materials to site of work except bajjri/crushed stone
aggregate.

chapter-18(R & Road Struc).xls Page 116


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

1) 1st coat:-

i) 40 lbs. bitumen, and 5.5 Cft. bajri of nominal size 1" (25 100Sft. 208.25 4,309.10 Sq.m 22.40 463.65
mm) per 100 sq. feet or 1.96 Kg bitumen and 0.017
cu.metre bajri per square metre..

ii) 35 lbs. bitumen, and 4.0 Cft. bajri of nominal size ¾" 100Sft. 208.25 3,754.45 Sq.m 22.40 404.00
(20 mm) per %Sft. or 1.72 Kg bitumen and 0.013 cu.metre
bajri per sq.metre.

2) 2nd coat:-

i) 25 lbs. bitumen, and 2.75 Cft. bajri of nominal size ½" 100Sft. 160.20 2,687.30 Sq.m 17.25 289.15
(13 mm) per %sft or 1.23 Kg bitumen and 0.008 cu. metre bajri per
sq.metre.

ii) 18 lbs. bitumen, and 2.0 Cft. bajri of nominal size 3/8" 100Sft. 160.20 1,980.95 Sq.m 17.25 213.15
(10 mm) per %Sft. or 0.89 Kg bitumen and 0.006 cu.metre
bajri per sq. metre.

3) 3rd coat:-

14 lbs. bitumen, and 1.5 Cft. bajri of nominal size ¼" (6 100Sft. 109.60 1,522.05 sq.m 11.80 163.75
mm) per %sft or 0.69 Kg bitumen and 0.005 cubic metre
bajjri per sq.metre.

b) Subsequent carriage of crushed stone aggregate/bajri, 100Cft. cu.m 1) The carriage for the whole
distance to the site of work shall be
calculated on the basis of the rates
of the actual means of transport
used in carriage, i.e. road and/or rail,
as the case may be.
2) It shall be payable from the
nearest approved quarry.

9 a) Resurfacing of road, including supply of bitumen and 6-3


bajri/crushed stone aggregate of approved quality,
including cleaning of road surface, heating and spraying
of bitumen, and spreading bajri/crushed stone
aggregate and rolling with road roller (including its
operation cost, fuel and hire charges, etc.) complete,
including carriage of all materials to site of work.

chapter-18(R & Road Struc).xls Page 117


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

i) 22 lbs. bitumen, and 2.5 Cft. bajri of nominal size ½" 100Sft. 138.85 2,366.70 sq.m 14.95 254.65
(13 mm) per %Sft. or 1.07 Kg bitumen and bajjri 0.007 cu.m
per sq.m.

ii) 20 lbs. bitumen, and 2.0 Cft. bajri of nominal size 3/8" 100Sft. 138.85 2,147.30 sq.m 14.95 231.05
(10 mm) per % Sft. or 0.79 Kg bitumen and 0.006
cu.metre bajri per sq.metre.

b) Subsequent carriage of crushed stone aggregate/bajri. 100Cft. cu.m Same remarks as against
item 8(b) above.

10 a) Providing and laying plant premixed bituminous carpet, per inch per 25mm 6-6
including compaction and finishing to required camber, grade thickness thickness
and density. per 100Sft. per Sq.m
i) 3% Bitumen -do- 2,374.05 6,129.45 -do- 255.55 659.75
ii) 3.5% Bitumen -do- 2,374.05 6,617.55 -do- 255.55 712.30
iii) 4% Bitumen -do- 2,374.05 7,105.60 -do- 255.55 764.85
iv) 4.5% Bitumen -do- 2,374.00 7,593.70 -do- 255.55 817.40
v) 5% Bitumen -do- 2,374.05 8,081.45 -do- 255.55 869.90
vi) 5.5% Bitumen -do- 2,374.05 8,569.90 -do- 255.55 922.45
vii) 6% Bitumen -do- 2,374.05 9,057.95 -do- 255.55 975.00
b) Subsequent carriage of crushed stone aggregate/bajri. 100Cft. cu.m Same remarks as against item 8(b)
above.
11 Scarifying old road surface including removal of debris within 100Sft. 424.60 - Sq.m 45.70 -
1 chain (30 m).
12 Cold milling of asphalt layer/concrete surface of specified thickness, 6-11
loading of debris onto haul trucks via conveyor system and disposal at
appropriate place i/c the charges of self propelled milling machine of
specified size, dumper, pump, water lorry, compressor and Tungsten
Carbide Bits etc complete in all respect as approved by Engineer
Incharge.
i) 0 ~ 1" thick Per Sft 11.65 16.15 Sq.m 125.15 173.35
ii) 0 ~ 2" thick Per Sft 14.55 23.45 Sq.m 156.00 252.55
iii) 0 ~ 3" thick Per Sft 17.40 30.85 Sq.m 187.00 331.75
iv) 0 ~ 4" thick Per Sft 20.25 38.20 Sq.m 217.90 410.80
I ncidental Construction
13 Providing R.C.C. railing on bridges, as per standard drawing. Per Rft. 241.30 2,042.40 Metre 791.70 6,700.75 9-14 The rate includes cost of steel, its
fabrication, laying in position and
fastening, including cost of binding
wire and removal of rust from the
bars, etc.

chapter-18(R & Road Struc).xls Page 118


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

14 Providing and fixing G.I. pipe railing, as per Per Rft. of 192.90 1,830.50 Metre 632.85 6,005.65 9-14
standard drawing. 3 rows of
Pipes

15 Providing and fixing steel bearings of standard quality and Each Set - 2,520.00 Each set - 2,520.00 8-12
type at site of work. of one of one
end end

16 Providing and fixing rubber bearing pad at site Per - 28.80 cu.cm - 1.75 8-12
of work. Cu. Inch

17 Providing and laying expansion joint of neoprine strip 4"x¼" Per Rft. 171.60 400.30 Metre 563.00 1,313.35 8-13
(100 mmx 6 mm) and plastic bitumen.

18 Providing and fixing rain water outlet of A.C. pipe. Each 85.80 442.25 Each 85.80 442.25

19 Providing and erection at site of work:- The rate is for complete item of
work according to Standard design
i) R.C.C. mile/Km. stone Each 4,450.70 10,048.60 Each 4,450.70 10,048.60 including cement concrete
ii) R.C.C. furlong/½ Km. stone Each 211.15 774.75 Each 211.15 774.75 foundation block and painting
iii) R.C.C. boundary pillar. Each 334.20 1,027.05 Each 334.20 1,027.05 letters etc.
iv) Sign post of M.S. plate 1/8" thick (3 mm)
a) Mandatory. Each 1,455.75 11,756.30 Each 1,455.75 11,756.30
b) Warning/Direction/Informatory. Each 1,407.95 10,983.50 Each 1,407.95 10,983.50

20 Providing and laying dry brick pavement/soling in streets or 100Cft. 5,820.60 26,535.00 cu.m 2,055.85 9,372.15 5-5 The nominal thickness of bricks
roads, etc. sand grounted, laid in proper camber, including ( 9" x 4-3/8"x 2-11/16") shall be taken
preparation, watering, compaction of bed to proper camber, for the purpose of measurement
and sand cushion. and payment.

21 Providing and fixing metalic expansion Joints of 3/4" thick Aluminium


Alloy strip of specified width duly bolted with check nuts @ 9" c/c with
the MS lugs for specified movements as mentioned by the designer i/c the
cost of polystrene joint fill but excluding the cost of Lugs complete in all
respect as approved and directed by the Engineer Incharge.

a) Flat plate Type


i) 25 mm to 50 mm Per Rft 299.20 8,759.20 Meter 981.40 28,730.20
ii) 40 mm to 80 mm Per Rft 299.20 9,899.20 Meter 981.40 32,469.40
iii) 50 mm to 100 mm Per Rft 299.20 11,099.20 Meter 981.40 36,405.40
b) Saw-tooth Type
i) 25 mm to 50 mm Per Rft 299.20 10,019.20 Meter 981.40 32,863.00
ii) 40 mm to 80 mm Per Rft 299.20 11,339.20 Meter 981.40 37,192.60
iii) 50 mm to 100 mm Per Rft 299.20 12,899.20 Meter 981.40 42,309.40

chapter-18(R & Road Struc).xls Page 119


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

c) Finger /Comb Plate Type


i) 25 mm to 50 mm Per Rft 299.20 11,279.20 Meter 981.40 36,995.80
ii) 40 mm to 80 mm Per Rft 299.20 12,599.20 Meter 981.40 41,325.40
iii) 50 mm to 100 mm Per Rft 299.20 14,039.20 Meter 981.40 46,048.60
22 Providing and laying Elastomeric Neoprene Bearing Pads of specified
grade,Specific gravity, hardness, elongation, min tensile strength of 2250
psi, and compressive strength of 2000 psi conforming to ASTM D2240 8-12
standard test method for rubber as approved and directed by the Engineer
Incharge.
I- Grade 50
(a) Plain
(i) Without Anchrage Cu. Inch - 48.00 Cu.cm - 2.95
(ii) With Anchrage Cu. Inch - 50.40 Cu.cm - 3.10
(b) Laminated
(i) Without Anchrage Cu. Inch - 49.20 Cu.cm - 3.00
(ii) With Anchrage Cu. Inch - 51.60 Cu.cm - 3.15
II- Grade 60
(a) Plain
(i) Without Anchrage Cu. Inch - 50.40 Cu.cm - 3.10
(ii) With Anchrage Cu. Inch - 54.00 Cu.cm - 3.30
(b) Laminated
(i) Without Anchrage Cu. Inch - 51.60 Cu.cm - 3.15
(ii) With Anchrage Cu. Inch - 55.20 Cu.cm - 3.35
III- Grade 70
(a) Plain
(i) Without Anchrage Cu. Inch - 52.80 Cu.cm - 3.20
(ii) With Anchrage Cu. Inch - 55.20 Cu.cm - 3.35
(b) Laminated
(i) Without Anchrage Cu. Inch - 54.00 Cu.cm - 3.30
(ii) With Anchrage Cu. Inch - 57.60 Cu.cm - 3.50

23 Providing and fixing M.S Grating comprising of Angle Iron frame size P.Sft 334.90 1,676.60 Sq.m 3,603.50 18,040.05
1.50" x 1.50" x 3/16" and 1/2" square bars duly welded @ 4" c/c,
including painting charges etc complete in all respect.
24 Providing and laying good quality / local sand cushion from approved P.Cft 0.50 29.00 Cu.m 16.85 1,023.45
source (compacted in layers not exceeding 6" thickness) by mechanized
means including the cost of front end loader, viberatory roller and all lead
and lifts,dressing,watering complete in all respect as approved and
directed by the Engineer Incharge.

ROAD SAFETY
25 Providing, fabrication and fixing pole mounted Direction Board / road
If 3 mm thick Aluminium sheet is
delineator of any shape and size, with specified Sheet and thickness,
9-16 used,increase composite rate by Rs
supported with G.I Channel, (excluding the cost of vertical post and
627/- Psft or Rs 6747/- Per Sq.Mtr
painting) etc complete in all respect.

chapter-18(R & Road Struc).xls Page 120


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

(a) G.I Sheet 14 SWG


i) CI RCULAR/TRI ANGULAR
3 ft size P.Sft 89.30 950.25 Sq.m 961.00 10,228.25
ii) RECTANGULAR SHAPE
(i) 12 -48 sft P.Sft 112.10 856.65 Sq.m 1,206.85 9,221.00
(ii) 54 -120 sft P.Sft 67.35 780.50 Sq.m 725.10 8,401.15
26 Providing and fixing pole mounted reflecting mirror (Convex type) of 36
inch diameter of specified material, excluding the cost of vertical post,
which will be paid extra etc complete in all respect.
(a) Acrylic made Each 63.70 19,863.70 Each 63.70 19,863.70
(b) Stainless Steel Each 63.70 16,263.70 Each 63.70 16,263.70
27 Providing, fabrication and fixing Vertical Post comprising of medium
quality G.I Pipe of specified diameter, including the cost of clamping
arrangements, top cover, hold fasts embeded in PCC 1:2:4 etc complete 9-16
in all respect.
(a) 2 inch diameter P.Rft 66.30 888.85 Meter 217.45 2,915.45
(b) 3 inch diameter P.Rft 66.30 1,260.85 Meter 217.45 4,135.60
(c) 4 inch diameter P.Rft 66.30 1,691.45 Meter 217.45 5,547.95
(d) 5 inch diameter P.Rft 66.30 2,213.75 Meter 217.45 7,261.15
(e ) 6 inch diameter P.Rft 66.30 2,549.55 Meter 217.45 8,362.55
28 Providing & fixing Cat Eyes of size 4" x 4" x 3/4" duly casted with
specified material having plastic strip containing mini retro-reflective
glass beads of color white/red/yellow having specifid reflections , quality if L-Key steel bolt is used, increase
& shape i/c the cost of self built in 12 mm diax120 mm long steel zinc Composite rate by Rs 25/- each
plated nail,fixing to road with epoxy/ hammering with separate nail
complete.
a) Acrylic material
(1) Dual-Directional
(i) 19x2=38 Glass beads a side Each 25.50 387.90 Each 25.50 387.90
(ii) 31x2=62 Glass beads a side Each 25.50 453.90 Each 25.50 453.90
(iii) Micro Cube Corner Spark glow reflectors Each 25.50 435.90 Each 25.50 435.90
(2) Uni-Directional
(i) 31 Glass beads a side Each 25.50 333.90 Each 25.50 333.90
(ii) 43 Glass beads a side Each 25.50 393.90 Each 25.50 393.90
b) Aluminium Alloy
(1) Dual-Directional
(i) 31x2=42 Glass beads a side Each 25.50 543.90 Each 25.50 543.90
(ii) 43x2=86 Glass beads a side Each 25.50 693.90 Each 25.50 693.90
(iii) Micro Cube Corner Spark glow reflectors Each 25.50 723.90 Each 25.50 723.90
(2) Uni-Directional
(i) 31 Glass beads a side Each 25.50 513.90 Each 25.50 513.90
(ii) 43 Glass beads a side Each 25.50 543.90 Each 25.50 543.90

chapter-18(R & Road Struc).xls Page 121


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

29 Providing & fixing Road Studs of aluminium alloy (raised profile) of


specified size with Diamond grade reflectors on both sides etc complete.

a) Uni-Directional
(i) 8" x 4" x 2" Each 25.50 813.90 Each 25.50 813.90
(ii) 6" x 4" x 1.75" Each 25.50 663.90 Each 25.50 663.90
b) Dual-Directional
(i) 8" x 4" x 2" Each 25.50 927.90 Each 25.50 927.90
(ii) 6" x 4" x 1.75" Each 25.50 783.90 Each 25.50 783.90
30 Providing and Fixing L-type Barrier delineator of specified material of
Size 150 x 100mm i/c the cost of hardware, reflective tape etc complete
in all respect.
(a) Acrylic made Each 63.70 508.10 Each 63.70 508.10
(b) Alluminium (3mm thick) Each 63.70 628.10 Each 63.70 628.10
31 Providing and fixing 3" dia G.I Pipe Delineator 3' long with HIP Each 110.35 4,979.70 Each 110.35 4,979.70
reflective tape (Red & White), duly embedded in P.C.C (1:2:4) etc
complete in all respect.
32 Providing of Portable Cautionary Plastic Barriers 6.50' Long & 2.50' Each - 14,160.00 Each - 14,160.00
high of approved shape & design etc complete in all respect.
33 Providing of Cautionary Portable Traffic safety Cones made of Plastic
polymer of approved shape, colour, size & design having wide
squar/hexagonal base provided with reflective sleeve having arrangement
for plastic chain etc complete in all respect.
a) 18" high, Bottom dia 13" & Top dia 2-1/2" Each - 600.00 Each - 600.00
b) 28" high, Bottom dia 13-3/4" & Top dia 2-1/2" Each - 720.00 Each - 720.00
c) 36" high, Bottom dia 15" & Top dia 2-1/2" Each - 960.00 Each - 960.00
34 Providing and fixing PLASTIC BODY Reflective cautionary flexible
spring post of specified height with reflective strips at the top for fixing
to road with bolts etc complete in all respect.
i) 300 mm high Each 63.70 663.70 Each 63.70 663.70
ii) 600 mm high Each 63.70 693.70 Each 63.70 693.70
iii) 700 mm high Each 63.70 783.70 Each 63.70 783.70
iv) 750 mm high Each 63.70 903.70 Each 63.70 903.70
35 Providing & Fixing W-Beam Guard Rail made of 1/8" thick galvanized
sheet, fixed on vertical posts of galvanized channel of (13.40 Kg P.Meter)
@ 6.25 ft c/c duly embeded in P.C.C (1:2:4) of specified depth i/c the
cost of hardwares, Reflectors,boxing glove end, fish tail end and double
face reflectors etc complete in all respect.
i) Single Face P.Rft 1,198.95 4,525.30 Meter 3,932.55 14,843.00
ii) Double Face P.Rft 1,548.20 5,895.35 Meter 5,078.05 19,336.80

chapter-18(R & Road Struc).xls Page 122


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

36 Providing and fixing Uni/Dual/Tri directional reflective extreme end Each 63.70 963.70 Each 63.70 963.70
road berm Vertical indicator made of plastic body of size 100x75x110
mm having ultra -violet resistant colors (white/yellow/red) with high
intensity reflectors provided with additional 31 mini-glass reflectors to a
side imbeded in plastic strip base duly fixed with a steel rectangular tube
i/c the cost of hardware as approved and dirrected by the Engineer
Incharge.
37 Providing and fixing Uni/Dual directional reflective extreme end road Each 63.70 543.70 Each 63.70 543.70
berm indicator made of plastic body of size 80x50x16 mm having ultra -
violet resistant colors (white/yellow/red) with high intensity reflectors
duly fixed on road egde Kerb with a hardened steel nail as approved and
dirrected by the Engineer Incharge.

ROAD FURNITURE
37 Providing and fixing Cantilever Gantry of specified portal made of 3 mm i) For GI sheet fascia on both sides,
thick GI sheet (Z-275) of size 4000x2400x3mm supported with a frame increase labor rate by Rs 3.25 Psft or
of MS angle iron frame of size 40x40x5mm all around the sheet with 3 no 35.00 Sq.Mtr and composite rate by Rs
vertical and one no horizontal braces of MS tees of size 40x40x5 mm 156.00 Psft or 1680.00 P.Sq.Mtr.
duly supported on a truss of 2 no chords of MS pipes 273x7 mmx9.27 ii) Area of Portal will be taken for
mtr and 3 no struts of MS pipe of size 143x4.5mmx3.098 mtr duly payment.
9-16
bolted with a post of MS pipe of size 7500x457.5x 12.7 mm thick duly iii) If 3 mm thick Aluminium sheet is
welded with Base plate of 850x850x36 mm with MS stiffners of 18 mm used,increase composite rate by Rs
thick MS sheet and fixed with anchor bolts in prelaid RCC footing i/c the 627/- Psft or Rs 6747/- Per Sq.Mtr.
cost of polyurethene Paint to MS skeleton but excluding the cost of iv) For Digital Display Reduce rate by
lettering/printing as approved and directed by the Engineer Incharge. Rs 465/-Psft and Rs 5000/-
P.Sq.Mtr.
i) Single Portal P.Sft 122.20 9,258.15 P.Sqm 1,314.90 99,617.85
ii) Double Portal P.Sft 75.35 6,824.40 P.Sqm 810.80 73,430.40
38 Providing and fixing Full width Gantry comprising of 3 mm thick GI i) For GI sheet fascia on both sides,
sheet (Z-275) fixed over double front and back truss made with Top & increase labor rate by Rs 3.25 Psft or
bottom chords of MS angle iron L-100x100x10 mm, webs and struts of L- 35.00 Sq.Mtr and composite rate by Rs
65x65x8 mm welded with top and bottom truss of webs and struts of 156.00 Psft or 1680.00 P.Sq.Mtr. ii)
65x65x8 mm duly supported on specified vertical posts of double Area of Portal will be taken for
9-16
columns of MS pipe of size 7500x219x8 mm thick duly welded with payment.
Base plate of 600x400x50 mm with MS stiffners of 350x150x15 mm iii) If 3 mm thick Aluminium sheet is
thick MS sheet for each column fixed in prelaid RCC footing i/c the cost used,increase composite rate by Rs
of polyurethene Paint to MS skeleton but excluding the cost of 627/- Psft or Rs 6747/- Per Sq.Mtr.
lettering/printing as approved and directed by the Engineer Incharge.
a) Two Supports
i. Two Lane P.Sft 43.45 4,161.80 P.Sqm 467.50 44,780.85
ii. Three Lane P.Sft 36.15 3,719.25 P.Sqm 389.05 40,018.95
b) Three Supports
i. Three Lane each P.Sft 26.10 3,491.80 P.Sqm 280.60 37,571.80

chapter-18(R & Road Struc).xls Page 123


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

39 Providing and fixing Full width Gantry comprising of 3 mm thick GI i) For GI sheet fascia on both sides,
sheet (Z-275) fixed over MS double front and back truss made with Top increase labor rate by Rs 3.25 Psft or
& bottom chords of L-100x100x10 mm, webs and struts of L-65x65x8 35.00 Sq.Mtr and composite rate by Rs
mm welded with top and bottom truss of webs and struts of 65x65x8 mm 156.00 Psft or 1680.00 P.Sq.Mtr.
duly supported on specified vertical posts of double columns MS pipe of ii) Area of Portal will be taken for
size 7500x457x12.5 mm thick duly welded with Base plate of 9-16 payment.
600x400x50 mm with MS stiffners of 350x150x15 mm thick MS sheet iii)If 3 mm thick Aluminium sheet is
for each column fixed in prelaid RCC footing i/c the cost of polyurethene used,increase composite rate by Rs
Paint to MS skeleton but excluding the cost of lettering/printing as 627/- Psft or Rs 6747/- Per Sq.Mtr.
approved and directed by the Engineer Incharge.
a) Two Supports
i. Four Lane P.Sft 33.25 3,312.45 P.Sqm 357.90 35,642.10
ii. Five Lane P.Sft 31.20 3,042.15 P.Sqm 335.65 32,733.50
b) Three Supports
i) Four Lane Each P.Sft 23.30 3,129.50 P.Sqm 250.55 33,673.60

chapter-18(R & Road Struc).xls Page 124


19. PLUMBING, SANITARY INSTALLATION & GAS FITTINGS
1 Rates for all finished works include the removal of surplus debris, unused material & by products.
2 The material used shall conform to Schedule of Rates, Vol. I, Part I, (Specifications for Materials of
Construction, 1964, and the work will be executed according to Buildings & Roads Department Specifications,
Vol II, 1966 (Public Health Works).
3 The rates include cutting and making good of the surface of walls, roof, floor, etc. where necessary.

MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

1 Providing and fitting glazed earthen ware water closet


European type, excluding seat and cover:-

i) white Each 858.00 8,238.05 Each 858.00 8,238.05


iii) coloured Each 858.00 9,198.05 Each 858.00 9,198.05

2 Providing and fixing, double seat and cover only.

i) bakelite Each 8.95 908.95 Each 8.95 908.95


ii) plastic Each 8.95 428.95 Each 8.95 428.95
3 Providing and fitting one piece Europeon Coupled set of Water Closet Each 1,494.90 20,022.90 Each 1,494.90 20,022.90
(WC) and flushing Cistern of PORTA brand (full size) i/c the cost of
CP/rubber connection, thimble, normal seat cover and rawal bolts complete
in all respects as approved and directed by the Engineer Incharge.

4 Providing and fitting glazed earthen ware water closet,


squatter type (Orisa pattern), combined with foot rest.

i) white Each 588.25 2,235.35 Each 588.25 2,235.35


ii) coloured Each 588.25 2,475.35 Each 588.25 2,475.35

5 Providing and fitting white glazed earthen ware water closet, Each 588.25 4,740.25 Each 588.25 4,740.25
squartter type, with separate foot rest.

6 Providing and fitting water closet, squatter type of terrazzo Each 588.25 1,071.35 Each 588.25 1,071.35
concrete.

7 Providing and fitting glazed earthen ware wash hand basin /vanity
56x40 cm (22"x16") including bracket set, waste pipe and
waste coupling, etc.
i) white, with pedestal Each 747.45 5,187.45 Each 747.45 5,187.45
ii) coloured, with pedestal Each 747.45 4,347.45 Each 747.45 4,347.45
iii) white, without pedestal Each 667.85 5,467.85 Each 667.85 5,467.85
iv) coloured, without pedestal Each 667.85 3,067.85 Each 667.85 3,067.85

chapter-19(PSI & GF).xls Page 125


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

v) Under Counter Vanity Basin Each 747.45 7,347.45 Each 747.45 7,347.45
8 Providing and fixing stainless steel sink with drain board, size Each 667.85 6,422.50 Each 667.85 6,422.50
120x60 cm (48"x24") including bracket set, waste pipe and
waste coupling.

9 Providing and fitting terrazzo concrete sink 60x45 cm (24"x18") Each 667.85 2,376.90 Each 667.85 2,376.90
with drain board of mosaic, including bracket set, waste pipe
and waste coupling.

10 Providing and fixing glazed earthen ware sink, including


bracket set, waste pipe and waste coupling:-

i) 60x45 cm (24"x18") Each 667.85 3,196.35 Each 667.85 3,196.35


ii) 37.5x45 cm (15"x18") Each 667.85 3,076.35 Each 667.85 3,076.35

11 Providing and fixing glazed earthen ware flat back urinal. Each 429.00 1,339.70 Each 429.00 1,339.70

12 Providing and fitting glazed earthen ware low down flushing


cistern 13.63 litres (3 gallons) capacity, including bracket
set, copper connection, etc.

i) white Each 667.85 4,046.60 Each 667.85 4,046.60


ii) coloured Each 667.85 4,646.60 Each 667.85 4,646.60

13 Providing and fitting plastic made low down flushing cistern


13.63 litre (3 gallons) capacity, including bracket set, copper
connection, etc. complete.

i) white Each 667.85 2,666.60 Each 667.85 2,666.60 If rubber connection is used, the
ii) coloured Each 667.85 2,666.60 Each 667.85 2,666.60 composite rate will be reduced by
Rs. 12.50

14 Providing and fixing white enameled cast iron low down flushing Each 667.85 2,758.95 Each 667.85 2,758.95
cistern 13.63 litres (3 gallons) capacity, including bracket
set, copper connection, etc.

15 Providing and fixing cast iron high level flushing cistern


including cost of bracket set, copper connection, etc.

i) 13.63 litres (3 gallons) capacity Each 710.75 6,281.85 Each 710.75 6,281.85
ii) 4.55 litres (1 gallon) capacity Each 710.75 2,681.85 Each 710.75 2,681.85

16 Providing and fixing, chromium plated soap dish. Each 42.90 280.40 Each 42.90 280.40

17 Providing and fitting, glazed earthen ware soap dish.

chapter-19(PSI & GF).xls Page 126


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

i) white Each 42.90 712.40 Each 42.90 712.40


ii) coloured Each 42.90 352.40 Each 42.90 352.40

18 Providing and fixing, chromium plated toilet paper holder. Each 57.20 529.25 Each 57.20 529.25

19 Providing and fixing, chromium plated towel rail:-

i) 60 cm (24") long, and 2 cm (¾") dia. Each 57.20 551.50 Each 57.20 551.50
ii) 50 cm (20") long, and 1.5 cm (½") dia. Each 57.20 431.50 Each 57.20 431.50

20 Providing and fixing looking glass 55x40 cm (22"x16") size, Each 107.25 642.30 Each 107.25 642.30
and 5 mm thick, first quality.

21 Providing and fixing glass shelf 60x13 cm (24"x5"), with


5mm thick glass:-

i) with chromium plated brackets and railing. Each 134.05 918.15 Each 134.05 918.15
ii) glass shelf only, without chromium plated brackets Each 85.80 445.80 Each 85.80 445.80
and railing.

22 Providing and fitting glazed earthen ware shelf 60x13 cm


(24"x5"), with chromium plated bracket and railing:-

i) white Each 134.05 1,362.15 Each 134.05 1,362.15


ii) coloured Each 134.05 1,482.15 Each 134.05 1,482.15

23 Providing and fixing Bathroom Accessories (7-piece set) Master brand -


One Cosmetic Shelf, One Towel rod with bracket, One soap dish, One
double hook, One towel ring, brush holder, toilet paper holder & looking
glass i/c the cost of hardwares etc complete in all respect as approved and
directed by the Engineer incharge.
i) Plastic soap dish Each 120.00 1,200.00 Each 120.00 1,200.00
ii) Plastic toilet paper holder Each 120.00 900.00 Each 120.00 900.00
iii) Plastic tower rail Each 120.00 1,400.00 Each 120.00 1,400.00
iv) Plastic shelf 60x13 cm (24:x5") with bracket and railing Each 120.00 900.00 Each 120.00 900.00
v) Plastic Brush holder Each 120.00 900.00 Each 120.00 900.00
vi) Looking glass with plastic frame Each 120.00 1,700.00 Each 120.00 1,700.00
vii) Towel ring Each 120.00 600.00 Each 120.00 600.00
24 Providing and fixing chromium plated pillar-cock, heavy:-

i) 2 cm (¾") Each 57.20 1,737.20 Each 57.20 1,737.20


ii) 1.5 cm (½") Each 57.20 1,497.20 Each 57.20 1,497.20

chapter-19(PSI & GF).xls Page 127


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

25 Providing and fixing chromium plated stop cock, heavy:-


i) 2 cm (¾") Each 57.20 897.20 Each 57.20 897.20
ii) 1.5 cm (½") Each 57.20 777.20 Each 57.20 777.20

26 Providing and fixing underground stop cock 13 mm (½"), Each 82.10 848.10 Each 82.10 848.10
with chromium plated cover.

27 Providing and fixing chromium plated bib cock:-


i) 2 cm (¾") Each 57.20 1,017.20 Each 57.20 1,017.20
ii) 1.5 cm (½") Each 57.20 777.20 Each 57.20 777.20

28 Providing and fixing chromium plated tee stop cock Each 57.20 957.20 Each 57.20 957.20
15mm (½").

29 Providing and fixing chromium plated shower rose:-

i) 1.5x10 cm (½"x4") Each 57.20 627.20 Each 57.20 627.20


ii) 2x15 cm (¾"x6") Each 57.20 1,197.20 Each 57.20 1,197.20

30 Providing and fixing, chromium plated mixing valve, for wash Each 71.50 2,231.50 Each 71.50 2,231.50
hand basin, sink or shower.

31 Providing and fixing gun metal peet/gate valve (screwed):- For brass peet/gate valve (screwed),
the composite rates of items (i) to (v)
i) 30 mm (1¼") dia Each 85.80 4,765.80 Each 85.80 4,765.80 will be reduced by Rs. 66, 77, 95, 107
ii) 40 mm(1½") dia Each 85.80 6,025.80 Each 85.80 6,025.80 and 120 respectively.
iii) 50 mm(2") dia Each 85.80 8,365.80 Each 85.80 8,365.80
iv) 65 mm(2½") dia Each 85.80 15,085.80 Each 85.80 15,085.80
v) 80 mm(3") dia Each 85.80 22,885.80 Each 85.80 22,885.80

32 Providing and fitting, chromium plated or brass oxidised,


swan neck cock 15 mm (½") dia.

i) single way Each 57.20 513.20 Each 57.20 513.20


ii) two way Each 85.80 805.80 Each 85.80 805.80
iii) three way Each 114.40 954.40 Each 114.40 954.40

33 Providing and fixing, union brass cock.

i) 13 mm (½") dia Each 57.20 393.20 Each 57.20 393.20


ii) 20 mm (¾") dia Each 57.20 453.20 Each 57.20 453.20

chapter-19(PSI & GF).xls Page 128


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

34 Providing and fixing, floor trap of cast iron, including concrete


chamber all round, and C.I. grating:-

i) 10x5 cm (4"x2") Each 171.60 634.55 Each 171.60 634.55


ii) 10x7.5 cm (4"x3") Each 171.60 610.55 Each 171.60 610.55

35 Providing and fitting "P" trap:-

i) 10 cm (4") of cast iron. Each 143.00 708.65 Each 143.00 708.65


ii) 10 cm (4") glazed. Each 143.00 288.65 Each 143.00 288.65

36 Providing and fitting 10 cm (4") gully trap, including cement Each 214.50 1,141.10 Each 214.50 1,141.10
concrete, cost of PVC grating 15x15 cm (6"x6") and
masonry chamber 30x30 cm (12"x12").

37 Providing and fitting, cast iron soil pipe with:-

a) lead caulked, yarn joint:-

i) 10 cm (4") i/d Per foot 65.00 330.40 Metre 213.20 1,083.65


ii) 5 cm (2") i/d Per foot 26.00 148.35 Metre 85.25 486.55

b) cement caulked joint:-

i) 10 cm (4") i/d Per foot 15.50 205.30 Metre 50.85 673.35


ii) 5 cm (2") i/d Per foot 6.20 119.40 Metre 20.35 391.60

38 Providing and fitting, A.C. soil pipe with cement caulked


joint, including all specials:-

i) 60 (2¼)" mm i/d Per foot 12.40 73.30 Metre 40.70 240.45


ii) 80 (3") mm i/d Per foot 13.80 118.95 Metre 45.20 390.20
iii) 100 (4") mm i/d Per foot 15.50 160.65 Metre 50.85 527.00
iv) 150 (6") mm i/d Per foot 20.70 208.60 Metre 67.80 684.30

39 Providing and fitting cast iron specials, such as tee bend, In case of plug type, the composite
collar, cross, etc. plain type:- rate shall be increased by Rs.2 per kg.

i) lead caulked joint Kg 54.10 317.65 Kg 54.10 317.65


ii) cement caulked joint Kg 33.20 249.35 Kg 33.20 249.35

40 Supply and fitting of cast iron manhole cover


with frame, etc. complete.

i) 30 cm (12") dia Each 85.80 745.80 Each 85.80 745.80


ii) 45 cm (18") dia Each 85.80 1,345.80 Each 85.80 1,345.80
chapter-19(PSI & GF).xls Page 129
MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

iii) 60 cm (24") dia Each 135.65 2,055.65 Each 135.65 2,055.65


41 Providing and fitting R.C.C. pipe 10 cm (4") dia, including Per foot 32.50 154.90 Metre 106.60 508.05
laying and jointing in trenches.

42 Providing and fitting chromium plated or oxidised, gas cock


6'mm (¼"):-

i) single way Each 57.20 321.20 Each 57.20 321.20


ii) two way Each 85.80 481.80 Each 85.80 481.80
iii) three way Each 114.40 630.40 Each 114.40 630.40

43 Providing and fitting nipple or bush, 6 mm to Each 42.90 106.60 Each 42.90 106.60
10 mm (¼" to 3/8") i/d.

44 Providing and fixing, brass gas cock:-

a) 15 mm (½") dia Each 8.95 368.95 Each 8.95 368.95


b) 20 mm (¾") dia Each 325.00 428.95 Each 325.00 428.95

45 Providing and fixing brass stop cock/bib cock:-

a) 15 mm (½") dia Each 14.30 554.30 Each 14.30 554.30


b) 20 mm (¾") dia Each 14.30 614.30 Each 14.30 614.30

46 Hoisting and placing in position, precast R.C. latrine seats. Each 858.00 - Each 858.00 -

47 Providing, fixing, testing and commissioning of µ-PVC (Unplasticized


Polyvinyl Chloride ) Nikasi/ waste pipe make of Dadex /Popular/Beta or
equivalent, plain /socket ended conforming to code EN-1329 of specified
SDR (Standard Dimension Ratio) including the cost of specials and
Solvents complete in all respect as approved and directed by the Engineer
Incharge.
a) Type (SDR 41/SN-4)
(i)1-1/4"(40 mm) Per Rft 7.50 72.85 Meter 24.50 238.90
(ii)1-1/2"(50 mm ) Per Rft 7.50 81.60 Meter 24.50 267.60
(iii)2"(60 mm) Per Rft 7.50 88.65 Meter 24.50 290.75
(iv)3"(85 mm ) Per Rft 7.50 129.35 Meter 24.50 424.25
(v)4"(110 mm) Per Rft 7.50 217.40 Meter 24.50 713.10
(vi)6"(160 mm) Per Rft 7.50 420.85 Meter 24.50 1,380.35
(vii)8"(200 mm) Per Rft 7.50 451.30 Meter 24.50 1,480.30
b) Type (SDR 32.5/SN-8)
(i)1-1/4"(40 mm) Per Rft 7.50 72.65 Meter 24.50 238.35
(ii)1-1/2"(50 mm ) Per Rft 7.50 82.90 Meter 24.50 271.85
(iii)2"(60 mm) Per Rft 7.50 89.00 Meter 24.50 291.95
(iv)3"(85 mm ) Per Rft 7.50 163.85 Meter 24.50 537.45
(v)4"(110 mm) Per Rft 7.50 260.70 Meter 24.50 855.15
chapter-19(PSI & GF).xls Page 130
MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

(vi)6"(160 mm) Per Rft 7.50 381.65 Meter 24.50 1,251.80


(vii)8"(200 mm) Per Rft 7.50 462.55 Meter 24.50 1,517.25
48 Providing, fixing, testing and commissioning of µ-PVC (Unplasticized
Polyvinyl Chloride ) sewerage pipe make of Dadex /Popular/Beta or
equivalent, plain /socket ended conforming to code EN-1401 of specified
SDR (Standard Dimension Ratio) including the cost of specials and
Solvents complete in all respect as approved and directed by the Engineer
Incharge.
a) Type (SDR 34/SN-8)
i) 6" dia 150mm Per Rft 7.50 1,143.75 Meter 24.50 3,751.45
ii) 8" dia 200 mm Per Rft 8.95 1,722.85 Meter 29.40 5,650.95
iii) 10"dia 250 mm Per Rft 10.45 2,667.35 Meter 34.30 8,748.95
iv) 12" dia 300 mm Per Rft 11.95 4,201.10 Meter 39.25 13,779.65
v) 14" dia 350 mm Per Rft 13.45 5,326.20 Meter 44.15 17,469.90
vi) 16" dia 400 mm Per Rft 14.95 6,870.50 Meter 49.05 22,535.25
49 Providing, fixing, testing and commissioning of µ-PVC (Unplasticized
polyvinyl Chloride ) Nikasi/ waste pipe Fittings make of Dadex
/Popular/Beta or equivalent, conforming to code EN-1329 including the
cost of Solvents complete in all respect as approved and directed by the
Engineer Incharge.
a) P-Trap
(i) 4" dia Each 85.80 1,075.80 Each 85.80 1,075.80
(ii) 3" dia Each 85.80 805.80 Each 85.80 805.80
b) M ulti-Trap
(i) 4" dia Each 85.80 1,033.80 Each 85.80 1,033.80
(ii) 3" dia Each 85.80 745.80 Each 85.80 745.80
c) Vent Cowel
(i) 4" dia Each 85.80 265.80 Each 85.80 265.80
(ii) 3" dia Each 85.80 223.80 Each 85.80 223.80
(iii) 2" dia Each 85.80 193.80 Each 85.80 193.80
d) Clean Out
(i) 4" dia Each 85.80 595.80 Each 85.80 595.80
(ii) 3" dia Each 85.80 475.80 Each 85.80 475.80
50 Providing, laying, testing and commissioning underground Yellow
Polyethelene (MDPE) gas pipe tubing of required IPS (Iron Pipe Size) in
the trenches , made of Dadex/ Popular / Beta or equivelant, for Gas supply
i/c the cost of solvent and specials complete as approved and directed by
the Engineer Incharge.
SDR-11
(i) 3/4" Per Rft 7.50 86.90 Meter 24.50 285.05
(ii) 1" Per Rft 7.50 128.40 Meter 24.50 421.10
(iii) 1-1/4" Per Rft 7.50 190.60 Meter 24.50 625.15

chapter-19(PSI & GF).xls Page 131


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

(iv) 1-1/2" Per Rft 7.50 363.05 Meter 24.50 1,190.75


(v) 2" Per Rft 7.50 643.55 Meter 24.50 2,110.75

51 Providing and hoisting vertical/ horizontal type storage tank of required Per Gallon 6.00 106.75 Per Ltr. 1.60 28.20
capacity made of rotationally molded from (HDPE), double ply
polyethelene of approved manufacturer i/c cost of making connection for
inlet/outlet pipe, float valve i/c all cost of specials & labour complete in all
respect as approved and directed by the Engineer Incharge.

52 Providing and fixing CP bath Room Set made of Sonex/Master/Faisal


comprising of 3-No Tee stop cocks, lever type Basin Mixer, double Bib
Cock, open wall shower, Muslim shower,waste coupling and bottle trap
etc. complete in all respect as approved and directed by the Engineer
incharge.
(i) 3 No Tee Stop Cock (set) Each 299.00 2,099.00 Each 299.00 2,099.00
(ii) Lever Type Basin Mixer Each 299.00 6,539.00 Each 299.00 6,539.00
(iii) Double Bib Cock Each 299.00 1,739.00 Each 299.00 1,739.00
(iv) Open Type Wall Shower Each 299.00 18,539.00 Each 299.00 18,539.00
(v) Muslim shower Each 299.00 2,219.00 Each 299.00 2,219.00
(vi) Waste Coupling Each 299.00 599.00 Each 299.00 599.00
(vii) Bottle Trap Each 299.00 1,319.00 Each 299.00 1,319.00

53 Providing/fixing Gas water heater (Geyser) of specified


capacity,comprising of water tank made of 14 SWG steel sheet and cover
with 20 SWG MS sheet, best quality of approved make of
Corona/Ambassador / Super Asia/Canon i/c the cost of non return
valve,imported thermostate,G.I. accessories, safety valve and making
connection with existing water supply pipe line complete in all respects as
approved and directed by the Engineer Incharge.
(i) 35 Gallons Each 2,131.80 41,011.10 Each 2,131.80 41,011.10
(ii) 50 Gallons Each 2,131.80 46,183.30 Each 2,131.80 46,183.30
(iii) 55 Gallons Each 2,131.80 51,583.30 Each 2,131.80 51,583.30
54 Supply & Fixing gas room heater of required plates of approved quality
made by Crona /Ambessedor/Canon i/c cost of fittings & pipe etc.
complete in all respect as directed and approved by the Engineer Incharge.

(i) Single plate Each 747.45 8,643.45 Each 747.45 8,643.45


(i) Double plate Each 747.45 14,043.45 Each 747.45 14,043.45
55 Providing/fixing Electric water heater (Geyser) comprising of tank of 14
SWG, GI sheet and external cover of 22 SWG MS sheet, insulated with 4"
thick high density glass wool, imported thermostat i/c electric rod, safety
valve (Ambassador / Canon) i/c cost of accessories & making connection
complete in all respect as approved and directed by Engineer Incharge.

(i) 15 Gal capacity Each 1,494.90 19,854.90 Each 1,494.90 19,854.90


(ii) 20 Gal capacity Each 1,494.90 23,454.90 Each 1,494.90 23,454.90

chapter-19(PSI & GF).xls Page 132


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

Replacement items

1 Providing and fixing, chromium plated waste coupling:-

i) 3 cm (1¼") Each 85.80 229.80 Each 85.80 229.80


ii) 4 cm (1½") Each 85.80 241.80 Each 85.80 241.80

2 Providing and fixing rubber plug with chain:-

i) 3 cm (1¼") Each 3.45 87.45 Each 3.45 87.45


ii) 4 cm (1½") Each 3.45 99.45 Each 3.45 99.45

3 Providing and fixing, waste pipe of PVC:-

i) 3 cm (1¼") Each 42.90 126.90 Each 42.90 126.90


ii) 4 cm (1½") Each 42.90 138.90 Each 42.90 138.90

4 Providing and fixing, flushing bend of PVC.


i) 3 cm (1¼") Each 38.15 206.15 Each 38.15 206.15
ii) 4 cm (1½") Each 38.15 218.15 Each 38.15 218.15
5 Providing and fixing chromium plated bottle trap with waste
pipe, etc. complete:-

i) 3 cm (1¼") Each 85.80 805.80 Each 85.80 805.80


ii) 4 cm (1½") Each 85.80 925.80 Each 85.80 925.80
6 Providing and fixing, angle iron brackets for:-
i) wash hand basin and cistern Each 85.80 325.80 Each 85.80 325.80
ii) sinks Each 85.80 325.80 Each 85.80 325.80
7 Providing and fixing 1.5 cm (½") dia connection, including
check nuts, etc.:-
i) plastic rubber connection Each 34.30 214.30 Each 34.30 214.30
ii) copper connection Each 34.30 190.30 Each 34.30 190.30

8 Providing and fixing brass ball float valve:-


i) 1.5 cm (½") dia Each 71.50 275.50 Each 71.50 275.50
ii) 32.0 cm (¾") dia Each 71.50 491.50 Each 71.50 491.50
iii) 2.5 cm (1") dia Each 71.50 611.50 Each 71.50 611.50
iv) 3 cm (1¼") dia Each 71.50 731.50 Each 71.50 731.50
v) '4.0 cm (1½") dia Each 71.50 851.50 Each 71.50 851.50
vi) 5 cm (2") dia Each 71.50 1,151.50 Each 71.50 1,151.50

chapter-19(PSI & GF).xls Page 133


20. SURFACE DRAINAGE
1. Specification No. correspond to Book of Specification (B & R Department ) Vol. II, 1966 (public Health Works).

