OFFICE OF THE
EXECUTIVE ENGINEER,
GW DIVISION, NIDADAVOLU
EAST GODAVARI DISTRICT :: ANDRA PRADESH.
Report to Accompany the estimate for “Temporary Restoration to Bank slip at
Kakaraparru Regulator D/s, R/B adjacent return wall in Velivennu (V) limits of
Undrajavaram (M), East Godavari District.”
Sl. Chapter
No wise Quantity Item description Unit Rate Amount
. item No.
Total: 1120.00
Cost of Sand at Quarry ( Rates of Materials & Work
2 30.00 Items, SSI No. 27 vide P.12 & As per W.R.D Material )
for 2022 - 23
Seignorage Charges on Sand 1.00 45.00 Cum 360.00
Total: 360.00
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
1 Angle dozer 90 hp Hour 2.70 1650.20 4455.54
Fuel / Energy charges Hour 2.70 1055.30 2849.31
2 Shovel 0.85 cum capacity Hour 8.00 1648.80 13190.40
Fuel / Energy charges Hour 8.00 1508.60 12068.80
3 Tippers 5.00 cum capacity 5 Nos. Hour 40.00 436.30 17452.00
Fuel / Energy charges Hour 40.00 518.40 20736.00
Total hire charges of Machinery Rs: 70752.05
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
1 Crew for Dozer Hour 2.70 326.30 881.01
2 Crew for Shovel Hour 8.00 326.30 2610.40
3 Crew for Tipper Hour 40.00 244.70 9788.00
4 work inspector Day 1.00 685.00 685.00
5 mazdoor Day 2.00 525.00 1050.00
Total cost of Labour Rs: 15014.41
ABSTRACT:
A. Cost of Materials including seigniorage Rs: 0.00
B. Hire charges of Machinery Rs: 70752.05
C. Cost of Labour Rs: 15014.41
Total Rs: 85766.46
D. Add for contractor's profit and over heads on (A+B+C) 13.615% 11677.10
Total cost for 807 cum Rs: 97443.56
Rate per cum (A+B+C)/807 Rs: 120.70
Sl.
No Item description Unit Quantity Rate Amount
.
Cost of Sand at Quarry ( Rates of Materials &
Work Items, SSI No. 27 vide P.12 & As per Cum 1 460 460
W.R.D Material ) for 2022 - 23
Conveyance Charges from Vadapalli to site of
2 Work - Avg. Lead 28 Km
Up to 5 Km = 96.00
23 Km x 14.40 = 331.20
Total Conveyance charges =427.6 Cum 1 427.6 427.6
Total (Cost & Conveyance of Sand) Cum 1 887.6
Supply of empty cement bags including cost and
conveyance and labour charges for filling with
earth and stitching with country twine and
convey with an average lead of 200 mts. Over
3 Each 1 7 7
the initial lead dumping and placing in position
etc. completed for the finished item of work as
directed by the department.Empty cement bag
(SOR Material Item no.23 vide page No. 12)
Labour charges for filling the HDPE Cement
Bags with sand/ earth/ gravel and stitching the
bag with country twine etc., and placing the
same in position within 100 m, by head load
4 including cost of country twine and nails etc., Each 1 8 8
but excluding the cost and conveyance of
material etc., complete (As per SE/ IC/ ELURU
Memo. No.SE/IC/Elr/DB/ATO.4/F.SSR Rates/
2279SE Dated 16.05.2014 - S.L.No.8)
Supply of casurina bullies of size 100 to 150
mm dia at middle of its cost (including cost and
5 conveyance to site of work etc complete) Vide Rmt 1 60 60
Memo No. SE/IC/Elr/DB/ATO: 4/F.SSR. Rates
No. 2297SE Dt. 16.5.2014
1.00 Mt
Sand Filled Bags
3.00 Mt
4.00 Mt
Bamboo Thatties