2. Rates for all finished works include the removal of surplus debris, unused material and by products.
MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

1 Tega formed of pacca bricks on end, laid in and over 17.1


cement sand mortar projecting to a height of not more
than 6" (150 mm) top of drain along the property side
where required, laid to lines, grades, slopes and shape
according to the Engineer's drawing:-

a) 3" thick (75 mm)

i) ratio 1:3 100Rft 2,195.70 7,195.35 Metre 72.00 236.00


ii) ratio 1:5 ditto 2,195.70 6,823.85 ditto 72.00 223.80

B) 4½" thick (113 mm)

i) ratio 1:3 100Rft 3,291.80 10,473.45 ditto 107.95 343.55


ii) ratio 1:5 ditto 3,291.80 9,910.75 ditto 107.95 325.05

2 Pacca flat brick 3" (75 mm ) thick, laid in reimbursement, 17.1


in cement, sand mortar, on sides of drains and in other
works where required. All joints to be completely filled
and struck flush:-

a) ratio 1:3 100Sft. 3,240.45 10,257.55 Sqm. 348.65 1,103.70


b) ratio 1:5 ditto 3,240.45 9,661.95 ditto 348.65 1,039.60
c) ratio 1:6 ditto 3,240.45 9,494.35 ditto 348.65 1,021.60

3 Pacca brick on edge, laid in reimbursement, in cement, 17.1


sand mortar, on sides of drains and on other works where
required. All joints to be completely filled and struck
flush:-

a) ratio 1:3 100Sft. 4,611.00 15,201.70 Sqm. 496.15 1,635.70


b) ratio 1:5 ditto 4,611.00 14,246.40 ditto 496.15 1,532.90
c) ratio 1:6 ditto 4,611.00 14,008.70 ditto 496.15 1,507.35

4 Pacca flat brick, Herring bond pitching in cement, sand 17.2


mortar, laid to lines, grades, shapes and slopes as per
Engineer's drawing:-

a) ratio 1:3 100Sft. 3,071.90 10,089.00 Sqm. 330.55 1,085.60


b) ratio 1:5 ditto 3,071.90 9,493.40 ditto 330.55 1,021.50
c) ratio 1:6 ditto 3,071.90 9,325.80 ditto 330.55 1,003.45

chapter-20(Surface Drainage).xls Page 134


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

5 Pacca brick on edge, Herring bond pitching in cement, 17.2


sand mortar, laid to lines, grades, shapes and slopes as
per Engineer's drawing:-

a) ratio 1:3 100Sft. 4,739.85 15,330.50 Sqm. 510.00 1,649.55


b) ratio 1:5 ditto 4,739.85 14,375.25 ditto 510.00 1,546.80
c) ratio 1:6 ditto 4,739.85 14,137.50 ditto 510.00 1,521.20

6 Constructing Punjab Standard Drains. of cement concrete


1:2 ½ :5, with cement concrete bedding ratio 1:6:12, 17.1
complete, laid to lines, grades, slopes and shapes,
rendering exposed surface of concrete with 1:1 cement,
sand mortar, ¼" (6 mm) thick, as per Engineer's drawing
(excluding excavation):-

a) Type I Per Rft 73.60 186.70 Metre 241.35 612.30


b) Type II ditto 147.15 353.10 ditto 482.75 1,158.20
c) Type III ditto 191.25 459.55 ditto 627.35 1,507.40
d) Type IV ditto 227.90 548.55 ditto 747.55 1,799.30
e) Type V ditto 300.70 748.35 ditto 986.30 2,454.50
f) Type VI ditto 345.85 858.80 ditto 1,134.35 2,816.80
g) Type VII ditto 383.30 947.65 ditto 1,257.30 3,108.20
h) Type VIII ditto 428.15 1,068.15 ditto 1,404.25 3,503.60
i) Type IX ditto 572.50 1,500.80 ditto 1,877.85 4,922.60
j) Type X ditto 628.85 1,645.50 ditto 2,062.65 5,397.25
k) Type XI ditto 702.85 1,829.80 ditto 2,305.30 6,001.75
l) Type XII ditto 749.25 1,943.25 ditto 2,457.55 6,373.85

7 Laying R.C.C hume pipes in position, including jointing:-


a) 6" to 12" (150 mm to 300 mm ) dia Per Lft. 136.20 142.95 Metre 446.80 468.85
b) 12" to 24" (300 mm to 600 mm) dia ditto 212.65 226.10 ditto 697.50 741.60
c) 24" to 36" (600 mm to 900 mm) dia ditto 272.45 292.70 ditto 893.65 960.05

chapter-20(Surface Drainage).xls Page 135


21. SEWERAGE
1 Specification No. correspond to Book of Specification of B& R Department Vol. II, 1966 (Public Health Works).
2 Rate for all finished works include the removal of surplus debris, unused material and byproducts.
MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
1 Providing and laying R.C.C. pipe, moulded with cement Chapter - 8
concrete 1:1½:3, with spigot socket or collar joint, etc.
including cost of reinforcement, conforming to B.S. 5911:
Part I: 1981, Class "L" including carriage of pipe from
factory to site of work, lowering in trenches to correct
alignment and grade, jointing, cutting pipes where
necessary, finishing and testing, etc., complete.
i) 100 mm (4") i/d Rft. 39.35 177.00 Metre 129.05 580.55
ii) 150 mm (6") i/d Rft. 48.10 263.75 Metre 157.75 865.10
iii) 225 mm (9:) i/d Rft. 90.75 529.90 Metre 297.65 1,738.05
2 Providing and laying non-reinforced concrete pipe, ditto
moulded with cement concrete 1:1½:3, conforming to
ASTM Specification C-14-73, Class 2, including carriage
of pipe from factory to site of work, lowering in trenches to
correct alignment and grade, jointing, cutting pipe where
necessary, finishing and testing, etc. complete.
i) 100 mm (4") i/d Rft. 28.50 89.30 Metre 93.50 292.90
ii) 150 mm (6") i/d Rft. 34.55 119.55 Metre 113.30 392.10
iii) 200 mm (8") i/d Rft. 55.00 164.20 Metre 180.40 538.60
iv) 225 mm (9:) i/d wall thickness 1 inch (25 mm) Rft. 58.40 192.10 Metre 191.55 630.10
v) 250 mm (10") i/d Rft. 59.35 212.55 Metre 194.65 697.15
3 Providing and laying R.C.C. pipe sewers, moulded with ditto
cement concrete 1:1½:3 conforming to ASTM
Specification C-76-20, Class II. Wall B, including carriage
of pipe from factory to site of work, lowering in trenches to
correct alignment and grade, jointing with rubber ring,
cutting pipes where necessary, testing, etc., complete.
i) 310 mm (12") i/d Rft. 87.70 697.25 Metre 287.65 2,287.00
ii) 380 mm (15") i/d Rft. 109.80 962.55 Metre 360.15 3,157.15
iii) 460 mm (18") i/d Rft. 131.90 1,184.25 Metre 432.65 3,884.35
iv) 530 mm (21":) i/d Rft. 164.40 1,358.25 Metre 539.25 4,455.05
v) 610 mm (24") i/d Rft. 187.90 1,697.65 Metre 616.30 5,568.30
vi) 690 mm (27") i/d Rft. 278.85 2,267.45 Metre 914.65 7,437.25
vii) 760 mm (30") i/d Rft. 334.00 2,610.10 Metre 1,095.50 8,561.15
viii) 840 mm (33") i/d Rft. 415.50 2,919.20 Metre 1,362.85 9,575.00
ix) 910 mm (36") i/d Rft. 514.10 4,011.75 Metre 1,686.25 13,158.55
x) 1070 mm (42") i/d Rft. 665.90 4,561.30 Metre 2,184.15 14,961.05
xi) 1220 mm (48") i/d Rft. 1,258.30 5,459.25 Metre 4,127.20 17,906.35
xii) 1370 mm (54") i/d Rft. 1,755.10 7,019.35 Metre 5,756.75 23,023.45
xiii) 1520 mm (60") i/d Rft. 2,204.35 9,580.70 Metre 7,230.25 31,424.70
xiv) 1680 mm (66") i/d Rft. 3,490.40 11,722.35 Metre 11,448.50 38,449.30
xv) 1830 mm (72") i/d Rft. 4,348.05 14,445.10 Metre 14,261.60 47,379.95

chapter-21(Sewerage).xls Page 136


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

4 Providing and laying R.C.C. pipe sewers, moulded with Chapter-8


cement concrete 1:1½:3 conforming to ASTM Specification
C-76-20, Class III, Wall B, including carriage of pipes from
factory to site of work, lowering in trenches to correct
alignment and grade, jointing with rubber ring, cutting pipes
where necessary, testing, etc. complete:-

i) 310 mm (12") i/d Rft. 87.70 755.35 Metre 287.55 2,477.55


ii) 380 mm (15") i/d Rft. 109.80 1,006.15 Metre 360.10 3,300.15
iii) 460 mm (18") i/d Rft. 131.90 1,227.85 Metre 432.60 4,027.35
iv) 530 mm (21":) i/d Rft. 164.40 1,460.00 Metre 539.30 4,788.80
v) 610 mm (24") i/d Rft. 187.90 2,133.70 Metre 616.25 6,998.55
vi) 690 mm (27") i/d Rft. 278.85 2,760.80 Metre 914.65 9,055.40
vii) 760 mm (30") i/d Rft. 334.00 3,377.85 Metre 1,095.55 11,079.35
viii) 840 mm (33") i/d Rft. 415.50 3,763.70 Metre 1,362.80 12,344.95
ix) 910 mm (36") i/d Rft. 514.10 4,706.40 Metre 1,686.20 15,437.00
x) 1070 mm (42") i/d Rft. 665.90 5,325.35 Metre 2,184.15 17,467.15
xi) 1220 mm (48") i/d Rft. 1,276.90 6,927.90 Metre 4,188.25 22,723.50
xii) 1370 mm (54") i/d Rft. 1,781.15 8,694.75 Metre 5,842.15 28,518.80
xiii) 1520 mm (60") i/d Rft. 2,236.90 10,987.70 Metre 7,337.00 36,039.65
xiv) 1680 mm (66") i/d Rft. 3,542.55 14,566.30 Metre 11,619.50 47,777.45
xv) 1830 mm (72") i/d Rft. 4,413.15 17,388.20 Metre 14,475.15 57,033.30

5 Providing and laying R.C.C. pipe sewers, moulded with Chapter - 8


cement concrete 1:1½:3 conforming to ASTM
Specification C-76-20, Class IV, Wall B, including carriage
of pipes from factory to site of work, lowering in trenches
to correct alignment and grade, jointing with rubber ring,
cutting pipes where necessary, testing, etc. complete:-

i) 310 mm (12") i/d Rft. 87.70 798.95 Metre 287.55 2,620.55


ii) 380 mm (15") i/d Rft. 109.80 1,049.75 Metre 360.10 3,443.15
iii) 460 mm (18") i/d Rft. 131.90 1,373.20 Metre 432.60 4,504.15
iv) 530 mm (21":) i/d Rft. 164.40 1,648.95 Metre 539.30 5,408.65
v) 610 mm (24") i/d Rft. 187.90 2,061.00 Metre 616.25 6,760.10
vi) 690 mm (27") i/d Rft. 278.85 2,901.75 Metre 914.65 9,517.70
vii) 760 mm (30") i/d Rft. 334.00 3,936.15 Metre 1,095.55 12,910.80
viii) 840 mm (33") i/d Rft. 415.50 4,377.90 Metre 1,362.80 14,359.55
ix) 910 mm (36") i/d Rft. 514.10 5,817.80 Metre 1,686.20 19,082.35
x) 1070 mm (42") i/d Rft. 665.90 7,826.00 Metre 2,184.15 25,669.30
xi) 1220 mm (48") i/d Rft. 1,276.90 9,689.80 Metre 4,188.00 31,782.60
xii) 1370 mm (54") i/d Rft. 1,781.15 11,856.05 Metre 5,842.35 38,887.80
xiii) 1520 mm (60") i/d Rft. 2,236.90 14,423.85 Metre 7,337.00 47,310.30
xiv) 1680 mm (66") i/d Rft. 3,542.55 20,847.95 Metre 11,619.50 68,381.25
xv) 1830 mm (72") i/d Rft. 4,413.15 23,573.30 Metre 14,475.15 77,320.35

chapter-21(Sewerage).xls Page 137


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
6 Lowering of sub-soil water table, by installation of tubewells 1) This rate shall be payable, in
along sewer line and pumping out water, for excavation in addition to the item of excavation
open cutting below sub-soil water level, concreting, curing, below SSWL for sewers and
laying and jointing pipes, filling haunches, etc. till the manholes under Chapter,
completion of sewer line, including disposal of pumped out EARTHWORK
water:- 2) The grant of these rates shall be
Rft of Metre of subject to Superintending Engineer's
1) 0-1 ft. (0 to 310 mm) below SSWL laid sewer - 493.20 laid sewer - 1,617.65 approval.
2) 0-2 ft. (0 to 610 mm) below SSWL ditto - 899.75 ditto - 2,951.25
3) 0-3 ft. (0 to 910 mm) below SSWL ditto - 1,576.05 ditto - 5,169.45 3) The rate includes cost of
4) 0-4 ft. (0 to 1220 mm) below SSWL ditto - 2,302.65 ditto - 7,552.65 providing pumps, POL and all
5) 0-5 ft. (0 to 1520 mm) below SSWL ditto - 3,261.35 ditto - 10,697.20 operation charges at the site
6) 0-6 ft. (0 to 1830 mm) below SSWL ditto - 4,030.40 ditto - 13,219.70 of work, etc.
7) 0-7 ft. (0 to 2170 mm) below SSWL ditto - 4,824.15 ditto - 15,823.20
8) 0-8 ft. (0 to 2480 mm) below SSWL ditto - 5,537.95 ditto - 18,164.50
9) 0-9 ft. (0 to 2790 mm) below SSWL ditto - 5,938.40 ditto - 19,477.85
10) 0-10 ft. (0 to 3100 mm) below SSWL ditto - 6,867.35 ditto - 22,525.00
11) 0-11 ft. (0 to 3410 mm) below SSWL ditto - 7,660.35 ditto - 25,125.95
12) 0-12 ft. (0 to 3720 mm) below SSWL ditto - 8,510.45 ditto - 27,914.35

7 Constructing gully grating chamber, 12"x12", ( 300x300 16.2 Pipe connection to be paid
mm) complete in all respects: separately.

a) with C.I. gully trap, weighing 81 lbs. (36.75 Kg.) frame Each 1,528.80 11,259.90 Each 1,528.80 11,259.90
hinged safety type.

b) concrete Gully trap. ditto 1,528.80 5,034.10 ditto 1,528.80 5,034.10

8 Constructing standard gully grating chamber, 3'x2½' Each 4,664.80 17,162.50 Each 4,664.80 17,162.50 ditto Pipe connection to be paid
(900x750 mm), with chinaware trap as per PHED Drawing separately.
STD/PD No. 3 of 1977, complete in all respects.

9 Extra for making and finishing benching floor work in 100Sft. 1,960.85 2,976.75 Sq.m 211.00 320.30 14.4
manhole chamber, with 1/8" (3 mm) thick cement finish.

10 Restoration of brick pavement on edge, over laid service 100Sft. 2,810.40 5,751.25 Sq.m 302.40 618.85 13.1
line, with 2" (50 mm) sand cushion under soling.

11 Restoration of flat brick pavement sand grouted, over 2" 100Sft. 1,705.95 3,811.60 Sq.m 183.55 410.15 13.1
(50 mm) thick dry sand cushion, under soling on laid
service line.

12 Restoration of metalled road, on laid service line, including 13.1


compaction:-

a) Carpetted road, with 2" (50 mm) carpet and 10" (250 100Sft. 6,446.70 17,262.25 Sq.m 693.65 1,857.40
mm) depth of stone metal for sub-base and base.

chapter-21(Sewerage).xls Page 138


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
b) Carpeted road, with 1½" (38 mm) carpet and 6" (150 100Sft. 4,592.60 12,650.55 Sq.m 494.15 1,361.20
mm) depth of stone metal, for sub-base and base.

c) Black Topped Road with two coats of surfacing & 10" 100Sft. 2,084.45 8,152.50 Sq.m 224.30 877.20
(250 mm) depth of stone metal, for sub base & base.

13 Providing and fixing 1¼"x1¼"x3/16" (31x31x5 mm) angle 14.7


iron step, in manhole chambers, including carriage and Each 144.75 594.45 Each 144.75 594.45
setting the same in work to correct lines and levels.

14 Fixing manhole frame and cover in R.C.C. slab including Per 402.80 - Per 402.80 - ditto
carriage to site. set set

15 Providing and fixing 3" (75 mm) thick R.C.C. manhole Per 251.90 11,564.50 Per 251.90 11,564.50 ditto
cover, 22" (550 mm) dia, with tee shaped C.I. frame of 20" set set
(500 mm) clear i/d (frame weighing 37.324 Kg. or one
maund) as per Standard Drawing STD/PD No. 5, of 1977,
complete in all respects.

16 Providing and fixing 6" thick R.C.C. manhole Per 592.50 15,119.75 Per 592.50 15,119.75
cover with tee shaped C.I. frame of 22" I/d (frame set set
weighing 37.324 Kg. or one maund as per Standard
Drawing STD/PD No. 6, of 1977, complete in all respect.

17 Providing and fixing, 6" (150 mm) thick R.C.C. manhole Per 524.05 6,876.60 Per 524.05 6,876.60 ditto
cover for 22" as per standard drawing STD/PD No. 6 of set set
1977, complete in all respects.

18 Providing and fixing, 6" (150 mm) thick R.C.C. manhole Per 430.00 11,097.90 Per 430.00 11,097.90 ditto
cover with 3"x3"x¼" (75x75x6mm) angle iron frame, 22" set set
(550 mm) i/d as per standard drawing STD/PD No. 7 of
1977, complete in all respects.

19 Desilting of disposal work collecting tank, including 100Cft. 1,455.75 1,510.05 cum 514.20 533.35 16.2
removal of sludge within 3 chains (90 metre).

20 Desilting of Manholes including rehandling of sludge within three chains


100Cft. 915.00 4,450.70 cum 323.30 1,572.70
and removal from site to Dumping Site. Complete in all respect.

21 Providing and installing, C.I. ventilating shaft painted with 14.6


bituminous paint with foundation bolts, as per PHED
Standard Drawing STD/PD No. 4 of 1977, complete in all
respects (except concrete foundation block):-

a) 6" (150 mm) i/d shaft

i) 18 ft. (5.5 metre) long Per Cwt 425.70 11,431.00 %kg 838.00 22,502.00
ii) 24 ft. (7.30 metre) long ditto 473.00 11,487.75 ditto 931.10 22,613.75

chapter-21(Sewerage).xls Page 139


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite
iii) 30 ft. (9.15 metre) long ditto 510.85 11,517.60 ditto 1,005.60 22,672.40
iv) 36 ft. (11 metre) long ditto 534.50 11,543.70 ditto 1,052.20 22,723.80

b) 9" (225 mm) i/d shaft

i) 18 ft. (5.5 metre) long Per Cwt 374.35 11,373.70 %kg 736.90 22,389.20
ii) 24 ft. (7.30 metre) long ditto 403.40 11,401.35 ditto 794.10 22,443.60
iii) 30 ft. (9.15 metre) long ditto 431.95 11,429.20 ditto 850.30 22,498.45
iv) 36 ft. (11 metre) long ditto 519.95 11,516.65 ditto 1,023.50 22,670.60

c) 12" (300 mm) i/d shaft

i) 18 ft. (5.5 metre) long Per Cwt 330.75 11,331.20 %kg 651.05 22,305.50
ii) 24 ft. (7.30 metre) long ditto 425.25 11,420.70 ditto 837.05 22,481.70
iii) 30 ft. (9.15 metre) long ditto 496.10 11,490.75 ditto 976.60 22,619.55

22 Silt clearing 10' (3.00 m) dia wells, and


removal of slush outside the compound:-

a) upto 10' (3.00 m) depth of slush Per well 12,153.90 - Per well 12,153.90 -
b) beyond 10' (3.00 m) depth of slush Per well 23,865.60 - Per well 23,865.60 -
23 Providing and laying crushed stone aggregate of 1/4" to 1" guage under 100Cft. 2,547.60 9,099.60 cum 899.80 3,214.00
and around the sewer pipe, including leveling, manual compaction,
complete in all respects.
24 Providing and laying sand under and around the sewer pipe, including 100Cft. 1,273.80 3,793.80 cum 449.90 1,339.95
leveling, manual compaction, complete in all respect.
25 Supply of Bamboos for removal of sewer blockage 4" dia from Bottom 04 pieces - 1,452.00 01 piece - 363.00
and 2" to 2.5" dia from Top, 22' long i/c cutting charges into four pieces, 22 feet 22 feet
including carriage charges. long long

chapter-21(Sewerage).xls Page 140


22. SINKING OF WELLS
1 Rates for all finished works include the removal of surplus debris, unused material and byproducts.
2 Well curbs to be laid at spring level or as deep as possible.
MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

1 Excavation of well in dry upto 20'(6 metre) below ground


level, and disposal of soil within one chain (30 metre)

a) in ordinary soil or sand :- 1000 Cft. Cu.m

i) from 0' to 5' (o to 1.5 m) depth 1000 Cft. 7,571.45 - Cu.m 267.40 -
ii) from 5.1' to 10' (1.5 to 3.0 metre) depth 1000 Cft. 7,907.75 - Cu.m 279.30 -
iii) from 10.1' to 15' (3.0 to 4.5 metre) depth 1000 Cft. 8,896.20 - Cu.m 314.20 -
iv) from 15.1' to 20' (4.5 metre to 6.0 metre) depth 1000 Cft. 10,210.80 - Cu.m 360.65 -

b) in hard soil

i) from 0' to 5'(0 to 1.5 metre) depth 1000 Cft. 9,222.30 - Cu.m 325.75 -
ii) from 5.1' to 10'(1.5 to 3.0 metre) depth 1000 Cft. 9,640.10 - Cu.m 340.50 -
iii) from 10.1' to 15'(3.0 to 4.5 metre) depth 1000 Cft. 10,536.85 - Cu.m 372.15 -
iv) from 15.1' to 20'(4.5 to 6.0 metre) depth 1000 Cft. 11,851.45 - Cu.m 418.60 -

c) in hard strata, such as shingle, gravel, etc.

i) from 0' to 5'(0 to 1.5 metre) depth 1000 Cft. 19,891.65 - Cu.m 702.55 -
ii) from 5.1' to 10'(1.5 to 3.0 metre) depth 1000 Cft. 20,605.00 - Cu.m 727.75 -
iii) from 10.1' to 15'(3.0 to 4.5 metre) depth 1000 Cft. 21,481.35 - Cu.m 758.70 -
iv) from 15.1' to 20'(4.5 to 6.0 metre ) depth 1000 Cft. 23,060.90 - Cu.m 814.50 -

2 Dry sinking of well, including loading, and removing


excavated material within one chain (30 m):-

a) in ordinary soil :-

i) from 10' to 15'(3.0 to 4.5 m) depth 1000 Cft. 40,761.60 - Cu.m 1,439.70
ii) from 15.1' to 20'(4.5 to 6.0 m) depth 1000 Cft. 50,952.00 - Cu.m 1,799.65
iii) from 20.1' to 25'(6.0 to 7.5 m) depth 1000 Cft. 61,142.40 - Cu.m 2,159.55
iv) from 25.1' to 30'(7.5 to 9.0 m) depth 1000 Cft. 71,332.80 - Cu.m 2,519.50
v) from 30.1' to 35'(9.0 to 10.5 m) depth 1000 Cft. 81,523.20 - Cu.m 2,879.40
vi) from 35.1' to 40'(10.5 to 12.0 m) depth 1000 Cft. 91,713.60 - Cu.m 3,239.30
vii) from 40.1'to 45'(12.0 to 13.5 m) depth 1000 Cft. 101,904.00 - Cu.m 3,599.25
viii) from 45'(13.5 Sm) to any depth 1000 Cft. 112,094.40 - Cu.m 3,959.15

b) in hard soil :-

i) from 10' to 15'(3.0 to 4.5 m) depth 1000 Cft. 56,047.20 - Cu.m 1,979.60 -
ii) from 15.1' to 20'(4.5 to 6.0 m) depth 1000 Cft. 66,237.60 - Cu.m 2,339.50 -
iii) from 20.1' to 25'(6.0 to 7.5 m) depth 1000 Cft. 76,428.00 - Cu.m 2,699.45 -
iv) from 25.1' to 30'(7.5 to 9.0 m) depth 1000 Cft. 86,618.40 - Cu.m 3,059.35 -

chapter-22(Sinking of Wells).xls Page 141


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

v) from 30.1' to 35'(9.0 to 10.5 m) depth 1000 Cft. 96,808.80 - Cu.m 3,419.30 -
vi) from 35.1' to 40'(10.5 to 12.0 m) depth 1000 Cft. 106,999.20 - Cu.m 3,779.20 -
vii) from 40.1' to 45'(12.0 to 13.5 m) depth 1000 Cft. 117,189.60 - Cu.m 4,139.15 -
viii) from 45'(13.5 m) to any depth 1000 Cft. 127,380.00 - Cu.m 4,499.05 -

c) in hard strata, such as shingle, gravel, etc.

i) from 10' to 15'(3.0 to 4.5 m) depth 1000 Cft. 76,428.00 - Cu.m 2,699.45 -
ii) from 15.1' to 20'(4.5 to 6.0 m) depth 1000 Cft. 86,618.40 - Cu.m 3,059.35 -
iii) from 20.1' to 25'(6.0 to 7.5 m) depth 1000 Cft. 96,808.80 - Cu.m 3,419.30 -
iv) from 25.1' to 30'(7.5 to 9.0 m) depth 1000 Cft. 98,082.60 - Cu.m 3,464.30 -
v) from 30.1' to 35'(9.0 to 10.5 m) depth 1000 Cft. 117,189.60 - Cu.m 4,139.15 -
vi) from 35.1' to 40'(10.5 to 12.0 m) depth 1000 Cft. 127,380.00 - Cu.m 4,499.05 -
vii)from 40.1' to 45'(12.0 to 13.5 m) depth 1000 Cft. 137,570.40 - Cu.m 4,859.00 -
viii) from 45'-1" (13.5 m) to any depth 1000 Cft. 147,760.80 - Cu.m 5,218.90 -

3 Wet sinking of well in ordinary soil (value of C upto 5), for * 841-1 The outer dimensions of the curb
depths below spring level, including charges of machinery, to shall form basis of payment.
shoring, kentledge and removal of excavated spoil within 841-9
one chain (30 m):-

i) i) from o' to 10'(0 to 3.0 m) depth 1000 Cft. 65,145.90 - Cu.m 2,300.95 -
ii) ii) above 10' to 20'(3.0 to 6.0 m) depth 1000 Cft. 138,435.00 - Cu.m 4,889.50 -
iii) iii) above 20' to 30'(6.0 to 9.0 m) depth 1000 Cft. 170,381.55 - Cu.m 6,017.90 -
iv) iv) above 30' to 40'(9.0 to 12.0 m) depth 1000 Cft. 221,496.00 - Cu.m 7,823.25 -
v) v) above 40' to 50'(12.0 to 15.0 m) depth 1000 Cft. 246,106.65 - Cu.m 8,692.50 -
vi) vi) above 50' to 60'(15.0 to 18.0 m) depth 1000 Cft. 276,870.00 - Cu.m 9,779.05 -
vii) vii) above 60' to 70'(18.0 to 21.0 m) depth 1000 Cft. 283,969.25 - Cu.m 10,029.80 -
viii) viii) above 70' to 80'(21.0 to 24.0 m) depth 1000 Cft. 291,442.10 - Cu.m 10,293.75 -
ix) ix) above 80'(24.0 m) to any depth 1000 Cft. 316,422.85 - Cu.m 11,176.05 -

4 Wet sinking of well in cohesive soil (value of Cmore than * 841-1 The outer dimensions of the curb
5), for depths below spring level, including charges of to shall form basis of payment.
machinery shoring, kentledge and removal of excavated 841-9
spoil within one chain (30 m):-

i) from o' to 10'(0 to 3.0 m) depth 1000 Cft. - 94,602.10 Cu.m - 3,341.35
ii) above 10' to 20'(3.0 to 6.0 m) depth 1000 Cft. - 118,252.65 Cu.m - 4,176.70
iii) above 20' to 30'(6.0 to 9.0 m) depth 1000 Cft. - 141,903.15 Cu.m - 5,012.00
iv) above 30' to 40'(9.0 to 12.0 m) depth 1000 Cft. - 189,204.20 Cu.m - 6,682.70
v) above 40' to 50'(12.0 to 15.0 m) depth 1000 Cft. - 218,312.55 Cu.m - 7,710.80
vi) above 50' to 60'(15.0 to 18.0 m) depth 1000 Cft. - 236,505.25 Cu.m - 8,353.35
vii) above 60' to 70'(18.0 to 21.0 m) depth 1000 Cft. - 258,005.75 Cu.m - 9,112.75
viii) above 70' to 80'(21.0 to 24.0 m) depth 1000 Cft. - 267,741.80 Cu.m - 9,456.65
ix) above 80'(24.0 m) to any depth 1000 Cft. - 283,806.30 Cu.m - 10,024.05

chapter-22(Sinking of Wells).xls Page 142


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

5 Wet sinking of well in shingle, or gravel, etc, for depths * 841-1 The outer dimensions of the curb
below spring level, including charges of machinery, to shall form basis of payment.
shoring, kentledge and removal of excavated spoil within 841-9
one chain (30 m) :-
i) from o' to 10'(0 to 3.0 m) depth 1000 Cft. - 129,002.85 Cu.m - 4,556.40
ii) above 10' to 20'(3.0 to 6.0 m) depth 1000 Cft. - 157,670.20 Cu.m - 5,568.90
iii) above 20' to 30'(6.0 to 9.0 m) depth 1000 Cft. - 189,204.20 Cu.m - 6,682.70
iv) above 30' to 40'(9.0 to 12.0 m) depth 1000 Cft. - 258,005.75 Cu.m - 9,112.75
v) above 40' to 50'(12.0 to 15.0 m) depth 1000 Cft. - 283,806.30 Cu.m - 10,024.05
vi) above 50' to 60'(15.0 to 18.0 m) depth 1000 Cft. - 315,340.35 Cu.m - 11,137.80
vii) above 60' to 70'(18.0 to 21.0 m) depth 1000 Cft. - 330,007.35 Cu.m - 11,655.85
viii) above 70' to 80'(21.0 to 24.0 m) depth 1000 Cft. - 337,864.65 Cu.m - 11,933.40
ix) above 80'(24.0 m) to any depth 1000 Cft. - 373,429.35 Cu.m - 13,189.55

6 Making and fixing in position, kiker wood well curb/ left over Per Cft. 1,902.55 6,259.20 Cu.m 67,197.50 221,075.40
shuttering.

7 Laying well curb in position only. Each 686.40 - Each 686.40 -

8 Providing, making and laying R.C.C. well curb in position, * 841-1 1) If concrete mixer is supplied by
using coarse sand, including all kinds of form, moulds, to Government, all charges including
curing, shuttering, rendering and finishing the exposed 841-9 depreciation will be recovered from
surface, (including screening and washing of aggregate :- the contractor.
2) The rate does not include cost of
a) Ratio 1:1½:3 Per Cft. 260.55 691.90 Cu.m 9,202.80 24,437.65 steel reinforcement and its labour for
b) ratio 1:2:4 ditto 260.55 636.20 ditto 9,202.80 22,470.20 bending, which is payable, separately.

9 Providing and fixing structural steel for cutting 100Kg 1,494.90 30,452.55 100Kg 1,494.90 30,452.55 841-1 to
edge. 841-9

10 Making and removing false masonry on well. 100Cft. 12,756.70 34,670.60 Cu.m 4,505.65 12,245.65 21.1 to The rate includes dismantling of false
21.5 & 18.1 masonry, scraping bricks obtained
from dismantling and credit of
byproducts.

* Specification No. correspond to Book of "Standard Specification for Road and Bridge Construction, 1971".

chapter-22(Sinking of Wells).xls Page 143


23. TUBEWELL AND WATER SUPPLY
1 Specification No. correspond to Book of "Specification for B& R Department, 1966, Vol. II (Public Health Works)".
2 Rates for all finished works include the removal of surplus debris, unused material and byproducts.
MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

1 Boring for tubewell in all types of soil except shingle and Chap. 2
rock, from ground level to 100 ft. (30 m) depth, including
sinking and withdrawing of casing pipe, complete:-

a) 3" (75 mm) i/d Per Rft. 240.80 Per Metre 789.85
b) 4" (100 mm) i/d of bore 324.85 of bore 1,065.55
c) 5" (125 mm) i/d ditto 597.40 ditto 1,959.40
d) 6" (150 mm) i/d ditto 902.50 ditto 2,960.25
e) 8" (200 mm) i/d ditto 1,194.35 ditto 3,917.50
f) 10" (250 mm) i/d ditto 1,497.70 ditto 4,912.50
g) 12" (300 mm) i/d ditto 1,618.55 ditto 5,308.85
h) 15" (375 mm) i/d ditto 2,463.00 ditto 8,078.55
i) 18" (450 mm) i/d ditto 2,612.75 ditto 8,569.75

2 Boring for tubewell in all types of soil except shingle, ditto


gravel & rock, from a depth of 100.1 ft. to 200 ft.
(30 to 60 m) below ground level, including sinking and
withdrawing of casing pipe, complete:-

a) 5" (125 mm) i/d Per Rft. 1,001.00 Per Metre 3,283.25
b) 6" (150 mm) i/d of bore 1,403.05 of bore 4,602.05
c) 8" (200 mm) i/d ditto 1,621.20 ditto 5,317.50
d) 10" (250 mm) i/d ditto 1,837.70 ditto 6,027.60
e) 12" (300 mm) i/d ditto 1,971.20 ditto 6,465.50
f) 15" (375 mm) i/d ditto 2,892.55 ditto 9,487.55
g) 18" (450 mm) i/d ditto 3,040.90 ditto 9,974.15

3 Boring for tubewell in all types of soil except shingle, ditto


gravel & rock, from a depth of 200.1 ft. to 300 ft. (60
to 90 m) below ground level, including sinking and
withdrawing of casing pipe, complete:-
a) 5" (125 mm) i/d Per Rft. 1,397.40 Per Metre 4,583.45
b) 6" (150 mm) i/d of bore 1,798.05 of bore 5,897.60
c) 8" (200 mm) i/d ditto 2,046.60 ditto 6,712.85
d) 10" (250 mm) i/d ditto 2,288.55 ditto 7,506.50
e) 12" (300 mm) i/d ditto 2,413.65 ditto 7,916.80
f) 15" (375 mm) i/d ditto 3,179.45 ditto 10,428.60
g) 18" (450 mm) i/d ditto 3,330.60 ditto 10,924.45
4 Boring for tubewell in all types of soil except shingle, Chap. 2
gravel & rock, from a depth of 300.1 ft. to 400 ft.
(90 to 120 m) below ground level, including sinking and
withdrawing of casing pipe, complete:-

a) 8" (200 mm) i/d Rft of bore 2,473.45 Per Metre 8,112.90

chapter-23(Tubewell).xls Page 144


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

b) 10" (250 mm) i/d ditto 2,742.30 of bore 8,994.75


c) 12" (300 mm) i/d ditto 2,870.20 ditto 9,414.30
d) 15" (375 mm) i/d ditto 3,892.95 ditto 12,768.95
e) 18" (450 mm) i/d ditto 3,902.90 ditto 12,801.45
5 Direct Rotary/Reverse Rotary drilling of bore for tubewells, ditto
in all types of soil except shingle, gravel and rock:-
a) from ground level to 250 ft. (75 m) below ground level:-
Per Rft. Per Metre
i) 15" to 18" (375 to 450 mm) i/d of bore 775.15 of bore 2,542.50 Upto 2 cusec discharge
ii) 20" to 26" (500 to 650 mm) i/d ditto 1,114.80 ditto 3,656.55 Above 2 cusec discharge
b) exceeding 250 ft. (75 m) depth below ground level:-
Rft Per Metre
i) 15" to 18" (375 to 450 mm) i/d of bore 775.15 of bore 2,542.50 Upto 2 cusec discharge
ii) 20" to 26" (500 to 650 mm) i/d ditto 1,114.80 ditto 3,656.55 Above 2 cusec discharge
6 Boring for tubewell in shingle, gravel and rock, including ditto Location and depth of shingle,
sinking and withdrawing of casing pipe:- gravel or rock is to be determined
from the bore log.
a) from ground level to 200 ft. (60 m) below ground level:-

Per Rft. Per Metre


i) 12" to 18" (300 to 450 mm) i/d of bore 1,748.20 of bore 5,734.15 Upto 2 cusec discharge
ii) 20" to 26" (500 to 650 mm) i/d ditto 2,364.40 ditto 7,755.20 Above 2 cusec discharge
b) exceeding 200 ft. (60 m) depth below
ground level:-
i) 12" to 18" (300 to 450 mm) i/d ditto 1,748.20 ditto 5,734.15 Upto 2 cusec discharge
ii) 20" to 26" (500 to 650 mm) i/d ditto 2,364.40 ditto 7,755.20 Above 2 cusec discharge
7 Providing strong substantially built box of deodar wood Job for 4,641.80 36,726.20 Job for 4,641.80 36,726.20 ditto
4'x2½'x9" (1200x750x225 mm), with compartments, lock compl- compl-
and locking arrangement, for preserving samples of strata ete bore ete bore
from bore hole.
8 Furnishing sample of water from bore hole. Per Set 118.80 183.95 Per Set 118.80 183.95 Chap. 2
of 2 of 2
bottles bottles
9 Providing and installing, brass strainer in tubewell bore ditto Cost/labour of jointing both ends is
hole, including sockets, special sockets, studs, etc. included in the rate.
complete:-
a) 2" i/d, 5/32" (50 mm i/d 4 mm) thick Per Rft. 54.65 2,039.95 Per Metre 179.25 6,691.05
b) 3" i/d, 5/32" (75 mm i/d 4 mm) thick Per Rft. 54.65 3,902.35 Per Metre 179.30 12,799.70
c) 4" i/d, 3/16" (100 mm i/d 5 mm) thick Per Rft. 72.40 4,761.05 Per Metre 237.55 15,616.30
d) 5" i/d, 3/16" (125 mm i/d 5 mm) thick Per Rft. 82.45 6,063.25 Per Metre 270.50 19,887.55
e) 6" i/d, 3/16" (150 mm i/d 5 mm) thick Per Rft. 90.15 6,829.35 Per Metre 295.75 22,400.35
f) 7" i/d, 3/16" (175 mm i/d 5 mm) thick Per Rft. 106.50 8,207.00 Per Metre 349.35 26,918.90
g) 8" i/d, 3/16" (200 mm i/d 5 mm) thick Per Rft. 131.00 9,729.10 Per Metre 429.70 31,911.40
h) 9" i/d, 3/16" (225 mm i/d 5 mm) thick Per Rft. 131.00 10,118.85 Per Metre 429.70 33,189.80
i) 10" i/d, 3/16" (250 mm i/d 5 mm) thick Per Rft. 148.50 11,153.95 Per Metre 487.10 36,584.95
j) 10" i/d, ¼" (250 mm i/d 6 mm) thick Per Rft. 148.50 12,628.50 Per Metre 487.10 41,421.50
chapter-23(Tubewell).xls Page 145
MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

k) 12" i/d, ¼" (300 mm i/d 6 mm) thick Per Rft. 149.95 16,241.45 Per Metre 491.75 53,271.95
l) 15" i/d, ¼" (375 mm i/d 6 mm) thick Per Rft. 173.25 19,985.75 Per Metre 568.30 65,553.25
m) 18" i/d, ¼" (450 mm i/d 6 mm) thick Per Rft. 173.25 22,771.65 Per Metre 568.30 74,691.05
n) 20" i/d, ¼" (500 mm i/d 6 mm) thick Per Rft. 205.95 25,108.35 Per Metre 675.45 82,355.35
o) 22" i/d, ¼" (550 mm i/d 6 mm) thick Per Rft. 207.35 28,855.65 Per Metre 680.10 94,646.60
10 Providing and installing M.S. Bail plug in tubewell bore In the case of increase or decrease
hole: in the length of Bail plug, the rates
will be increased or decreased as
a) 2" i/d, 1.5 ft. (50 mm i/d 450 mm) long. Each 257.30 1,053.15 Each 257.30 1,053.15 per rates given in serial No. 14 of
b) 3" i/d, 1.5 ft. (75 mm i/d 450 mm) long. Each 257.30 1,366.55 Each 257.30 1,366.55 this chapter for the respective
c) 4" i/d, 2 ft. (100 mm i/d 600 mm) long. Each 429.45 2,447.25 Each 429.45 2,447.25 diameter.
d) 5" i/d, 2 ft. (125 mm i/d 600 mm) long. Each 429.45 3,047.55 Each 429.45 3,047.55
e) 6" i/d, 2 ft. (150 mm i/d 600 mm) long. Each 581.40 3,802.75 Each 581.40 3,802.75
f) 7" i/d, 2 ft. (175 mm i/d 600 mm) long. Each 581.40 4,393.95 Each 581.40 4,393.95
g) 8" i/d, 2 ft. (200 mm i/d 600 mm) long Each 714.55 4,906.15 Each 714.55 4,906.15
h) 9" i/d, 2 ft. (225 mm i/d 600 mm) long Each 714.55 5,314.60 Each 714.55 5,314.60
i) 10" i/d, 2 ft. (250 mm i/d 600 mm) long Each 714.55 6,661.95 Each 714.55 6,661.95
j) 12" i/d, 2 ft. (300 mm i/d 600 mm) long Each 857.65 8,017.85 Each 857.65 8,017.85
k) 15" i/d, 2 ft. (375 mm i/d 600 mm) long Each 857.65 9,740.10 Each 857.65 9,740.10
l) 18" i/d, 2 ft. (450 mm i/d 600 mm) long Each 1,033.45 11,396.55 Each 1,033.45 11,396.55
m) 20" i/d, 2 ft. (500 mm i/d 600 mm) long Each 1,122.90 12,486.80 Each 1,122.90 12,486.80
n) 22" i/d, 2 ft. (550 mm i/d 600 mm) long Each 1,122.90 13,762.50 Each 1,122.90 13,762.50

11 Providing and installing, P.V.C. strainer B.S.S. Class 'B', Chap. 2


in tubewell bore hole, including sockets and solvents, etc.
complete:-

a) 3" i/d (75 mm) Per Rft. 40.85 175.25 Per Metre 134.05 574.90
b) 4" i/d (100 mm) Per Rft. 46.35 254.65 Per Metre 152.00 835.30
c) 5" i/d (125 mm) Per Rft. 48.80 337.75 Per Metre 160.05 1,107.85
d) 6" i/d (150 mm) Per Rft. 56.80 433.10 Per Metre 186.30 1,420.65
e) 8" i/d (200 mm) Per Rft. 76.45 1,017.25 Per Metre 250.80 3,336.60
f) 10" i/d (250 mm) Per Rft. 78.10 1,422.10 Per Metre 256.15 4,664.45
g) 12" i/d (300 mm) Per Rft. 78.10 2,026.90 Per Metre 256.15 6,648.20

12 Providing and installing P.V.C. strainer B.S.S. Class `D' ,


in tubewell bore hole, including sockets and solvent, etc.
complete:-

a) 1¼" i/d (30 mm) Per Rft. 28.65 82.40 Per Metre 94.00 270.35
b) 1½" i/d (40 mm) Per Rft. 29.25 89.75 Per Metre 95.95 294.30
c) 2" i/d (50 mm) Per Rft. 29.50 130.30 Per Metre 96.70 427.30
d) 3" i/d (75 mm) Per Rft. 40.90 255.95 Per Metre 134.15 839.45
e) 4" i/d (100 mm) Per Rft. 46.25 409.10 Per Metre 151.65 1,341.85
f) 5" i/d (125 mm) Per Rft. 48.80 586.40 Per Metre 160.00 1,923.35
g) 6" i/d (150 mm) Per Rft. 83.80 823.00 Per Metre 274.85 2,699.40

chapter-23(Tubewell).xls Page 146


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

13 Providing and installing Fiberglass Reinforced Polypropelene (FRP) Specified wall thickness from 2" to 10"dia is
strainer of specifid wall thickness having slot size of 0.9 mm to 1.10 mm in 6 mm and 12" to 18" dia is 8 mm.
Tubewell borehole i/c the cost of male/female coupling with Nylone
Strip,studs complete in all respect as approved and directed by the Engineer
Incharge.
i) 2" inch dia (5 mm thickness) Per Rft 189.20 789.20 Meter 620.65 2,588.65
ii) 3" inch dia (5 mm thickness) Per Rft 189.20 1,059.20 Meter 620.65 3,474.25
iii) 4" inch dia (5 mm thickness) Per Rft 189.20 1,269.20 Meter 620.65 4,163.05
iv) 6" inch dia (5 mm thickness) Per Rft 189.20 1,852.40 Meter 620.65 6,075.95
v) 8" inch dia (5 mm thickness) Per Rft 189.20 2,066.00 Meter 620.65 6,776.55
vi) 10" inch dia (6.35 mm thickness) Per Rft 189.20 2,892.80 Meter 620.65 9,488.45
vii) 12" inch dia (6.35 mm thickness) Per Rft 189.20 3,432.80 Meter 620.65 11,259.65
viii) 14" inch dia (6.35 mm thickness) Per Rft 199.10 3,983.90 Meter 653.05 13,067.20
ix) 16" inch dia (6.35 mm thickness) Per Rft 199.10 4,523.90 Meter 653.05 14,838.40
x) 18" inch dia (6.35 mm thickness) Per Rft 212.30 5,078.30 Meter 696.30 16,656.80

14 Providing and installing P.V.C. Bail/End plug, in tubewell


bore hole:-

a) B.S.S. Class `B'


i) 3" i/d (75 mm) Each 19.15 86.35 Each 19.15 86.35
ii) 4" i/d (100 mm) Each 21.35 115.45 Each 21.35 115.45
iii) 5" i/d (125 mm) Each 23.20 171.05 Each 23.20 171.05
iv) 6" i/d (150 mm) Each 29.20 244.25 Each 29.20 244.25
v) 8" i/d (200 mm) Each 34.65 478.20 Each 34.65 478.20
vi) 10" i/d (250 mm) Each 36.55 654.80 Each 36.55 654.80
vii) 12" i/d (300 mm) Each 41.80 888.55 Each 41.80 888.55
viii) 14" i/d (350 mm) Each 41.80 915.40 Each 41.80 915.40

b) B.S.S. Class `D'


i) 1¼" i/d (30 mm) Each 13.40 53.75 Each 13.40 53.75
ii) 1½" i/d (40 mm) Each 14.10 81.30 Each 14.10 81.30
iii) 2" i/d (50 mm) Each 14.55 95.20 Each 14.55 95.20
iv) 3" i/d (75 mm) Each 19.15 126.65 Each 19.15 126.65
v) 4" i/d (100 mm) Each 21.40 155.80 Each 21.40 155.80
vi) 5" i/d (125 mm) Each 23.25 224.85 Each 23.25 224.85
vii) 6" i/d (150 mm) Each 29.25 298.05 Each 29.25 298.05

15 Providing and installing M.S. blind pipe socketed/welded Chap.


joint, M.S. reducer (where necessary), in tubewell bore 2
hole, including jointing/welding with strainer, etc.
complete:-

a) 2" i/d, 1/8" (50 mm i/d 3 mm) thick Per Rft. 154.40 584.00 Per Metre 506.45 1,915.50
b) 3" i/d, 1/8" (75 mm i/d 3 mm) thick Per Rft. 154.40 778.40 Per Metre 506.45 2,553.15
c) 4" i/d, 1/8" (100 mm i/d 3 mm) thick Per Rft. 193.10 1,007.90 Per Metre 633.35 3,305.90
d) 5" i/d, 3/16" (125 mm i/d 5 mm) thick Per Rft. 193.10 1,882.70 Per Metre 633.35 6,175.25
e) 6" i/d, 3/16" (150 mm i/d 5 mm) thick Per Rft. 275.60 2,325.20 Per Metre 903.95 7,626.65
f) 7" i/d, 3/16" (175 mm i/d 5 mm) thick Per Rft. 275.60 2,607.20 Per Metre 903.95 8,551.60
g) 8" i/d, 3/16" (200 mm i/d 5 mm) thick Per Rft. 321.60 2,886.00 Per Metre 1,054.85 9,466.10
chapter-23(Tubewell).xls Page 147
MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

h) 9" i/d, 3/16" (225 mm i/d 5 mm) thick Per Rft. 321.60 3,135.60 Per Metre 1,054.85 10,284.75
i) 10" i/d, ¼" (250 mm i/d 6 mm) thick Per Rft. 321.60 4,014.00 Per Metre 1,054.85 13,165.90
j) 12" i/d, ¼" (300 mm i/d 6 mm) thick Per Rft. 385.95 4,729.95 Per Metre 1,265.90 15,514.25
k) 15" i/d, ¼" (375 mm i/d 6 mm) thick Per Rft. 385.95 5,825.55 Per Metre 1,265.90 19,107.80
l) 18" i/d, ¼" (450 mm i/d 6 mm) thick Per Rft. 473.85 7,234.65 Per Metre 1,554.25 23,729.65
m) 20" i/d, ¼" (500 mm i/d 6 mm) thick Per Rft. 510.05 8,020.85 Per Metre 1,672.95 26,308.40
n) 22" i/d, ¼" (550 mm i/d 6 mm) thick Per Rft. 510.05 8,772.05 Per Metre 1,672.95 28,772.30

16 Providing and installing P.V.C. blind pipe, B.S.S. Class ditto


`B', in tubewell bore hole, including sockets and solvents
and jointing with strainer, etc. complete.

a) 3" i/d (75 mm) Per Rft. 55.35 320.55 Per Metre 181.60 1,051.45
b) 4" i/d (100 mm) Per Rft. 62.40 484.80 Per Metre 204.65 1,590.10
c) 5" i/d (125 mm) Per Rft. 64.85 664.85 Per Metre 212.75 2,180.75
d) 6" i/d (150 mm) Per Rft. 76.70 919.10 Per Metre 250.10 3,013.15
e) 8" i/d (200 mm) Per Rft. 101.55 1,379.55 Per Metre 333.10 4,524.95
f) 10" i/d (250 mm) Per Rft. 105.40 2,227.00 Per Metre 345.75 7,304.60
g) 12" i/d (300 mm) Per Rft. 126.25 3,095.05 Per Metre 414.10 10,151.75
h) 14" i/d (350 mm) Per Rft. 120.60 3,688.20 Per Metre 395.50 12,097.25

17 Providing and installing P.V.C. blind pipe, B.S.S. Class


`D', in tubewell bore hole, including sockets and solvents
and jointing with strainer, etc. complete.
a) 1¼" i/d (30 mm) Per Rft. 34.65 129.45 Per Metre 113.70 424.65
b) 1½" i/d (40 mm) Per Rft. 35.20 158.80 Per Metre 115.50 520.90
c) 2" i/d (50 mm) Per Rft. 37.40 230.60 Per Metre 122.70 756.40
d) 3" i/d (75 mm) Per Rft. 46.80 480.00 Per Metre 153.45 1,574.35
e) 4" i/d (100 mm) Per Rft. 62.40 795.60 Per Metre 204.65 2,609.50
f) 5" i/d (125 mm) Per Rft. 64.85 1,159.25 Per Metre 212.75 3,802.35
g) 6" i/d (150 mm) Per Rft. 77.65 1,684.45 Per Metre 254.75 5,525.05

18 Testing and developing of tubewell of size 6" (150 mm) Compressor, accessories along with
i/d and above continuously. working staff, to be supplied by
Government.
i) upto 1.5 cs. discharge Per 2,828.55 Per 2,828.55
Hour Hour
ii) above 1.5 cs. discharge ditto 3,409.50 ditto 3,409.50

19 Shrouding with graded pea gravel 3/8" to 1/8" (10 to 3 Per Cft. 69.40 156.35 cu.m 2,451.20 5,522.25 The rate includes wastage, etc.
mm), around tubewell in bore hole.

20 Providing, laying, cutting, jointing, testing and disinfecting cast iron Chap.
pipe line (BS-2035) in trenches, with spigot and socket caulked lead 2
joints, including cost of materials, such as lead, yarn, etc.
complete in all respects:-

a) 3" (75 mm) i/d Per Rft. 1,205.85 Per Metre 3,955.15
b) 4" (100 mm) i/d Per Rft. 1,518.05 Per Metre 4,979.15
chapter-23(Tubewell).xls Page 148
MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

c) 5" (125 mm) i/d Per Rft. 1,904.00 Per Metre 6,245.10
d) 6" (150 mm) i/d Per Rft. 2,202.75 Per Metre 7,225.05
e) 8" (200 mm) i/d Per Rft. 3,772.85 Per Metre 12,374.90
f) 10" (250 mm) i/d Per Rft. 5,041.70 Per Metre 16,536.75
g) 12" (300 mm) i/d Per Rft. 9,930.75 Per Metre 32,572.90
h) 15" (375 mm) i/d Per Rft. 12,904.30 Per Metre 42,326.10
i) 18" (450 mm) i/d Per Rft. 16,879.50 Per Metre 55,364.75

21 Providing, laying, cutting, jointing, testing and disinfecting cast iron ditto
pipe line (BS-2035) in trenches, with flanged and flanged joints,
complete in all respects:-

a) 3" (75 mm) i/d Per Rft. 1,148.85 Per Metre 3,768.15
b) 4" (100 mm) i/d Per Rft. 1,441.15 Per Metre 4,726.95
c) 5" (125 mm) i/d Per Rft. 1,812.50 Per Metre 5,945.00
d) 6" (150 mm) i/d Per Rft. 2,090.15 Per Metre 6,855.70
e) 8" (200 mm) i/d Per Rft. 3,636.80 Per Metre 11,928.65
f) 10" (250 mm) i/d Per Rft. 4,821.10 Per Metre 15,813.25
g) 12" (300 mm) i/d Per Rft. 9,672.20 Per Metre 31,724.80
h) 15" (375 mm) i/d Per Rft. 12,589.15 Per Metre 41,292.35
i) 18" (450 mm) i/d Per Rft. 16,460.25 Per Metre 53,989.60
22 Providing, laying, cutting, jointing, testing and disinfecting cast iron Chap. 2
pipe line (BS-2035) in trenches with Tyton joints, complete in all
respects:-

a) 3" (75 mm) i/d Per Rft. 1,123.45 Per Metre 3,684.95
b) 4" (100 mm) i/d Per Rft. 1,413.50 Per Metre 4,636.35
c) 5" (125 mm) i/d Per Rft. 1,773.35 Per Metre 5,816.55
d) 6" (150 mm) i/d Per Rft. 2,047.30 Per Metre 6,715.10
e) 8" (200 mm) i/d Per Rft. 3,593.20 Per Metre 11,785.60
f) 10" (250 mm) i/d Per Rft. 4,755.90 Per Metre 15,599.35
g) 12" (300 mm) i/d Per Rft. 9,595.60 Per Metre 31,473.60
h) 15" (375 mm) i/d Per Rft. 12,479.85 Per Metre 40,933.85
i) 18" (450 mm) i/d Per Rft. 16,308.75 Per Metre 53,492.65

23 Providing, laying, cutting, jointing, testing and disinfecting Chap. Cost of sockets, tees, elbows,
G.I. pipeline in trenches, with socket joints, using G.I. 2 bends, valves, crosses, unions and
pipes of B.S.S. 1387-1967 complete in all respects, with plugs, etc. is included in the rates.
specials and valves.

i) Light Quality
a) ½" i/d (15 mm) 2mm thick Per Rft. 15.25 138.65 Per Metre 50.00 454.75
b) ¾" i/d (20 mm) 2.35mm thick Per Rft. 16.90 194.55 Per Metre 55.40 638.05
c) 1" i/d (25 mm) 2.65mm thick Per Rft. 19.30 275.60 Per Metre 63.35 904.00
d) 1¼" i/d (32 mm) 2.65mm thick Per Rft. 19.45 350.30 Per Metre 63.75 1,149.00
e) 1½" i/d (40 mm) 2.9mm thick Per Rft. 19.55 444.00 Per Metre 64.20 1,456.30
f) 2" i/d (50 mm) 2.9mm thick Per Rft. 21.60 557.20 Per Metre 70.80 1,827.65
g) 2"½ i/d (65 mm) 3.25mm thick Per Rft. 22.25 765.30 Per Metre 72.95 2,510.25
h) 3" i/d (75 mm) 3.25mm thick Per Rft. 25.35 901.35 Per Metre 83.15 2,956.35

chapter-23(Tubewell).xls Page 149


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

i) 4" i/d (100 mm) 3.65mm thick Per Rft. 27.55 1,276.40 Per Metre 90.35 4,186.65
ii) M edium Quality i.  Cost of sockets, tees, elbow,
bends, valves, crosses, unions and
a) ½" i/d (15 mm) 2.65mm thick Per Rft. 15.25 168.50 Per Metre 50.00 552.60 plugs etc is included in the rates
b) ¾" i/d (20 mm) 2.65mm thick Per Rft. 16.90 216.20 Per Metre 55.40 709.20 except for internal G.I piping (1"dia,
c) 1" i/d (25 mm) 3.25mm thick Per Rft. 19.30 324.40 Per Metre 63.35 1,064.10 3/4"dia & 1/2"dia) for Bath rooms/
d) 1¼" i/d (32 mm) 3.25mm thick Per Rft. 19.45 414.05 Per Metre 63.75 1,358.05 Lavoratary.
e) 1½" i/d (40 mm) 3.25mm thick Per Rft. 19.75 469.95 Per Metre 64.85 1,541.45
f) 2" i/d (50 mm) 3.65mm thick Per Rft. 21.60 660.25 Per Metre 70.80 2,165.70 ii.  For internal G.I piping (1"dia, 3/4"dia &
g) 2"½ i/d (65 mm) 3.65mm thick Per Rft. 22.25 845.35 Per Metre 72.95 2,772.65 Bath room(s)/ Lavoratary of rate
h) 3" i/d (75 mm) 4.05mm thick Per Rft. 25.35 1,084.40 Per Metre 83.15 3,556.80 (composite) shall be reduced by 8%
i) 4" i/d (100 mm) 4.5mm thick Per Rft. 27.55 1,565.25 Per Metre 90.35 5,134.00 and specials mentioned above may
j) 5" i/d (150 mm) 4.85mm thick Per Rft. 31.80 2,121.40 Per Metre 104.30 6,958.20 be paid at the rates placed on
k) 6" i/d (200 mm) 4.85mm thick Per Rft. 32.15 2,493.30 Per Metre 105.50 8,178.05 website as per actual quantity used.
iii) Heavy Quality

a) ½" i/d (15 mm) 3.25mm thick Per Rft. 15.25 207.80 Per Metre 50.05 681.60
b) ¾" i/d (20 mm) 3.25mm thick Per Rft. 16.90 271.80 Per Metre 55.40 891.55
c) 1" i/d (25 mm) 4.05mm thick Per Rft. 19.30 413.90 Per Metre 63.35 1,357.65
d) 1¼" i/d (32 mm) 4.05mm thick Per Rft. 19.45 533.35 Per Metre 63.75 1,749.45
e) 1½" i/d (40 mm) 4.05mm thick Per Rft. 19.75 612.35 Per Metre 64.85 2,008.50
f) 2" i/d (50 mm) 4.5mm thick Per Rft. 21.60 840.60 Per Metre 70.80 2,757.20
g) 2"½ i/d (65 mm) 4.5mm thick Per Rft. 22.25 1,066.35 Per Metre 72.95 3,497.65
h) 3" i/d (75 mm) 4.85mm thick Per Rft. 25.35 1,389.50 Per Metre 83.15 4,557.55
i) 4" i/d (100 mm) 5.4mm thick Per Rft. 27.55 1,935.45 Per Metre 90.35 6,348.25
j) 5" i/d (125 mm) 5.4mm thick Per Rft. 31.80 2,384.45 Per Metre 104.30 7,821.05
k) 6" i/d (150 mm) 5.4mm thick Per Rft. 32.15 2,873.00 Per Metre 105.50 9,423.40

24 Providing, laying, cutting, jointing, testing and disinfecting


Asbestos Cement / Fibre Cement pipe line in trenches, with PS 428 & Providing and installing specials
comet joint and rubber ring, complete in all respects:- ISO 160 and valves is not included in the
rate, which is payable separately.
B Class Working Pressure
a) 3" i/d (75 mm) Per Rft. 26.65 263.05 Per Metre 87.45 862.80
b) 4" i/d (100 mm) Per Rft. 28.35 340.65 Per Metre 92.90 1,117.35
c) 6" i/d (150 mm) Per Rft. 39.00 538.70 Per Metre 128.00 1,767.00
d) 8" i/d (200 mm) Per Rft. 53.85 897.75 Per Metre 176.70 2,944.55
e) 10" i/d (250 mm) Per Rft. 70.35 1,221.60 Per Metre 230.75 4,006.90
f) 12" i/d (300 mm) Per Rft. 89.60 1,613.20 Per Metre 293.95 5,291.25
g) 14" i/d (350 mm) Per Rft. 104.10 2,313.35 Per Metre 341.35 7,587.85
h) 16" i/d (400 mm) Per Rft. 117.75 2,930.75 Per Metre 386.15 9,612.85
i) 18" i/d (450 mm) Per Rft. 139.00 3,650.10 Per Metre 455.90 11,972.40
j) 20" i/d (500 mm) Per Rft. 163.60 4,487.60 Per Metre 536.65 14,719.30
k) 24" i/d (600 mm) Per Rft. 197.00 6,179.75 Per Metre 646.20 20,269.50
l) 28" i/d (700 mm) Per Rft. 208.80 9,868.65 Per Metre 684.95 32,369.15
m) 32" i/d (800 mm) Per Rft. 226.15 11,286.45 Per Metre 741.70 37,019.50
n) 40" i/d 1000 mm) Per Rft. 248.05 17,383.30 Per Metre 813.65 57,017.20

chapter-23(Tubewell).xls Page 150


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

25 C Class Working Pressure PS 428 &


a) 3" i/d (75 mm) Per Rft. 26.65 263.05 Per Metre 87.45 862.80 ISO 160
b) 4" i/d (100 mm) Per Rft. 28.35 372.45 Per Metre 92.90 1,221.70
c) 6" i/d (150 mm) Per Rft. 39.00 640.30 Per Metre 128.00 2,100.20
d) 8" i/d (200 mm) Per Rft. 53.85 1,009.10 Per Metre 176.70 3,309.90
e) 10" i/d (250 mm) Per Rft. 70.35 1,406.45 Per Metre 230.75 4,613.10
f) 12" i/d (300 mm) Per Rft. 89.60 1,954.70 Per Metre 293.95 6,411.35
g) 14" i/d (350 mm) Per Rft. 104.10 3,348.90 Per Metre 341.35 10,984.30
h) 16" i/d (400 mm) Per Rft. 117.75 4,273.45 Per Metre 386.15 14,017.00
i) 18" i/d (450 mm) Per Rft. 139.00 5,240.10 Per Metre 455.90 17,187.50
j) 20" i/d (500 mm) Per Rft. 163.60 6,236.70 Per Metre 536.65 20,456.35
k) 24" i/d (600 mm) Per Rft. 199.80 8,770.05 Per Metre 655.30 28,765.75
26 D Class Working Pressure PS 428 &
a) 3" i/d (75 mm) Per Rft. 26.65 263.05 Per Metre 87.45 862.80 ISO 160
b) 4" i/d (100 mm) Per Rft. 28.35 372.45 Per Metre 92.90 1,221.70
c) 6" i/d (150 mm) Per Rft. 39.00 640.30 Per Metre 128.00 2,100.20
d) 8" i/d (200 mm) Per Rft. 53.85 1,009.10 Per Metre 176.70 3,309.90
e) 10" i/d (250 mm) Per Rft. 70.35 1,406.45 Per Metre 230.75 4,613.10
f) 12" i/d (300 mm) Per Rft. 89.60 1,954.70 Per Metre 293.95 6,411.35
g) 14" i/d (350 mm) Per Rft. 104.10 3,348.90 Per Metre 341.35 10,984.30
h) 16" i/d (400 mm) Per Rft. 117.75 4,273.45 Per Metre 386.15 14,017.00
i) 18" i/d (450 mm) Per Rft. 139.00 5,240.10 Per Metre 455.90 17,187.50
j) 20" i/d (500 mm) Per Rft. 163.60 6,236.70 Per Metre 536.65 20,456.35
27 Providing, laying, cutting, jointing, testing and disinfecting PS 3051 Providing and installing specials
PVC/ uPVC pipe line with `B' Class working pressure BS 3505 and valves is not included in the
pipe, in trenches, complete in all respects:- rate, which is payable separately.
a) 3" i/d (75 mm) Per Rft. 7.80 278.35 Per Metre 25.65 912.90
b) 4" i/d (100 mm) Per Rft. 10.10 440.95 Per Metre 33.20 1,446.35
c) 5" i/d (125 mm) Per Rft. 12.30 624.30 Per Metre 40.35 2,047.70
d) 6" i/d (150 mm) Per Rft. 12.70 871.95 Per Metre 41.70 2,860.05
e) 8" i/d (200 mm) Per Rft. 18.10 1,321.65 Per Metre 59.30 4,335.00
f) 10" i/d (250 mm) Per Rft. 24.35 2,188.40 Per Metre 79.90 7,177.95
h) 12" i/d (300 mm) Per Rft. 30.25 3,058.45 Per Metre 99.25 10,031.70
g) 14" i/d (350 mm) Per Rft. 39.45 3,678.45 Per Metre 129.45 12,065.25
28 Providing, laying, cutting, jointing, testing and disinfecting Chap Providing and installing specials
pipe line in trenches with PVC/ uPVC pipes of B.S.S. with `D' 2 and valves is not included in the
Class working pressure complete in all respects:- rate, which is payable separately.
a) 2" i/d (50 mm) Per Rft. 6.60 203.70 Per Metre 21.70 668.05
b) 3" i/d (75 mm) Per Rft. 8.10 449.95 Per Metre 26.60 1,475.90
c) 4" i/d (100 mm) Per Rft. 10.45 758.30 Per Metre 34.25 2,487.20
d) 5" i/d (125 mm) Per Rft. 12.75 1,129.00 Per Metre 41.75 3,703.20
e) 6" i/d (150 mm) Per Rft. 13.20 1,652.15 Per Metre 43.35 5,419.10

chapter-23(Tubewell).xls Page 151


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

29 Providing and fixing cast iron special of B.S.S. Class `B' 9.1 i) Labour rates include the cost of
(such as bend, tee cross collar, reducer, tail piece, jointing material & labour.
flanged spigot, cap, flanged socket, taper, angle branch,
plug etc.) for cast iron pipe line , complete:- ii) The internal dia of the pipe, from
which the branch is taken out will
a) C.I.S.S. Specials, with spigot. and be considered the internal dia for
socket joint:- the purpose of payments of
i) 3" to 6" (75 to 150 mm) i/d Per Kg. 43.35 149.65 Per Kg 43.35 149.65 specials.
ii) 8" to 12" (200 to 300 mm) i/d Per Kg. 23.75 130.05 Per Kg 23.75 130.05
iii) 15" to 18" (375 to 450 mm) i/d Per Kg. 18.70 125.00 Per Kg 18.70 125.00
b) C.I. flanged specials, with flanged and
flanged joints:-

i) 3" to 6" (75 to 150 mm) i/d Per Kg 16.75 123.05 Per Kg 16.75 123.05
ii) 8" to 12" (200 to 300 mm) i/d Per Kg 3.40 109.70 Per Kg 3.40 109.70
iii) 15" to 18" (375 to 450 mm) i/d Per Kg 7.35 109.70 Per Kg 7.35 109.70

c) C.I. Specials, with tyton joints:-

i) 3" to 6" (75 to 150 mm) i/d Per Kg 26.90 133.20 Per Kg 26.90 133.20
ii) 8" to 12" (200 to 300 mm) i/d Per Kg 26.90 133.20 Per Kg 26.90 133.20
iii) 15" to 18" (375 to 450 mm) i/d Per Kg 26.90 133.20 Per Kg 26.90 133.20

30 Providing and fixing cast iron specials of B.S.S. Class 'B' 9.1 1) Labour rates include the cost of
(such as bend, tee, cross collar, reducer, tail piece, jointing material and labour.
flanged socket, flanged spigot, cap, taper, angle branch,
plug, etc) for Asbestos cement pipe line, with comet joint 2) The internal dia of the pipe, from
and rubber ring, complete. which the branch is taken out, will
i) 3" to 6" (75 to 150 mm) i/d Per Kg 18.35 124.65 Per Kg 18.35 124.65 be considered the internal dia for
ii) 8" to 18" (200 to 450 mm) i/d Per Kg 9.10 115.40 Per Kg 9.10 115.40 the purpose of payment.
iii) 20" to 24" (500 to 600 mm) i/d Per Kg 7.10 113.40 Per Kg 7.10 113.40

31 Providing and fixing sluice valve of B.S.S. quality and 9.1 Labour rates include cost of jointing
weight, Class `B', for cast iron pipe line, and Asbestos material and labour.
cement pipe line (including cost of jointing material):-
a) 3" i/d (75 mm) Each 1,750.30 16,750.30 Each 1,750.30 16,750.30
b) 4" i/d (100 mm) Each 1,904.75 18,404.75 Each 1,904.75 18,404.75
c) 5" i/d (125 mm) Each 3,428.55 24,428.55 Each 3,428.55 24,428.55
d) 6" i/d (150 mm) Each 3,655.10 31,405.10 Each 3,655.10 31,405.10
e) 8" i/d (200 mm) Each 4,267.70 44,767.70 Each 4,267.70 44,767.70
f) 10" i/d (250 mm) Each 6,841.40 61,591.40 Each 6,841.40 61,591.40
g) 12" i/d (300 mm) Each 7,687.90 88,687.90 Each 7,687.90 88,687.90
h) 16" i/d (400 mm) Each 10,196.65 130,196.65 Each 10,196.65 130,196.65
i) 18" i/d (450 mm) Each 11,735.80 203,735.80 Each 11,735.80 203,735.80

chapter-23(Tubewell).xls Page 152


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

32 Providing and fixing, sluice valve of B.S.S. quality and Labour rates include cost of jointing
weight, for Asbestos cement pipe line, with comet joint 9.1 material and labour.
and rubber ring, complete (including cost of jointing
materials):-
a) 3" i/d (75 mm) Each 760.75 10,000.75 Each 760.75 10,000.75
b) 4" i/d (100 mm) Each 900.00 11,460.00 Each 900.00 11,460.00
c) 6" i/d (150 mm) Each 1,087.40 18,247.40 Each 1,087.40 18,247.40
d) 8" i/d (200 mm) Each 1,722.30 33,402.30 Each 1,722.30 33,402.30
e) 10" i/d (250 mm) Each 2,125.50 44,365.50 Each 2,125.50 44,365.50
f) 12" i/d (300 mm) Each 2,620.90 55,420.90 Each 2,620.90 55,420.90
g) 16" i/d (400 mm) Each 3,055.15 106,015.15 Each 3,055.15 106,015.15
h) 18" i/d (450 mm) Each 3,573.40 173,853.40 Each 3,573.40 173,853.40
33 Each 2,989.80 49,848.30 Each 2,989.80 49,848.30
Supply, installation, testing, and commissioning of Garden/fire Hydrants
made by Haseen Habib / Teepu Engineering or equivalent, according to
Labour rates include cost of jointing
B.S.S. 750 standard double delivery type having 4" dia barrel with 2 Nos. 2-
material.
1/2" valve including the cost of jointing material with all fittings and
accessories complete in all respect as approved by the Engineer Incharge.

34 Providing and fixing, air valve 2½ (65mm) dia of B.S.S. 9.1


quality and weight (complete with jointing material).

a) single Each 211.15 5,011.15 Each 211.15 5,011.15

b) double Each 211.15 11,461.15 Each 211.15 11,461.15

35 Providing and fitting C.I. flanges on pipes, including


turning, threading, facing and fitting, etc. complete in all 9.1
respects:-

a) 3" to 6" (75 to 150 mm) i/d Per Kg 71.70 160.25 Per Kg 71.70 160.25

b) 8" to 12" (200 to 300 mm) i/d Per Kg 45.50 134.05 Per Kg 45.50 134.05

c) 15" to 18" (375 to 450 mm) i/d Per Kg 38.25 126.80 Per Kg 38.25 126.80

36 Cutting C.I. pipe, and welding spigot or socket, flanged or


tyton end, after finishing ends of pipes:
Per Inch Per cm i/d
a) 3" to 6" (75 to 150 mm) i/d i/d of pipe 110.85 of pipe 44.35
b) 8" to 12" (200 to 300 mm) i/d ditto 141.95 ditto 56.80
c) 15" to 18" (375 to 450 mm) i/d ditto 129.60 ditto 51.85

chapter-23(Tubewell).xls Page 153


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

37 Providing, laying, cutting, jointing, testing and disinfecting Cost of sockets, tees, elbows,
G.I. pipe line in trenches, with flanged joints, using G.I. bends, valves, crosses, unions and
pipe of B.S.S. 1387-1967 complete in all respects, plugs, etc. is included in the rates.
including specials and valves:-

i) G.I. flanged joints (Heavy Quality)


a) 1½" i/d (40 mm) Per Rft. 29.70 622.30 Per Metre 97.45 2,041.05
b) 2" i/d (50 mm) Per Rft. 29.70 848.75 Per Metre 97.45 2,783.85
c) 2½" i/d (65 mm) Per Rft. 30.90 1,075.00 Per Metre 101.35 3,526.10
d) 3" i/d (75 mm) Per Rft. 31.05 1,395.15 Per Metre 101.80 4,576.15
e) 4" i/d (100 mm) Per Rft. 37.10 1,945.00 Per Metre 121.65 6,379.55
f) 6" i/d (150 mm) Per Rft. 43.05 2,395.75 Per Metre 141.25 7,858.00
g) 8" i/d (200 mm) Per Rft. 43.10 2,883.90 Per Metre 141.45 9,459.25
ii) C.I. flanged joints (Medium Quality)

a) 1½" i/d (40 mm) Per Rft. 34.80 536.80 Per Metre 114.20 1,760.70
b) 2" i/d (50 mm) Per Rft. 32.40 744.55 Per Metre 106.25 2,442.10
c) 2½" i/d (65 mm) Per Rft. 35.90 953.70 Per Metre 117.75 3,128.10
d) 3" i/d (75 mm) Per Rft. 35.95 1,216.85 Per Metre 117.95 3,991.20
e) 4" i/d (100 mm) Per Rft. 42.45 1,757.10 Per Metre 139.30 5,763.20
f) 6" i/d (150 mm) Per Rft. 48.90 2,378.90 Per Metre 160.35 7,802.70
g) 8" i/d (200 mm) Per Rft. 49.20 2,793.50 Per Metre 161.35 9,162.60
38 Providing and installing P.V.C. bends, of B.S.S.

i) Class `B' working pressure:-


a) 3" i/d (75 mm) Each 167.95 335.95 Each 167.95 335.95
b) 4" i/d (100 mm) Each 186.30 546.30 Each 186.30 546.30
c) 5" i/d (125 mm) Each 232.90 976.90 Each 232.90 976.90
d) 6" i/d (150 mm) Each 238.80 1,306.80 Each 238.80 1,306.80
ii) Class `D' working pressure:-
a) 1¼" i/d (30 mm) Each 118.40 164.00 Each 118.40 164.00
b) 1½" i/d (40 mm) Each 124.60 175.00 Each 124.60 175.00
c) 2" i/d (50 mm) Each 131.65 233.65 Each 131.65 233.65
d) 3" i/d (75 mm) Each 167.95 433.15 Each 167.95 433.15
e) 4" i/d (100 mm) Each 186.30 798.30 Each 186.30 798.30
f) 5" i/d (125 mm) Each 232.90 1,552.90 Each 232.90 1,552.90
g) 6" i/d (150 mm) Each 238.80 2,194.80 Each 238.80 2,194.80
39 Providing and installing P.V.C. tees, of B.S.S.
i) Class `B' working pressure:-
a) 3" i/d (80 mm) Each 251.95 899.95 Each 251.95 899.95
b) 4" i/d (100 mm) Each 282.20 1,590.20 Each 282.20 1,590.20
c) 5" i/d (125 mm) Each 345.30 2,967.30 Each 345.30 2,967.30
d) 6" i/d (150 mm) Each 358.20 3,022.20 Each 358.20 3,022.20
ii) Class `D' working pressure:-
a) 1¼" i/d (30 mm) Each 179.80 365.80 Each 179.80 365.80
b) 1½" i/d (40 mm) Each 187.30 397.30 Each 187.30 397.30

chapter-23(Tubewell).xls Page 154


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

c) 2" i/d (50 mm) Each 196.85 478.85 Each 196.85 478.85
d) 3" i/d (75 mm) Each 251.95 851.95 Each 251.95 851.95
e) 4" i/d (100 mm) Each 282.20 1,590.20 Each 282.20 1,590.20
f) 5" i/d (125 mm) Each 345.30 2,907.30 Each 345.30 2,907.30
g) 6" i/d (150 mm) Each 358.20 3,058.20 Each 358.20 3,058.20

40 Providing and installing P.V.C. sockets, B.S.S.

i) Class `B' working pressure:-


a) 3" i/d (75 mm) Each 110.20 227.80 Each 110.20 227.80
b) 4" i/d (100 mm) Each 128.55 332.55 Each 128.55 332.55
c) 5" i/d (125 mm) Each 160.70 448.70 Each 160.70 448.70
d) 6" i/d (150 mm) Each 166.60 550.60 Each 166.60 550.60
e) 8" i/d (200 mm) Each 237.85 1,125.85 Each 237.85 1,125.85
f) 10" i/d (250 mm) Each 273.25 2,673.25 Each 273.25 2,673.25
g) 12" i/d (300 mm) Each 317.80 6,017.80 Each 317.80 6,017.80
h) 14" i/d (350 mm) Each 351.50 4,851.50 Each 351.50 4,851.50
ii) Class `D' working pressure:-
a) 1¼" i/d (30 mm) Each 70.25 100.25 Each 70.25 100.25
b) 1½" i/d (40 mm) Each 76.45 118.45 Each 76.45 118.45
c) 2" i/d (50 mm) Each 83.55 149.55 Each 83.55 149.55
d) 3" i/d (75 mm) Each 110.20 326.20 Each 110.20 326.20
e) 4" i/d (100 mm) Each 128.55 500.55 Each 128.55 500.55
f) 5" i/d (125 mm) Each 160.70 868.70 Each 160.70 868.70
g) 6" i/d (150 mm) Each 166.60 1,354.60 Each 166.60 1,354.60
41 Providing and installing P.V.C. Tapered core, B.S.S.
i) Class `B' working pressure:-
a) 3" i/d (75 mm) Each 167.95 225.55 Each 167.95 225.55
b) 4" i/d (100 mm) Each 186.30 260.70 Each 186.30 260.70
c) 5" i/d (125 mm) Each 232.90 322.90 Each 232.90 322.90
d) 6" i/d (150 mm) Each 238.80 352.80 Each 238.80 352.80
e) 8" i/d (200 mm) Each 334.15 520.15 Each 334.15 520.15
f) 10" i/d (250 mm) Each 369.55 609.55 Each 369.55 609.55
g) 12" i/d (300 mm) Each 433.30 709.30 Each 433.30 709.30
h) 14" i/d (350 mm) Each 467.05 827.05 Each 467.05 827.05
ii) Class `D' working pressure:-
a) 1¼" i/d (30 mm) Each 118.40 147.20 Each 118.40 147.20
b) 1½" i/d (40 mm) Each 124.60 163.00 Each 124.60 163.00
c) 2" i/d (50 mm) Each 131.65 180.85 Each 131.65 180.85
42 Making connection for new watersupply lines with the The rate includes the component of
running main, including excavation of trench and refilling, bailing out water from the trench
complete, but excluding cost of pipe and specials, etc. and cutting of existing pipe line.
Diameter of running main:
Per Per
i) upto 6" i/d (150 mm) Connection 2,976.60 Connection 2,976.60
ii) upto 8" i/d (200 mm) ditto 3,740.90 ditto 3,740.90
iii) upto 10" i/d (250 mm) ction 5,316.30 ction 5,316.30
chapter-23(Tubewell).xls Page 155
MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

iv) upto 12" i/d (300 mm) ditto 7,227.00 ditto 7,227.00
v) upto 16" i/d (400 mm) ditto 8,897.95 ditto 8,897.95
vi) upto 20" i/d (500 mm) ditto 11,477.40 ditto 11,477.40
vii) upto 24" i/d (600 mm) ditto 13,817.10 ditto 13,817.10
Providing, laying, cutting, jointing, testing and disinfecting High Density
Polyethylene Pipe (HDPE-100) working presure pipe, Beta/ Dadex/
Popular/ I I L or equivalent, in trenches, as approved & directed by the
43 engineer incharge, complete in all respects.
a) PN-6 (SDR-26)
i) 90 mm P.Rft 4.60 162.20 PM 12.55 532.10
ii) 110 mm P.Rft 12.85 244.35 PM 35.10 801.75
iii) 125 mm P.Rft 14.20 312.45 PM 38.80 1,025.10
iv) 160 mm P.Rft 15.60 502.50 PM 42.65 1,648.65
v) 180 mm P.Rft 20.00 636.45 PM 54.70 2,088.20
vi) 200 mm P.Rft 22.35 787.50 PM 61.10 2,583.80
vii) 225 mm P.Rft 25.50 988.30 PM 69.70 3,242.60
viii) 250 mm P.Rft 35.20 1,227.60 PM 96.30 4,027.70
ix) 315 mm P.Rft 62.45 1,952.65 PM 170.70 6,406.65
x) 355 mm P.Rft 69.45 2,459.80 PM 189.85 8,070.55
xi) 400 mm P.Rft 78.60 3,112.15 PM 214.95 10,211.05
xii) 450 mm P.Rft 79.85 3,926.10 PM 218.40 12,881.50
xiii) 500 mm P.Rft 94.05 4,849.65 PM 257.10 15,911.75
xiv) 560 mm P.Rft 104.40 6,094.75 PM 285.40 19,996.90
xv) 630 mm P.Rft 117.10 7,686.25 PM 320.15 25,218.50
xvi) 710 mm P.Rft 132.65 9,806.70 PM 362.65 32,175.70
xvii) 800 mm P.Rft 150.45 12,366.05 PM 411.30 40,573.05
xviii) 900 mm P.Rft 189.25 15,809.25 PM 517.45 51,870.20
xix) 1000 mm P.Rft 219.70 19,368.80 PM 600.70 63,549.00
b) PN-8 (SDR-21)
i) 90 mm P.Rft 4.60 196.10 PM 12.55 643.40
ii) 110 mm P.Rft 12.85 300.45 PM 35.10 985.80
iii) 125 mm P.Rft 14.20 381.80 PM 38.80 1,252.65
iv) 160 mm P.Rft 15.60 620.65 PM 42.65 2,036.35
v) 180 mm P.Rft 20.00 780.30 PM 54.70 2,560.20
vi) 200 mm P.Rft 22.35 965.00 PM 61.10 3,166.15
vii) 225 mm P.Rft 25.50 1,218.05 PM 69.70 3,996.45
viii) 250 mm P.Rft 35.20 1,494.05 PM 96.30 4,901.95
ix) 315 mm P.Rft 62.45 2,372.35 PM 170.70 7,783.60
x) 355 mm P.Rft 69.45 3,003.90 PM 189.85 9,855.75
xi) 400 mm P.Rft 78.60 3,822.75 PM 214.95 12,542.45
xii) 450 mm P.Rft 79.85 4,825.50 PM 218.40 15,832.50
xiii) 500 mm P.Rft 94.05 5,960.15 PM 257.10 19,555.20
xiv) 560 mm P.Rft 104.40 7,475.60 PM 285.40 24,527.35
xv) 630 mm P.Rft 117.10 9,407.65 PM 320.15 30,866.50
xvi) 710 mm P.Rft 132.65 12,018.05 PM 362.65 39,431.15
xvii) 800 mm P.Rft 150.45 15,178.65 PM 411.30 49,801.15
xviii) 900 mm P.Rft 189.25 19,313.40 PM 517.45 63,367.20
xix) 1000 mm P.Rft 219.70 23,822.00 PM 600.70 78,160.00

chapter-23(Tubewell).xls Page 156


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

c) PN-10 (SDR-17)
i) 90 mm P.Rft 4.60 240.85 PM 12.55 790.25
ii) 110 mm P.Rft 12.85 364.65 PM 35.10 1,196.45
iii) 125 mm P.Rft 14.20 463.00 PM 38.80 1,519.05
iv) 160 mm P.Rft 15.60 752.25 PM 42.65 2,468.20
v) 180 mm P.Rft 20.00 951.85 PM 54.70 3,122.95
vi) 200 mm P.Rft 22.35 1,172.85 PM 61.10 3,848.15
vii) 225 mm P.Rft 25.50 1,486.00 PM 69.70 4,875.65
viii) 250 mm P.Rft 35.20 1,824.55 PM 96.30 5,986.40
ix) 315 mm P.Rft 62.45 2,904.80 PM 170.70 9,530.70
x) 355 mm P.Rft 69.45 3,688.60 PM 189.85 12,102.25
xi) 400 mm P.Rft 78.60 4,654.90 PM 214.95 15,272.70
xii) 450 mm P.Rft 79.85 5,888.40 PM 218.40 19,319.85
xiii) 500 mm P.Rft 94.05 7,281.95 PM 257.10 23,892.05
xiv) 560 mm P.Rft 104.40 9,138.50 PM 285.40 29,983.35
xv) 630 mm P.Rft 117.10 11,537.95 PM 320.15 37,856.00
xvi) 710 mm P.Rft 132.65 14,684.75 PM 362.65 48,180.60
xvii) 800 mm P.Rft 150.45 18,566.10 PM 411.30 60,915.35
xviii) 900 mm P.Rft 189.25 23,593.55 PM 517.45 77,410.35
xix) 1000 mm P.Rft 219.70 29,119.95 PM 600.70 95,542.55
d) PN-12.5 (SDR-13.6)
i) 90 mm P.Rft 4.60 291.75 PM 12.55 957.25
ii) 110 mm P.Rft 12.85 440.75 PM 35.10 1,446.05
iii) 125 mm P.Rft 14.20 565.30 PM 38.80 1,854.65
iv) 160 mm P.Rft 15.60 913.50 PM 42.65 2,997.25
v) 180 mm P.Rft 20.00 1,163.35 PM 54.70 3,816.85
vi) 200 mm P.Rft 22.35 1,424.80 PM 61.10 4,674.75
vii) 225 mm P.Rft 25.50 1,807.15 PM 69.70 5,929.30
viii) 250 mm P.Rft 35.20 2,228.90 PM 96.30 7,312.95
ix) 315 mm P.Rft 62.45 3,533.35 PM 170.70 11,592.95
x) 355 mm P.Rft 69.45 4,471.70 PM 189.85 14,671.60
xi) 400 mm P.Rft 78.60 5,663.60 PM 214.95 18,582.25
xii) 450 mm P.Rft 79.85 7,164.80 PM 218.40 23,507.65
xiii) 500 mm P.Rft 94.05 8,847.25 PM 257.10 29,027.85
xiv) 560 mm P.Rft 104.40 11,115.60 PM 285.40 36,470.35
xv) 630 mm P.Rft 117.10 14,014.40 PM 320.15 45,981.20
xvi) 710 mm P.Rft 132.65 17,853.85 PM 362.65 58,578.40
xvii) 800 mm P.Rft 150.45 22,612.25 PM 411.30 74,190.75
xviii) 900 mm P.Rft 189.25 28,732.40 PM 517.45 94,270.95
xix) 1000 mm P.Rft 219.70 34,959.20 PM 600.70 114,701.10
e) PN-16 (SDR-11)
i) 90 mm P.Rft 4.60 349.80 PM 12.55 1,147.65
ii) 110 mm P.Rft 12.85 525.05 PM 35.10 1,722.70
iii) 125 mm P.Rft 14.20 678.70 PM 38.80 2,226.80
iv) 160 mm P.Rft 15.60 1,104.00 PM 42.65 3,622.30
v) 180 mm P.Rft 20.00 1,395.70 PM 54.70 4,579.20
vi) 200 mm P.Rft 22.35 1,719.50 PM 61.10 5,641.70
vii) 225 mm P.Rft 25.50 2,174.95 PM 69.70 7,136.05
viii) 250 mm P.Rft 35.20 2,678.15 PM 96.30 8,787.10

chapter-23(Tubewell).xls Page 157


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

ix) 315 mm P.Rft 62.45 4,252.35 PM 170.70 13,951.95


x) 355 mm P.Rft 69.45 5,389.80 PM 189.85 17,683.90
xi) 400 mm P.Rft 78.60 6,835.50 PM 214.95 22,427.30
xii) 450 mm P.Rft 79.85 8,646.70 PM 218.40 28,369.75
xiii) 500 mm P.Rft 94.05 10,675.80 PM 257.10 35,027.30
xiv) 560 mm P.Rft 104.40 13,390.15 PM 285.40 43,933.15
xv) 630 mm P.Rft 117.10 16,929.15 PM 320.15 55,544.45
xvi) 710 mm P.Rft 132.65 21,561.70 PM 362.65 70,743.95
f) PN-20 (SDR-9)
i) 90 mm P.Rft 4.60 418.85 PM 12.60 1,374.30
ii) 110 mm P.Rft 12.85 628.60 PM 35.10 2,062.35
iii) 125 mm P.Rft 14.20 810.65 PM 38.80 2,659.70
iv) 160 mm P.Rft 15.60 1,316.05 PM 42.65 4,318.00
v) 180 mm P.Rft 20.00 1,665.40 PM 54.70 5,464.15
vi) 200 mm P.Rft 22.35 2,057.50 PM 61.10 6,750.70
vii) 225 mm P.Rft 25.50 2,602.80 PM 69.70 8,539.85
viii) 250 mm P.Rft 35.20 3,202.20 PM 96.30 10,506.40
ix) 315 mm P.Rft 62.45 5,094.15 PM 170.70 16,713.95
x) 355 mm P.Rft 69.45 6,461.60 PM 189.85 21,200.45
xi) 400 mm P.Rft 78.60 8,189.30 PM 214.95 26,869.10
xii) 450 mm P.Rft 79.85 10,359.85 PM 218.40 33,990.60
xiii) 500 mm P.Rft 94.05 12,772.40 PM 257.10 41,906.25
xiv) 560 mm P.Rft 104.40 16,040.50 PM 285.40 52,628.85
xv) 630 mm P.Rft 117.10 24,597.45 PM 320.15 80,704.20
xvi) 710 mm P.Rft 132.65 30,978.10 PM 362.65 101,639.15
44 Providing & mixing bentonite clay / powder have swelling factor of Per 3.90 8.60 Per Kg. 25.65 56.60
1200% for lining /seal and plug earthen bore holes / ponds in the specified Pound
ratio conforming to IS:6186 for stabilization of soil as specified by the
designer etc complete in all respect.
45 P/F Ejector Pump of specified Suction and Delivery heads,coupled with
Single Phase Seimen Electric Motor of required rating for water supply i/c
the cost of connection charges, necessary wire, PVC pipes etc complete in
all respect as approved and directed by the Engineer Incharge.

i) G-II (1-1/4"x3/4") with 1 HP Electric Motor, 21-Mtr Suction and 21 Each 1,494.90 12,561.30 Each 1,494.90 12,561.30
M delivery head
ii) G-IV (2-1/2"x2") with 2.5 HP Electric Motor, 38-Mtr Suction and 38 Each 1,494.90 17,940.90 Each 1,494.90 17,940.90
M delivery head
46 Providing and fixing CP heavy duty brass Ball valve with CP handle of
specified diameter made of Faisal/Sonex / Master best quality or
equivalent complete in all respect as approved and directed by the Engineer
Incharge.
i) i) 1/2" dia Each 343.20 1,003.20 Each 343.20 1,003.20
ii) ii) 3/4" dia Each 343.20 1,447.20 Each 343.20 1,447.20
iii) iii) 1" dia Each 343.20 1,687.20 Each 343.20 1,687.20
iv) iv) 1-1/4" dia Each 343.20 1,843.20 Each 343.20 1,843.20
v) v) 1-1/2" dia Each 343.20 2,143.20 Each 343.20 2,143.20
vi) vi) 2" dia Each 343.20 2,563.20 Each 343.20 2,563.20

chapter-23(Tubewell).xls Page 158


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

vii) vii) 2-1/2" dia Each 343.20 2,683.20 Each 343.20 2,683.20
47 Providing, laying, testing and commissioning of POLYPROPYLENE
RANDOM COPOLYMER (PPRC) water supply pipe (Dadex /Popular/
Beta or equivalent) with specified pressure rating PN (PRESSURE
NOMINAL)and conforming to DIN 8077-8078 code i/c cost of solvent,
specials,making jharries complete in all respect as approved and directed
by Engineer Incharge.(Internal/External Diameters mentioned).
a) PN-16 pipe
(i)(1/2") 20 mm Per Rft 6.70 43.05 Meter 21.95 141.25
(ii)(3/4") 25 mm Per Rft 6.70 58.05 Meter 21.95 190.35
(iii)(1") 32 mm Per Rft 7.75 93.75 Meter 25.45 307.55
(iv) (1-1/4") 40 mm Per Rft 7.80 129.55 Meter 25.65 424.85
(v)(1-1/2") 50 mm Per Rft 7.90 215.70 Meter 25.85 707.45
(vi)(2") 63 mm Per Rft 8.65 327.55 Meter 28.30 1,074.45
(vii)(2-1/4") 75 mm Per Rft 8.85 548.90 Meter 29.05 1,800.40
(viii)(2-1/2") 90 mm Per Rft 9.95 785.60 Meter 32.60 2,576.75
(ix) (3") 110 mm Per Rft 11.10 1,167.50 Meter 36.40 3,829.45
b) PN-20 pipe
(i)(1/2") 20 mm Per Rft 6.70 48.20 Meter 21.95 158.05
(ii)(3/4") 25 mm Per Rft 6.70 66.60 Meter 21.95 218.45
(iii)(1") 32 mm Per Rft 7.75 107.05 Meter 25.45 351.10
(iv) (1-1/4") 40 mm Per Rft 7.80 161.45 Meter 25.65 529.55
(v)(1-1/2") 50 mm Per Rft 7.90 249.35 Meter 25.85 817.80
(vi)(2") 63 mm Per Rft 8.65 378.05 Meter 28.30 1,240.05
(vii)(2-1/4") 75 mm Per Rft 8.85 633.85 Meter 29.05 2,078.95
(viii)(2-1/2") 90 mm Per Rft 9.95 907.70 Meter 32.60 2,977.20
(ix) (3") 110 mm Per Rft 11.10 1,348.70 Meter 36.40 4,423.80
c) PN-25 pipe
(i)(1/2") 20 mm Per Rft 6.70 55.90 Meter 21.95 183.35
(ii)(5/8") 25 mm Per Rft 6.70 76.00 Meter 21.95 249.30
(iii)(3/4") 32 mm Per Rft 7.75 123.75 Meter 25.45 405.80
(iv)(1") 40 mm Per Rft 7.80 192.70 Meter 25.65 632.00
(v)(1-1/4") 50 mm Per Rft 7.90 283.00 Meter 25.85 928.20
(vi)(1-1/2") 63 mm Per Rft 8.65 405.05 Meter 28.30 1,328.60
48 Providing, laying, testing and commissioning µ-PVC (Un plasticized
Polyvinyl Chloride) Schedule pipe of nominal diameter, Dadex/Popular /
Beta or equivalent, i/c the cost of solvent and specials complete as
approved and directed by the Engineer Incharge.
a) Schedule 40
(i) 1/2" Per Rft 7.08 82.65 Meter 23.22 271.15
(ii) 3/4" Per Rft 7.08 91.95 Meter 23.22 301.60
(iii) 1" Per Rft 7.08 134.70 Meter 23.22 441.80
(iv) 1-1/4" Per Rft 7.08 163.20 Meter 23.22 535.30
(v) 1-1/2" Per Rft 7.08 183.55 Meter 23.22 602.10
(vi) 2" Per Rft 7.08 250.75 Meter 23.22 822.40
(vii) 3" Per Rft 7.08 570.35 Meter 23.22 1,870.70
(viii) 4" Per Rft 7.08 749.95 Meter 23.22 2,459.85

chapter-23(Tubewell).xls Page 159


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

(ix) 6" Per Rft 7.08 1,495.00 Meter 23.22 4,903.60


(x) 8" Per Rft 7.08 2,231.90 Meter 23.22 7,320.70
(xi) 10" Per Rft 7.08 3,243.40 Meter 23.22 10,638.35
(xii) 12" Per Rft 7.08 4,045.95 Meter 23.22 13,270.75
b) Schedule 80
(i) 1/2" Per Rft 7.08 94.65 Meter 23.22 310.50
(ii) 3/4" Per Rft 7.08 115.35 Meter 23.22 378.25
(iii) 1" Per Rft 7.08 158.05 Meter 23.22 518.45
(iv)1-1/4" Per Rft 7.08 200.80 Meter 23.22 658.60
(v) 1-1/2" Per Rft 7.08 222.15 Meter 23.22 728.70
(vi) 2" Per Rft 7.08 329.00 Meter 23.22 1,079.10
(vii) 3" Per Rft 7.08 756.80 Meter 23.22 2,482.25
(viii) 4" Per Rft 7.08 949.10 Meter 23.22 3,113.00
(ix) 6" Per Rft 7.08 1,761.00 Meter 23.22 5,776.10
(x) 8" Per Rft 7.08 2,722.50 Meter 23.22 8,929.80
(xi) 10" Per Rft 7.08 4,665.60 Meter 23.22 15,303.15
(xii) 12" Per Rft 7.08 5,648.45 Meter 23.22 18,526.90
49 Providing, laying, testing and commissioning of Grade-B,MS Seamless
Schedule pipe of nominal diameter, conforming to ASTM -A106, Lontrin/
Hufaz / Pecific baolai or equivalent, duly welded i/c the cost of specials
complete as approved and directed by the Engineer Incharge.

a) Schedule 40
(i) 1/2" Per Rft 14.15 164.15 Meter 46.45 538.35
(ii) 3/4" Per Rft 14.15 169.55 Meter 46.45 556.10
(iii) 1" Per Rft 14.15 272.50 Meter 46.45 893.80
(iv) 1-1/4" Per Rft 14.15 312.80 Meter 46.45 1,026.00
(v) 1-1/2" Per Rft 21.25 356.90 Meter 69.65 1,170.55
(vi) 2" Per Rft 21.25 473.70 Meter 69.65 1,553.80
(vii) 2-1/2" Per Rft 21.25 998.15 Meter 69.65 3,274.00
(viii) 3" Per Rft 21.25 1,519.60 Meter 69.65 4,984.35
(ix) 4" Per Rft 28.30 1,870.60 Meter 92.85 6,135.50
(x) 5" Per Rft 28.30 2,675.30 Meter 92.85 8,775.05
(xi) 6" Per Rft 28.30 2,786.50 Meter 92.85 9,139.80
(xii) 8" Per Rft 35.40 3,545.30 Meter 116.10 11,628.60
(xiii) 10" Per Rft 35.40 4,856.45 Meter 116.10 15,929.10
(xiv) 12" Per Rft 35.40 6,060.70 Meter 116.10 19,879.15
(xv) 14" Per Rft 42.45 9,080.45 Meter 139.30 29,783.90
(xvi) 16" Per Rft 42.45 13,575.15 Meter 139.30 44,526.55
(xvii) 18" Per Rft 42.45 19,790.85 Meter 139.30 64,914.00
(xviii) 20" Per Rft 56.65 21,914.45 Meter 185.75 71,879.40
(xix) 24" Per Rft 56.65 21,643.80 Meter 185.75 70,991.65
(xx) 30" Per Rft 56.65 27,040.60 Meter 185.75 88,693.15
50 Providing and fixing heavy duty Strainer valve of specified diameter and
material for pressure rating PN-16 made of Crane (USA), Hatersly (UK) or
Scon (Pakistan)i/c the cost of all accessories flanges,nut/bolt and gaskit
where required complete in all respect as approved and directed by the
Engineer Incharge.
(a) Brass Threaded Valves
(i) 1/2" dia Each 343.20 2,503.20 Each 343.20 2,503.20
chapter-23(Tubewell).xls Page 160
MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

(ii) 3/4" dia Each 343.20 3,583.20 Each 343.20 3,583.20


(iii) 1" dia Each 343.20 4,543.20 Each 343.20 4,543.20
(iv) 1-1/4" dia Each 343.20 7,543.20 Each 343.20 7,543.20
(v) 1-1/2" dia Each 514.80 10,114.80 Each 514.80 10,114.80
(vi) 2" dia Each 514.80 13,714.80 Each 514.80 13,714.80
(b) Flange Ended Ductile I ron Valve
(vii) 2-1/2" dia Each 1,716.00 20,988.00 Each 1,716.00 20,988.00
(viii) 3" dia Each 1,716.00 23,388.00 Each 1,716.00 23,388.00
(ix) 4" dia Each 1,716.00 31,248.00 Each 1,716.00 31,248.00
(x) 5" dia Each 1,716.00 36,108.00 Each 1,716.00 36,108.00
(xi) 6" dia Each 1,716.00 60,198.00 Each 1,716.00 60,198.00
(xii) 8" dia Each 1,716.00 73,452.00 Each 1,716.00 73,452.00
(xiii) 10" dia Each 1,716.00 122,748.00 Each 1,716.00 122,748.00
(xiv) 12" dia Each 1,716.00 170,808.00 Each 1,716.00 170,808.00
(xv) 14" dia Each 1,716.00 290,838.00 Each 1,716.00 290,838.00
51 Providing and fixing heavy duty Globe valve of specified diameter and
material for pressure rating PN-16 made of Crane (USA), Hatersly (UK) or
Scon (Pakistan) i/c the cost of all accessories flanges,nut/bolt and gaskit
where required complete in all respect as approved and directed by the
Engineer Incharge.
(a) Brass Threaded Valves
(i) 1/2" dia Each 343.20 2,743.20 Each 343.20 2,743.20
(ii) 3/4" dia Each 343.20 3,463.20 Each 343.20 3,463.20
(iii) 1" dia Each 343.20 4,903.20 Each 343.20 4,903.20
(iv) 1-1/4" dia Each 343.20 6,583.20 Each 343.20 6,583.20
(v) 1-1/2" dia Each 514.80 10,594.80 Each 514.80 10,594.80
(vi) 2" dia Each 514.80 17,914.80 Each 514.80 17,914.80
(b) Flange Ended Ductile I ron Valve
(vii) 2-1/2" dia Each 514.80 20,314.80 Each 514.80 20,314.80
(viii) 3" dia Each 686.40 30,686.40 Each 686.40 30,686.40
(ix) 4" dia Each 686.40 34,886.40 Each 686.40 34,886.40
(x) 5" dia Each 686.40 48,086.40 Each 686.40 48,086.40
(xi) 6" dia Each 686.40 60,206.40 Each 686.40 60,206.40
(xii) 8" dia Each 858.00 108,378.00 Each 858.00 108,378.00
(xiii) 10" dia Each 858.00 182,778.00 Each 858.00 182,778.00
(xiv) 12" dia Each 858.00 242,178.00 Each 858.00 242,178.00
(xv) 14" dia Each 858.00 422,178.00 Each 858.00 422,178.00
(xvi)16" dia Each 858.00 554,178.00 Each 858.00 554,178.00
(xvii) 18" dia Each 858.00 704,178.00 Each 858.00 704,178.00
(xviii) 20" dia Each 858.00 950,178.00 Each 858.00 950,178.00
(xix) 24" dia Each 858.00 1,178,178.00 Each 858.00 1,178,178.00
(xx) 30" dia Each 858.00 1,262,178.00 Each 858.00 1,262,178.00
52 Providing and fixing heavy duty Gate valve of specified diameter and
material for pressure rating PN-16 mde of Crane (USA), Hatersly (UK) or
Scon (Pakistan) i/c the cost of all accessories flanges,nut/bolt and gaskit
where required complete in all respect as approved and directed by the
Engineer Incharge.
(a) Brass Threaded Valves
(i) 1/2" dia Each 343.20 2,683.20 Each 343.20 2,683.20

chapter-23(Tubewell).xls Page 161


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

(ii) 3/4" dia Each 343.20 3,463.20 Each 343.20 3,463.20


(iii) 1" dia Each 343.20 4,543.20 Each 343.20 4,543.20
(iv) 1-1/4" dia Each 343.20 6,703.20 Each 343.20 6,703.20
(v) 1-1/2" dia Each 514.80 10,354.80 Each 514.80 10,354.80
(vi) 2" dia Each 514.80 16,714.80 Each 514.80 16,714.80
(b) Flange Ended Ductile I ron Valve
(vii) 2-1/2" dia Each 514.80 25,258.80 Each 514.80 25,258.80
(viii) 3" dia Each 686.40 30,830.40 Each 686.40 30,830.40
(ix) 4" dia Each 686.40 40,430.40 Each 686.40 40,430.40
(x) 5" dia Each 686.40 51,230.40 Each 686.40 51,230.40
(xi) 6" dia Each 686.40 66,950.40 Each 686.40 66,950.40
(xii) 8" dia Each 858.00 82,078.00 Each 858.00 82,078.00
(xiii) 10" dia Each 858.00 132,078.00 Each 858.00 132,078.00
(xiv) 12" dia Each 858.00 192,078.00 Each 858.00 192,078.00
(xv) 14" dia Each 858.00 242,078.00 Each 858.00 242,078.00
(xvi)16" dia Each 858.00 352,078.00 Each 858.00 352,078.00
(xvii) 18" dia Each 858.00 457,078.00 Each 858.00 457,078.00
(xviii) 20" dia Each 858.00 502,078.00 Each 858.00 502,078.00
(xix) 24" dia Each 858.00 852,078.00 Each 858.00 852,078.00
(xx) 30" dia Each 858.00 1,022,078.00 Each 858.00 1,022,078.00
53 Providing and fixing heavy duty Balancing valve of specified diameter and
material for pressure rating PN-16 made of Crane (USA), Hatersly (UK) or
Scon (Pakistan) i/c the cost of all accessories flanges,nut/bolt and gaskit
where required complete in all respect as approved and directed by the
Engineer Incharge.
(a) Brass Threaded Valves
(i) 1/2" dia Each 343.20 13,543.20 Each 343.20 13,543.20
(ii) 3/4" dia Each 343.20 15,943.20 Each 343.20 15,943.20
(iii) 1" dia Each 343.20 20,143.20 Each 343.20 20,143.20
(iv) 1-1/4" dia Each 343.20 20,143.20 Each 343.20 20,143.20
(v) 1-1/2" dia Each 514.80 23,143.20 Each 514.80 23,143.20
(vi) 2" dia Each 514.80 26,314.80 Each 514.80 26,314.80
(b) Flange Ended Ductile I ron Valve
(vii) 2-1/2" dia Each 514.80 32,314.80 Each 514.80 32,314.80
(viii) 3" dia Each 514.80 35,386.80 Each 514.80 35,386.80
(ix) 4" dia Each 686.40 43,358.40 Each 686.40 43,358.40
(x) 5" dia Each 686.40 47,558.40 Each 686.40 47,558.40
(xi) 6" dia Each 686.40 54,758.40 Each 686.40 54,758.40
(xii) 8" dia Each 858.00 59,730.00 Each 858.00 59,730.00
(xiii) 10" dia Each 858.00 164,202.00 Each 858.00 164,202.00
(xiv) 12" dia Each 858.00 266,202.00 Each 858.00 266,202.00
54 Providing and fixing heavy duty Check valve of specified diameter and
material for pressure rating PN-16 made of Crane (USA), Hatersly (UK) or
Scon (Pakistan) i/c the cost of all accessories flanges,nut/bolt and gaskit
where required complete in all respect as approved and directed by the
Engineer Incharge.
(a) Brass Threaded Valves
(i) 1/2" dia Each 343.20 3,943.20 Each 343.20 3,943.20
(ii) 3/4" dia Each 343.20 4,423.20 Each 343.20 4,423.20

chapter-23(Tubewell).xls Page 162


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

(iii) 1" dia Each 343.20 6,703.20 Each 343.20 6,703.20


(iv) 1-1/4" dia Each 343.20 9,943.20 Each 343.20 9,943.20
(v) 1-1/2" dia Each 514.80 11,074.80 Each 514.80 11,074.80
(vi) 2" dia Each 514.80 11,914.80 Each 514.80 11,914.80
(b) Flange Ended Ductile I ron Valve
(vii) 2-1/2" dia Each 514.80 16,786.80 Each 514.80 16,786.80
(viii) 3" dia Each 686.40 21,758.40 Each 686.40 21,758.40
(ix) 4" dia Each 686.40 30,158.40 Each 686.40 30,158.40
(x) 5" dia Each 686.40 36,158.40 Each 686.40 36,158.40
(xi) 6" dia Each 858.00 47,730.00 Each 858.00 47,730.00
(xii) 8" dia Each 858.00 69,402.00 Each 858.00 69,402.00
(xiii) 10" dia Each 858.00 116,202.00 Each 858.00 116,202.00
(xiv) 12" dia Each 858.00 160,602.00 Each 858.00 160,602.00
55 Supply & installation of heavy duty Brass PN-16 air Vents of specified
size provided at the highest points (Pipe Risers) to expel air as approved
and directed by the Engineer Incharge
(a) Automatic
(i) 1/2" Each 171.60 2,811.60 Each 171.60 2,811.60
(ii) 3/4" Each 171.60 3,411.60 Each 171.60 3,411.60
(iii) 1" Each 171.60 3,771.60 Each 171.60 3,771.60
(b) M annual
(i) 1/2" Each 171.60 2,331.60 Each 171.60 2,331.60
(ii) 3/4" Each 171.60 2,931.60 Each 171.60 2,931.60
(iii) 1" Each 171.60 3,411.60 Each 171.60 3,411.60
56 Providing and fixing heavy duty Pressure Relief Valve of specified
diameter and material for pressure rating PN-16 made of Crane (USA),
Hatersly (UK) or Scon (Pakistan) integral device with a pressure setting, a
restrictor and a sensor all in the one body, i/c the cost of all accessories
flanges,nut/bolt and gaskit where required complete in all respect as
approved and directed by the Engineer Incharge.
(i) 3/4" dia Each 343.20 23,743.20 Each 343.20 23,743.20
(ii) 1" dia Each 343.20 26,743.20 Each 343.20 26,743.20
(iii) 1-1/2" dia Each 343.20 31,543.20 Each 343.20 31,543.20
(iv) 2" dia Each 343.20 38,743.20 Each 343.20 38,743.20
(v) 2-1/2" dia Each 514.80 46,114.80 Each 514.80 46,114.80
57 Supply and Installation of Gas & Liquid Copper Piping of specified size
and thickness including the cost of Fittings, Welding Complete
clamps/hangers/supports,testing charges and all other related material for
installation purpose complete in all respect as approved and directed by the
Engineer Incharge
(i) Ø 1/4" Per Rft 14.15 226.00 Meter 46.45 741.35
(ii) Ø 3/8" Per Rft 14.15 317.65 Meter 46.45 1,041.90
(iii) Ø 1/2" Per Rft 14.15 414.80 Meter 46.45 1,360.45
(iv) Ø 5/8" Per Rft 14.15 548.30 Meter 46.45 1,798.50
(v) Ø 3/4" Per Rft 21.25 652.50 Meter 69.65 2,140.25
(vi) Ø 7/8" Per Rft 21.25 773.90 Meter 69.65 2,538.45
(vii) Ø 1" Per Rft 21.25 810.35 Meter 69.65 2,657.90
(viii) Ø 1-1/8" Per Rft 21.25 1,053.15 Meter 69.65 3,454.30
(ix) Ø 1-1/4" Per Rft 28.30 1,120.90 Meter 92.85 3,676.60

chapter-23(Tubewell).xls Page 163


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

(x) Ø 1-3/8" Per Rft 28.30 1,230.15 Meter 92.85 4,034.95


(xi)Ø 1-1/2" Per Rft 28.30 1,727.90 Meter 92.85 5,667.55
(xii)Ø 1-3/4" Per Rft 35.40 1,917.10 Meter 116.10 6,288.05
(xiii)Ø 2" Per Rft 35.40 2,038.50 Meter 116.10 6,686.25
(xiv)Ø 2-1/2" Per Rft 35.40 2,281.30 Meter 116.10 7,482.65
(xv)Ø 3" Per Rft 42.45 4,048.65 Meter 139.30 13,279.65

FIRE FIGHTING WORKS


58 Supply , installation and commissioning of Concealed/Open type wall If floor mounted Rack is used, increase
mounted fire Hose Rack of specified size made of 18 SWG MS sheet , composite rate by 5%.
single/double Cabin having demountable single/double doors of
steel/glazed with 4 mm thick glass,with warning sign on it,duly painted
with 70 micron electrostated powder coated Red color, housing at least 100
ft length of pipe i/c the cost of specified valve , complete in all respects as
approved and directed by Engineer Incharge ( The accessories will be paid
separately). 23.6
I ndoor/Outdoor Type
(i) 8"-10"deep P.Cft 580.50 2,601.90 P.Cum 20,479.45 91,794.80
(ii) 12" deep P.Cft 377.25 1,913.70 P.Cum 13,308.50 67,515.55
59 Supply , installation and commissioning of Concealed/open type fire Hose If floor mounted Cabinet is used, increase
reel cabinet of specified size made of 18 SWG MS sheet , single/double composite rate by 5%.
Cabin having demountable single/double doors of steel/glazed with 4 mm
thick glass with warning sign on it,duly painted with 70 micron
electrostated powder coated Red color, housing at least 100 ft length of
pipe i/c the cost of specified valve , complete in all respects. as approved
and directed by Engineer Incharge ( The accessories will be paid
separately).
Indoor/Outdoor Type
(i) 8-10" deep P.Cft 580.50 2,567.35 P.Cum 20,479.45 90,576.05
(ii) 12" deep P.Cft 377.25 1,871.60 P.Cum 13,308.50 66,030.20
60 Supply , installation and commissioning of fire Hose reel Cabinet
accessories of specified size and make, complete in all respects. as
approved and directed by Engineer Incharge.
A) Rubber covered hose pipe
(i) 1" dia P.Rft 71.35 878.95 P.Mtr 234.00 2,882.95
B) Jacket of Polyurethane/100% Polyester filmant yarn Twin wave
,full Synthetic rubber compound with brass connectors UL listed.
(i) 1-1/2" dia
(a) Burst pressure 500 psi P.Rft 71.35 784.15 P.Mtr 234.00 2,572.00
(b) Burst pressure 750 psi P.Rft 71.35 856.15 P.Mtr 234.00 2,808.15
(ii) 2-1/2" dia Hose
Burst pressure 650 psi P.Rft 71.35 1,001.35 P.Mtr 234.00 3,284.40
C) PVC lining Canvas Fire Hose with brass connectors UL listed.
Burst pressure 650 psi P.Rft 2.40 9.75 P.Mtr 7.95 31.95
D) Fire hose Spray Nozzle with jet
(a) 1" dia Polycarbonate Nozzle(75gpm) Each 713.50 2,873.50 Each 713.50 2,873.50
(b)1-1/2" dia Gunmetal/Chrome Nozzle Each 713.50 4,373.50 Each 713.50 4,373.50
('c) 2-1/2" dia Gunmetal/Chrome Nozzle

chapter-23(Tubewell).xls Page 164


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

(i) Fog spray Tripple Purpose Each 713.50 6,113.50 Each 713.50 6,113.50
(ii) Jet Nozzel Each 713.50 5,513.50 Each 713.50 5,513.50
61 Supplying, fixing and testing ductile iron pipe with flange including the
cost of specials, (teepu pipe / alpine steel or approved equivalent)
complying Class K-12, ISO - 2531 & BS - 4772, & jointing material with
all fittings and accessories complete in all respect as approved by the
Engineer Incharge
i) 3" dia (75 mm) P.Rft 25.60 3,309.30 P.Mtr 83.95 10,854.55
ii) 4" dia (100 mm) P.Rft 33.10 4,123.35 P.Mtr 108.55 13,524.50
iii) 6" dia (150 mm) P.Rft 40.55 6,407.75 P.Mtr 133.00 21,017.40
iv) 8" dia (200mm) P.Rft 48.05 9,169.20 P.Mtr 157.60 30,075.00
v) 10" dia (250 mm) P.Rft 55.50 12,229.80 P.Mtr 182.05 40,113.70
vi) 12" dia (300 mm) P.Rft 63.00 15,732.00 P.Mtr 206.65 51,600.95
62 Providing and fixing Chain Pulley Block of 5 ton capacity with 5 meter Each 1,273.80 58,874.00 Each 1,273.80 58,874.00
length of chain, as per required specifications complete in all respect and as
approved by the Engineer Incharge.
63 Two Coats of Bitumen Grade 80/100 (40 Lbs/100Sft)(NRL/PARCO) and 100 Sft 2,866.05 7,284.45 P.Sqm 308.40 783.80
Wrapping of Polythene (500 gauge) on M.S. Pipe

chapter-23(Tubewell).xls Page 165


24. ELECTRIC INSTALLATION
Rates for all finished works include the removal of surplus debris, unused material and byproducts.

MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

1 Supply and erection of G.I. pipes for wiring purposes, including


pull boxes, inspection boxes, bends, tees, etc. complete with
all specials.

a) on surface, including clamps, etc. 38.4

i) 15 mm i/d Per Rft. 41.85 190.75 Per Metre 137.30 625.65


ii) 20 mm i/d Per Rft. 41.85 205.45 Per Metre 137.30 673.90
iii) 25 mm i/d Per Rft. 41.85 273.40 Per Metre 137.30 896.70
iv) 32 mm i/d Per Rft. 52.30 349.05 Per Metre 171.60 1,144.95
v) 40 mm i/d Per Rft. 52.30 429.30 Per Metre 171.60 1,408.10
vi) 50 mm i/d Per Rft. 62.30 535.20 Per Metre 204.30 1,755.55
vii) 80 mm i/d Per Rft. 79.25 852.90 Per Metre 260.00 2,797.45

b) recessed in walls, including hooks, cutting jharries and


repairing surface: 38.3

i) 15 mm i/d Per Rft. 62.80 177.20 Per Metre 205.90 581.25


ii) 20 mm i/d Per Rft. 62.80 222.05 Per Metre 205.90 728.40
iii) 25 mm i/d Per Rft. 65.40 293.90 Per Metre 214.50 963.95
iv) 32 mm i/d Per Rft. 65.40 359.45 Per Metre 214.50 1,179.05
v) 40 mm i/d Per Rft. 71.35 445.15 Per Metre 234.00 1,460.00
vi) 50 mm i/d Per Rft. 98.10 569.30 Per Metre 321.75 1,867.25
vii) 80 mm i/d Per Rft. 156.95 929.80 Per Metre 514.80 3,049.70

2 Supply and erection of M.S. conduit pipes for wiring, including 38.4 & 38.6
pull boxes, inspection boxes, bends, tees, etc. complete with
all specials.

a) on surface, including clamps, etc.

i) 16 mm i/d Per Rft. 29.05 65.85 Per Metre 95.35 216.00


ii) 20 mm i/d Per Rft. 29.05 69.20 Per Metre 95.35 226.95
iii) 25 mm i/d Per Rft. 29.05 83.35 Per Metre 95.35 273.30
iv) 32 mm i/d Per Rft. 29.05 89.85 Per Metre 95.35 294.70
v) 40 mm i/d Per Rft. 32.70 109.90 Per Metre 107.25 360.55
vi) 50 mm i/d Per Rft. 40.25 135.55 Per Metre 132.00 444.55
b) recessed in walls, including cutting jharries, cost of 38.3 &
hooks and repairing surface etc. 38.7

i) 16 mm i/d Per Rft. 56.05 89.45 Per Metre 183.85 293.40


ii) 20 mm i/d Per Rft. 56.05 91.55 Per Metre 183.85 300.25
iii) 25 mm i/d Per Rft. 62.80 110.60 Per Metre 205.90 362.70

chapter-24(Electric Installation).xls Page 166


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

iv) 32 mm i/d Per Rft. 65.40 119.70 Per Metre 214.50 392.60
v) 40 mm i/d Per Rft. 68.25 137.10 Per Metre 223.85 449.75
vi) 50 mm i/d Per Rft. 71.35 159.50 Per Metre 234.00 523.10

3 Supply and erection of PVC pipe for wiring recessed in walls, 38.3 &
including inspection boxes, pull boxes, hooks, cutting jharries, 38.5
and repairing surface, etc., complete with all specials.

i) 12 mm i/d Per Rft. 50.65 71.90 Per Metre 166.05 235.90


ii) 20 mm i/d Per Rft. 52.30 83.70 Per Metre 171.60 274.55
iii) 25 mm i/d Per Rft. 58.15 96.85 Per Metre 190.65 317.65
iv) 32 mm i/d Per Rft. 62.80 123.05 Per Metre 205.90 403.55
v) 40 mm i/d Per Rft. 65.40 148.15 Per Metre 214.50 485.85
vi) 50 mm i/d Per Rft. 68.25 186.05 Per Metre 223.85 610.30

4 Supply and erection of PVC pipe for wiring on surface


including clamps inspection boxes, pull boxes, bends, tees,
repairing surface, etc., complete with all specials:-

i) 12 mm i/d Per Rft. 13.10 41.60 Per Metre 42.90 136.45


ii) 20 mm i/d Per Rft. 13.10 51.55 Per Metre 42.90 169.15
iii) 25 mm i/d Per Rft. 13.10 61.95 Per Metre 42.90 203.15
iv) 32 mm i/d Per Rft. 14.95 87.05 Per Metre 49.05 285.45
v) 40 mm i/d Per Rft. 14.95 112.55 Per Metre 49.05 369.25
vi) 50 mm i/d Per Rft. 18.05 158.60 Per Metre 59.15 520.25

5 Supply and erection of G.I. flexible pipe for wiring, including 38.4
welding of sockets, nipples and check nuts, etc. complete:-

i) 12 mm i/d Per Rft. 34.25 119.90 Per Metre 112.30 393.35


ii) 20 mm i/d Per Rft. 36.50 150.85 Per Metre 119.80 494.75
iii) 25 mm i/d Per Rft. 37.80 184.10 Per Metre 123.90 603.90
iv) 32 mm i/d Per Rft. 45.65 217.50 Per Metre 149.75 713.40
v) 40 mm i/d Per Rft. 49.80 250.60 Per Metre 163.35 822.00
vi) 50 mm i/d Per Rft. 54.80 296.60 Per Metre 179.70 972.90
vii) 80 mm i/d Per Rft. 73.05 488.50 Per Metre 239.55 1,602.20

6 Supply and erection PVC pipe for recessed wiring (main and 38.2 &
sub-main) purpose, including bends, specials, etc. in floor, 38.3
wall or trenches:-

i) 50 mm i/d Per Rft. 68.25 188.45 Per Metre 223.85 618.20


ii) 80 mm i/d Per Rft. 78.50 236.75 Per Metre 257.40 776.55
iii) 100 mm i/d Per Rft. 78.50 293.75 Per Metre 257.40 963.55

chapter-24(Electric Installation).xls Page 167


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

7 Supply and erection of PVC pipe for surface wiring (main and
sub-main) including clamps, inspection boxes, pull boxes
bends etc., complete with all specials:-

i) 50 mm i/d Per Rft. 18.05 140.70 Per Metre 59.15 461.40


ii) 80 mm i/d Per Rft. 26.15 209.60 Per Metre 85.80 687.45
iii) 100 mm i/d Per Rft. 29.90 293.85 Per Metre 98.05 963.85

8 Supply and erection of wooden strip batten for wiring Per Rft. 5.25 9.05 Per Metre 17.15 29.75 38.8 Additional width required to
purposes, including clips, insulation cleats, etc. accommodate wires will be provided
by erection of additional strips.

9 Supply and erection of Sahl wood casing and capping for Per Rft. 5.25 23.10 Per Metre 17.15 75.75 38.8
wiring purposes, including insulation cleats, screws, etc.
complete.

10 Supply and erection of single core PVC insulated copper 38.1


conductor cables, in prelaid PVC pipe/M.S. conduit/G.I
pipe/wooden strip batten/wooden casing an capping/G.I.
wire/trenches (rate for cables only):-

a) 250/440 volts, PVC insulated:

i) 3/0.74 mm (3/0.029") Per Rft. 10.45 26.10 Per Metre 34.30 85.55
ii) 3/0.91 mm (3/0.036") Per Rft. 10.45 22.10 Per Metre 34.30 72.55
iii) 7/0.74 mm (7/0.029") Per Rft. 10.45 41.15 Per Metre 34.30 134.95
iv) 7/0.91 mm (7/0.036") Per Rft. 11.65 54.25 Per Metre 38.15 177.95
v) 7/1.12 mm (7/0.044") Per Rft. 13.10 75.60 Per Metre 42.90 248.05
vi) 7/1.63 mm (7/0.064") Per Rft. 16.10 176.15 Per Metre 52.80 577.70
vii) 19/1.32 mm (19/0.052") Per Rft. 37.35 313.50 Per Metre 122.55 1,028.35
viii) 19/1.63 mm (19/0.064") Per Rft. 43.60 418.25 Per Metre 143.00 1,371.90

b) 250/440 volts, PVC insulated cotton braided and


compounded cables:-

i) 3/0.74 mm (3/0.029") Per Rft. 11.65 27.25 Per Metre 38.15 89.35
ii) 3/0.91 mm (3/0.036") Per Rft. 11.65 23.30 Per Metre 38.15 76.35
iii) 7/0.74 mm (7/0.029") Per Rft. 11.65 42.30 Per Metre 38.15 138.80
iv) 7/0.91 mm (7/0.036") Per Rft. 12.30 54.95 Per Metre 40.40 180.20
v) 7/1.12 mm (7/0.044") Per Rft. 13.75 76.30 Per Metre 45.15 250.30
vi) 7/1.63 mm (7/0.064") Per Rft. 15.85 175.65 Per Metre 52.00 576.05

c) 450/750 volts, PVC insulated:


i) 1 mm sq (1/0.039") Per Rft 11.65 27.10 Per Metre 38.15 88.80
ii) 1.5 mm sq (3/0.029") Per Rft 11.65 30.45 Per Metre 38.15 99.95
iii) 2.5 mm sq (7/0.029") Per Rft 11.65 51.20 Per Metre 38.15 167.90
iv) 4 mm sq (7/0.036") Per Rft 12.30 56.80 Per Metre 40.40 186.25
v) 6 mm sq (7/0.044") Per Rft 13.75 79.35 Per Metre 45.15 260.20
vi) 10 mm sq (7/0.052") Per Rft 15.85 129.65 Per Metre 52.00 425.25

chapter-24(Electric Installation).xls Page 168


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

vii) 16 mm sq (7/0.064") Per Rft 15.85 189.20 Per Metre 52.00 620.55
viii) 25 mm sq (19/0.052") Per Rft 17.45 343.00 Per Metre 57.20 1,125.10
ix) 35 mm sq (19/0.064") Per Rft 17.45 474.55 Per Metre 57.20 1,556.45

11 Supply and erection of single core PVC insulated, PVC


sheathed copper conductor, 250/440 volts grade cable
(BSS-2004), in prelaid PVC pipes/M.S. conduit/G.I.
pipe/wooden strip batten/wooden casing and
capping/trenches, etc. (rate for cable only):-

i) 3/0.74 mm (3/0.029") Per Rft. 10.45 25.15 Per Metre 34.30 82.50
ii) 3/0.91 mm (3/0.036") Per Rft. 10.45 21.00 Per Metre 34.30 68.95
iii) 7/0.74 mm (7/0.029") Per Rft. 10.45 40.25 Per Metre 34.30 131.95
iv) 7/0.91 mm (7/0.036") Per Rft. 11.65 53.10 Per Metre 38.15 174.10
v) 7/1.12 mm (7/0.044") Per Rft. 13.10 73.35 Per Metre 42.90 240.65
vi) 7/1.63 mm (7/0.064") Per Rft. 16.10 174.35 Per Metre 52.80 571.90

12 Supply and erection of single core PVC insulated, PVC


sheathed copper conductor, 600/1000 volts grade cable, in 38.1 to
prelaid G.I. pipe/M.S. conduits/PVC pipe/G.I. wire/trenches, 38.7
etc (rate for cable only):-
i) 4 .00 mm sq (7/0.036") Per Rft. 13.10 93.35 Per Metre 42.90 306.15
ii) 6 mm sq (7/0.044") Per Rft. 13.10 118.20 Per Metre 42.90 387.75
iii) 10.00 mm sq (7/0.052") Per Rft. 13.10 155.15 Per Metre 42.90 508.85
iv) 16 mm sq (7/0.064") Per Rft. 13.95 174.50 Per Metre 45.75 572.30
v) 25 mm sq (19/0.052") Per Rft. 13.95 255.10 Per Metre 45.75 836.80
vi) 35 mm sq (19/0.064") Per Rft. 16.10 343.55 Per Metre 52.80 1,126.90
vii) 50 mm sq (19/0.072") Per Rft. 16.10 467.15 Per Metre 52.80 1,532.30
viii) 70 mm sq (19/0.083") Per Rft. 16.10 665.00 Per Metre 52.80 2,181.20
ix) 95 mm sq (37/0.072") Per Rft. 16.10 912.20 Per Metre 52.80 2,992.00
x) 120 mm sq (37/0.083") Per Rft. 19.00 1,156.30 Per Metre 62.40 3,792.65
xi) 150 mm Sq (37/0.093") Per Rft. 19.00 1,391.05 Per Metre 62.40 4,562.70
xii) 185 mm sq (37/0.103") Per Rft. 19.00 1,767.90 Per Metre 62.40 5,798.70
xiii) 240 mm sq (37/0.114") Per Rft. 20.95 2,313.55 Per Metre 68.65 7,588.45
xiv) 300 mm sq (61/0.099") Per Rft. 20.95 2,894.65 Per Metre 68.65 9,494.40
xv) 400 mm sq (61/0.114") Per Rft. 20.95 3,685.60 Per Metre 68.65 12,088.75
xvi) 500 mm sq (91/0.103") Per Rft. 26.15 4,667.20 Per Metre 85.80 15,308.40
xvii) 630 mm sq (127/0.093") Per Rft. 26.15 6,008.30 Per Metre 85.80 19,707.30

13 Supply and erection of copper conductor cables for service ditto


connection, in prelaid pipe/G.I. wire/trenches, etc. (rate for
cable only):-
a) PVC insulated, PVC sheathed twin core, 250/440 volts.
i) 3/0.74 mm (3/0.029") Per Rft. 11.65 43.65 Per Metre 38.15 143.20
ii) 3/0.91 mm (3/0.036") Per Rft. 11.65 79.45 Per Metre 38.15 260.60
iii) 7/0.74 mm (7/0.029") Per Rft. 11.65 87.00 Per Metre 38.15 285.35
iv) 7/0.91 mm (7/0.036") Per Rft. 12.30 110.30 Per Metre 40.40 361.75

chapter-24(Electric Installation).xls Page 169


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

v) 7/1.12 mm (7/0.044") Per Rft. 13.75 160.75 Per Metre 45.15 527.20
vi) 7/1.63 mm (7/0.064") Per Rft. 15.85 306.95 Per Metre 52.00 1,006.70

b) PVC insulated, PVC sheathed 3 core,


600/1000 volt cable:-

i) 3/0.74 mm (3/0.029") Per Rft. 12.30 70.20 Per Metre 40.40 230.25
ii) 3/0.91 mm (3/0.036") Per Rft. 12.30 117.20 Per Metre 40.40 384.50
iii) 7/0.74 mm (7/0.029") Per Rft. 12.30 105.65 Per Metre 40.40 346.50
iv) 7/0.91 mm (7/0.036") Per Rft. 13.75 171.40 Per Metre 45.15 562.20
v) 7/1.12 mm (7/0.044") Per Rft. 14.55 247.40 Per Metre 47.65 811.45
vi) 7/1.63 mm (7/0.064") Per Rft. 16.60 496.65 Per Metre 54.50 1,629.05

c) PVC insulated, PVC sheathed 4 core, 600/1000 volt non armoured


cable:-
i) 1.5 mm (3/0.029") Per Rft. 13.10 85.45 Per Metre 42.90 280.20
ii) 1.5 mm (3/0.036") Per Rft. 13.10 111.50 Per Metre 42.90 365.65
iii) 2.5 mm (7/0.029") Per Rft. 13.75 151.70 Per Metre 45.15 497.55
iv) 4 mm (7/0.036") Per Rft. 13.75 223.35 Per Metre 45.15 732.55
v) 6 mm (7/0.044") Per Rft. 14.55 319.05 Per Metre 47.65 1,046.45
vi) 10 mm (7/0.052") Per Rft. 16.60 524.50 Per Metre 54.50 1,720.35
vii) 16 mm (7/0.064") Per Rft. 16.60 643.55 Per Metre 54.50 2,110.80
viii) 25 mm (19/0.052") Per Rft. 23.25 1,205.45 Per Metre 76.25 3,953.90
ix) 35 mm sq (19/0.064") Per Rft. 23.25 1,706.25 Per Metre 76.25 5,596.50
x) 50 mm sq (19/0.072") Per Rft. 23.25 1,859.25 Per Metre 76.25 6,098.35
xi) 70 mm sq (19/0.083") Per Rft. 23.25 2,656.70 Per Metre 76.25 8,714.05
xii) 95 mm sq (37/0.072") Per Rft. 23.25 3,676.95 Per Metre 76.25 12,060.45
xiii) 120 mm sq (37/0.083") Per Rft. 26.15 4,634.45 Per Metre 85.80 15,201.00
xiv) 150 mm sq (37/0.093") Per Rft. 26.15 5,687.15 Per Metre 85.80 18,653.90
xv) 185 mm sq (37/0.103") Per Rft. 26.15 7,119.40 Per Metre 85.80 23,351.60
xvi) 240 mm sq (37/0.114") Per Rft. 26.15 9,346.85 Per Metre 85.80 30,657.65
xvii) 300 mm sq (61/0.099") Per Rft. 26.15 11,703.05 Per Metre 85.80 38,386.00
xviii) 400 mm sq (61/0.114") Per Rft. 29.90 14,938.05 Per Metre 98.05 48,996.85

d) PVC insulated, PVC sheathed 4 Core, 600/1000 volt armoured cable:- Cost of trenches where necessary
is included in the rates.
i) 4 mm sq (7/0.036) Per Rft. 13.75 254.45 Per Metre 45.15 834.65
ii) 6 mm sq (7/0.044) Per Rft. 14.55 341.05 Per Metre 47.65 1,118.65
iii) 10 mm sq (7/0.052) Per Rft. 16.60 530.10 Per Metre 54.50 1,738.70
iv) 16 mm sq (7/0.064) Per Rft. 23.25 817.00 Per Metre 76.25 2,679.70
v) 25 mm sq (19/0.052) Per Rft. 23.25 1,341.60 Per Metre 76.25 4,400.40
vi) 35 mm sq (19/0.064) Per Rft. 24.90 1,413.85 Per Metre 81.70 4,637.35
vii) 50 mm sq (19/0.072) Per Rft. 26.15 1,901.90 Per Metre 85.80 6,238.30
viii) 70 mm sq (19/0.083) Per Rft. 28.30 2,716.90 Per Metre 92.75 8,911.45
ix) 95 mm sq (37/0.072) Per Rft. 29.05 3,750.50 Per Metre 95.35 12,301.65
x) 120 mm sq (37/0.083) Per Rft. 29.90 4,711.05 Per Metre 98.05 15,452.30
xi) 150 mm (37/0.093) Per Rft. 34.90 5,785.75 Per Metre 114.40 18,977.30
xii) 185 mm sq (37/0.103) Per Rft. 41.85 7,243.25 Per Metre 137.30 23,757.95

chapter-24(Electric Installation).xls Page 170


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

xiii) 240 mm sq (37/0.114) Per Rft. 52.30 10,033.50 Per Metre 171.60 32,909.95
xiv) 300 mm sq (61/0.099) Per Rft. 52.30 12,486.35 Per Metre 171.60 40,955.30
xv) 400 mm sq (61/0.114) Per Rft. 58.15 15,996.65 Per Metre 190.65 52,468.95

14 Supply and erection of M.S. sheet box of 16 SWG, 10 cm (4") 38.1


deep, with 4.75 mm thick (3/16") bakelite sheet top, for to
recessed wiring, including making holes for regulators, 38.7
switches, plugs, etc.
i) 10 x 10 cm (4"x4") Each 171.60 277.20 Each 171.60 277.20
ii) 17.5 x 10 cm (7"x4") Each 214.50 380.60 Each 214.50 380.60
iii) 22.5 x 10 cm (9"x4") Each 286.00 489.40 Each 286.00 489.40
iv) 20 x 25 cm (8"x10") Each 343.20 698.40 Each 343.20 698.40
v) 25 x 30 cm (10"x12") Each 429.00 923.20 Each 429.00 923.20
vi) 30 x 35 cm (12"x14") Each 572.00 1,203.00 Each 572.00 1,203.00

15 Supply and erection of round block of Sahl wood, 10x4 cm Each 49.05 77.85 Each 49.05 77.85 38.1
(4"x1½") thick.

16 Supply and erection of teak wood board, 4.5 cm (1¾") thick. 38.1

i) 17.5 x 10 cm (7"x4") Each 68.65 145.00 Each 68.65 145.00


ii) 22.5 x 10 cm (9"x4") Each 68.65 157.00 Each 68.65 157.00
iii) 20 x 25 cm (8"x10") Each 76.25 176.65 Each 76.25 176.65
iv) 25 x 30 cm (10"x12") Each 85.80 245.20 Each 85.80 245.20
v) 30 x 35 cm (12"x14") Each 98.05 317.45 Each 98.05 317.45

17 Supply and erection of Sahl wood board, 4.5 cm (1¾") thick.

i) 17.5 x 10 cm (7"x4") Each 68.65 124.35 Each 68.65 124.35


ii) 22.5 x 10 cm (9"x4") Each 68.65 148.35 Each 68.65 148.35
iii) 20 x 25 cm (8"x10") Each 76.25 164.65 Each 76.25 164.65
iv) 25 x 30 cm (10"x12") Each 85.80 192.20 Each 85.80 192.20
v) 30 x 35 cm (12"x14") Each 98.05 231.75 Each 98.05 231.75

18 Supply and erection of iron/aluminum clad, 500 volts main 38.1 When the base frame is already
switches with kitkat fuses, on angle iron board with 3 mm installed, the labour and composite
(1/8") thick M.S. sheet covering, including bonding to earth rates will be reduced as follows:- For
with necessary flexible pipe and thimbles, etc. 15 to 35 Amps. by Rs. 21.20 and Rs.
145.50. For 60 to 65 Amps. by Rs.
a) double pole: 38.80 and Rs. 252.60. For 100 Amps.
by Rs. 38.80 and Rs. 350.80.
i) 15/20 Amp. Each 1,144.00 2,892.90 Each 1,144.00 2,892.90
ii) 30/35 Amp. Each 1,144.00 3,275.20 Each 1,144.00 3,275.20
iii) 60/65 Amp. Each 1,716.00 4,365.10 Each 1,716.00 4,365.10
iv) 100 Amp. Each 1,716.00 5,053.30 Each 1,716.00 5,053.30

b) triple pole:
i) 15/20 Amp. Each 1,716.00 4,021.80 Each 1,716.00 4,021.80

chapter-24(Electric Installation).xls Page 171


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

ii) 30/35 Amp. Each 1,144.00 3,982.25 Each 1,144.00 3,982.25

c) triple pole with neutral link:


i) 30/35 Amp. Each 1,144.00 4,265.45 Each 1,144.00 4,265.45
ii) 60/65 Amp. Each 1,716.00 5,362.75 Each 1,716.00 5,362.75
iii) 100 Amp. Each 2,247.95 6,523.45 Each 2,247.95 6,523.45

19 Supply and erection of iron/aluminum clad, 500 volts main When the base frame is already
switches with triple pole and neutral link and HRC fuses, on 38.1 installed, the labour & composite
angle iron board with 3 mm (1/8") thick M.S. sheet covering, rates will be reduced as follows:-
including bonding to earth with necessary flexible pipe and
thimbles. i) For 60/65 Amp. by Rs. 21.20 and
Rs. 145.50.
60/65 Amp Each 1,716.00 5,249.30 Each 1,716.00 5,249.30 ii) For 100 to 300 Amp. by Rs. 21.20
100 Amp Each 2,247.95 7,497.85 Each 2,247.95 7,497.85 and Rs. 350.80
150 Amp Each 2,247.95 9,704.40 Each 2,247.95 9,704.40 iii) For 400 to 500 Amp. by Rs. 42.20
200 Amp Each 5,148.00 15,786.70 Each 5,148.00 15,786.70 and Rs. 526.20
300 Amp Each 5,148.00 17,967.35 Each 5,148.00 17,967.35
400 Amp Each 7,293.00 23,265.10 Each 7,293.00 23,265.10
500 Amp Each 7,722.00 30,913.50 Each 7,722.00 30,913.50

20 Supply and erection of iron/aluminum clad, branch ditto When the base frame is already
distribution board, 250 volt, on angle iron frame of suitable installed the labour and composite
size with 3 mm (1/8") M.S. sheet covering: rates will be reduced by Rs. 19.50 &
Rs. 152.20 respectively.
i) 2 way, 15 Amp per way Each 572.00 1,264.25 Each 572.00 1,264.25
ii) 3 way, 15 Amp per way Each 572.00 1,324.25 Each 572.00 1,324.25
iii) 4 way, 15 Amp per way Each 572.00 1,396.25 Each 572.00 1,396.25
iv) 5 way, 15 Amp per way Each 572.00 1,468.25 Each 572.00 1,468.25
v) 6 way, 15 Amp per way Each 572.00 1,540.25 Each 572.00 1,540.25
vi) 7 way, 15 Amp per way Each 572.00 1,612.25 Each 572.00 1,612.25
vii) 8 way, 15 Amp per way Each 572.00 1,684.25 Each 572.00 1,684.25
viii) 9 way, 15 Amp per way Each 572.00 1,744.25 Each 572.00 1,744.25
ix) 10 way, 15 Amp per way Each 572.00 1,804.25 Each 572.00 1,804.25
x) 11 way, 15 Amp per way Each 572.00 1,864.25 Each 572.00 1,864.25
xi) 12 way, 15 Amp per way Each 572.00 1,924.25 Each 572.00 1,924.25
xii) 2 way, 30 Amp per way Each 858.00 1,514.25 Each 858.00 1,514.25
xiii) 3 way, 30 Amp per way Each 858.00 1,550.25 Each 858.00 1,550.25
xiv) 4 way, 30 Amp per way Each 858.00 1,580.25 Each 858.00 1,580.25
xv) 5 way, 30 Amp per way Each 858.00 1,634.25 Each 858.00 1,634.25
xvi) 6 way, 30 Amp per way Each 858.00 1,730.25 Each 858.00 1,730.25
xvii) 7 way, 30 Amp per way Each 858.00 1,790.25 Each 858.00 1,790.25
xviii) 8 way, 30 Amp per way Each 858.00 1,874.25 Each 858.00 1,874.25
xix) 9 way, 30 Amp per way Each 858.00 1,910.25 Each 858.00 1,910.25
xx) 10 way, 30 Amp per way Each 858.00 2,030.25 Each 858.00 2,030.25

chapter-24(Electric Installation).xls Page 172


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

21 Supply and erection of bus bars, for 500 volts 3 phase A.C. When the base frame is already
supply with four copper bars, including glazed porcelain 38.1 installed the labour and composite
bridges, on angle iron board, fixed with rag bolts and M.S. rates will be reduced by Rs. 21.20 and
sheet box 1.5 mm thick, etc. complete:- Rs. 145.50 respectively.

i) 60 Amp. with 4 copper bars Each 1,923.90 4,976.30 Each 1,923.90 4,976.30
size 1½"x1/8" (40 x 3 mm)
ii) 100 Amp. with 4 copper bars Each 1,923.90 4,976.30 Each 1,923.90 4,976.30
size 1½"x1/8" (40 x 3 mm)
iii) 200 Amp with 4 copper bars Each 2,989.80 6,212.15 Each 2,989.80 6,212.15
size 2"x1/8" (50x 3 mm)
iv) 300 Amp with 4 copper bars Each 3,861.00 7,083.35 Each 3,861.00 7,083.35
size 2"x3/16" (50x 5 mm)
v) 500 Amp with 4 copper Each 2,352.90 6,452.05 Each 2,352.90 6,452.05
size 2"x1/4" (50x 6 mm)

22 i) Supply and erection of plain pendent lamp holder, Each 35.75 289.85 Each 35.75 289.85 38.1
complete with bakelite lamp holder and flexible twin wire
23/0.0076" upto 2 metre length (without bulb and shade).

ii) Extra for additional length of flexible wire, beyond Per Rft. -- 1.65 Per Metre -- 5.45
2 metres.

23 Supply and erection of counter weight pedent with porcelain Each 71.50 551.80 Each 71.50 551.80 38.1
counter weight, and fitting on bakelite lamp holder, with
flexible twin wire 23/0.0076" complete (without bulb and
shade).

24 Supply and erection of stiff pedent with brass/metal pipe 6.3 Each 99.65 994.55 Each 99.65 994.55 ditto
cm (2.5") long, and 15 mm (½") dia brass oxidised or painted,
along with brass lamp holder with VIR/PVC cable 3/0.74 mm
(3/0.029").

25 Supply and erection of 22.5 cm (9") long swan neck plain Each 103.10 286.80 Each 103.10 286.80 ditto
brass/steel brass oxidised bracket lamp holder, complete.

26 Supply and erection of wall type/pole type bracket, with double Each 142.35 993.00 Each 142.35 993.00 ditto
cover water tight reflector, flexible wire and brass bolder.

27 Supply and erection of bakelite button holder shade, large Each 23.55 104.85 Each 23.55 104.85 ditto
size.

28 Supply and erection of call bell 220/250 volts, fixed on teak Each 99.65 502.15 Each 99.65 502.15 38.1
wood board 17.5x10 cm (7"x4").

29 Supply and erection of bell push or bed switch, with 5 metres Each 21.45 614.25 Each 21.45 614.25 38.1
twin flexible wire 23/0.0076".

30 Supply and erection of ceiling rose, bakelite. Each 35.75 67.65 Each 35.75 67.65 ditto

chapter-24(Electric Installation).xls Page 173


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

31 Supply and erection of switches 5 Amp.

i) open type Each 34.30 73.30 Each 34.30 73.30 ditto


ii) piano type Each 34.30 73.30 Each 34.30 73.30
iii) ring type, recessed Each 34.30 69.70 Each 34.30 69.70
iv) plate type, recessed Each 34.30 101.65 Each 34.30 101.65
v) double control, open type Each 46.25 114.75 Each 46.25 114.75
vi) double control, ring type recessed Each 46.25 107.70 Each 46.25 107.70
vii) double control, piano type Each 46.25 107.70 Each 46.25 107.70

32 Supply and erection of switches 10/15 Amp. ditto

i) open type Each 34.30 74.50 Each 34.30 74.50


ii) recessed type Each 34.30 88.70 Each 34.30 88.70

33 Supply and erection of wall socket with 3 pin 5 Amp, shoe. Each 34.30 126.90 Each 34.30 126.90 ditto

34 Supply and erection of 3 pin. 5 Amp wall socket. Each 34.30 91.50 Each 34.30 91.50 ditto

35 Supply and erection of 3 pin, 10/15 Amp. wall socket. ditto

i) open type Each 34.30 84.45 Each 34.30 84.45


ii) recessed type Each 34.30 135.40 Each 34.30 135.40

36 Supply and erection of 3 pin switch and plug combined, ditto


recessed type.

i) 5 Amp Each 34.30 113.30 Each 34.30 113.30


ii) 10/15 Amp Each 34.30 151.10 Each 34.30 151.10

37 Supply and erection of 3 pin 10/15 Amp. wall socket with shoe, Each 34.30 224.60 Each 34.30 224.60 ditto
open type.

38 Supply and erection of cut out, bakelite. ditto


i) open type Each 19.05 66.35 Each 19.05 66.35
ii) recessed type Each 19.05 73.45 Each 19.05 73.45

39 Supply and erection of button holder. 38.1

i) bakelite large size Each 21.45 54.55 Each 21.45 54.55


ii) brass Each 21.45 68.75 Each 21.45 68.75

40 Supply and erection of brass bracket with holder. Each 28.60 132.50 Each 28.60 132.50 ditto

41 Supply and erection of bell push open/recessed type Each 19.05 52.20 Each 19.05 52.20 ditto
(without flexible wire).

chapter-24(Electric Installation).xls Page 174


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

42 Supply and erection of kitkat, 500 volt: ditto

i) 15/20 Amp Each 33.90 121.70 Each 33.90 121.70


ii) 30/35 Amp Each 37.00 141.75 Each 37.00 141.75
iii) 60/65 Amp Each 56.50 179.95 Each 56.50 179.95
iv) 100 Amp Each 63.60 238.00 Each 63.60 238.00
v) 200 Amp Each 72.65 360.35 Each 72.65 360.35
vi) 300 Amp Each 72.65 501.95 Each 72.65 501.95
vii) 400 Amp Each 94.10 665.00 Each 94.10 665.00
viii) 500 Amp Each 94.10 881.90 Each 94.10 881.90

43 Supply and erection of tube light, including rod, choke, starter 38.1
with frame, flexible wire, including connection from ceiling
rose, etc., complete.

i) double rod (80 watts) with two chokes and 2 starters. Per set 588.25 2,181.65 Per set 588.25 2,181.65

ii) single rod (40 watts) with one choke and one starter. ditto 470.60 1,235.30 ditto 470.60 1,235.30

iii) round tube, 32 watt, with one choke and one starter, Each 470.60 1,243.45 Each 470.60 1,243.45
without cover.

iv) round tube, 32 watt with one chock and one starter, with ditto 392.15 1,334.95 ditto 392.15 1,334.95
cover.

44 Providing and fixing M.S. iron box for housing main switches, ditto
made of 1.5 mm (1/16") thick M.S. sheet, with locking
arrangement, including painting:-
i) 60x35x15 cm (24"x14"x6") Each 1,230.10 6,810.55 Each 1,230.10 6,810.55
ii) 95x40x20 cm (38"x16"x8") Each 1,783.10 8,766.50 Each 1,783.10 8,766.50
iii) 105x52.5x22.5 cm (42"x21"x9") Each 2,713.25 12,179.30 Each 2,713.25 12,179.30
iv) 135x70x27.5 cm (54"x28"x11") Each 2,996.40 18,197.55 Each 2,996.40 18,197.55

45 Supply and erection of girder clamp hook, 16 mm (5/8") with Each 78.45 237.00 Each 78.45 237.00 38.1
M.S. plate 25x6 mm (1"x¼"), with bolts and nuts for hanging &
ceiling fans. 38.10

46 Supply and erection of girder strut, of M.S. tee section Each 99.65 2,393.10 Each 99.65 2,393.10 ditto
40x40x6 mm (1½"1½"x ¼"), complete with clamp, bolts and
nuts, etc., including fixing with cement concrete 1:3:6.

chapter-24(Electric Installation).xls Page 175


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

47 Supply and erection of roof suspension hook, 16 mm (5/8") Each 106.80 3,124.70 Each 106.80 3,124.70 38.1
dia rod with 75x40x3 mm (3"x1½"x1/8") M.S. steel channel,
with clamp, bolts and nuts, etc., including fixing with cement
concrete 1:3:6.

48 Supply and erection of roof suspension hook of M.S plate Each 142.35 845.95 Each 142.35 845.95
75x40x12.7mm (3"x1½"x½") with 16 mm (5/8") hook complete
with bolts, nuts and fixing with cement concrete 1:3:6

49 Supply and erection of 3/8" (10 mm) dia M.S. bar fan hook, Each 44.00 69.50 Each 44.00 69.50 ditto
placed at the time of casting of slab.

50 Erection of circular L.T. pole in cement concrete 1:3:6 one Each 1,203.60 4,794.55 Each 1,203.60 4,794.55 38.12
metre below ground level (excluding the cost of pole),
including cement concrete collar (1:2:4) excavation of
foundation, and finishing surface.

51 Supply and erection of bracket of M.S. channel 75x40x6 mm


(3"x1½"x¼") section:-
i) 0.60 metre (2') long for 2 lines. Each 306.45 1,009.35 Each 306.45 1,009.35
ii) 1.200 metre (4') long for 4 lines. Each 357.50 2,218.30 Each 357.50 2,218.30

52 Supply and erection of anchor rod Henley type for pole, Per Rft. 18.55 40.45 Per Metre 60.90 132.75 38.14
including necessary clamps and 7/12" stay wire, straining
screws, etc., erected in cement concrete 1:3:6 and collar of
cement concrete.

53 Supply and erection of stay for house service pipe, erected Per Rft. 29.90 63.25 Per Metre 98.05 207.45 ditto
with straining screws and 7/14" stay wire, complete.

54 Supply and erection of house service pipe Henley (G.I. pipe Per Rft. 130.80 655.10 Per Metre 429.00 2,148.75
water quality) or pole type, 50 mm (2") dia, erected to instal
insulated overhead line,include shackle insulator for holding
insulated wire and straining devices for bearer wire and other
accessories etc., complete.
55 Supply and erection of house service pipe 50 mm (2") dia G.I. Per Rft. 108.30 628.95 Per Metre 355.30 2,063.00
pipe Henley or pole type for bare copper wire overhead line,
including shackle insulator, straining devices and other
accessories etc.

56 Supply and erection of lightning arrestor horn type, complete. Each 597.95 3,783.95 Each 597.95 3,783.95

57 Supply and erection of shackle insulator, medium size. Each 80.90 364.10 Each 80.90 364.10 38.12

58 Supply and erection of pin insulator, green medium size. Each 80.90 151.70 Each 80.90 151.70 ditto

59 Supply and erection of bare copper conductor wire No. 2 to Per Kg 42.05 2,690.45 Per Kg 42.05 2,690.45 38.1
No. 10 SWG, including binding wire No. 16 SWG.

chapter-24(Electric Installation).xls Page 176


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

60 Supply and erection of G.I. wire of all sizes, including binding Per Kg 42.05 314.45 Per Kg 42.05 314.45 ditto
wire No. 16 SWG for support of rubber wire or earthing wire,
pole to pole etc.

61 Wiring overhead line in 2 single core, PVC/weather proof 38.12


cable, on G.I. wire No. 8 SWG bearer wire and in house
service pipe, including connection through joint box.

i) 3/0.74 mm (3/0.029") Per Rft. 10.15 31.00 Per Metre 33.20 101.70
ii) 7/0.74 mm (7/0.029") ditto 10.15 47.90 ditto 33.20 157.10
iii) 7/0.91 mm (7/0.036") ditto 10.15 60.00 ditto 33.20 196.70
iv) 7/1.12 mm (7/0.044") ditto 10.15 79.00 ditto 33.20 259.10

62 Supply and erection of all aluminum stranded hard drawn bare Per Rft. 20.10 65.80 Per Metre 66.00 215.75 38.1
conductor, of size 7/3.099 mm (7/0.122").

63 Supply and erection of street light pole bracket 30 mm (1¼") Each 498.30 2,555.85 Each 498.30 2,555.85
G.I. pipe 2 metre long, complete with 2 No. pole clamp.
64 Supply and erection of pole mounted street light, holders,
shade and glass, etc., for fitting 125/250 watts mercury vapour
lamp (excluding cost of lamps):
i) G.E.C. design Each 996.60 4,409.15 Each 996.60 4,409.15
ii) Philips design ditto 996.60 5,093.40 ditto 996.60 5,093.40

65 Supply and fitting of mercury vapour lamp, complete with


choke set.
i) 125 watt lamp Each 392.15 1,808.15 Each 392.15 1,808.15
ii) 250 watt lamp ditto 470.60 3,019.40 ditto 470.60 3,019.40

66 Manufacture and erection of angle iron lattice steel structure Each 17,121.90 60,703.65 Each 17,121.90 60,703.65 38.13 The composite rate will be reduced
pole (36.0') 10,923 mm long 9348 mm (30.5') above ground or increased by Rs. 36.50 for each
level) 355 mm (14") square at base and 204 mm (8") square at (100 mm) of reduction or addition in
top for electric distribution line, using 1¼"x1¼"x3/16" (30x30x5 the height of the pole above ground
mm) angle iron legs and ¾"x¾"1/8" (20x20x3 mm) angle iron level.
bracing 420 mm (17") long fixed between legs on all the four
sides in diagonal position, and 1¾"x1¾"x3/16"(45x45x5 mm)
angle iron on top and 4 bands of M.S. flat iron 2"x¼" (50x6 mm)
305 mm (12") centre to centre, as per standard drawing
including silver painting of pole 3 coats, excavation and refilling
of foundation cement concrete 1:2:4. 6'-0"x1'-8"x1'-8"
(1807x500x500 mm) for foundation, etc, complete in all
respects.

chapter-24(Electric Installation).xls Page 177


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

67 Manufacture and erection of galvanized angle iron lattice steel Each 16,131.15 94,502.45 Each 16,131.15 94,502.45 38.13 The composite rate will be reduced
structure pole 37 ft. (11.25 m) long 30 ft. (9 m) above ground or increased by Rs. 237.00 for each
level), 34" square (850 mm) at base, 13.75" (35 mm) square at foot (300 mm) of reduction or
top, for electric distribution line, using 2"x2"x5/32" addition in the height of the pole
(50x50x4mm) high tensile steel angle iron legs, and 1-3/8"x above ground level.
1-3/8"x1/8" (35x35x3 mm) M.S. angle iron bracings fixed
between legs on all the four sides in diagonal position as per
standard drawing including silver painting of pole, excavation
and refilling of foundation, one ft. (300 mm) thick cement
concrete 1:3:6 foundation of outer size 8'x3½'x3½'
(2400x1050x1050 mm), etc. complete in all respects.

68 Supplying, installation testing and commissioning of Octagonal shape electric


street light pole, made of hot dipped 4.5 mm thick (7 SWG) galvanized steel,
tappered from 225 mm at bottom to 100 mm at top, with 1500 mm x 60 mm x
4mm thick dia. arm for luminaire installation, duly G.I.welded with
470x470x20 mm base plate with the help of 4 no triangular stiffeners
100x350x20 mm of GI sheet, with built in junction box with shutter, i/c the
cost of nuts & J-rag bolts, duly fixed in prelaid concrete foundation, foundation
will be paid additionally as approved and directed by the Engineer In charge.

a) Single Arm
(i) 10 mtr height Each 3,847.80 106,327.30 Each 3,847.80 106,327.30
(ii) 12 mtr height Each 3,847.80 120,475.60 Each 3,847.80 120,475.60
(iii) 15 mtr height Each 3,847.80 141,698.05 Each 3,847.80 141,698.05
b) Double Arm
(i) 10 mtr height Each 3,847.80 109,969.30 Each 3,847.80 109,969.30
(ii) 12 mtr height Each 3,847.80 124,117.60 Each 3,847.80 124,117.60
(iii) 15 mtr height Each 3,847.80 145,340.05 Each 3,847.80 145,340.05
69 Supplying, installation and commissioning of LED Cobra-head Luminaries of
specified wattage and lumens conforming to IP 66 & IK 08 or above
Philips/Osram/Thorn or equivalent with corrosion resistant die casted
Aluminum housing, silicon gasket in special groove, UV stable & scratch
resistant synthetic materials, thermally hardened glass complete with LED
Chip (Philips Lumiled/Cree/Nichia/Osram make or equivalent), programmable
LED driver (Harvard/TCI/Lumotech/Philips/VOSSLOH Schwabe/Lightech
make or equivalent), minimum 10kV surge protection rating i/c the cost of all
accessories/components required for proper operation, fully flexible for future
upgradation and easy replacements for maintenance purposes, bucket elevator
charges as approved and directed by the Engineer Incharge.

a) 140 Lm/Watt
(i) 30 Watt with 4200 lumens Each 343.20 47,584.60 Each 343.20 47,584.60
(ii) 50 Watt with 7000 Lumens Each 343.20 50,186.15 Each 343.20 50,186.15
(iii) 60 Watt with 8400 lumens Each 343.20 51,592.40 Each 343.20 51,592.40
(iv) 90 Watt with 12600 Lumens Each 343.20 51,768.15 Each 343.20 51,768.15
(v) 120 Watt with 16800 Lumens Each 343.20 53,315.05 Each 343.20 53,315.05
(vi) 140 Watt with 19600 lumens Each 327.60 58,134.60 Each 327.60 58,134.60
(vii) 150 Watt with 21000 lumens Each 327.60 59,634.60 Each 327.60 59,634.60

chapter-24(Electric Installation).xls Page 178


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

(ix) 180 Watt with 25200 Lumens Each 327.60 62,334.60 Each 327.60 62,334.60
(x) 250 Watt with 35000 Lumens Each 327.60 64,097.10 Each 327.60 64,097.10
b) 130 Lm/Watt
(i) 30 Watt with 3900 lumens Each 327.60 37,622.10 Each 327.60 37,622.10
(ii) 50 Watt with 6500 Lumens Each 327.60 52,397.10 Each 327.60 52,397.10
(iii) 60 Watt with 7800 lumens Each 327.60 53,897.10 Each 327.60 53,897.10
(iv) 90 Watt with 11700 Lumens Each 327.60 58,653.60 Each 327.60 58,653.60
(v) 120 Watt with 15600 Lumens Each 327.60 60,273.60 Each 327.60 60,273.60
(vi) 140 Watt with 18200 lumens Each 327.60 61,407.60 Each 327.60 61,407.60
(vii) 150 Watt with 19500 lumens Each 327.60 63,027.60 Each 327.60 63,027.60
(ix) 180 Watt with 23400 Lumens Each 327.60 66,267.60 Each 327.60 66,267.60
(x) 250 Watt with 32500 Lumens Each 327.60 68,333.10 Each 327.60 68,333.10
c) 120 Lm/Watt
(i) 30 Watt with 3600 lumens Each 327.60 48,812.10 Each 327.60 48,812.10
(ii) 40 Watt with 4800 Lumens Each 327.60 49,397.10 Each 327.60 49,397.10
(iii) 50 Watt with 6000 lumens Each 327.60 46,172.10 Each 327.60 46,172.10
(iv) 60 Watt with 7200 Lumens Each 327.60 46,884.60 Each 327.60 46,884.60
(v) 90 Watt with 10800 Lumens Each 327.60 51,687.60 Each 327.60 51,687.60
(vi) 120 Watt with 14400 Lumens Each 327.60 53,307.60 Each 327.60 53,307.60
(vii) 140 Watt with 16800 lumens Each 327.60 57,033.60 Each 327.60 57,033.60
(viii) 150 Watt with 18000 lumens Each 327.60 58,653.60 Each 327.60 58,653.60
(ix) 180 Watt with 21600 Lumens Each 327.60 63,392.10 Each 327.60 63,392.10
(x) 250 Watt with 30000 Lumens Each 327.60 66,227.10 Each 327.60 66,227.10

70 Earthing of iron clad/aluminum switches, etc. with G.I. wire No. Job 2,131.80 9,635.35 Job 2,131.80 9,635.35
8 SWG in G.I. pipe 15 mm (½") dia, recessed or on surface of
wall and floor, complete with 1.5 metre long G.I. pipe, 50 mm
(2") dia with reducing socket 4 to 5 metre below ground level,
and 2 metre away from building plinth.

71 Earthing of Metallic cases, etc. with G.I. wire No. 8 SWG, in 38.11
15 mm (½") dia G.I. pipe, best quality:-
i) on surface, including clamps, etc. Per Rft. 22.80 141.90 Per Metre 74.75 465.50
ii) recessed in wall, including hooks, ditto 52.00 172.85 ditto 170.55 566.90
jharries and making good surface.

72 Bonding to earth with wire on surface, including cost of wire, ditto


clamps, thimbles, etc.
a) G.I. wire:
i) 8 SWG Per Rft. 10.45 23.70 Per Metre 34.30 77.65
ii) 16 SWG ditto 10.45 13.70 ditto 34.30 44.95

b) Copper wire:

i) 16 SWG Per Rft. 10.45 28.05 Per Metre 34.30 92.00


ii) 20 SWG ditto 10.45 16.55 ditto 34.30 54.20

chapter-24(Electric Installation).xls Page 179


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

73 Erection only, of lightning conductor of copper tape, including Per Rft. 36.45 45.85 Per Metre 119.60 150.45 38.11 Rate includes all materials required
supply of copper staple and copper nails and cement, sand in erection (excluding copper tape
mortar. lightning conductor).

74 Supply and erection of 600x600x3 mm (2'x2'x1/8") copper Each 1,421.20 7,582.60 Each 1,421.20 7,582.60 ditto
plate, including revitting to copper tape and placing in mixture
of salt and charcoal, etc.

75 Supply and erection of copper tape, including copper staple


copper nails, cement, sand, etc.

i) tape 40x3 mm (1½"x1/8") Per Rft. 52.00 397.20 Per Metre 170.55 1,302.85
ii) tape 50x3 mm (2"x1/8") ditto 52.00 467.85 ditto 170.55 1,534.55

76 Supply and erection of 25 mm (1") dia and one metre long Job 996.60 4,297.30 Job 996.60 4,297.30
lightning conductor copper rod with 5 spikes on ball and base,
etc. complete.

77 Supply and erection of electric energy meter, including meter 38.1


testing fee, etc.

a) single phase:

i) 1x10 Amp, 250 volts Each 429.00 3,957.00 Each 429.00 3,957.00
ii) 1x30 Amp, 250 volts ditto 429.00 3,957.00 ditto 429.00 3,957.00

b) three phase, 4 wires:

i) 3x15 Amp, 400 volts Each 858.00 14,374.80 Each 858.00 14,374.80
ii) 3x50 Amp, 400 volts ditto 1,176.45 14,693.25 ditto 1,176.45 14,693.25
iii) 3x80 Amp, 400 volts ditto 1,176.45 14,693.25 ditto 1,176.45 14,693.25

78 Rewinding of A.C. ceiling fan, capacitor type, including cost of The credit of out turn of dismantled
wire, leatheride paper cotton tape, soldering, etc. material has been accounted for in
the rate.
i) 1200 mm (48") sweep, 275-300 RPM. Each 802.75 2,647.35 Each 802.75 2,647.35
ii) 1400 mm (56") sweep, 250-275 RPM. ditto 882.35 3,076.80 ditto 882.35 3,076.80
79 Rewinding of A.C. exhaust fan, including cost of wire, The credit of out turn of dismantled
leatheride paper, cotton tape, soldering, etc. material has been accounted for in
the rate.
i) 375 mm (15") sweep, and 1300-1500 RPM Each 572.00 1,865.85 Each 572.00 1,865.85
ii) 450 mm (18") sweep, and 1300-1500 RPM ditto 572.00 2,097.80 ditto 572.00 2,097.80

80 Rewinding of pedestal fan 600 mm (24") sweep, and 900-950 Each 686.40 2,400.00 Each 686.40 2,400.00 The credit of out turn of dismantled
RPM, including wire, leatheride paper, cotton, tape, etc. material has been accounted for in
the rate.

chapter-24(Electric Installation).xls Page 180


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

81 Supply and fitting of regulator knob with shaft Each 107.25 220.55 Each 107.25 220.55 38.1
and plate of electric fan regulator.

82 Supply and fitting of capacitor 2.2 uF, for ceiling fans. Each 85.80 217.80 Each 85.80 217.80 ditto

83 Supply and fitting of ball bearing of size Each 107.25 277.15 Each 107.25 277.15 ditto
6201, 6202 or 6203 for ceiling fans.

84 Rewinding regulator of ceiling fan 48"/56" (1200/1400 mm) Each 214.50 551.70 Each 214.50 551.70 The credit out turn of dismantled
sweep, to control 3/4 speeds. material has been accounted for in
the rate.
85 Erection of ceiling fan alongwith regulator (all sizes), including Each 366.00 469.65 Each 366.00 469.65
carriage from local Railway Station/Store to site of work,
electric wire/cable for suspension rod and board connection,
and cutting, threading on the rod, where necessary.

86 Suppling,Installation and comissioning of MCB (Miniature Circuit Breaker) of


specified rating made of LEGRAND FRANCE/ GE U.S.A / SCHNEIDER
GERMANY /SIEMEN GERMAN/TERASAKI JAPAN/ ABB
SWITZERLAND in prelaid DBs and Panels i/c the cost of screwes,necessary
wire complete in all respect as approved and directed by the Engineer Incharge.

a) Single Pole
(i) 1-4 Amp (6KA,10KA) Each 34.30 484.30 Each 34.30 484.30
(ii) 6-40 Amp (6 KA) Each 34.30 1,103.05 Each 34.30 1,103.05
(iii) 6-63 Amp (10 KA) Each 34.30 1,299.95 Each 34.30 1,299.95
b) Double Pole
(i) 1-4 Amp(6 KA,10 KA) Each 34.30 2,059.30 Each 34.30 2,059.30
(ii) 6-40 Amp (6 KA) Each 34.30 3,353.05 Each 34.30 3,353.05
(iii) 6-63 Amp (10 KA) Each 34.30 5,293.70 Each 34.30 5,293.70
c) Tripple Pole
(i) 1-4 Amp(6 KA,10 KA) Each 34.32 5,794.32 Each 34.32 5,794.32
(ii) 6-40 Amp (6 KA) Each 34.30 6,754.30 Each 34.30 6,754.30
(iii) 6-63 Amp (10 KA) Each 34.30 8,434.30 Each 34.30 8,434.30
d) Four Pole
(i) 1-4 Amp (6KA,10KA) Each 34.30 9,034.30 Each 34.30 9,034.30
(ii) 6-40 Amp(6 KA) Each 34.30 9,034.30 Each 34.30 9,034.30
(iii) 6-63 Amp (10 KA) Each 34.30 10,264.30 Each 34.30 10,264.30
87 Supplying ,Installation and commissioning of MCCB (Moulded Case Circuit
Breaker) of specified rating made of LEGRAND FRANCE/ GE U.S.A /
SCHNEIDER GERMANY / TERASAKI JAPAN/SIEMEN/ABB
SWITZERLAND (with fixed Thermal-Magnetic Trip ) in prelaid DBs and
Panels i/c the cost of screws, necessary wire complete in all respect as
approved and directed by the Engineer Incharge.
a) Tripple Pole
(i) 15-63 Amp(7.5 KA) Each 34.30 11,254.30 Each 34.30 11,254.30
(ii) 15-100 Amp (10 KA,15KA) Each 34.30 11,434.30 Each 34.30 11,434.30
(iii) 15-100 Amp(18 KA) Each 34.30 12,634.30 Each 34.30 12,634.30
(iv) 125-250 Amp(18 KA) Each 34.30 23,494.30 Each 34.30 23,494.30
(v) 15-100 Amp(25 KA) Each 34.30 16,234.30 Each 34.30 16,234.30

chapter-24(Electric Installation).xls Page 181


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

(vi) 125-250 Amp(25KA) Each 34.30 31,654.30 Each 34.30 31,654.30


(vii) 15-100 Amp(36 KA) Each 34.30 17,434.30 Each 34.30 17,434.30
(viii) 125-150 Amp(36 KA) Each 34.30 18,094.30 Each 34.30 18,094.30
(ix) 200-250 Amp(36 KA) Each 34.30 39,814.30 Each 34.30 39,814.30
(x) 300-630 Amp(36 KA) Each 34.30 62,434.30 Each 34.30 62,434.30
(xi) 300-630 Amp(50 KA) Each 34.30 72,034.30 Each 34.30 72,034.30
b) Four Pole
(i) 15-100 Amp(18KA) Each 34.30 28,834.30 Each 34.30 28,834.30
(ii) 125-250 Amp(18 KA) Each 34.30 42,784.30 Each 34.30 42,784.30
(iii) 15-100 Amp(25 KA) Each 34.30 30,071.80 Each 34.30 30,071.80
(iv) 125-250 Amp(25 KA) Each 34.30 45,878.05 Each 34.30 45,878.05
(v) 15-200 Amp(36 KA) Each 34.30 54,203.05 Each 34.30 54,203.05
(vi) 225-630 Amp(36 KA) Each 34.30 72,596.80 Each 34.30 72,596.80
(vii) 300-630 Amp(50 KA) Each 34.30 118,159.30 Each 34.30 118,159.30
88 Supplying,Installation and commissioning of MCCB (Moulded Case Circuit
Breaker) of specified rating made of LEGRAND FRANCE/ GE U.S.A /
SCHNEIDER GERMANY / TERASAKI JAPAN/ABB SWITZERL(with
adjustable Thermal-Magnetic Trip ) in prelaid DBs and Panels i/c the cost of
screws, necessary wire complete in all respect as approved and directed by the
Engineer Incharge.
a) Tripple Pole With Adjustable Thermal-M agnetic Trip /Electronic
Trip (60-100% )
(i) 25-100 Amp(25 KA) Each 34.30 26,854.30 Each 34.30 26,854.30
(ii) 125-400 Amp(25 KA) Each 34.30 51,034.30 Each 34.30 51,034.30
(iii) 32-100 Amp(36 KA) Each 34.30 37,234.30 Each 34.30 37,234.30
(iv) 125-160 Amp(36 KA) Each 34.30 48,034.30 Each 34.30 48,034.30
(v) 200-250 Amp(36 KA) Each 34.30 68,434.30 Each 34.30 68,434.30
(vi) 300-1000 Amp(36 KA) Each 34.30 138,634.30 Each 34.30 138,634.30
(vii) 16-100 Amp(50 KA) Each 34.30 36,634.30 Each 34.30 36,634.30
(viii) 125-160 Amp(50 KA) Each 34.30 55,054.30 Each 34.30 55,054.30
(ix) 200-400 Amp(50 KA) Each 34.30 66,034.30 Each 34.30 66,034.30
(x) 630-1600 Amp(50 KA) Each 34.30 234,034.30 Each 34.30 234,034.30
(xi) 16-80 Amp(70 KA) Each 34.30 67,834.30 Each 34.30 67,834.30
(xii) 100-160 Amp(70 KA) Each 34.30 97,954.30 Each 34.30 97,954.30
(xiii) 250-630 Amp(70 KA) Each 34.30 171,394.30 Each 34.30 171,394.30
(xiv) 800-1250 Amp(70 KA) Each 34.30 280,774.30 Each 34.30 280,774.30
(xv) 1600-3200 Amp(70 KA) Each 34.30 312,034.30 Each 34.30 312,034.30
Four Pole With Adjustable Thermal-M agnetic Trip/Electronic Trip
b)
(40-100% )
(i) 25-60 Amp(25 KA) Each 34.30 27,596.80 Each 34.30 27,596.80
(ii) 80-160 Amp(25 KA) Each 34.30 38,846.80 Each 34.30 38,846.80
(iii) 32-63 Amp(36 KA) Each 34.30 32,096.80 Each 34.30 32,096.80
(iv) 80-160 Amp(36 KA) Each 34.30 40,196.80 Each 34.30 40,196.80
(v) 200-630 Amp(36 KA) Each 34.30 152,134.30 Each 34.30 152,134.30
(vi) 800-1000 Amp(36KA) Each 34.30 348,784.30 Each 34.30 348,784.30
(vii) 60-250 Amp(50 KA) Each 34.30 103,534.30 Each 34.30 103,534.30
(viii) 400-630 Amp(50 KA) Each 34.30 202,534.30 Each 34.30 202,534.30
(ix) 800 Amp(50 KA) Each 34.30 354,409.30 Each 34.30 354,409.30
(x) 1000-1250 Amp(50KA) Each 34.30 401,659.30 Each 34.30 401,659.30
(xi) 1600 Amp(50 KA) Each 34.30 517,534.30 Each 34.30 517,534.30
chapter-24(Electric Installation).xls Page 182
MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

(xii) 32-80 Amp(70 KA) Each 34.30 67,534.30 Each 34.30 67,534.30
(xiii) 100-250 Amp(70 KA) Each 34.30 112,534.30 Each 34.30 112,534.30
(xiv) 400-630 Amp(70 KA) Each 34.30 234,034.30 Each 34.30 234,034.30
(xv) 800 Amp(70 KA) Each 34.30 371,284.30 Each 34.30 371,284.30
(xvi) 1000-1600 Amp(70 KA) Each 34.30 517,534.30 Each 34.30 517,534.30
89 P/F ACB (Air Circuit Breaker) of specified rating made of LEGRAND
FRANCE/ GE U.S.A / SCHNEIDER GERMANY / TERASAKI
JAPAN/ABB SWITZERLAND in prelaid Panels i/c the cost of
screws,necessary wire complete in all respect as approved and directed by the
Engineer Incharge.
a) Tripple Pole (65 KA)
(i) 800 Amp Each 34.30 504,034.30 Each 34.30 504,034.30
(ii) 1000-1250 Amp Each 34.30 478,159.30 Each 34.30 478,159.30
(iii) 1600 Amp Each 34.30 586,834.30 Each 34.30 586,834.30
(iv) 2000 Amp Each 34.30 755,471.80 Each 34.30 755,471.80
b) Tripple Pole (85-100 KA)
(i) 2500 Amp Each 34.30 847,834.30 Each 34.30 847,834.30
(ii) 3200 Amp Each 34.30 1,080,034.30 Each 34.30 1,080,034.30
(iii) 4000 Amp Each 34.30 1,518,784.30 Each 34.30 1,518,784.30
c) Four Pole (65-100 KA)
(i) 800 Amp Each 34.30 736,346.80 Each 34.30 736,346.80
(ii) 1000 Amp Each 34.30 776,846.80 Each 34.30 776,846.80
(iii) 1250 Amp Each 34.30 844,346.80 Each 34.30 844,346.80
(iv) 1600 Amp Each 34.30 908,471.80 Each 34.30 908,471.80
(v) 2000 Amp Each 34.30 1,040,659.30 Each 34.30 1,040,659.30
(vi) 2500 Amp Each 34.30 1,378,721.80 Each 34.30 1,378,721.80
(vii) 3200 Amp Each 34.30 1,519,346.80 Each 34.30 1,519,346.80
(viii) 4000 Amp Each 34.30 1,586,284.30 Each 34.30 1,586,284.30
(ix) 6300 Amp Each 34.30 1,676,284.30 Each 34.30 1,676,284.30
90 P/F wall mounted DB (Distribution Board) made with 16SWG Sheet
(Recessded/Surface mounted Type), Powder coated Paint, i/c the cost of Lock,
Indication lights,Thimble, Copper Comb, Wiring, Netural & Earth Bar, Door
Earthing, Digital Voltmeter,Digital Ammeter,Volt Selector Switch,Ammeter
selector switch,Current Transformers and Controles Complete in all respect as
approved and directed by the Engineer Incharge (Breakers will be Paid
Separately).
(a) 6" deep
(i) 20~60A P.Cft 2,066.90 18,691.40
(ii) 75~100A P.Cft 1,672.95 13,809.80
(b) 12" deep
(i) 125~150A P.Cft 593.65 5,146.40
(ii) 160~200A P.Cft 605.55 4,512.80

chapter-24(Electric Installation).xls Page 183


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

91
P/F floor mounted Electric Panel board of required depth and size, fabricarted
with 14SWG M.S sheet (Indoor/Outdoor Type),derusting, zinc Phosphated,
finish with electro static powder coating in approved colour i/c the cost of
Lock, Indication lights,thimbles, Copper Comb, Wiring, Netural & Earth Bar,
glands,Current Transformers of specified capacity ,Door Earthing, Brass
glands,bus bars,controles complete in all respects as approved and directed by
the Engineer Incharge (Breakers will be Paid Separately).

i)
LT Switchboards
a) 2.50 Ft deep
(i)300~600A P.Cft 171.00 3,438.40
(ii)800~1200A P.Cft 171.00 4,377.05
b) 3.00 Ft deep
(i)1600~2000A P.Cft 171.00 6,873.75
(ii)2500~3200A P.Cft 179.25 10,630.80
ii) HT Switchboards
a) 3.00 Ft deep
(i)630A P.Cft 131.10 4,688.30
92 P/F floor mounted ATS (Auto Transfer Switch) panel board , fabricarted with
14S WG M.S sheet (Indoor Type) duly painted with 100 microns powder
coated paint in approved colour , front access ,extendable,insulation class of
600 volts IP-44, incomimg & outgoing connections from bottom with flexible
copper cable suitable for 415 VAC, 3-phase 4 wire, 50 HZ TPN& E system
having rated service, short circuit breaking capacity at 400VAC conformimg to
IEC-947-2 to accomodate given no of circuit components, instruments &
accessories,assembled & wired with Electrolitic Copper bus bars at 50 deg and
cables duly cleaned down to bare shining metal phosphate, manual change
Over i/c the cost of Lock, Indication lights,thimbles, Copper Comb, Wiring,
Netural & Earth Bar,CTs,Contactors,Relays, Door Earthing, Brass glands
complete in all respects as approved and directed by the Engineer Incharge.
(Breakers wil be paid additionally)

a) 1.00 Ft deep
(i) 15-40 KVA Each 8,553.60 790,029.70 Each 8,553.60 790,029.70
(ii) 50-100 KVA Each 9,411.60 801,447.70 Each 9,411.60 801,447.70
b) 2.00 Ft deep
(i)125-250 KVA Each 9,411.60 1,833,923.45 Each 9,411.60 1,833,923.45
c) 2.50 Ft deep
(i)300-500 KVA Each 11,127.60 3,491,792.95 Each 11,127.60 3,491,792.95
(ii)630-1000 KVA Each 11,127.60 5,100,512.95 Each 11,127.60 5,100,512.95

chapter-24(Electric Installation).xls Page 184


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

93 P/F PFI PLANT (Power Factor Improvement Plant) comprising of components


of required ratitngs, in MS box of 14 SWG i/c the cost of 3mm thick Backlite
sheet(Safety Sheet)Lock, thimbles, Copper Comb, Wiring, Netural & Earth
Bar, Door Earthing, brass glands,Indication lights,Push buttons,CTs,
Contactors,Controle MCB,Surge Suppressors,Auto/Manual Switches,Exhaust
Fan,Temp regulators as per WAPDA standards complete in all respects as
approved and directed by the Engineer Incharge.

(i)62.5KVAr Each 12,048.75 296,653.30 Each 12,048.75 296,653.30


(ii)100KVAr Each 12,048.75 334,633.30 Each 12,048.75 334,633.30
(iii)150KVAr Each 12,048.75 511,454.95 Each 12,048.75 511,454.95
(iv)250KVAr Each 12,048.75 750,725.15 Each 12,048.75 750,725.15
(v)300KVAr Each 13,686.75 1,027,668.50 Each 13,686.75 1,027,668.50
(vi)400KVAr Each 13,686.75 1,194,708.50 Each 13,686.75 1,194,708.50
(vii)500KVAr Each 15,113.70 1,556,328.15 Each 15,113.70 1,556,328.15
(viii)600KVAr Each 15,113.70 1,748,328.15 Each 15,113.70 1,748,328.15
(ix)800KVAr Each 15,113.70 1,990,248.15 Each 15,113.70 1,990,248.15
(x)1000KVAr Each 17,967.60 2,693,215.95 Each 17,967.60 2,693,215.95
(xi)1500KVAr Each 17,967.60 3,747,535.95 Each 17,967.60 3,747,535.95
(xii)2000KVAr Each 17,967.60 4,889,575.95 Each 17,967.60 4,889,575.95
94 Providing and fixing DB/Panel accessories of required rating and size i/c
copper screws of approved brand Complete in all respect as approved and
directed by the Engineer Incharge.
(i) Selector Switch Each 34.30 994.30 Each 34.30 994.30
(ii) Current Transformer Coil (Make: Metelx/Fico) Each 34.30 1,534.30 Each 34.30 1,534.30
(iii) Digital Voltmeter (0-600 Volt) Each 34.30 754.30 Each 34.30 754.30
(iv) Digital Ammeter (0-9999 Amp) Each 34.30 994.30 Each 34.30 994.30
(v) LED Phase Indicator Each 34.30 514.30 Each 34.30 514.30
(vi) Push Button ON/OFF (Make: Schneider/Himal/Eqv.) Each 28.60 448.60 Each 28.60 448.60
(vii) Auxiliary Contactor. (Make: Schneider/ Terasaki/ABB) Each 34.30 3,874.30 Each 34.30 3,874.30
(viii)Control MCB S/P 6A (Make: Schneider/ Terasaki/ABB) Each 34.30 1,174.30 Each 34.30 1,174.30
(ix) Surge Suppressors. Each 34.30 874.30 Each 34.30 874.30
(x) Auto/Manual Switch 3-Steps (Make: GGT/Camsco) Each 34.30 1,834.30 Each 34.30 1,834.30
(xi) Exhaust Fan with Louvers (Make: Imported/Plastim) Each 34.30 4,234.30 Each 34.30 4,234.30
(xii) Temperature Regulator 0~60C Each 34.30 1,534.30 Each 34.30 1,534.30
(xiii)Power Capacitors
(a) 12.5 KVAR Each 34.30 28,834.30 Each 34.30 28,834.30
(b) 25 KVAR Each 34.30 38,434.30 Each 34.30 38,434.30
(c) 50 KVAR Each 34.30 70,114.30 Each 34.30 70,114.30
(d) 100 KVAR Each 34.30 142,234.30 Each 34.30 142,234.30
(xiv) Power Capacitors with Harmonic Blocker
(a) for 12.5 KVAR Each 34.30 23,434.30 Each 34.30 23,434.30
(b) for 25 KVAR Each 34.30 27,244.30 Each 34.30 27,244.30
(c) for 50 KVAR Each 34.30 55,534.30 Each 34.30 55,534.30
(xv) Magnetic Contactor
(a) 25 A (AC 3) for 12.5 KVAR Each 34.30 10,594.30 Each 34.30 10,594.30
(b) 40 A (AC 3) for 25 KVAR Each 34.30 20,194.30 Each 34.30 20,194.30
(c) 80 A (AC 3) for 50 KVAR Each 34.30 39,874.30 Each 34.30 39,874.30
(d)185A (AC3) 4-Pole Each 34.30 134,434.30 Each 34.30 134,434.30
(e)630A (AC3) 4-Pole Each 34.30 546,034.30 Each 34.30 546,034.30
chapter-24(Electric Installation).xls Page 185
MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

(f)1250A ACB 65 KA (AC 3) Adj. 4-Pole Each 34.30 804,634.30 Each 34.30 804,634.30
(g)2000A ACB 65 KA Adj.(AC 3) 4-Pole Each 34.30 828,634.30 Each 34.30 828,634.30
(xvi) HRC Fuses With Base
(a) 32 Amp Each 34.30 1,354.30 Each 34.30 1,354.30
(b) 63 Amp Each 34.30 1,354.30 Each 34.30 1,354.30
(c) 125 Amp Each 34.30 2,074.30 Each 34.30 2,074.30
(xvii) Power Factor Controller
(a) 6 Steps Each 34.30 61,834.30 Each 34.30 61,834.30
(b) 12 Steps Each 34.30 68,434.30 Each 34.30 68,434.30
95 Suplying,Installation,testing and commissioning of 415-Volt ,5 Pole
(TP+N+E) compact Copper Busway (Bus Tie Duct B.T.D) of specified
size/rating comprising of 10 mm thick sandwitch copper Bus bars,insulated
with non-flammable/flame resistant resin applied at 130 OC by Automatic
Electro-static application with Mayler Class-B, housed in Aluminium Housing
i/c the cost of hangers, accessories,enclosures IP55, IEC 61439-1, complete in
all respect,spaced to a minimum reducing reactance as approved & directed by
the Engineer Incharge.
(i) 400 Amp P.Rft 65.50 20,425.70 P.Mtr 214.90 66,996.25
(ii) 630 Amp P.Rft 65.50 26,417.65 P.Mtr 214.90 86,649.90
(iii) 800 Amp P.Rft 65.50 34,993.60 P.Mtr 214.90 114,779.05
(iv) 1000 Amp P.Rft 65.50 41,603.60 P.Mtr 214.90 136,459.75
(v) 1250 Amp P.Rft 65.50 46,137.55 P.Mtr 214.90 151,331.20
(vi) 1600 Amp P.Rft 65.50 57,305.50 P.Mtr 214.90 187,962.10
(vii) 2000 Amp P.Rft 65.50 70,577.45 P.Mtr 214.90 231,494.00
(viii) 2500 Amp P.Rft 163.80 79,975.65 P.Mtr 537.25 262,320.10
(ix) 3200 Amp P.Rft 163.80 96,791.55 P.Mtr 537.25 317,476.30
(x) 3600 Amp P.Rft 163.80 106,109.45 P.Mtr 537.25 348,039.10
(xi) 4000 Amp P.Rft 163.80 116,851.45 P.Mtr 537.25 383,272.65
(xii)4250 Amp P.Rft 163.80 129,801.40 P.Mtr 537.25 425,748.50
(xiii) 5000 Amp P.Rft 180.20 146,983.25 P.Mtr 591.00 482,105.00
(xiv) 6300 Amp P.Rft 180.20 175,421.45 P.Mtr 591.00 575,382.30
96 Suplying,Installation,testing and commissioning of 415-Volt ,5 Pole
(TP+N+E) compact joint modules for Copper Busway (Bus Tie Duct B.T.D)
of specified size/rating comprising of 10 mm thick copper Bus bars,insulated
with non-flammable/flame resistant resin applied at 130 OC by Automatic
Electro-static application/with epoxy coated insulation with Mayler Class-B,
housed in Aluminium Housing i/c the cost of, accessories,enclosures IP55,
IEC 61439-1, complete in all respect,as approved & directed by the Engineer
Incharge.
(a) Flange End
(i) 400-800 Amp Each 327.60 29,823.60 Each 327.60 29,823.60
(ii) 1000-1600 Amp Each 327.60 54,903.60 Each 327.60 54,903.60
(iii) 1600-2000 Amp Each 327.60 63,015.60 Each 327.60 63,015.60
(iv) 2500-3200 Amp Each 327.60 81,124.80 Each 327.60 81,124.80
(v) 4000 Amp Each 327.60 104,415.60 Each 327.60 104,415.60
(vi) 4250-6300 Amp Each 327.60 123,903.60 Each 327.60 123,903.60
(b) Elbow 90 degree
(i) 400-800 Amp Each 327.60 29,823.60 Each 327.60 29,823.60
(ii) 1000-1600 Amp Each 327.60 45,141.60 Each 327.60 45,141.60
(iii) 1600-2000 Amp Each 327.60 57,663.60 Each 327.60 57,663.60
chapter-24(Electric Installation).xls Page 186
MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

(iv) 2500-3200 Amp Each 327.60 76,812.00 Each 327.60 76,812.00


(v) 4000-6300 Amp Each 327.60 104,413.20 Each 327.60 104,413.20
(c) Reducer/Tee jont
(i) 400-800 Amp Each 327.60 31,203.60 Each 327.60 31,203.60
(ii) 1000-1600 Amp Each 327.60 46,515.60 Each 327.60 46,515.60
(iii) 1600-2000 Amp Each 327.60 59,043.60 Each 327.60 59,043.60
(iv) 2500-3200 Amp Each 327.60 78,195.60 Each 327.60 78,195.60
(v) 4000-6300 Amp Each 327.60 107,175.60 Each 327.60 107,175.60
(d) Flexible Connector
(i) 2500-3200 Amp Each 327.60 379,443.60 Each 327.60 379,443.60
(ii) 4000-4250 Amp Each 327.60 429,063.60 Each 327.60 429,063.60
(iii) 6300 Amp Each 327.60 1,139,343.60 Each 327.60 1,139,343.60
e) 4 pole TAP OFF Units i/c the cost of, circuit breakers
(i) 400 Amp (50 KA) Each 327.60 263,247.60 Each 327.60 263,247.60
(ii) 630-800 Amp (50 KA) Each 327.60 460,047.60 Each 327.60 460,047.60
(iii) 1000-1250 Amp (50 KA) Each 327.60 545,847.60 Each 327.60 545,847.60
(iv) 1600-2000 Amp (50 KA) Each 327.60 771,567.60 Each 327.60 771,567.60
(v) 2500-6300 Amp (50 KA) Each 327.60 885,677.60 Each 327.60 885,677.60
97 Providing and fixing 3" deep cable tray with straight flange fabricated with
perforated G.I. Sheet of specified guage,size and depth duly wall
supported/ceiling hung on painted brackets of MS angle iron of 1"x1"x1/8" and
MS patti of 1-1/2"x3/16" size @ 5 ft C/C, hangers i/c the cost of hardwares as
approved and directed by the Engineer Incharge.
(a) 16SWG
(i) 4"x3" P.Rft 149.50 338.85 P.Mtr 490.35 1,111.35
(ii) 6"x3" P.Rft 149.50 406.15 P.Mtr 490.35 1,332.15
98 Providing and fixing 4" deep cable tray with straight flange fabricated with
perforated G.I. Sheet of specified guage,size and depth duly wall
supported/ceiling hung,supported on painted brackets of MS angle iron of 1-
1/2"x1-1/2"x3/16" and MS patti of 1-1/2"x3/16" size @ 5 ft C/C, hangers i/c
the cost of hardwares as approved and directed by the Engineer Incharge.

(a) 16SWG
(i) 4"x4" P.Rft 150.50 393.55 P.Mtr 493.55 1,290.80
(ii) 9"x4" P.Rft 179.40 647.95 P.Mtr 588.40 2,125.30
(iii) 10"x4" P.Rft 179.40 1,009.85 P.Mtr 588.40 3,312.35
99 Providing and fixing cable tray with straight flange fabricated with perforated
G.I. Sheet of specified guage,size and depth duly supported on painted brackets
of MS angle iron of 1-1/2"x1-1/2"x3/16" and MS patti of 1-1/2"x3/16" size @
3 ft C/C, hangers i/c the cost of hardwares as approved and directed by the
Engineer Incharge.
(a) 14 SWG
(i) 12"x4" P.Rft 179.40 1,094.75 P.Mtr 588.40 3,590.80
(ii) 16"x4" P.Rft 179.40 1,280.95 P.Mtr 588.40 4,201.60
(iii) 24"x4" P.Rft 179.40 1,555.90 P.Mtr 588.40 5,103.40

chapter-24(Electric Installation).xls Page 187


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

100 Providing and fixing screwless cable tray cover fabricated with 18 SWG G.I.
Sheet of required size i/c the cost of hardware as approved and directed by the
Engineer Incharge.
(i) 4" wide P.Rft 14.95 117.30 P.Mtr 49.05 384.75
(ii) 6" wide P.Rft 14.95 149.95 P.Mtr 49.05 491.85
(iii) 9" wide P.Rft 14.95 203.00 P.Mtr 49.05 665.80
(iv) 10" wide P.Rft 22.40 226.80 P.Mtr 73.55 743.85
(vi) 12" wide P.Rft 22.40 267.60 P.Mtr 73.55 877.65
(v) 16" wide P.Rft 22.40 328.80 P.Mtr 73.55 1,078.40
(vii) 24" wide P.Rft 29.90 472.95 P.Mtr 98.05 1,551.25
101 Providing and fixing hot dipped Galvanized Cable Ladder fabricated with side
channels of specified size and guage duly fixed with rungs of 35x15 mm run
@ 10"C/C i/c the cost of coupler plates (1-1/4"x8") and hardwares as approved
and directed by the Engineer Incharge.
I- Side Channel (2"x1/2")
(a) 16SWG
(i) 4"x2" P.Rft 59.80 192.05 P.Mtr 196.15 629.90
(ii) 6"x2" P.Rft 59.80 198.05 P.Mtr 196.15 649.55
(iii) 8"x2" P.Rft 59.80 204.05 P.Mtr 196.15 669.25
(iv) 12"x2" P.Rft 59.80 222.05 P.Mtr 196.15 728.30
(v) 18"x2" P.Rft 59.80 257.55 P.Mtr 196.15 844.80
(vi) 24"x2" P.Rft 59.80 265.25 P.Mtr 196.15 869.95
(vii) 30"x2" P.Rft 59.80 294.05 P.Mtr 196.15 964.45
(viii) 36"x2" P.Rft 59.80 318.05 P.Mtr 196.15 1,043.15
(b) 14SWG
(i) 4"x2" P.Rft 59.80 216.05 P.Mtr 196.15 708.60
(ii) 6"x2" P.Rft 59.80 222.05 P.Mtr 196.15 728.30
(iii) 8"x2" P.Rft 59.80 270.05 P.Mtr 196.15 885.70
(iv) 12"x2" P.Rft 59.80 282.05 P.Mtr 196.15 925.10
(v) 18"x2" P.Rft 59.80 318.75 P.Mtr 196.15 1,045.50
(vi) 24"x2" P.Rft 59.80 336.05 P.Mtr 196.15 1,102.20
(vii) 30"x2" P.Rft 59.80 360.05 P.Mtr 196.15 1,180.90
(viii) 36"x2" P.Rft 59.80 390.05 P.Mtr 196.15 1,279.30
I I - Side Channel (3"x1/2")
(c) 16SWG
(i) 4"x3" P.Rft 59.80 222.05 P.Mtr 196.15 728.30
(ii) 6"x3" P.Rft 59.80 234.05 P.Mtr 196.15 767.65
(iii) 8"x3" P.Rft 59.80 240.05 P.Mtr 196.15 787.30
(iv) 12"x3" P.Rft 59.80 252.05 P.Mtr 196.15 826.70
(v) 18"x3" P.Rft 59.80 293.55 P.Mtr 196.15 962.85
(vi) 24"x3" P.Rft 59.80 306.05 P.Mtr 196.15 1,003.80
(vii) 30"x2" P.Rft 59.80 330.05 P.Mtr 196.15 1,082.50
(viii) 36"x2" P.Rft 59.80 354.05 P.Mtr 196.15 1,161.25
(d) 14SWG
(i) 4"x3" P.Rft 59.80 258.05 P.Mtr 196.15 846.35
(ii) 6"x3" P.Rft 59.80 270.05 P.Mtr 196.15 885.70
(iii) 8"x3" P.Rft 59.80 276.05 P.Mtr 196.15 905.40
(iv) 12"x3" P.Rft 59.80 294.05 P.Mtr 196.15 964.45
(v) 18"x3" P.Rft 59.80 335.55 P.Mtr 196.15 1,100.60

chapter-24(Electric Installation).xls Page 188


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

(vi) 24"x3" P.Rft 59.80 354.05 P.Mtr 196.15 1,161.25


(vii) 30"x2" P.Rft 59.80 390.05 P.Mtr 196.15 1,279.30
(viii) 36"x2" P.Rft 59.80 414.05 P.Mtr 196.15 1,358.05
102 Providing and fixing Copper winded Exhaust fan with louver and shutter
made of Pak/Younas/G.F.C. i/c the cost of necessary cable and hardware for
connection from ceiling rose complete as approved and directed by Engineer
Incharge.
(a) Plastic body
(i) 10" dia Each 74.75 2,834.75 Each 74.75 2,834.75
(ii) 12 " dia Each 74.75 3,134.75 Each 74.75 3,134.75
(b) Steel body
(i) 12" sweep Each 74.75 3,974.75 Each 74.75 3,974.75
(ii) 18" sweep Each 74.75 4,454.75 Each 74.75 4,454.75
103 P/F PVC double layer Switch kit Face plate with specified switch holes i/c the
cost of switches / sockets / dimmer made of Hi-Life / Bush / Schenider, screws
complete as approved and directed by the Engineer Incharge
(a) One way Gange Switch
Small
(i) 01 Gange Each 85.80 385.80 Each 85.80 385.80
(ii) 02 Gange Each 85.80 637.80 Each 85.80 637.80
(iii) 03 Gange Each 85.80 745.80 Each 85.80 745.80
(iv) Three pin Light Plug 10/13 Amp Each 85.80 613.80 Each 85.80 613.80
(v) Telephone / TV/Datacable socket Each 85.80 535.80 Each 85.80 535.80
(vi) Fan Dimmer Each 85.80 601.80 Each 85.80 601.80
(vii) Bell push Each 85.80 481.80 Each 85.80 481.80
(viii) Three Pin Power Plug 15-32 Amp Each 85.80 757.80 Each 85.80 757.80
Large
(i) 04 Gange Each 85.80 805.80 Each 85.80 805.80
(ii) 05 Gange Each 85.80 949.80 Each 85.80 949.80
(iii) 06 Gange Each 85.80 1,165.80 Each 85.80 1,165.80
(b) Two way Gange Switch
Small
(i) 01 Gange one way/ Two way Each 85.80 397.80 Each 85.80 397.80
(ii) 02 Gange Each 85.80 631.80 Each 85.80 631.80
(iii) 03 Gange Each 85.80 757.80 Each 85.80 757.80
(iv) 04 Gange Each 85.80 913.80 Each 85.80 913.80
104 P/F PVC concealed Switch kit Box i/c the cost of screws complete as
approved and directed by the Engineer Incharge
(i) Small Each 85.80 137.40 Each 85.80 137.40
(ii) Large Each 85.80 161.40 Each 85.80 161.40

chapter-24(Electric Installation).xls Page 189


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

105 Supply, insatllation, commissioning and testing of oil cooled type, Step down
Power Transformer of specified rating,11/0.415 kV, i/c the cost of lifting
hooks, thermometers, LT & HT bushing 5-steps, tap changer, imported double
float buchholz relay, 2 earthing terminals, roller wheels, connecting terminals
for cables M.S box on transformer in order to cover complete L.T side, all
necessary materials required for connections on H.T & L.T side, rated voltage
11000/415/240 V impedance 6.25% or as specified by WAPDA/IEC system
earth: Delta / Star, neutral solidly earthed, i/c Wapda testing charges,complete
in all respects made of PEL, Siemens, as approved and directed by the
Engineer Incharge
(i) 10 KVA Each 6,800.05 157,626.55 Each 6,800.05 157,626.55
(ii) 15 KVA Each 6,800.05 203,562.55 Each 6,800.05 203,562.55
(iii) 25 KVA Each 6,800.05 329,622.55 Each 6,800.05 329,622.55
(iv) 50 KVA Each 6,800.05 428,226.55 Each 6,800.05 428,226.55
(v) 100 KVA Each 6,800.05 672,426.55 Each 6,800.05 672,426.55
(vi) 200 KVA Each 6,800.05 1,068,426.55 Each 6,800.05 1,068,426.55
(vii) 300 KVA Each 6,800.05 1,339,158.55 Each 6,800.05 1,339,158.55
(viii) 400 KVA Each 6,800.05 1,648,962.55 Each 6,800.05 1,648,962.55
(ix) 630 KVA Each 6,800.05 1,923,644.90 Each 6,800.05 1,923,644.90
(x) 750 KVA Each 6,800.05 2,427,762.55 Each 6,800.05 2,427,762.55
(xi) 1000 KVA Each 6,800.05 3,229,081.95 Each 6,800.05 3,229,081.95
(xii) 1250 KVA Each 6,800.05 3,334,494.45 Each 6,800.05 3,334,494.45
(xiii) 1500 KVA Each 6,800.05 4,182,804.00 Each 6,800.05 4,182,804.00
(xiv) 2000 KVA Each 6,800.05 5,639,600.05 Each 6,800.05 5,639,600.05

DATA CABLI NG SYSTEM


106 Supply, Installation and commissioning of wiring with 4-pair data Cable, 23 38.1 to 38.7
AWG UL/EN listed cable * Conforming to following standards: TIA/EIA 568 /
ISO/IEC 11801, in prelaid conduit / cable tray from including all accessories,
Manufacturer/OEM Authorization, Make: Schneider / i-connect UK/3M
Corning USA/ D-Link/ Pollo Australian or equivalent complete in all respect as
approved and directed by Engineer Incharge.
a) UTP (Unshielded Twisted pair)
(i)CAT-6 (Min.1G @ 250MHz or higher) Per Rft 3.10 32.05 Meter 10.25 105.15
(ii)CAT-6A (Min.1G/ 10G @ 500MHz or higher) Per Rft 3.10 55.50 Meter 10.25 182.10
b) Shielded Twisted pair
(i)CAT-7 (Min.1G/ 10G @ 600MHz or higher ) Per Rft 3.10 58.25 Meter 10.25 191.15
107 Supply, Installation and commissioning of wiring with Multimode OM3 Per Rft 7.80 49.20 Meter 25.60 161.40 38.1 to 38.7
Armored Fiber Optic Cable Central Loose Tube for 10 Giga Fiber Optic
Connection UL/EN listed cable or equivalent, in prelaid cable tray from Main
Cabinet to Floor Level Cabinets, including all accessories, Manufacturer/OEM
Authorization, Make: Schneider / i-Connect UK/3M Corning USA/ D-Link/
Pollo Australia or equivalent complete in all respect as approved and directed
by the Engineer Incharge.

chapter-24(Electric Installation).xls Page 190


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

108 Supply, Installation and commissioning of wiring with fiber optic cable with 38.1 to 38.7
Unitube, Light-Armoured Cable, Single-Mode, OS2, of specified Core, 9μm,
in pre laid conduit or cable tray etc. from Fiber switch to Fiber Switch in ODF
Panel, including all accessories, made of Schnider/i-Connect UK/Panduit USA
Pollo Australia or equivalent as approved and directed by the Engineer
Incharge.
(i) 12 Core Per Rft 12.50 150.50 Meter 40.95 493.55
(ii) 24 Core Per Rft 12.50 302.30 Meter 40.95 991.50
(iii) 48 Core Per Rft 12.50 530.00 Meter 40.95 1,738.35
(iv) 96 Core Per Rft 12.50 840.50 Meter 40.95 2,756.75
109 Supply, Installation and commissioning of Cat-6, UTP Machine Made Patch 38.1 to 38.7
Cord of Specified Length, Support 10 Giga, UL listed cable, with anti snag
boots, Gold Over Nickel Plated, Manufacturer/OEM Authorization, confirming
to manufacturer warranty, Made of Schneider / i-Connect UK /Panduit USA/D-
Link/3M, Corning ,Pollo Australian or equivalent Approved and Directed by
Engineer Incharge.
(i) 1 meter Patch Cord Each 57.20 781.70 Each 57.20 781.70
(ii) 3 Meter Patch Cord Each 57.20 954.20 Each 57.20 954.20

110 Supply, installation and connections of CAT-6A UTP (Unsheilded Twisted 38.1 to 38.7
Pair) , patch cord of specified length,Factory Fabricated and UL Listed with
anti Snag Boots- Gold over nickel plated made of Schneider, Pollo Australia or
equivalent as approved and directed by Engineer Incharge .

(i) 1 meter Patch Cord Each 57.20 2,334.20 Each 57.20 2,334.20
(ii) 3 Meter Patch Cord Each 57.20 2,472.20 Each 57.20 2,472.20
111 Supply, Installation and Connection of Specified Ports Layer-2 PoE (Power
Over Ethernet) data Network Switch specified ports x100 Mbps PoE,
Min.2x1Gbps SFP UPLINK ports, made of Cisco USA/NOVAS
Europe/Juniper USA / Huawei / H3C, Pollo Australia or equivalent as
approved and directed by the Engineer Incharge.
(i) 8 port, Min. 120 Watt PoE power Each 1,144.00 35,644.00 Each 1,144.00 35,644.00
(ii) 12 port, Min. 250 Watt PoE power Each 1,144.00 46,684.00 Each 1,144.00 46,684.00
(iii) 16 port, Min. 300 Watt PoE power Each 1,144.00 61,864.00 Each 1,144.00 61,864.00
(iv) 24 port, Min. 365 Watt PoE power Each 1,144.00 89,464.00 Each 1,144.00 89,464.00
(v) 48 port, Min. 665 Watt PoE power Each 1,144.00 146,044.00 Each 1,144.00 146,044.00
112 Supply, Installation and Connection of Data switch ,10/100/1000 Mbps with
SFP UPLINK made of Cisco USA/NOVAS Europe/Juniper USA / Huawei
/H3C Pollo Australian or equivalent as approved and directed by the Engineer
Incharge.
(i) 8 Ports,(PoE) Each 34.30 1,759.30 Each 34.30 1,759.30
(ii) 12 Ports,(PoE) Each 34.30 1,931.80 Each 34.30 1,931.80
(iii) 16 Ports( PoE ) Each 34.30 2,276.80 Each 34.30 2,276.80
(iv) 24 Ports(PoE) Each 34.30 2,621.80 Each 34.30 2,621.80
(v) 48 Ports(PoE) Each 34.30 3,553.30 Each 34.30 3,553.30

chapter-24(Electric Installation).xls Page 191


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

113 Supply, Installation and Connection of Single /Multimode SFP (Small form
Pluggable) Tranceiver Duplex Multimode of Specified Capacity. made of
Cisco USA/NOVAS Europe / Juniper USA / Huawei /H3C/ Pollo Australia or
equivalent as approved and directed by Engineer Incharge.
(i) 10/100/1000 SFP (as per site specific port type requirements) Each 1,716.00 41,087.40 Each 1,716.00 41,087.40
(ii) 10 Gigabit SFP (as per site specific port type requirements) Each 1,716.00 103,180.50 Each 1,716.00 103,180.50
114 Supply and installation of Cable Metal Organizer, 19" Rack mounted with Each 686.40 2,928.90 Each 686.40 2,928.90
high graded epoxy powder coating and slideable top- UL Listed. Made of
Schneider/i-Connect UK/3M Corning: Pollo Australia or equivalent as
approved and directed by the Engineer Incharge.
115 Supply, Installation and commissioning of 19" Rack Mounted of specified,
UTP Patch Panel with specified toolless support & Rear Cable Management,
UL listed, Loaded with UTP of specified Keystone Jack Toolless Support ,
Made of Schneider / Norden /3M Corning/D-Link, Pollo Australia or
equivalent or as Approved and Directed by Engineer Incharge.

(i) CAT-6 (24 Port Patch Panel with Toolless Support 1-Gigabit) Each 85.80 24,814.45 Each 85.80 24,814.45
(ii) CAT-6A (24 Port Patch Panel with Toolless Support 10-Gigabit) Each 85.80 27,712.40 Each 85.80 27,712.40
CCTV
116 Supply & Installation of NVR (Network Video Recorder) for Real Time View
of specified Channels, video and Audio channels,Supported protocoles:
ONVIF,RTSP etc, Internal HDDs mount support:2/4/8 or higher as per site
requirement,Monitor outputs,(HDMI,4K Ultra HD),VGA (Video Graphic
array), Support Raid 5/6, Embeded OS, Data Encryption, Min. 1 x RJ-45
1000Mbps Ports, with PC Video Monitoring Software, Web Server, Embedded
Server complete in all respect. made of AXIS Europe/NOVAS
Europe/Avigilon by Motrola USA /Huawei, Pollo Australia or equivalent as
approved and directed by the Engineer Incharge.

(i) 8-Channel Each 429.00 72,927.30 Each 429.00 72,927.30


(ii) 16-Channel Each 429.00 91,143.30 Each 429.00 91,143.30
(iii) 32-Channel Each 429.00 102,894.00 Each 429.00 102,894.00
(iv) 42-Channel Each 429.00 304,374.00 Each 429.00 304,374.00
(v) 50-Channel Each 429.00 367,143.30 Each 429.00 367,143.30
(vi) 64-Channel Each 429.00 378,894.00 Each 429.00 378,894.00
(iv) 150-Channel Each 429.00 580,374.00 Each 429.00 580,374.00
117 Supply, Installation and Connection of Surveillance Grade Hard Drives (HDD)
of Specified Capacity for CCTV System Backup. made of Seagate / WD,
Pollo Australia or equivalent, as approved and directed by Engineer Incharge.

(i) 4 TB(Tera Bite) Each 858.00 21,903.00 Each 858.00 21,903.00


(ii) 8 TB(Tera Bite) Each 858.00 35,841.00 Each 858.00 35,841.00
(iii)10 TB(Tera Bite) Each 858.00 54,195.00 Each 858.00 54,195.00
(iv)14 TB(Tera Bite) Each 858.00 59,853.00 Each 858.00 59,853.00

chapter-24(Electric Installation).xls Page 192


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

118 Supply, Installation and Connection of L2 Access Switches 24xEthernet Each 1,638.00 284,979.60 Each 1,638.00 284,979.60
10/100/1000 base-T port, min 2x1Gigabit SFP ports with 2x1G single mode
SFP. POE/POE+. Switching capacity at least 200 Gbps full-duplex or higher
supporting bi-directional ACL, port based ACL,VLAN based ACL, automatic
Isolation of attack sources, DAI (Dyanamic ARP inspection), DHCP Snooping,
IP Source Gaurd, port based network acess control conforming IEEE 802.1 x
standard, Stackable or Cluster setup complete with Stack Modules, Stack
cables, necessary licenses etc made of Cisco/HP/Planet/H3C/Huawei, Pollo
Australia or equivalent as approved and directed by Engineer Incharge.

119 Supply, Installation and Connection of Layer-3, Core Switches, of specified


speeds, supporting 10 Giga SFP+ (Small Form Pluggable +) Tranceiver,
Switching Capacity at least 500 Gbps or higher ,supporting bidirectional
ACL,port-based ACL., Stackable or Cluster setup complete with stacking
cable, Stack modules, necessary licenses made of Cisco/ HP /
Planet/Huawei/H3C Pollo Australia or equivalent i/c the cost of tags as
approved and directed by Engineer Incharge.
a) 10/100/1000
(i) 12 port(SFP) Each 1,638.00 505,793.40 Each 1,638.00 505,793.40
(ii) 24 port (SFP) Each 1,638.00 878,296.80 Each 1,638.00 878,296.80
b) 24/100/1000
(i) 12 port(SFP) Each 1,638.00 588,593.40 Each 1,638.00 588,593.40
(ii) 24 port (SFP) Each 1,638.00 1,016,296.80 Each 1,638.00 1,016,296.80
120 Supply and installation of ODF (Optical Distribution frame) having specified
ports,mounting tray loaded, including Splicing, labeling, tagging, support for
OM3 multi mode fibre, duplex adopters, and simplex pig-tails. Make
Schneider, Pollo Australia or equivalent as approved and directed by the
Engineer Incharge .
(i) 8 Port Each 81.90 22,575.90 Each 81.90 22,575.90
(ii) 12 Port Each 81.90 54,177.90 Each 81.90 54,177.90
(iii) 24 Port Each 81.90 87,573.90 Each 81.90 87,573.90
121 Supply, Installation and Connection of Fiber Optic SC-LC Patch Cords OS2 or Per Rft 28.60 1,408.60 P.Mtr 93.80 4,620.20
OM3 of Specified Length from PoE Switch to ODF Point, UL Listed, Made of
Schneider / Norden ,Pollo Australia or equivalent as approved and directed by
Engineer Incharge.
122 Supply, installation & connecting IP based Camera of specified resolution, 1/3"
Progressive scan, fixed lens 2.8 mm AF, Max resolution 2592 x 1920 mm,
Codec H-265, Camera with 25 fps, day night (ICR), ONVIF, IP-66, Max IR
distance 30 meter, WDR Smart Analytics, i/c the cost of mounting bracket,
mounting accessories/ materials. Make: - Honey Well / Bosch / Norden, Pollo
Australia or equivalent, as approved as directed by the Engineer Incharge.

(a) 2 M ega Pixel


(i)Fixed Bullet Type Each 429.00 67,359.00 Each 429.00 67,359.00
(ii)Fixed Dome type Each 429.00 76,674.00 Each 429.00 76,674.00
(b) 4 M ega Pixel
(i)Fixed Bullet Type Each 429.00 73,934.70 Each 429.00 73,934.70
(ii)Fixed Dome type Each 429.00 85,644.00 Each 429.00 85,644.00

chapter-24(Electric Installation).xls Page 193


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

(c) 8 M ega Pixel


(i)Fixed Bullet Type Each 429.00 76,694.70 Each 429.00 76,694.70
(ii)Fixed Dome type Each 429.00 87,714.00 Each 429.00 87,714.00
123 Supply, installation & connecting IP based Camera of specified resolution,
lens,motorized,auto-iris and auto-focus function,f=2.8~12 mm,human/vehicle
object classification ,D/N function-IR cut filter,Video content analysis based on
Deep learning,micro SD card support,WDR with double scan sensor, Min,
illumination: 0.007 Ix(01xIR on),IR LED,range upto 50 m, i/c the cost of
mounting bracket,accessories,made of AXIS Europe/NOVAS Europe/Avigilon
by Motorla USA/Bosch Germany, Pollo Australia or equivalent, as approved as
directed by the Engineer Incharge.

a) 2 M ega Pixel
(i)Fixed Bullet Type Each 429.00 67,704.00 Each 429.00 67,704.00
(ii)Fixed Dome type Each 429.00 76,674.00 Each 429.00 76,674.00
b) 4 M ega Pixel
(i)Fixed Bullet Type Each 429.00 69,794.70 Each 429.00 69,794.70
(ii)Fixed Dome type Each 429.00 81,504.00 Each 429.00 81,504.00
c) 5 M ega Pixel
(i)Fixed Bullet Type Each 429.00 73,934.70 Each 429.00 73,934.70
(ii)Fixed Dome type Each 429.00 85,644.00 Each 429.00 85,644.00
124 Supply, installation & connecting IP based Camera of specified resolution,
lens,motorized,auto-iris and auto-focus function,f=3-12 mm, D/N function-IR
cut filter,Video content analysis based on Deep learning,micro SD card
support,WDR, Min, illumination: 0.007 Ix(01xIR on),IR LED,range upto 40
m, pivacy zone,motion detection,system reaction to alarm event i/c the cost of
mounting bracket,accessories,made of AXIS Europe/NOVAS Europe/Avigilon
by Motorla USA/Bosch Germany, Pollo Australia or equivalent, as approved as
directed by the Engineer Incharge.
a) 6 M ega Pixel
(i)Fixed Bullet Type Each 429.00 77,364.00 Each 429.00 77,364.00
(ii)Fixed Dome type Each 429.00 90,474.00 Each 429.00 90,474.00
b) 8 M ega Pixel
(i)Fixed Bullet Type Each 429.00 80,834.70 Each 429.00 80,834.70
(ii)Fixed Dome type Each 429.00 95,304.00 Each 429.00 95,304.00
c) 12 M ega Pixel
(i)Fixed Bullet Type Each 429.00 83,594.70 Each 429.00 83,594.70
(ii)Fixed Dome type Each 429.00 96,684.00 Each 429.00 96,684.00
125 Supply, installation & connecting IP based Camera of specified resolution,
LPR -Camera,Lens: motorized,auto-iris and auto-focus function,f=7~22
mm,human/vehicle no plate recognition,D/N function-IR cut filter,Video
content analysis based on Deep learning,micro SD card support,WDR with
double scan sensor, Min, illumination: 0.007 Ix(01xIR on), IR LED,range upto
50 m, Barrier controle i/c the cost of mounting bracket,accessories,made of
AXIS Europe/NOVAS Europe/Avigilon by Motorla USA/Bosch Germany,
Pollo Australia or equivalent, as approved as directed by the Engineer
Incharge.

chapter-24(Electric Installation).xls Page 194


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

a) 2 M ega Pixel
(i)Fixed Bullet Type Each 429.00 81,504.00 Each 429.00 81,504.00
(ii)Fixed Dome type Each 429.00 90,474.00 Each 429.00 90,474.00
126 Supply, installation & connecting outdoor PTZ (Pan-Tilt-Zoom),IP based
Camera of specified resolution, lens,motorized varfocal,AL & AF
function,specified optical zoom,D/N function-IR cut filter,Video content
analysis,micro SD card support, Min, illumination:face recognition, specified
IR LED range RANGE i/c the cost of mounting bracket,accessories,made of
AXIS Europe/NOVAS Europe/Avigilon by Motorla USA/Bosch Germany,
Pollo Australia or equivalent, as approved as directed by the Engineer
Incharge.
i) 2 MPxl optical zoom 20x,f=5.5-110 mm with min illumination from Each 429.00 353,364.00 Each 429.00 353,364.00
0.003x (01xIR ON),IR LED range upto 150 m.
ii) 3 MPxl,optical zoom 30x,f=4.5- 135 mm,with min illumination from Each 429.00 366,474.00 Each 429.00 366,474.00
01x(01x,IR ON),IR LED range upto 180 m
iii) 4.0 MPxl, Optical zoom 30x,Digital zoom 16x,,laser distance 200 meter, Each 429.00 408,012.00 Each 429.00 408,012.00
Main stream H-264+/265+, sub stream H.264/265, Third Stream
H.264/265, Max resolution 2560 x 1440 with 30 fps,IP-67.
127 Supply, installation and connections of POLE ADAPTER, Esprit system to Each 780.00 28,932.00 Each 780.00 28,932.00
convert any wall mount to pole mount. Made of PELCO( USA) /AXIS
(Sweden) , Pollo Australia or equivalent as approved and direcyed by the
Engineer Incharge.
128 Supply, installation and connections of HD Video Decoder that support digital Each 1,287.00 502,227.00 Each 1,287.00 502,227.00
video stream on network and allow for the decoding upto 16 simultaneous
streams with HDMI cable as required at site. made of PELCO ( USA) /AXIS
(Sweden) , Pollo Australia or equivalent as approved and directed by the
Engineer Incharge.
129 Supply , installation of wall mounted CCTV Cabinet comprising of Powder
Coated M.S frame, front glass & two side openings, 02 way fans for cooling,
top & bottom entry, handle lock with 6 way PDU (Power Distribution Unit)
with all necessary accessories/ materials, complete in all respects. Made of
Bosch/ HP / Dell , Pollo Australia or equivalent or as approved and directed by
Engineer Incharge.
(i) 12U size (600x550x635 mm) Each 1,716.00 44,140.50 Each 1,716.00 44,140.50
(ii) 15U size (600x550x770 mm) Each 1,716.00 45,450.65 Each 1,716.00 45,450.65
(iii) 18U size (600x550x900 mm) Each 1,716.00 47,790.25 Each 1,716.00 47,790.25
130 Supply , installation of floor mounted Main CCTV Cabinet of specified size,
installed in Main IT / Server room/Security Room, made of Powder Coated
M.S frame, perforated front & rear doors, removable side panels, 04 way fans
for cooling, top/bottom entry, handle lock with 4 lockable wheels, cable
manager, with 6 way PDU (Power Distribution Unit) & 2 x 6 way PDU
(Power Distribution Unit) for 42U size with all necessary accessories/
materials, complete in all respects. made of Bosch/ HP / Dell , Pollo Australia
or equivalent or as approved and directed by Engineer Incharge.

(i) 42U (800x800x2055mm) Each 2,140.45 151,547.35 Each 2,140.45 151,547.35


(ii) 27U (600x600x1300mm) Each 2,140.45 79,660.00 Each 2,140.45 79,660.00

chapter-24(Electric Installation).xls Page 195


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

DATA NETWORK & WI FI SYSTEM


131 Supply, Installation and commissioning of Simple type, Dual Shutter Face
Plates having fully populated I/O:
Option 1:RJ-11 with RJ45/8P8C I/Os supporting either Cat6 or Cat6a cables as
required by project
Option 2: Two RJ45/8P8C I/Os supporting either Cat6 or Cat6a cables as
required by project.
(i) Single I/O Each 31.20 1,307.70 Each 31.20 1,307.70
(ii) Double I/O Each 31.20 2,050.15 Each 31.20 2,050.15
132 Supply, Installation and commissioning of Core Switches with interface :
10GBASE-R(SFP+)/1000 BASE-X(SFP) 4X40 BASE -SR4/LR4 (QSFP)
,Bandwidth: Tbps or higher with Quad-core processor or higher,MAC Table:
96K ,AC Power: 220V+-10%,cooling fans made of RUCKS USA/Cisco
USA/Juniper USA, Pollo Australia or equivalent as approved and directed by
Engineer's Incharge.
(i) 24 Ports Each 31.20 98,431.20 Each 31.20 98,431.20
(ii) 48 Ports Each 31.20 168,031.20 Each 31.20 168,031.20
133 Supply, Installation and commissioning of Access Switches Layer 3, with
specified 1000 Base-T (RJ-45) Ports (PoE/PoE+) with 4 x 10 G SFP+ with
license , Switching capacity 128 Gbps or higher,Packet forwarding capacity :90
Mpps,RAM (DDR3):512 MB, DHCP snooping, ACL, power supply Min.350
Watt AC, made of RUCKS USA/Cisco USA/Juniper USA / Huawei / H3C,
Pollo Australia or equivalent as approved and directed by Engineer's Incharge.

(i) 24 Ports Each 31.20 72,031.20 Each 31.20 72,031.20


134 Supply, Installation and commissioning of Armored Fiber Optic Cable of 38.1 to 38.7
specified core and mode, Fiber Optic Connection, UL listed , in prelaid/pipe,
cable tray , including all accessories, made of Norden / Schneider /
Panduit/Pollo Australia or equivalent Complete in all respect as approved and
directed by Engineer Incharge.
a) M ultimode OM 3
(i) 04 Core Per Rft 31.20 287.20 Mtr 102.35 942.00
(ii) 06 Core Per Rft 31.20 434.85 Mtr 102.35 1,426.30
(iii) 12 Core Per Rft 31.20 646.00 Mtr 102.35 2,118.85
b) Singlemode OS2
(i) 04 Core Per Rft 31.20 259.60 Mtr 102.35 851.45
(ii) 06 Core Per Rft 31.20 370.00 Mtr 102.35 1,213.55
(iii) 12 Core Per Rft 31.20 508.00 Mtr 102.35 1,666.20
135 Supply, Installation of OFDF (Optical Fiber Distribution Frame) having
specified mode ports Loaded with Splicing Tray, with splicing of Pigtails, Fully
loaded DUPLEX SC Couplers & Pigtail supplied with Patch Leads (LC-SC) or
as per site SFP based required cords, UL Listed, Made of Schneider / Norden,
Pollo Australia or equivalent or as approved and directed by the Engineer
Incharge.
a) M ultimode (M M ) Ports
(i) 06 Ports Each 1,170.00 27,252.00 Each 1,170.00 27,252.00
(ii) 12 Ports Each 1,170.00 50,367.00 Each 1,170.00 50,367.00
(iii) 24 Ports Each 1,170.00 100,323.00 Each 1,170.00 100,323.00
(iv) 48 Ports Each 1,170.00 200,580.00 Each 1,170.00 200,580.00

chapter-24(Electric Installation).xls Page 196


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

(v) 96 Ports Each 1,170.00 355,140.00 Each 1,170.00 355,140.00


b) Singlemode (SM ) Ports
(i) 06 Ports Each 1,170.00 23,112.00 Each 1,170.00 23,112.00
(ii) 12 Ports Each 1,170.00 40,707.00 Each 1,170.00 40,707.00
(iii) 24 Ports Each 1,170.00 83,487.00 Each 1,170.00 83,487.00
(iv) 48 Ports Each 1,170.00 173,670.00 Each 1,170.00 173,670.00
(v) 96 Ports Each 1,170.00 332,646.00 Each 1,170.00 332,646.00
136 Supply, installation and connections of 42U Racks 800 x1000 MM with Fans Each 15.60 162,855.60 Each 15.60 162,855.60
and:02 nos PDU-IMPORTED. Make Schneider as specified as approved and
directed by Engineer's Incharge .
137 Supply, Installation of WiFi access points(APs),conforming IEEE as approved
and directed by the Engineer Incharge.
i) Support upto 50 concurrent connections
(a) Data transfer rate Min. 802.11ac: 1200 Mbps Each 624.00 68,934.00 Each 624.00 68,934.00
(b) Support upto 50 concurrent connections
(c) 4X4 MIMO support (3SU,3MU)
(d) 2xEthernet 10/100/1000 Base-T (RJ-45)
(e) 1x100/1000 BASE -X (SFP) optionally
(f) N- Type (Female) for external antennas (Omni,sector rod,etc.)
(g) IEEEa/b/g/n/ac wave 2 standards, should work on 2.4 & 5.8 Ghz
band Simultaneously ans @ 2.4 Ghz support 500 Mbps ,
(h) VLAN 802.1Xauthentication ,NAT and DHCP client,LLDP,ACL
Ipv4 and lpv 6 support.
(i) Power supply: PoE + 48 V /54 V (IEEE 802.3 at -2009) 48 V DC.
(j) Operating Temperature from -10 to +45 C. managed by wireless
controller. Make: - Aruba / Cisco / Al-Catel.as approved and directed by
Engineer Incharge.Support Automatic RF channel selection, and dual
stack. Make: - Aruba / Cisco / Al-Catel.
ii) Support upto 500 concurrent connections
(a) Data transfer rate 802.11ac:1300 Mbps Each 624.00 587,814.00 Each 624.00 587,814.00
(b) Support upto 500 concurrent connections
(c) 3x3 MIMO support
(d) 2xEthernet 10/100/1000 Base-T (RJ-45)
(e) 1x100/1000 BASE -X (SFP) optionally
(f) N- Type (Female) for external antennas (Omni,sector rod,etc.)
(g) IEEE 802.11 a/b/g/n/ac standard support
(h) VLAN 802.1Xauthentication ,DHCP client,LLDP,ACL and lpv 6
support.
(i) Power supply: PoE + 48 V /54 V (IEEE 802.3 at -2009) 48 V DC.
(j) Operating Temperature from -10 to +45 C. managed by wireless
controller. Make: - Aruba / Cisco / Al-Catel.

chapter-24(Electric Installation).xls Page 197


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

138 Supply , installation of Wifi Access Controller installed in the Main Cabinet,
supportting specified Access Points, concurrent users, customizeable dash
board, DHCP(Dynamic Host Configeration Protocol),min 2x1 Giga Ethernet
ports,min 2X 10 Giga Ethernet/SFP+ ports,packet forwarding capacity>= 4
Gbps, authentication based on MAC,802.1X WEP, WPA-TKIP, WPA2-AES,
and ACL Layer-2, Layer-3 and Layer-4, compatible with Apple & Andriod
devices, Console Port. Make Aruba, Cisco, Al-Catel as approved and directed
by Engineer Incharge.

(i) 15 Access Points Each 1,170.00 284,070.00 Each 1,170.00 284,070.00


(ii) 25 Access Points Each 1,170.00 422,070.00 Each 1,170.00 422,070.00
(iii) 50 Access Points Each 1,170.00 519,843.00 Each 1,170.00 519,843.00
(iv) 100 Access Points Each 1,170.00 588,843.00 Each 1,170.00 588,843.00
ACCESS CONTROL SYSTEM
139 Supply, Installation and commissioining of wire free standalone network Based Each 2,718.00 76,403.40 Each 2,718.00 76,403.40
RFID (Radio Frequency Identification) Door Lock AELEMENT AE model AE
901MBA3A8 with reader, wireless DNA. Mechanical Dead bolt, 1000 Audit
trail, SVN Compatible, UL Listed with ANSI Mortise lock, (For minimum
40mm door), 4 built in Switches (DND, Mechanical override, Inside opening
and Door Ajar), Handle "U" Model, Satin Stainless Steel. Make Salto (USA)/
Fingertec (USA) / Pollo Australia or equivalent as specified complete in all
respects and approved by Engineer Incharge.
140 Supply, Installation and commissioining of RFID Based NODE with wireless Each 2,428.50 13,159.40 Each 2,428.50 13,159.40
DNA. control, read and transmit data to operate door locks to main server for
upto 15-20 meters. Make Salto (USA)/ Fingertec (USA)/ Pollo Australia or
equivalent as specified complete in all respects approved by Engineer
Incharge.
141 Supply, installation Testing and Connections of signal distribution Salto Each 624.00 45,630.50 Each 624.00 45,630.50
Model GATEWAY controller PoE (Power Over Ethernet), Wireless Gateway
connect via nodes, Wireless radio frequency based on IEEE 802.15.4 at 2,4
Ghz. AES 128 bits encryption, Software SALTO Spaonline SPAC-OPT-0021
Connection to the LAN Network 10 BASE-T/100 BASE-TX, Make Salto
(USA)/ Fingertec (USA) as specified complete in all respect as approved and
directed by Engineer Incharge.
142 Supply , installation of Push Buttons or manual access control system (Exit Each 390.00 1,321.50 Each 390.00 1,321.50
switch) with British standard size back box, including Emergency door release
break glass button complete in all respects. Make: Norden / Bosch / Honey
Well, Complete in all respect as approved and Directed by Engineer Incharge.

143 Supply , installation of Power Supply with stabilized voltage of 12 volt DC (+/- Each 390.00 7,980.00 Each 390.00 7,980.00
15%). The PSU supplies voltage U= 13.8 V DC with current efficiency I =4.5
A +0.5A battery charging for access control machines, in case of power
failure,instantaneous switching to battery operation complete in all respects.
Make: Norden / Bosch / Honey Well, Complete in all Respect as approved and
directed by Engineer Incharge.

chapter-24(Electric Installation).xls Page 198


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

144 Supply and energization of RFID ( Radio Frequency Identification) Proximity Each 624.00 1,120.80 Each 624.00 1,120.80
Cards , ISO credit card standard size and thickness,thin as specified made of
KADE Europe/Siemen Europe complete in all respect as approved and directed
by the Engineer Incharge.
145 Supply and energization of Proximity Cards reader with keypad for Each 468.00 785.40 Each 468.00 785.40
Unique(EM), ISO credit card standard size ,HID Prox(125 KHz) and Mifare
Classics (13.56 MHzs) card type.Read range from 2 to 10 cm made of KADE
Europe/Siemen Europe complete in all respect as approved and directed by the
Engineer Incharge.
146 Supply and energization of Administrator Proximity Card Unique Mifare Each 468.00 923.40 Each 468.00 923.40
HID,Prox,Reader type,operating frequency:125 kHz,13.56 MHz and USB
interface,made of KADE Europe/Siemen Europe complete in all respect as
approved and directed by the Engineer Incharge.
147 Supply, installation and connection of POE (Port of Ethernet) of specified Port
Switch or equivalent, rated 10/100/1000 Mbps unmanaged switch, & 4-U
Cabinet Racks equipped as per specifications, make of Schneider (UK)/ Cisco
(UK, Ireland) as specified complete in all respect as approved & directed by
Engineer Incharge.
(i) 8-Port Gigabite Switch with 2xSFP Each 816.25 56,331.10 Each 816.25 56,331.10
(ii) 24-Port Gigabite Switch with 14xSFP Each 816.25 181,307.05 Each 816.25 181,307.05
(iii) 48-Port Gigabite Switch with 14xSFP Each 816.25 293,624.45 Each 816.25 293,624.45
148 Supply, installation of following RFID based Access Control Machines with
display i/c the cost of mounting accessories, complete in all respect. Make:
Norden / Bosch / Honey Well, complete in all respect as approved and directed
by Engineer Incharge.
(i) Keypad Each 468.00 49,389.00 Each 468.00 49,389.00
(ii) Keypad Finger/Thumb Each 468.00 87,201.00 Each 468.00 87,201.00
(iii) Keypad Finger/Thumb,Retina Each 468.00 108,625.50 Each 468.00 108,625.50
149 Supply , installation and commissioning of Access Controller suitable for
standard controller with TCP/RS-485,commuinication ports, for specified
doors, complete in all respect. make: KADE Europe/Norden / Bosch / Honey
Well, complete in all respect as approved and directed by Engineer Incharge.

(i)2-doors Each 468.00 10,668.00 Each 468.00 10,668.00


(ii) 4-doors Each 468.00 18,770.40 Each 468.00 18,770.40
(iii) 8-doors Each 468.00 30,888.00 Each 468.00 30,888.00
PUBLI C ADDRESS SYSTEM
150 Supply, Installation & Commissioning of recessed/surface mounted Speakers
of specified capacity housed in metalic enclosure with builtin 70v/100v
transformer , aluminium grill, SPL (Sound Pressure Level) (1W / 1M)= 92dB
max 99dB, frequency response 130-13 Khz, EN-54 compliant, Including cost
of all accessories and matierlas, complete in all respect made of Ecler
Europe/Bosch/ Norden / Honey Well or equivalent as approved and directed
by the Engineer Incharge.
a) Ceiling mounted speaker
(i) 1.5-6 Watt Each 156.00 4,986.00 Each 156.00 4,986.00

chapter-24(Electric Installation).xls Page 199


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

(ii) 8-10 Watt Each 156.00 7,332.00 Each 156.00 7,332.00


(iii) 20 Watt Each 156.00 10,713.00 Each 156.00 10,713.00
(iv) 40 Watt Each 156.00 14,853.00 Each 156.00 14,853.00
b) Column Type Speaker
(i) 10-15 Watt Each 156.00 32,586.00 Each 156.00 32,586.00
(ii)20 Watt Each 156.00 39,141.00 Each 156.00 39,141.00
(iii) 40 Watt Each 156.00 48,773.40 Each 156.00 48,773.40
(iv) 60 Watt Each 156.00 62,739.00 Each 156.00 62,739.00
(v) 80 Watt Each 156.00 87,786.00 Each 156.00 87,786.00
151 Supply, Installation & Commissioning of surface mounted Line array speakers
of specified capacity housed in metalic enclosure with builtin 70v/100v
transformer , aluminium grill, SPL (Sound Pressure Level) (1W / 1M)= 92dB
max 99dB, frequency response 130-13 Khz, EN-54 compliant, with output
power adjustment for full,half and quarter power output,including cost of all
necessary accessories and matierlas, complete in all respect made of Bosch/
Norden / Honey Well or Equivalent as approved and Directed by Engineer
Incharge.
a) frquency range 136-20000 sensitivity @ 4m,1W:79 db SPL @ 4m,94
dB
(i) 60 Watt Each 156.00 60,296.40 Each 156.00 60,296.40
b) frquency range 140-20000 sensitivity @ 4m,1W: SPL @ 4m,105 dB

(i) 30 Watt Each 156.00 45,116.40 Each 156.00 45,116.40


c) Sound Projector frquency range 150-20000, sensitivity @ 4m,1W:
SPL @ 1m,1W:90 dB
(i) 20 Watt Each 156.00 46,386.00 Each 156.00 46,386.00
152 Supply, Installation and commissioning of Power / Mixer Amplifier of
specified wattage, Including cost of all necessary accessories / materials ,
complete in all respects made of Ecler Europe/Bosch/ Norden / Honey Well or
Equivalent or as approved and directed by Engineer Incharge.
(i) 30 Watt Each 156.00 57,081.00 Each 156.00 57,081.00
(ii) 60 Watt Each 156.00 105,381.00 Each 156.00 105,381.00
(iii) 120 Watt Each 156.00 151,956.00 Each 156.00 151,956.00
(iv) 160 Watt Each 156.00 182,661.00 Each 156.00 182,661.00
(v) 240 Watt Each 156.00 196,806.00 Each 156.00 196,806.00
(vi) 480 Watt Each 156.00 367,581.00 Each 156.00 367,581.00
153 Supply, Installation and commissioning of Power Amplifier of specified watts
and channels, Including cost of all necessary accessories / materials , complete
in all respects.made of Ecler Erope/ Bosch/ Norden / Honey Well or equivalent
as approved and directed by Engineer Incharge.

a) 2-Channel
(i) 2x60 Watt Each 1,170.00 100,875.00 Each 1,170.00 100,875.00
(ii) 2x120 Watt Each 1,170.00 132,615.00 Each 1,170.00 132,615.00
(iii)2x150 Watt Each 1,170.00 201,753.00 Each 1,170.00 201,753.00
(iv) 2x240 Watt Each 1,170.00 270,753.00 Each 1,170.00 270,753.00
b) 4-Channel
(i) 120 Watt Each 1,170.00 414,273.00 Each 1,170.00 414,273.00

chapter-24(Electric Installation).xls Page 200


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

(ii) 240 Watt Each 1,170.00 450,153.00 Each 1,170.00 450,153.00


c) 8-Channel
(i) 150 Watt Each 1,170.00 270,753.00 Each 1,170.00 270,753.00
(ii) 240 Watt Each 1,170.00 414,135.00 Each 1,170.00 414,135.00
154 Supplying ,Installation and comissioning of IP based Audio Matrix Paging
Controller in specified Channels, suport specified Music source input,
specified remote control panels, 02 paging consoles and 01 microphone input,
expandable to 32 Zones and support cascade 4 Amplifire units to make 8 x 32
matrix system. and capable of specified zone voice alarm system. made of
Ecler Europe/Norden, Bosch, Honeywell. Complete in all respect as approved
and directed by Engineer Incharge.
(i) Digital zones 8x8 (8 input & 8 output channels) Each 780.00 422,025.00 Each 780.00 422,025.00
(i) Digital zones 16x16 (16 input & 16 output channels) Each 780.00 560,025.00 Each 780.00 560,025.00
155 Supply, Installation of Microphone of specified quality as per requirement
made of : Norden, Bosch, Honeywell. Complete in all respect. as approved
and directed by Engineer Incharge.
(i) Cordless Microphone with Transmitter Each 780.00 118,563.00 Each 780.00 118,563.00
(ii) Desktop Remote Paging Microphone Each 780.00 422,025.00 Each 780.00 422,025.00
(iii) Handheld Microphone with Stand Each 780.00 36,004.50 Each 780.00 36,004.50
(iv) Headset Condensor Microphone Each 780.00 49,804.50 Each 780.00 49,804.50
156 Supplying, Installation of musical source multiformat audio player, including Each 780.00 90,997.50 Each 780.00 90,997.50
cost of all necessary accessories / materials , complete in all respects. made of
Bosch/ Norden / Honey Well or equivalent, as approved and directed by
Engineer Incharge.

157 Supply, installation, testing, commissioning and termination of 8.7 / 15kV,


AL/XLPE/UA/PVC three Core (MV cables) of Pakistan cables / Newage or
approved equivalent along with cable glands, in already installed cable trench /
cable ladder / cable tray / duct bank. (Non armoured)
i) 50mm sq Per Rft 36.25 1,114.75 P.Meter 118.95 3,656.40
ii) 70mm sq Per Rft 36.25 1,289.60 P.Meter 118.95 4,229.90
iii) 95mm sq Per Rft 36.25 1,484.40 P.Meter 118.95 4,868.90
iv) 120mm sq Per Rft 36.25 1,694.30 P.Meter 118.95 5,557.35
v) 150mm sq Per Rft 36.25 1,900.45 P.Meter 118.95 6,233.45
vi) 185mm sq Per Rft 36.25 2,119.40 P.Meter 118.95 6,951.55
vii) 300mm sq Per Rft 36.25 2,796.55 P.Meter 118.95 9,172.65
158 Supply, installation, testing, commissioning and termination of 8.7 / 15kV,
AL/XLPE/SWA/PVC three Core (MV cables) along with cable glands, in
already installed cable trench / cable ladder / cable tray / duct bank.
(Armoured)
i) 50mm sq Per Rft 36.25 1,737.65 P.Meter 118.95 5,699.50
ii) 70mm sq Per Rft 36.25 1,917.80 P.Meter 118.95 6,290.30
iii) 95mm sq Per Rft 36.25 2,071.50 P.Meter 118.95 6,794.60
iv) 120mm sq Per Rft 36.25 2,175.15 P.Meter 118.95 7,134.50
v) 150mm sq Per Rft 36.25 2,617.90 P.Meter 118.95 8,586.80
vi) 185mm sq Per Rft 36.25 3,107.80 P.Meter 118.95 10,193.60
vii) 300mm sq Per Rft 36.25 3,403.25 P.Meter 118.95 11,162.60

chapter-24(Electric Installation).xls Page 201


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

159 Supply, installation, testing, commissioning and termination of 8.7 / 15kV,


AL/XLPE/UA/PVC Single Core (MV cables) along with cable glands, in
already installed cable trench / cable ladder / cable tray / duct bank.
(Non armoured)
i) 500mm sq Per Rft 36.25 1,368.00 P.Meter 118.95 4,487.00
ii) 630mm sq Per Rft 36.25 1,510.80 P.Meter 118.95 4,955.40
160 Supply, installation, testing, commissioning and termination of following 8.7
/ 15kV, AL/XLPE/SWA/PVC Single Core (MV cables) along with cable
glands, in already installed cable trench / cable ladder / cable tray / duct bank.
(Armoured)
i) 500mm sq Per Rft 36.25 1,804.75 P.Meter 118.95 5,919.50
ii) 630mm sq Per Rft 36.25 1,917.40 P.Meter 118.95 6,289.05
Grounding / Earthing System
161 Supply, Installation, Testing & Commissioning of complete grounding system:

i) 4 mm² CU bare conductor Per Rft 13.85 52.30 P.Meter 45.40 171.50
ii) 6 mm² CU bare conductor Per Rft 13.85 70.00 P.Meter 45.40 229.55
iii) 10 mm² CU bare conductor Per Rft 13.85 108.80 P.Meter 45.40 356.90
iv) 16 mm² CU bare conductor Per Rft 13.85 164.20 P.Meter 45.40 538.55
v) 25 mm² CU bare conductor Per Rft 13.85 251.25 P.Meter 45.40 824.10
vi) 35 mm² CU bare conductor Per Rft 13.85 342.45 P.Meter 45.40 1,123.20
vii) 50 mm² CU bare conductor Per Rft 13.85 458.90 P.Meter 45.40 1,505.10
viii) 70 mm² CU bare conductor Per Rft 13.85 656.70 P.Meter 45.40 2,154.00
ix) 95 mm² CU bare conductor Per Rft 13.85 905.65 P.Meter 45.40 2,970.55
x) 120 mm² CU bare conductor Per Rft 13.85 1,140.20 P.Meter 45.40 3,739.80
xi) 150 mm² CU bare conductor Per Rft 13.85 1,397.20 P.Meter 45.40 4,582.75

chapter-24(Electric Installation).xls Page 202


25. IRON WORK
The Rates for all finished works include the removal of surplus debris, unused material and byproducts.

MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

Railway Track, etc.

1 Laying, linking and packing tramway line. 100Lft. 3,528.15 Metre 115.70

2 Dismantling tramway track. 100Lft. 1,155.00 Metre 37.90

3 Laying, linking of B.G. track, including packing, 100Lft. 9,229.00 Metre 302.70
straightening and leveling.

4 Linking points and crossings, complete with fastenings. Each 8,721.90 Each 8,721.90

5 Bending or strainghtening B.G. rail with Jim Each 980.10 Each 980.10
Crow. Point Point

6 Fixing street lamp posts. Each 1,082.75 Each 1,082.75

7 Binding ends of sleepers and timber of all sizes and kinds, 100 Nos 10,756.35 100 Nos 10,756.35
including spreading and restacking.

8 Opening stacks of sleepers and timber of all kinds and 100 Nos 1,303.30 100 Nos 1,303.30
sizes, including spreading for inspection and restacking
within one chain lead.

I RON WORK

9 Small iron work, such as gusset plates, knees, bends, Per Cwt 5,758.50 20,999.80 100 Kg 11,335.65 41,338.15
stirrups, straps, rings, etc. including cutting, drilling,
riveting, handling, assembling and fixing; but excluding
erection in position.

10 Fabrication of heavy steel work, with angle, tees, flat iron Per Cwt 2,013.90 16,531.50 100 Kg 3,964.40 32,542.25
round iron and sheet iron for making trusses, girders,
tanks, etc., including cutting, drilling, revitting, handling,
assembling and fixing, but excluding erection in position.

11 Erection and fitting in position iron trusses, staging of Per Cwt 664.40 100 Kg 1,307.85
water tanks, etc.

12 Fixing corrugated iron sheet, including revitting, etc. 100 Sft. 2,391.85 sq.m 257.35

13 Erecting corrugated iron sheet tanks, upto 20' Per Cwt 1,090.05 100 Kg 2,145.75
(6 m) height.

chapter-25(Iron work).xls Page 203


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

14 Erecting rolled steel beams or old rails, in roofs, etc., Per Cwt 644.25 100 Kg 1,268.25
erection and fixing in position.

15 Erecting rolled steel beams or rails, erection for posts etc. Per Cwt 315.20 100 Kg 620.50
(other than in roofs).

16 Making bolts and nuts of iron rods. Per Cwt 4,492.60 22,272.25 100 Kg 8,843.75 43,843.00

17 Cutting rails, rolled steel joists and beams, with hacksaw:-

a) upto 6" size (150 mm) Per Cut 448.45 Per Cut 448.45
b) above 6" size (150 mm) Per Cut 666.60 Per Cut 666.60

18 Cutting rails or rolled steel beams of size below 6" Per 213.55 Per Cwt 213.55
(150 mm), with jim. Cut Cut

19 Bending rolled steel beams or rails. Per 225.05 560.90 Per 225.05 560.90
Bend Bend

20 Drilling holes, in plates upto ½" (13 mm) thick, per inch Per 85.15 Per 85.15
dia, (25mm) or part thereof. Hole Hole

21 Extra for drilling holes in plates over ½" (13 mm) thick, per Per 46.05 Per 46.05
inch dia, (25 mm) or part thereof. Hole Hole

22 Rivetting 1/8" dia (3 mm). 100 Nos 1,065.90 100 Nos 1,065.90

23 Cutting out Rivets, all sizes. 100 Nos 3,750.45 100 Nos 3,750.45

24 Fitting and erection of gutters of sheet iron. Per Lft. 140.60 Metre 461.20

25 Cutting and fixing iron bars, for barred windows. Per bar 85.40 Per bar 85.40

26 Cutting G.I. sheets. Each 46.15 Each 46.15


Cut Cut
27 Notching web or foot of rail posts, for housing rail beams. Per 1,000.10 1,224.10 Per 1,000.10 1,224.10
Notch Notch
28 Hoop iron netted trellis work fixed with nails. Per Sft. 59.80 sq.m 643.40

29 Fixing zinc iron or G.I. sheet on table tops. Per Sft. 35.15 sq.m 378.45
30 Making and fixing steel grated doors, complete with Per Sft. 351.15 1,933.45 sq.m 3,778.55 20,803.95
locking arrangement, angle iron frame 2"x2"x3/8"
(50x50x10 mm) and ¾" (20 mm) square bars 4" (100 mm)
centre to centre.
31 Making and fixing steel grated door with 1/16" thick Per Sft. 366.50 2,377.55 sq.m 3,943.40 25,582.55
(1.5mm) sheeting, including angle iron frame 2"x2"x3/8"
(50x50x10 mm) and ¾" (20 mm) square bars 4" (100 mm)
centre to centre, with locking arrangement.

chapter-25(Iron work).xls Page 204


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

32 Making and fixing grating in opening, including fixing at Per Sft. 141.55 958.55 sq.m 1,522.85 10,314.15
site with flat iron 2"x3/8" (50x10 mm) and ¾" (19 mm)
square bars, at 4" (100 mm) centre to centre.

33 Providing and fixing stair railing (all types and designs) of Per Rft. 751.90 2,088.10 Metre 2,466.85 6,850.65 The composite rate shall be
hard wood, including bends and corners, screwed to reduced or increased by Rs. 31.90
5/8"x5/8" (16x16 mm) M.S. square bars 2.75 ft. (838 mm) for each foot of reduction or
high, at 5.5 inch (137 mm) inch centre to centre, fixed in addition in the height of the square
steps of stairs, M.S. flat 1"x1/8" (25x3 mm) welded to bars.
bars, painting/polishing 3 coats, etc. complete.

34 Providing/fixing stair railing consisting of M.S. Box section Per Rft. 399.35 1,076.45 Metre 1,310.15 3,531.70
size 1-1/2"x3" of 16 SWG welded with M.S. flat 1"x1/8"
continuously and welded over M.S. square bars 5/8"x5/8"
punched in M.S. flat 2 ¾' high @ 5½" c/c fixed in steps of
stair I/C painting 3 coats complete.

35 Providing and fixing terrace railing of 2" (50 mm) i/d Per Rft. 288.70 1,598.00 Metre 947.18 5,242.78 -do-
conduit pipe 16 SWG, welded with 5/8"x5/8" (16x16 mm)
square bar 2.75 ft. (838 mm) high fixed at 5" (125 mm)
centre to centre, in reinforced cement concrete slab with
suitable arrangement, complete in all respects, as per
design and drawing.

36 Providing and fixing collapsible gate made of 2"x2"x"¼" Per Sft. 558.20 1,613.35 sq.m 6,006.35 17,359.70
(50x50x6 mm) tee iron at top and bottom, channel iron
verticals ¾"x¼"x¼"x1/8" (20x6x6x3 mm) at 3" (75 mm) to
5" (125 mm) centre to centre (approximate) and flat iron
crosses 3"x3/16" (75x5 mm), and best quality rollers at
bottom of 3" (75 mm) diameter including holdfasts,
handles 12" (300 mm) long of ¾"x¼"x¼"x1/8" (20x6x6x3
mm) channel iron, locking arrangement inside and
outside, painting 3 coats of black Japan enameled,
complete in working order.

37 Providing and fixing 24 SWG G.I. sheet rolling shutter, Per Sft. 124.95 623.80 sq.m 1,344.35 6,711.85
consisting of steel frame of M.S. channel 2"x1¼"x1/8"
(50x30x3 mm), angle iron 1½"x1½"x1/8" (40x40x3 mm),
M.S. plate 1'x1'x1/8" (300x300x3 mm), G.I. pipe 1½" (37
mm) dia, springs 2' (600 mm) centre to centre, rollers, 24
SWG G.I. covering 1 ft. x 1 ft. (300x300 mm), handles,
holdfast, and painting three coats, complete in all
respects.

38 Providing and fixing M.S. angle iron 1½"x1½"x¼" Per Rft. 60.55 377.60 Metre 198.70 1,238.80
(40x40x6 mm) edge protector nozing of steps of stairs,
having holdfast or 3/8" (10 mm) dia M.S. bars 8" (200 mm)
long welded at 2' (600 mm) centre to centre and
embedded in cement concrete on steps, complete in all
respects.
39 Providing and fixing stair railing of 2½" (63 mm) i/d G.I. Per Rft. 323.65 1,766.55 Metre 1,061.90 5,795.80 The composite rate shall be
pipe, welded with 5/8"x5/8" (16x16 mm) square M.S. bars reduced or increased by Rs. 31.90

chapter-25(Iron work).xls Page 205


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

2'-9" (838 mm) high, fixed in each step, complete in all for each foot of reduction or
respects, including painting, polishing three coats. addition in the height of the square
bars.
40 Providing and fixing G.I. wire gauze 24 SWG, 12x12 Per Sft. 57.20 146.45 sq.m 615.45 1,575.75
meshes per square inch, fixed to steel windows or doors,
etc., complete in all respects.

41 Providing and fixing steel windows with openable glazed


panels, using beam section for frame 1½"x1"x5/8"x1/8" For fixed pannels, the composite
(40x25x16x3 mm), Z-section for leaves ¾"x1"x¾"x1/8" rate will be reduced by Rs.30.00
(20x25x20x3 mm), T-section sashes 1"x1"x1/8" (25x25x3 per Sft. or Rs. 305.00 per Sq.
mm), glass panes, wooden screed for glazing embedded metre.
over a thin layer of putty duly screwed with leaves, brass
fittings, holdfast, duly painted, complete in all respects,
including all cost of material and labour, etc. as per
approved design and as directed by the
Engineer-in-charge:-

a) without wire gauze:

i) glass pane 2 mm thick Per Sft. 145.70 807.00 sq.m 1,567.65 8,683.45
ii) glass pane 2.5 mm thick ditto 145.70 819.00 ditto 1,567.65 8,812.60
iii) glass pane 3 mm thick ditto 145.70 855.00 ditto 1,567.65 9,199.95
iv) glass pane 4 mm thick ditto 145.70 903.00 ditto 1,567.65 9,716.45
v) glass pane 5 mm thick ditto 145.70 927.00 ditto 1,567.65 9,974.65
b) fixed with wire gauze, 22 SWG

i) glass pane 2 mm thick Per Sft. 205.95 969.60 sq.m 2,216.05 10,433.10
ii) glass pane 2.5 mm thick ditto 205.95 981.60 ditto 2,216.05 10,562.20
iii) glass pane 3 mm thick ditto 205.95 1,017.60 ditto 2,216.05 10,949.55
iv) glass pane 4 mm thick ditto 205.95 1,065.60 ditto 2,216.05 11,466.05
v) glass pane 5 mm thick ditto 205.95 1,089.60 ditto 2,216.05 11,724.30

42 Providing and fixing steel windows using M.S. sheet (16


SWG) moulded tubular pipe 1½"x1½" (40x40mm) for
frame and 1¼"x1¼" (30x30mm) for leaves including M.S.
square bars ¼"x¼" (6x6 mm) welded around each panel
of frame, 5 mm thick glass panes fixed with double M.S.
square tubular pipe 3/8"x3/8" (10x10mm) (22 SWG)
beading with U' shaped rubber lining, brass fitting,
holdfast, including painting three coats complete in all
respects.
a) For openable panels fixed with wire Per Sft. 108.70 980.75 Sq.m 1,169.40 10,552.60
gauze 24 SWG, 12x12 mesh and glass
panes ¼" (6 mm) thick.
b) For fixed panels without wire gauze. ditto 104.40 535.80 ditto 1,123.25 5,765.20
43 Providing and fixing windows consisting of M.S. box Per Sft. 138.40 1,342.55 Sq.m 1,488.95 14,445.75
section frame 2"x1½" (50x40mm), leaves frame 1-½"x1"
(40x25mm) box section frame for glazing 3/8"x3/8"

chapter-25(Iron work).xls Page 206


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

(10x10mm) using 16 SWG sheet 'U' shaped rubber


supported with 1"x1/8" (25x3mm) M.S. flat for fixing 3/16"
(5 mm) thick glass panes M.S. box section ½"x½"
(13x13mm) of 16 SWG for fixing 24 SWG wire gauze on
outer side by means of ¾"x1/8" (20x3mm) M.S. flat and
screws I/C all C.P. fitting and painting 3 coats complete in
all respect.

44 Providing and fixing windows consisting of M.S. box Per Sft. 188.70 1,610.90 Per Sft. 2,030.65 17,333.20
section frame 2"x1½", (50x40mm) leaves frame 1½"x1"
(40x25mm) box section frame for glazing 3/8"x3/8"
(10x10mm) using 16 SWG sheet 'U' shaped rubber
supported with 1"x1/8" (25x3mm) M.S. flat for fixing 3/16"
(5 mm) thick glass panes M.S. box section ½"x½"
(13x13mm) of 16 SWG for fixing 24 SWG wire gauze on
outer side by means of ¾"x1/8" (20x3mm) M.S. flat and
screws including grill of M.S. flat ½"x1/8" (13x3mm) or
¼"x¼" (6x6mm) square bar with independent frame of
½"x½" (13x13mm) box section of 16 SWG i/c all C.P.
fitting and painting 3 coats complete in all respect.

45 Flapping G.I. pipes for bath room drains. Each 1,287.00 1,371.00 Each 1,287.00 1,371.00

46 Supply and fixing iron grating for fire place. Per Sft. 235.30 391.30 sq.m 2,531.70 4,210.30

47 Fixing copper flashing, including cutting of sheets, Per Lft. 99.65 Metre 326.90
grooving and rivetting.

48 Providing and fixing angle iron railing, using 2½"x2½"x3/8" Per Rft. 157.80 2,205.95 Metre 517.80 7,237.40
(63x63x10 mm) angle iron post 4½" (113 mm) long, 5' to
6' (1500 to 1800 mm) apart, with 2½"x2½"x3/8" (63x63x10
mm) angle iron top rail, and two rows of M.S. flat 2½"x¼"
(63x6 mm) including fixing to side of Bridge/structure with
U.bolt 1½' (450 mm) long ¾" (20 mm) dia, painting posts,
etc. complete in all respects.

49 Providing and fixing barbed wire fencing on compound 100Rft. 3,614.85 24,960.25 Metre 118.60 818.90
wall, consisting of 1½"x1½"x3/16" (40x40x5 mm), angle
iron post 3¼ ft. (990 mm) long, 5 to 6 ft. (1500 to 1800
mm) centre to centre, embedded in cement concrete
1:4:8, base of size 9"x9"x12" (225x225x300 mm), and
three rows of barbed wire, painting posts, etc. complete in
all respects.
50 Providing and fixing barbed wire fencing on compound 100Rft. 6,033.65 31,861.35 Metre 197.95 1,045.30
wall, consisting of 1½"x1½"x3/16" (40x40x5mm) angle
iron post 3' (900 mm) long, 4' (1200 mm) apart embedded
in cement concrete 1:4:8 base of size 6"x6"x9"
(150x150x225 mm) and 4 rows of barbed wire, including
binding wire, painting posts, etc. complete in all respects.
chapter-25(Iron work).xls Page 207
MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

51 Providing and fixing all types of partly fixed and partly (1) Increase rate by Rs. 40.00 per
openable glazed anodised/ powder coated Sft or Rs.430.50 per Sq-metre if
aluminium doors, using delux section of M/s Al-Cop or Pakistan sections thickness is 2 mm.
Cables, having chowkat frame of size 40 x 100 mm (1½" x (2) Reduce rate by Rs.20.00 per Sft
4") and leaf frame of 60x40mm (2½"x1½") wide sections or Rs.215.20 per Sq-metre if
including the cost of ¼" (5 mm) thick imported tinted sections are of dull aluminimum
glass with aluminium triangular gola and rubber gasket to shade.
support the glass and leaf edging, using approved (3) Reduce rate by Rs.20.00 per
standard fittings, locks, 3" (75 mm) wide long handles Sft or Rs.215.20 per Sq-metre if
etc., and hardware any required as approved by the local glass is used.
engineer in-charge. Per Sft 186.60 1,441.20 sq. m 2,007.80 15,507.30

52 Providing and fitting all types of glazed aluminium Per Sft 272.60 1,353.75 sq. m 2,933.20 14,566.35 (1) Reduce rate by Rs.20.00 per Sft
windows of anodised/ powder coated partly fixed or Rs.215.20 per Sq-metre if
and partly sliding using delux sections of approved manufacturer section thickness is 1.2 mm.
having frame size of 100 x 30 mm (4"x1-1/4") and (2) Reduce rate by Rs.20.00 per Sft
leaf frame sections of 50 x 20 mm (2"x¾"), all of 1.6mm or Rs.215.20 per Sq-metre if
thickness including 5 mm thick imported tinted glass with sections are of dull aluminium
rubber gasket using approved standard latches, hardware shade.
etc., as approved by the Engineer in-charge. (3) Reduce rate by Rs.20.00 per Sft
or Rs.215.20 per sq-metre if local
glass is used.

53 Providing and fixing Aluminum Fly screen comprising of Fiber / Per Sft 62.30 494.50 P.Sqm 670.20 5,320.70 Reduce composite rate by Rs.29.40
Aluminum wire guaze (Malasian) fixed in aluminum frame of P.Sft, if 1.2mm thick aluminum is
approved manufacturer / powder coated of size 1-1/2"x1/2" and used.
1.6mm thick with rubber gasket i/c cost of Hardwares as approved
and directed by the engineer incharge. complete in all respect.

54 P/F MS box section window of 16 SWG, having frames of 2” x 1- Per Sft 129.00 1,315.50 P.Sqm 1,387.90 14,154.60 i. If Brass stays will be provided, rate
1/2” , leave frame of T-type box section of 2” x1” x1” , with ½” x1/2” of Rs.20/- P.Sft will be paid.
box section using, U shaped rubber for fixing 5 mm thick glass ii. For fixed pannels without guaze,
panes i/c the cost of fixing of 24 SWG wire guaze on inner side by reduce rate of Rs.150/- P.Sft.
means of ½” x1/8” MS flat patti, MS grill fitted within the window Iii. If box sections of 18SWG used,
frame and screws including hinges, brass handles and painting 3 reduce rate of Rs. 25/- P.Sft.
coats. Complete in all respect
55 Providing / Laying M.S Liner of specified thickness for concrete Cwt 1.05 6.70 P.Kg 52.70 340.05
bored piles, placed at the upper part of bore, as mentioned on
drawings etc complete in all respect.

chapter-25(Iron work).xls Page 208


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

56 Providing and fixing 2 mm thick Double glazed aluminium windows Per Sft 381.65 2,586.55 Sq.m 4,106.50 27,831.50 If natural color sections are used,
of anodize / powder coated partly fixed and party sliding using reduce composite rate by Rs 50/- Psft
deluxe section of 100mm x 40mm x2 mm using frame (70501) at or Rs 538/- P.Sq Mtr.
bottom, (70502) at Top & Side made of Pakistan Cables/Alcop
having Leaf Frame size 31mm x 60mm x2 mm (70506) at Top &
Bottom, 35mm x 60mm x2 mm (70505) at center and 35mm x
60mm x2 mm(70503) at sides , fixing 5 mm thick imported tinted
double glass and air tight using double tape, chemical strips, Silicon
using approved latches, wheels for channel, stopper, brush channel
angle joint and hardware etc.( excluding the cost of Fly Proofing).
Complete in all respect as approved and directed by the Engineer
Incharge.
57 Providing and fixing aluminium glazed partition of anodized / Per Sft 318.95 1,244.20 Sq.m 3,431.85 13,387.35 If natural color sections are used,
powder coated using section of M/s. Al-Cop/ Pakistan Cable having reduce composite rate by Rs 50/- Psft
2 mm thick Frame size D48-A , i/c 12 mm tinted TEMPERED glass or Rs 538/- P.Sq Mtr.
with sand blasting and edge polishing i/c the cost of tear resistance
film,rubber gasket and hardware etc. complete in all respect as
approved and directed by the Engineer Incharge.(Floor hinge will be
paid separately)
58 Providing and fixing M.S. flat ½"x1/8" (13mm x 3mm) grill Per Sft. 123.55 496.60 sq.m 1,329.40 5,343.40
including ¾" x 1/8" (20 mmx3 mm) M.S. flat frame, in
windows of approved design, including painting three
coats, complete in all respects.
59 Providing and fixing M.S. grill fabricated with MS Square polished
Vertical/horizontal Bars of specified size @ 4" c/c ' passed through
punched holes in MS Patti of 1-1/4"x1/8" i/c the cost of 1-1/4"x1/8''
MS patti for Frame of windows and painting 3 coat complete in all
respect as approved and directed by the Engineer Incharge.

(i) 3/8" Squar Bars Per Sft 233.05 863.20 Sq.m 2,507.50 9,287.95
(ii) 1/2" Squar Bars Per Sft 233.05 996.45 Sq.m 2,507.50 10,721.60
60 P/F Double locking arrangement for steel grated door consisting of Each 2,538.20 12,498.50 Each 2,538.20 12,498.50
MS Box of size 9"x13-1/2"x9" made with 1/4" thick MS sheet i/c
double sliding bolt of 1-1/4" dia rod operated with 1-1/2" dia GI pipe
duly embedded with cement concrete (1:2:4) i/c holdfast i/c painting
3 coats complete in all respect as approved and directed by the
Engineer Incharge.
61 P/F 1.5' deep gun racks comprising of 18 SWG M.S Sheet and M.S Per Sft 268.55 1,726.85 Sq.m 2,889.35 18,580.70
angle iron 1-1/2"x1-1/2"x1/4" for frame including 02-Nos
Sheesham wood planks 1-1/2" thick with polishing for guns hold i/c
all labour and painting with hammer paint complete in all respect as
approved and directed by the Engineer Incharge.

chapter-25(Iron work).xls Page 209


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

62 P/F Iron door comprising of specified leaves made of 1-1/4” x1-


1/4” x3/16" MS angle iron for leaf frame, diagonal and horizontal
braces duly welded with MS. sheet 18-SWG i/c the cost of
sliding bolt, tower bolt and painting 3-coats but excluding the cost
of Chowkat complete in all respect as approved and directed by the
Engineer incharge.
(i) Single Leaf Per Sft 71.85 1,005.20 Sq.m 773.25 10,816.00
(ii) Double Leaf Per Sft 78.55 1,395.65 Sq.m 845.25 15,017.05
63 Providing and fixing 5.00 ft dia MS spiral stair comprising of P. Rft 228.80 6,889.60 P.Meter 750.45 22,597.90
triangular steps made of 1-1/4"x1-1/4"x3/16" duly welded with Height Height
3/8"MS squar bars steps, supported/welded with main vertical post
of 4" dia GI pipe (Medium Quality) embeded in PCC in ground i/c
the cost of pipe railing comprising of 2" dia MS pipe of 16 SWG
supportrd with 2 no 5/8" squar bars in each step, i/c fixing &
painting complete in all respects as approved and directed by the
Engineer Incharge(Measurement will be made above ground level).

64 Providing and fixing 2'-9" high stair railing comprising of non Per Rft 299.00 2,368.45 Meter 980.65 7,768.60
magnetic (304) Stain less steel 2" dia pipe railing of 18 SWG welded
with vertical posts of 2" dia stainless steel round/ Squar pipe/ Tong
(chimta) @ 2-ft c/c fixed on alternate steps with 3" long steel screws
and brass rawal plugs , 3-Nos diagonal stainless steel pipes of 1/2"
dia passes through goties fixed on vertical post, i/c stainles steel
welding, fixing & polishing complete in all respects as approved and
directed by the Engineer Incharge.
65 Providing and fixing 2" dia 18 SWG non-magnetic Stain less steel Per Rft 175.90 508.90 Meter 576.90 1,669.15
pipe (304) wall mounted hand rail comprising fixed with 2" long
steel bracket with screws i/c the cost of hardware etc. & stainless
steel welding & polishing complete in all respects as approved and
directed by the Engineer Incharge.
66 Providing and fixing 2.00 ft deep M.Steel Lockers (Wardrobes) Per Sft 256.05 2,042.60 Sq.m 2,754.85 21,978.35
consisting of 1-1/4” x1-1/4” x3/16” angle Iron Frame & 1” x1” x1/8”
MS Flat for center vertical bracing duly welded with MS sheet 24-
SWG Sheet on all Sides, Back & Top and for partitions / Shelves
and 1"x1"x1/8" Angle Iron for Leaf Frame duly welded with 18-
SWG for Front Door and hinges and locking arragement ,handles
duly painted with hammar paint 3-coats complete in all respect as
approved by the Engineer Incharge.
67 Providing and Fixing steel grating on windows comprising of ¾” MS Per Sft 85.75 1,170.95 Sq.m 922.65 12,599.20
square bars of 4"c/c penetrated through punched holes of 3 no Ms
flat 2” x3/8” duly welded wiith 2” x2” x3/8" angle iron frame i/c three
coat painting complete in all respect as approved by the Engineer
incharge.

chapter-25(Iron work).xls Page 210


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

68 P/F iron grated doors comprising of 2-1/2” x2-1/2” x3/8” angle iron Per Sft 76.50 2,835.10 Sq.m 823.35 30,505.75
chowkat ,2” x2” x3/8” angle iron frame and with ¾” square bar at 4”
center to center penetrate through punch holes of 2-nos 2” x3/8” MS
flat horizantal bracings i/c cost of gussest plates of 3/8” MS sheet,
hinges, MS Sliding Bolts and three coats of painting complete in all
respect as approved and directed by the Engineer incharge.

69 Providing and fixing rolling Shutter, comprising of 8 mm dia plain Per Sft 109.70 497.95 Sq.m 1,180.35 5,357.85
MS steel bars duly bent in the shape of sine waves roll in MS
Channels of size 2"X 1-1/4"X 1/8" i/c the cost of 1-1/2" dia G1 Pipe
for rolling,pullies , springes, 24 SWG G1 sheet covering box for
machine,puling handles of of angle iron 1-1/2"X1-1/2"X1/8",
holdfast and painting charges , complete in all respects as approved
and directed by the Engineer Incharge.
70 Providing and fixing MS louvered door comprising of 3/4"x3/4"x2" Per Sft 157.70 1,251.80 Sq.m 1,696.95 13,469.25
louvers of 16 SWG MS sheet welded with door frame of size 2"x4"
16 SWG MS pipe with lock rail i/c the cost of handles, 1" dia MS
sliding bolt ,three coats of fire proof paint complete in all respect as
approved and directed by the Engineer Incharge.

chapter-25(Iron work).xls Page 211


26. MISCELLANEOUS
Rates for all finished works include the removal of surplus debris, unused material and byproducts.

MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

1 Notice board made of cement, sand mortar 1:3. Per Sft. 128.05 147.90 Per 1,377.70 1,591.55 The board is to be of cement
sq.m plaster ½" (13 mm) thick, with 2"
(50 mm) wide and 1" (25 mm) thick
beading.
2 Fixing handles to iron hammers. Each 178.75 - Each 178.75 -
3 Providing and fixing barbed wire fencing, with 4 horizontal 100Lft. 13,142.65 54,623.75 L.m. 431.20 1,792.10 Vertical bars in straining and
and 2 number cross wires fixed with posts of R.C.C., 1:2:4 stiffening posts to be 4 No. each by
(straining posts 7'x9"x9" (2.13 mx225x225 mm) at 100' ½" (13 mm) dia and for
(30 m) centre to centre, stiffening posts 7'x6"x6" (2.13 intermediate posts to be 4 No. of
mx150x150 mm) at 50 ft. (15 m) interval and intermediate 3/8" (10 mm) dia Stirrups for all
post 7'x5"x5" (2.13 mx125x125 mm) at 8 ft.(2.4 m) centre posts to be ¼" (6 mm) dia. at 12"
to centre), including cost of steel, its fabrication and (300 mm) centre to centre.
placing of steel reinforcement, eye bolts, washers, etc.
complete.
Surveying
4 Supplying Bamboo Jhandies 10' to 12' (3.00 to 3.65 m) with Each 77.90 869.90 Each 77.90 869.90
iron shoes, and flags 15" (375mm) square.
5 Supplying wooden pegs for levelling, 1½" (40 mm) dia, 6" 100Nos. 286.00 310.95 100Nos. 286.00 310.95
(150mm) long.
6 Supplying wooden pegs for alignment, 2" to 3" dia (50 to 100Nos. 686.40 974.40 100Nos. 686.40 974.40
75 mm), 9" (225 mm) long.
7 Fixing enamalled iron gauges flush with masonry, including Per Lft. 149.50 162.10 Per 490.45 531.80
cost of hooks. L.M.
8 Placing boundary pillars in position, including digging pits. Each 99.65 - Each 99.65 -
9 Fixing main line type distance mark in position, including Each 426.35 747.95 Each 426.35 747.95 Composite rate does not include
making 1:3:6 cement concrete base block, size cost of iron distance marks.
14"x10"x15" (350x250x375 mm).

Hand Pumps & Pressure Pipes


10 Cutting pipes, upto 2" (50 mm) dia. Per cut 99.65 - Per cut 99.65 -
11 Cutting pipe, above 2" (50 mm) dia. Per cut 183.80 - Per cut 183.80 -
12 Threading pipe ends, 1½" (40 mm) to 4" (100 mm) dia. Each 128.25 - Each 128.25 -
End End
13 Assembling 1½" (40 mm) dia pressure pipe. 100Lft. 453.35 - Per Metre 14.85 -
14 Boring and fixing 1½" (40 mm) dia pressure pipe:
a) in ordinary soil Per Lft. 154.35 - Per Metre 506.40 -
b) in clay Per Lft. 297.65 - Per Metre 976.60 -
c) in shingle Per Lft. 440.96 - Per Metre 1,446.75 -

chapter-26( Misc).xls Page 212


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

15 Repairs to hand pump, pulling out and refitting. Per Lft. 68.10 - Per Metre 223.45 -

16 Fixing hand pump (Machine only) Each 343.20 - Each 343.20 -


Rest House Furniture & Fuel, etc.
17 Washing Niwar of bed. Per bed 955.35 1,020.85 Per bed 955.35 1,020.85

18 Washing Durries. 100Sft. 1,273.80 1,429.80 sq.m 137.10 153.90


19 Recaning chairs:
i) office chairs, single caning seat only. Each 600.60 649.55 Each 600.60 649.55
ii) office chairs, double canning seat only. Each 772.20 841.30 Each 772.20 841.30
iii) office chairs, single caning back only. Each 429.00 432.10 Each 429.00 432.10
iv) office chairs, double caning back only. Each 686.40 712.90 Each 686.40 712.90
v) easy chairs, single caning seat only. Each 429.00 494.65 Each 429.00 494.65
vi) easy chairs, double caning seat only. Each 1,201.20 1,299.10 Each 1,201.20 1,299.10
vii) easy chairs, single caning only, back and seat in one Each 1,716.00 2,119.20 Each 1,716.00 2,119.20
piece.
viii) easy chairs, double caning back & seat in one piece Each 2,574.00 3,553.20 Each 2,574.00 3,553.20
or couches with caned area about 16 Sft (1.5 Sqm).
20 Making and fixing Hat pegs ordinary. Each 308.90 1,987.70 Each 308.90 1,987.70
21 Weaving charpoy. Each 1,115.40 - Each 1,115.40 -
22 Sweeping chimney. Each 212.30 213.60 Each 212.30 213.60
23 Picture railing, including making, fixing and painting. Per Lft. 88.35 298.70 Per LM 289.95 980.00
24 Cutting fuel wood, from plantation. 100Kg 284.35 - 100Kg 284.35 -
25 Splitting fuel wood. 100Kg 595.55 - 100Kg 595.55 -
26 Burning charcoal, including loading, unloading and 100Kg of 1,028.20 - 100Kg of 1,028.20 -
repairing kilns. Char- Char-
coal coal
27 Filling cement bags with coal and sewing (including cost 100Cft. 2,611.30 2,614.40 cu.m 922.30 923.40
of strings).
28 Supplying manure. Cart 318.45 486.45 Cart 318.45 486.45 Capacity of cart, 20 Cft. (0.57
Load Load cu.m).
29 Washing punkha frills. Each 343.20 - Each 343.20 -
30 Washing:-
a) table cloth Each 85.80 - Each 85.80 -
b) napkins, dusters, etc. Each 57.20 - Each 57.20 -
31 Hoisting and placing sleepers for centring, including Each 117.00 - Each 117.00 -
carriage within one chain. No. No.
32 Dismantling sleepers from centring, including stacking Each 132.90 - Each 132.90 -
within one chain. No. No.
33 Dredging Sumps. Per 4,776.75 - Per 4,776.75 - Not less than five gangmen to be
Shift Shift employed for each shift to ensure
effective dredging.
34 Fixing `U' bolt in masonry or concrete, including levelling Each 392.15 - Each 392.15 -
and tying for fixing angle iron post.

chapter-26( Misc).xls Page 213


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

35 Bailing out water:-

a) by hand 1000 Cft. 3,821.40 - cu.m 134.95 - Rate includes cost of providing
b) by pump 1000 Cft. 467.15 870.25 ditto 16.50 30.75 pump, POL and operation charges,
etc.

36 Drilling holes in R.C. Trough. Per Nos. 249.15 - Per Nos. 249.15 -

37 Supplying and laying polythene sheet over D.P.C. under The rate includes overlaps.
floors and on roofs, etc.

i) 300 gauge (.003" thick) Per Sft. 2.55 6.00 sq.m 27.70 64.75
ii) 500 gauge (.005" thick) Per Sft. 5.15 8.05 sq.m 55.40 86.40

38 Laying 2" (50 mm) thick sand and bitumen carpet, on top 100Sft. 2,645.10 11,949.05 sq.m 284.60 1,285.70
of foundation of oil tank.

39 Cutting hole 4"x6" (100x150 mm) in stone masonry or Per 427.10 - Per 427.10 - Same rate to be paid for other type
brick wall with chisel, repairing masonry and removing Hole Hole of masonry and R.C.C. work.
debris within one chain lead.

40 Making 1½"x1½" (40x40 mm) groove in wall of stone or Per 373.75 - Per 373.75 -
brick masonry in cement for fixing planks upto 9" (225 Plank Plank
mm) deep.

41 Drilling holes in stone or brick masonry upto 2" (50 mm) Per hole 127.40 Per hole 50.95
dia, per inch (25 mm) depth. per inch per c.m
depth depth
42 Providing and fixing barbed wire fencing, with 4 horizontal
and two cross wires, with R.C.C. 1:2:4 posts, 5.5'x6"x9"
(1.68mx150mmx225 mm) at 8 ft. (2.45 m) centre to
centre, reinforced with 4 No. 3/8" (10 mm) dia vertical bars
and 1/8" (3 mm) dia stirrups 12" (300 mm) centre to
centre, complete in all respects.
i) without cement concrete base. 100Rft. 14,009.25 50,496.05 Per Metre 459.50 1,656.25
ii) in cement concrete 1:4:8 base of size 12"x12"x21" 100Rft. 15,489.55 55,483.10 Per Metre 508.05 1,819.85
(300x300x525 mm).
43 Spraying termite proofing by using liquid FMC/ Biflex/ Terminex Per Sft 1.20 9.25 Sq.m 12.70 99.55 (Only applicable for new buildings)
Exin/ Ms Hextar or equivalent @ specified suspension concenterate
(SC), Mixing Ability-HEXTAR with Ratio (1:250) = 540 Sft or
equivalent approved liquid applying with shower and certificate will
be provided by the contractor for 10-years complete in all respect .as
approved by the Engineer Incharge.

chapter-26( Misc).xls Page 214


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

44 Supply and Erection of Car Parking Shed consisting of 3 mm thick


fiber glass sheet roof (3-layers) fixed / riveted on moulded curved
frame of M.S box pipe 1-1/2"x1-1/2"16-SWG supported on trusses of
MS angle iron 1-1/2"x1-1/2"x3/16" all around duly supported on
M.S sheet 6"x6"x1/4" welded on GI pipe post (Medium Quality) of
specified diameter embeded in P:C:C (1:2:4 ) i/c the cost of
excavation,cutting straightening assembling, bending as per design,
welding / grinding of joints and painting three coats complete in all
respect as approved and directed by the Engineer Incharge.

(i) 4" dia GI Pipe Supports Per Sft 27.00 748.35 Sq.m 290.30 8,052.20
(ii) 3" dia GI pipe Supports Per Sft 27.00 686.10 Sq.m 290.30 7,382.15
45 Supply and Erection of 10 ft high Cantiliver type Car Parking Shed
consisting of 3 mm thick fiber glass sheet roof fixed / riveted with
moulded curved frame comprising of 1-1/2"x1-1/2" 16-SWG MS box
placed @ 2 ft C/C both sides and 1-1/2"x3" M.S box 16-SWG at front
and back side welded on cantillever arch type MS pipe 3" dia arms
welded with 3/8" thick and 8 " dia Main Post duly welded with 1/2"
thick 1.5'x1.5' base plate and 4 no stiffeners of 1/2" thick MS sheet
embeded in PCC 2'x2'x3' with 18" long nut bolts 1"dia i/c cost of
foundation,cutting straightening assembling, bending as per drawing,
welding / grinding of joints and painting three coats complete in all
respect as approved by the Engineer Incharge.

(i) One side Cantilever Per Sft 39.90 770.50 Sq.m 429.35 8,290.65
(ii) Both side Cantilever Per Sft 27.70 647.85 Sq.m 297.85 6,970.60
46 Providing and fixing anti climb high security galvanized razor cut
wire having double sharp four U-shaped pointed 0.5 mm thick (
22mmx15 mm barbs) spaced @ 33 mm c/c cladded over 2.5 mm dia
high tensile Core wire making coil fencing of specified diameter @ 4"
c/c fixed on 2'-3" high M/S angle iron post 1½"x1½"x3/16"embeded
in base of PCC (1:2:4) (4"x4"x9") @ 4' apart i/c the cost of 2 No.
bars 3/8" dia welded horizantally with angle iron posts , binding wire,
painting of posts, etc. complete in all respects as pproved and directed
by the Engineer incharge.
(i) 24 " diameter Per Rft 99.15 544.05 P.Mtr 1,067.05 5,854.10
(ii) 18 " diameter Per Rft 99.15 502.75 P.Mtr 1,067.05 5,409.45
47 Providing and fixing hot dipped Galvanized Iron chainlink
mesh/fence of 2"x2"mesh made of wire of specified guage, with the
help of 1"x1/8" GI patti, GI.clamps and screws, i/c the cost of 3 nos 8
SWG GI tie wires penetrated through mesh at top,middle and bottom,
fixed on vertical posts of 2" diameter GI pipes (medium quality)
erected @ 8 ft C/C duly embeded in PCC(1:2:4) etc. complete in all
respect as approved and directed by the Engineer Incharge.

(i) 8 SWG Per Sft 22.70 369.25 Sq.m 244.30 3,972.95


(ii) 10 SWG Per Sft 22.70 369.25 Sq.m 244.30 3,972.95

chapter-26( Misc).xls Page 215


MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA

Sr. Description Rate (British System) Rate (M etric System) Spec. Remarks
No. No.
Unit Labour Composite Unit Labour Composite

48 Providing and fixing slip joint sandwich panels composed of two steel
layers injected in between with polyurethane foam on existing
surface, lightweight of specified density and fire resistance grade-B.
The steel sheet layers are polyester coated hot dipped galvanized ,
sandwich sheets panels are painted with reflective, anti dust and
durable electrostatic paint from both sides i/c the cost of flasing
trims,screws,revits,sealants,tapes etc.complete in all respects as
approved and directed by the Engineer Incharge.

(a) 40 Kg/m3
(i) 50 mm thick Per Sft 46.80 847.00 Sq.m 503.75 9,117.10
(ii) 60 mm thick Per Sft 46.80 950.00 Sq.m 503.75 10,225.80
(iii) 75 mm thick Per Sft 46.80 1,233.25 Sq.m 503.75 13,274.70
(iv)100 mm thick Per Sft 46.80 1,619.50 Sq.m 503.75 17,432.30
(v)125 mm thick Per Sft 46.80 2,000.60 Sq.m 503.75 21,534.45
(vi)150 mm thick Per Sft 46.80 2,752.50 Sq.m 503.75 29,627.90
SURVEY AND M APPI NG OF ROADS, BRI DGES AND
BUI LDI NGS
49 Detailed Plan & Profile, Levelling of Carriageway road at 100'
interval, Observing cross sections at 200' interval or as directed by the
Engineer incharge, Marking of Benchmarks at safe places (01) one
number in each km. Preparing of existing Plan & Profile, Cross
Sections on Computer, fixing of proposed profile line after
finalization by the Engineer Incharge. Providing (4) four sets of plan
& profile drawings and computerized calculation sheets of earth work
after profile finalization, complete in all respect upto the entire
satisfaction of Engineer Incharge.
a) Plain Terrain
i) Single Carriageway P.KM - 15,584.20 P.KM - 15,584.20
ii) Dual Carriageway P.KM - 19,871.70 P.KM - 19,871.70
b) Hilly Terrain
i) Single Carriageway P.KM - 21,035.95 P.KM - 21,035.95
ii) Dual Carriageway P.KM - 24,413.20 P.KM - 24,413.20
50 Topographic Survey with coordinates for buildings, bridge P.Kanal - 372.15 P.Kanal - 372.15
construction or road covering detail of all existing features within
1000' each side. Existing Cross Sections at specified intervals of the
area of interest at each change in topographic feature or as directed by
the Engineer Incharge. Plan and Profile data of Existing Roads,
collecting all utilities data such as Buildings, telephone poles, electric
lines/poles, HT Lines, Manholes etc complete in all respect upto the
entire satisfaction of the Engineer Incharge.

chapter-26( Misc).xls Page 216


27. Heating Ventilation & Air Conditioning

MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA
Sr. Rate (British System) Rate (Metric System) Spec.
Description No. Remarks
No. Unit Labour Composite Unit Labour Composite
1 Supplying, fabrication and installation of duct using prime quality hot
dipped G.I sheet metal (Z-275) of specified thickness including the cost
of hangers , tees, bends , reducers, elbows, turning vanes and splitter etc
23.60
coupled with jointing sealant , mounting supports @ 8 ft c/c and smoke
testing charges complete in all respects as approved and directed by the
Engineer Incharge.
(i)28-SWG Per Sft 13.60 184.55 Sq.m 146.25 1,985.90
(ii)26-SWG Per Sft 13.60 209.25 Sq.m 146.25 2,251.65
(iii)24-SWG Per Sft 13.60 261.20 Sq.m 146.25 2,810.55
(iv)22-SWG Per Sft 18.10 316.00 Sq.m 194.95 3,400.25
(v)20-SWG Per Sft 18.10 369.40 Sq.m 194.95 3,974.50
(vi)18-SWG Per Sft 18.10 469.95 Sq.m 194.95 5,056.40
2 Supplying, fabrication and installation of round flue duct of specified Per Sft 25.95 837.00 Sq.m 279.40 9,006.20
diameter,using prime quality MS sheet of 12 SWG duly welded i/c the
cost of hangers , tees, bends , reducers, elbows , mounting supports @ 6
ft c/c complete in all respects as approved and directed by the Engineer
Incharge.
3 Supplying, fabrication and installation of round welded type grease Per Sft 25.95 589.05 Sq.m 279.40 6,338.05
exhaust duct of specified diameter,using prime quality MS sheet of 14
SWG duly welded i/c the cost of hangers , tees, bends , reducers,
elbows ,cleanout access panel, mounting supports @ 6 ft c/c complete
in all respects as approved and directed by the Engineer Incharge.

4 Supply & Installation of foil faced round flexible duct made of


reinforced Fabric Flexible round duct mechanically interlocked with
corrosion resitant metal spiral helix with 1" factory applied fibreglass
insulation of specified size i/c the cost of insulation and supports as per
drawings with all accessories and fittings complete in all respect as
approved and directed by Engineer Incharge.
(i) 6" dia Per Rft 37.45 470.50 P.Mtr 122.80 1,543.30
(ii) 8" dia Per Rft 37.45 576.10 P.Mtr 122.80 1,889.65
(iii) 10" Dia Per Rft 37.45 690.00 P.Mtr 122.80 2,263.20
(iv) 12" Dia Per Rft 37.45 843.10 P.Mtr 122.80 2,765.45
(v) 14" Dia Per Rft 37.45 1,008.35 P.Mtr 122.80 3,307.40
(vi) 16" Dia Per Rft 37.45 1,325.30 P.Mtr 122.80 4,346.90
5 Supply, wrapping of 3" thick foil-faced Rockwool thermal Insulation of
nominal density with built in GI wire mesh as per specifications and
drawings conforming to BS 5422:2009 complete in all respect as
approved and directed by the Engineer Incharge.
(i) 30-40 kg/m3 Per Sft 6.70 99.10 Sq.m 71.95 1,066.15
chapter-27(HVAC).xls Page 217
27. Heating Ventilation & Air Conditioning

MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA
Sr. Rate (British System) Rate (Metric System) Spec.
Description No. Remarks
No. Unit Labour Composite Unit Labour Composite
(ii) 45-50 kg/m3 Per Sft 6.70 125.50 Sq.m 71.95 1,350.75
(iii) 55-60 kg/m3 Per Sft 6.70 142.65 Sq.m 71.95 1,535.45
(iv) 65-80 kg/m3 Per Sft 6.70 166.40 Sq.m 71.95 1,791.20
(v) 85-90 kg/m3 Per Sft 6.70 184.90 Sq.m 71.95 1,990.10
(vi) 95-100 kg/m3 Per Sft 6.70 202.05 Sq.m 71.95 2,174.80
6 Providing and wrapping foil-faced fiber glass blanket insulation having
specified density with factory applied vapour barrier/Aluminium foil
i/c the cost of 8 oz canvas cloth wrapping around with 2" wide self
adhesive Aluminium tape and PVC mechanical fasteners.All
longitudinal and circumferential joints shall be sealed complete in all
respects as approved and directed by Engineer Incharge.

a) 12 kg/m3
(i)1" thick Per Sft 15.60 78.40 Sq.m 167.85 843.35
(ii)2" thick Per Sft 15.60 85.90 Sq.m 167.85 924.20
b) 16 kg/m3
(i)1" thick Per Sft 15.60 72.05 Sq.m 167.85 775.05
(ii)2" thick Per Sft 15.60 88.40 Sq.m 167.85 951.30
c) 24 kg/m3
(i)1" thick Per Sft 15.60 73.30 Sq.m 167.85 788.60
(ii)2" thick Per Sft 15.60 89.65 Sq.m 167.85 964.85
7 Providing and fixing 1" thick bonded fiberglass Blanket sound liner Per Sft 13.00 123.30 Sq.m 139.90 1,326.70
(Acoustic Liner) having density of 24 kg/m3 with NRC (Noise
Reduction Coefficient of 0.6 ) in ducts, fire retardant type with 100%
surface applied with adhesive as well as mechanical fasteners (
Gripnails) complete in all respect as aprroved and directed by Engineer
Incharge,
8 Providing and installation extruded anodized/Powder coated aluminum Per Sft 195.00 2,475.00 Sq.m 2,098.20 26,631.00
Supply Air registers have horizontal and vertical adjustable deflecting
bars and opposed blade volume control dampers adjustable from face
with a removable key with minimum of 75% free area complete in all
respects as approved and directed by the Engineer Incharge.

9 Providing and installation Return/Exhaust Air grilles made of specified


material having horizontal and vertical adjustable deflecting bars,grilles
with minimum of 75% free area complete in all respects as approved
and directed by the Engineer Incharge .
a) Electrostatic oven Cured Powder Coated/Anodized
Extruded Aluminum
(i) 1.00 mm thick Per Sft 195.00 1,635.00 Sq.m 2,098.20 17,592.60
chapter-27(HVAC).xls Page 218
27. Heating Ventilation & Air Conditioning

MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA
Sr. Rate (British System) Rate (Metric System) Spec.
Description No. Remarks
No. Unit Labour Composite Unit Labour Composite
(i) 1.20 mm thick Per Sft 195.00 1,875.00 Sq.m 2,098.20 20,175.00
b) Powder Coated ACRYLONI TRI LE BUTADI ENE
STYRENE (ABS) Plastic made
(i) 2mm Thick Per Sft 195.00 1,635.00 Sq.m 2,098.20 17,592.60
(ii) 3 mm Thick Per Sft 195.00 1,755.00 Sq.m 2,098.20 18,883.80
(iii) 4 mm Thick Per Sft 195.00 1,935.00 Sq.m 2,098.20 20,820.60
(iv) 5 mm Thick Per Sft 195.00 2,055.00 Sq.m 2,098.20 22,111.80
10 Providing and installation Air Difuser made of specified material (of
any shape, round, square , rectangular or linear and furnished with multi-
louver type volume dampers in neck controlled from face of the
diffusers) complete in all respects as approved and directed by the
Engineer Incharge.
a) Electrostatic oven Cured Powder Coated/Anodized
Extruded Aluminum
(i) 1.00 mm thick Per Sft 156.00 1,596.00 Sq.m 1,678.55 17,172.95
(ii) 1.20 mm thick Per Sft 156.00 1,836.00 Sq.m 1,678.55 19,755.35
(iii) Linear Slotted Diffuser Per Sft 156.00 1,476.00 Sq.m 1,678.55 15,881.75
b) Powder Coated ACRYLONI TRI LE BUTADI ENE
STYRENE (ABS) Plastic made
(i) 2 mm Thick Per Sft 156.00 1,596.00 Sq.m 1,678.55 17,172.95
(ii) 3 mm Thick Per Sft 156.00 1,716.00 Sq.m 1,678.55 18,464.15
(iii) 4 mm Thick Per Sft 156.00 1,896.00 Sq.m 1,678.55 20,400.95
(iv) 5 mm Thick Per Sft 156.00 2,016.00 Sq.m 1,678.55 21,692.15
11 Providing and installing opposed blade Volume Dampers (Air-Handler)
, of Prime Quality G.I sheet of specified thickness,(The quadrant
volume damper shall be muti-leaf type, with a mximum blade width of
8", heavy duty quadrant operators of brass with stand off mountings on
thermally insulated ducts to provide clearance between the duct surface
and operator, equal to the thickness of the insulation , capable of being
locked at desired position conveniently, provided with a baked enamel
finish complete in all respects as approved and directed by the Engineer
Incharge.
(i) 16 SWG Per Sft 97.50 2,617.50 Sq.m 1,049.10 28,164.30
(ii) 18 SWG Per Sft 97.50 2,737.50 Sq.m 1,049.10 29,455.50

chapter-27(HVAC).xls Page 219


27. Heating Ventilation & Air Conditioning

MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA
Sr. Rate (British System) Rate (Metric System) Spec.
Description No. Remarks
No. Unit Labour Composite Unit Labour Composite
12 Supply & Installation of multi layer aluminium sheet jacketting of
specified thickness,coated with UV ( Ultra Violet) protection &
polymer backing having saltwater resistance and fire performance
conformimg to ASTM-C1729M over exposed duct/pipe insulations
where required and specified i/c the cost of Metal banding solution
sealant as approved and directed by Engineer Incharge.
i) 0.3 mm Thick Per Sft 8.70 78.40 Sq.m 93.45 843.55
ii) 0.4 mm Thick Per Sft 8.70 100.10 Sq.m 93.45 1,077.25
iii) 0.5 mm Thick Per Sft 8.70 121.85 Sq.m 93.45 1,310.95
iv) 0.6 mm Thick Per Sft 8.70 143.55 Sq.m 93.45 1,544.65
v) 0.8 mm Thick Per Sft 8.70 187.00 Sq.m 93.45 2,012.00
vi) 1.00 mm Thick Per Sft 8.70 230.45 Sq.m 93.45 2,479.40
vii) 1.20 mm Thick Per Sft 8.70 266.25 Sq.m 93.45 2,865.10
13 Supply & Installation of duct flexible connector of specified material
and and coatings and width as per drawings with all accessories and
fittings complete in all respect as approved and directed by Engineer
Incharge.
a) Robust Polyester with PVC Coating
(i) 9" Wide Per Rft 31.20 603.95 P.Mtr 102.35 1,981.00
(ii) 6" Wide Per Rft 31.20 509.45 P.Mtr 102.35 1,671.05
b) Glassfiber with Neoprene Coating
(i) 9" Wide Per Rft 31.20 1,044.95 P.Mtr 102.35 3,427.45
(ii) 6" Wide Per Rft 31.20 918.95 P.Mtr 102.35 3,014.20
c) Glassfiber with Polyurethane Coating
(i) 9" Wide Per Rft 31.20 477.95 P.Mtr 102.35 1,567.70
(ii) 6" Wide Per Rft 31.20 452.75 P.Mtr 102.35 1,485.05
d) Glassfiber with Silicon Coating
(i) 9" Wide Per Rft 31.20 509.45 P.Mtr 102.35 1,671.05
(ii) 6" Wide Per Rft 31.20 452.75 P.Mtr 102.35 1,485.05
14 Supply & Installation of bellow type pipe flexible connector
manufactured with high resistant - impregnated rubber and metal
flanges made of Econosto (Holand), Tozen (Japan) or Scon (Pakistan)
i/c the cost of Gaskit and not bolts, as approved and directed by
Engineer Incharge.
i) 6" dia Each 1,087.20 28,807.20 Each 1,087.20 28,807.20
ii) 8" dia Each 1,087.20 45,487.20 Each 1,087.20 45,487.20
iii) 10" dia Each 1,087.20 59,887.20 Each 1,087.20 59,887.20

chapter-27(HVAC).xls Page 220


27. Heating Ventilation & Air Conditioning

MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA
Sr. Rate (British System) Rate (Metric System) Spec.
Description No. Remarks
No. Unit Labour Composite Unit Labour Composite
15 Supply & Installation of pre-formed tube of Elastomaric closed cell FM
foam type insulation of specified thickness having density of 65 Kg / m3
and thermal condcutivity of 0.035 W/M at 25 degree centigrade of fire
performance conforming to UK building regulation of class - 0 rating
C2, complete including the cost of adhesives and sealers as specified for
chilled water piping and fittings including valves, strainers as approved
and directed by Engineer Incharge.

a) 19mm thick
(i) 3/4"dia Per Rft 13.60 201.85 Meter 44.60 662.15
(ii) 1" dia Per Rft 13.60 288.15 Meter 44.60 945.15
(iii) 1-1/4" dia Per Rft 13.60 356.15 Meter 44.60 1,168.10
(iv) 1-1/2" dia Per Rft 13.60 399.40 Meter 44.60 1,310.00
(v) 2" dia Per Rft 27.20 493.30 Meter 89.15 1,618.10
(vi) 2-1/2" dia Per Rft 27.20 586.00 Meter 89.15 1,922.15
(vii) 3"dia Per Rft 27.20 709.60 Meter 89.15 2,327.55
(viii) 4" dia Per Rft 40.75 859.15 Meter 133.75 2,818.10
b) 25m thick
(i) 5" dia Per Rft 40.75 1,032.20 Meter 133.75 3,385.65
(ii) 6" dia Per Rft 40.75 1,168.15 Meter 133.75 3,831.60
(iii) 8" dia Per Rft 54.35 1,441.30 Meter 178.30 4,727.55
c) 32m thick
(i) 10" dia Per Rft 54.35 1,750.30 Meter 178.30 5,741.05
(ii) 12" dia Per Rft 54.35 1,972.80 Meter 178.30 6,470.80
(iii) 14" dia Per Rft 67.95 2,171.80 Meter 222.90 7,123.45
16 Supply & Installation of High Density ( 64 Kg/m3) Aluminum foil
faced fiberglass pipe insulation for chilled/hot water pipeing and
fittings and protections of valves,strainers etc i/c the cost of canvas cloth
as approved and directed by Engineer Incharge.
a) 25 mm thick
(i) 3/4"dia Per Rft 27.20 277.65 Meter 89.15 910.70
(ii) 1" dia Per Rft 27.20 302.35 Meter 89.15 991.75
(iii) 1-1/4" dia Per Rft 27.20 327.10 Meter 89.15 1,072.85
(iv) 1-1/2" dia Per Rft 27.20 351.80 Meter 89.15 1,153.95
(v) 2" dia Per Rft 40.75 390.10 Meter 133.75 1,279.60
(vi) 2-1/2" dia Per Rft 40.75 414.85 Meter 133.75 1,360.70
(vii) 3"dia Per Rft 40.75 439.55 Meter 133.75 1,441.75
b) 50 mm thick
(i) 4" dia Per Rft 54.35 654.60 Meter 178.30 2,147.15
(ii) 5" dia Per Rft 54.35 816.55 Meter 178.30 2,678.25
(iii) 6" dia Per Rft 54.35 856.10 Meter 178.30 2,807.95
(iv) 8" dia Per Rft 54.35 929.50 Meter 178.30 3,048.75
chapter-27(HVAC).xls Page 221
27. Heating Ventilation & Air Conditioning

MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA
Sr. Rate (British System) Rate (Metric System) Spec.
Description No. Remarks
No. Unit Labour Composite Unit Labour Composite
(v) 10" dia Per Rft 67.95 1,159.40 Meter 222.90 3,802.80
(vi) 12" dia Per Rft 67.95 1,308.75 Meter 222.90 4,292.65
17 Supply & Installation built in Microban Elastomeric closed cell FM
approved Foam type insulation of 40-65 kg/m3 density and thermal
condcutivity of 0.035 W/M at 25 degree centigrade of fire performance
closely woven fiberglass cloth conforming to UK building regulation of
clause - 0 rating as specified, complete including the cost of adhesives
and sealers as approved and directed by Engineer Incharge.

(i) 6 mm thick Per Sft 10.85 167.75 Sq.m 117.05 1,805.90


(ii) 9 mm thick Per Sft 10.85 219.25 Sq.m 117.05 2,360.25
(iii) 12 mm thick Per Sft 10.85 291.35 Sq.m 117.05 3,136.35
(iv) 19 mm thick Per Sft 10.85 363.25 Sq.m 117.05 3,910.25
18 Supply & Installation of 5 mm thick polyethelene (PE) insulation for
condensate drain pipes of required size for AHU and FCU pipes
covered with PVC tape as per specifications /drawings with all
accessories and fittings as approved and directed by Engineer Incharge.

(i)3/4 " dia pipe Per Rft 13.60 61.45 Meter 44.60 201.50
(ii)1 " dia pipe Per Rft 13.60 118.10 Meter 44.60 387.35
(iii)1-1/4" dia pipe Per Rft 27.20 167.75 Meter 89.15 550.15
(iv)1-1/2 " dia pipe Per Rft 27.20 198.65 Meter 89.15 651.50
(v)2 " dia pipe Per Rft 27.20 214.10 Meter 89.15 702.20
19 Supply & Installation of washable aluminium metal mesh filter consists
primarily of layers of aluminium slit and expanded into mesh of
differing densities duly fixed in frame of specified thickness for AHUs
fabricated with min. 12 mesh layers at fresh air intake on outside of
AHU as approved and directed by Engineer Incharge.

(i) 1" Thick Per Sft 67.95 1,237.95 Sq.m 731.15 13,320.35
(ii) 2" Thick Per Sft 67.95 1,357.95 Sq.m 731.15 14,611.55
(iii) 3" Thick Per Sft 67.95 1,447.95 Sq.m 731.15 15,579.95
20 Supply & Installation of Electrostatic Ovencured Powder coated/ Per Sft 34.00 1,444.00 Sq.m 365.55 15,537.15
extruded anodized rectangular/Squar aluminium louver duly fixed in
frame of specified thickness for intake/Exhaust air with fine finishing as
approved and directed by Engineer Incharge.

chapter-27(HVAC).xls Page 222


27. Heating Ventilation & Air Conditioning

MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA
Sr. Rate (British System) Rate (Metric System) Spec.
Description No. Remarks
No. Unit Labour Composite Unit Labour Composite
21 Supply & installation closed cell type Aluminium foil faced XLPE
(Cross linked polyethelene) polyolefin pipe insulation tube of density
25 Kg/m³ of specified thickness & thermal conductivity 0.035 w/m °C
and fire retardent of Class "o" rating as specified for refrigerant copper
piping as approved by the Engineer Incharge.
a) 20 mm thick
(i) 1/4"dia Per Rft 6.80 134.60 Meter 22.30 441.45
(ii) 3/8" dia Per Rft 6.80 146.95 Meter 22.30 482.00
(iii) 1/2" dia Per Rft 6.80 171.70 Meter 22.30 563.10
(iv) 5/8" dia Per Rft 13.60 203.20 Meter 44.60 666.45
(v) 3/4" dia Per Rft 13.60 215.55 Meter 44.60 707.00
(vi) 7/8" dia Per Rft 13.60 240.25 Meter 44.60 788.10
(vii) 1"dia Per Rft 27.20 272.40 Meter 89.15 893.45
(viii) 1-1/8" dia Per Rft 27.20 278.60 Meter 89.15 913.75
(ix) 1-1/4" dia Per Rft 27.20 290.95 Meter 89.15 954.30
(x) 1-1/2" dia Per Rft 40.75 316.90 Meter 133.75 1,039.40
(xi) 1-5/8" dia Per Rft 40.75 335.45 Meter 133.75 1,100.20
(xii) 1-3/4" dia Per Rft 40.75 347.80 Meter 133.75 1,140.75
(xiii) 2" dia Per Rft 54.35 417.00 Meter 178.30 1,367.75
(xiv) 2-1/2" dia Per Rft 54.35 491.15 Meter 178.30 1,611.00
(xv) 3" dia Per Rft 54.35 538.55 Meter 178.30 1,766.50
b) 25 mm thick
(i) 1/4"dia Per Rft 6.80 159.30 Meter 22.30 522.55
(ii) 3/8" dia Per Rft 6.80 177.85 Meter 22.30 583.35
(iii) 1/2" dia Per Rft 6.80 190.20 Meter 22.30 623.90
(iv) 5/8" dia Per Rft 13.60 221.75 Meter 44.60 727.25
(v) 3/4" dia Per Rft 13.60 234.10 Meter 44.60 767.80
(vi) 7/8" dia Per Rft 13.60 265.00 Meter 44.60 869.15
(vii) 1"dia Per Rft 27.20 297.10 Meter 89.15 974.55
(viii) 1-1/8" dia Per Rft 27.20 315.65 Meter 89.15 1,035.35
(ix) 1-1/4" dia Per Rft 27.20 334.20 Meter 89.15 1,096.20
(x) 1-1/2" dia Per Rft 40.75 360.15 Meter 133.75 1,181.30
(xi) 1-5/8" dia Per Rft 40.75 366.35 Meter 133.75 1,201.55
(xii) 1-3/4" dia Per Rft 40.75 397.25 Meter 133.75 1,302.90
(xiii) 2" dia Per Rft 54.35 454.10 Meter 178.30 1,489.40
(xiv) 2-1/2" dia Per Rft 54.35 515.90 Meter 178.30 1,692.10
(xv) 3" dia Per Rft 54.35 574.55 Meter 178.30 1,884.55

chapter-27(HVAC).xls Page 223


27. Heating Ventilation & Air Conditioning

MRS, 2nd BI-ANNUAL-2022 (01.07.2022 to 31.12.2022)

DISTRICT GUJRANWALA
Sr. Rate (British System) Rate (Metric System) Spec.
Description No. Remarks
No. Unit Labour Composite Unit Labour Composite
22 Supply & installation of mild steel closed cylinderical diaphragm
type,pre-charged replaceble butyl bladder & pressurized type expansion
tank of specified capacity to withstand the specified water supply
pressure for specified water heater capacity, duly Epoxy coated paint
for heating/cooling ,made of Steam Master (Pak), Caleffi (Italy), Elbi
(Italy), Flamco (UK) complete i/c the cost of Air Trol Fittings,Tank
drainer,Sight glass with valves,Hoze nozzle,and Hoze pipe ,as shown
on the drawings as approved and directed by the Engineer Incharge
(i) 2- Gal Capacity, Size 12-1/2"x8" Each 679.50 21,269.50 Each 679.50 21,269.50
(ii) 3.2 Gal Capacity, Size 12-1/2"x11" Each 679.50 26,269.50 Each 679.50 26,269.50
(iii) 4.5 Gal Capacity, Size 15"x11" Each 679.50 35,769.50 Each 679.50 35,769.50
(iv) 7.0 Gal Capacity, Size 11"x21-3/8" Each 679.50 39,269.50 Each 679.50 39,269.50
(v)14 Gal Capacity, Size 20"x15-1/2" Each 679.50 42,769.50 Each 679.50 42,769.50
(vi) 20 Gal Capacity, Size 27"x15-1/2" Each 679.50 78,269.50 Each 679.50 78,269.50

chapter-27(HVAC).xls Page 224