BILL OF QUANTITIES
GRAND SUMMARY
Client/ Owner : Gwadar Development Authority (GDA) Baluchistan.

Name of Project : Rehabilitation of Old Town Gwadar (Phase-1) - Road works (Package-1G)
Name of Work : CONSTRUCTION /BLACK TOPPING OF ROAD FROM C&W OFFICE TO RCDC GWADAR

Sub Head Description Amount (Rs)

A ROAD WORKS.

B CIVIL WORKS.

Grand Total (Rs.)

In MILLION (Rs.)

(Rupees )
In Words

CONTRACTOR GWADAR DEVELOPMENT AUTHORITY (GDA)


2

BILL OF QUANTITIES

Client/ Owner : Gwadar Development Authority (GDA) Baluchistan.

Name of Project : Rehabilitation of Old Town Gwadar (Phase-1) - Road works (Package-1G)
Name of Work CONSTRUCTION /BLACK TOPPING OF ROAD FROM C&W OFFICE TO RCDC GWADAR

Sr. Item Ref:- Rate (Rs)


No. # Description Qty Unit In Figure In Words Amount (Rs)

A - Road Works.
Part A - Schedule Items
Link Roads (1.925 KM) and Main Road (1.664 KM)
1 21-63 Dismantling bitumen carpet of any description
from existing road surface including its removal
8,000.00 Sqm 52.50 420,000.00
and disposal within 90m lead. (0-15 cm thickness)

2 21-1/a Excavation or cutting to a required grade camber


and side slopes i.e dressing top and side. For all 2,880.00 Cum 258.25 743,760.00
kind of soil except gravelly.
3 21-12 Preparation of sub-grade over bottom of
excavation with required dressing to
required grade, camber and side slopes including
cutting to required depth and breaking clods,
watering and consolidation with suitable
mechanical means to attain maximum density of 6,400.00 Sqm 214.40 1,372,160.00
95% modified AASHTO for top 6" (150mm)
layer including disposal of surplus earth within a
lead of 90m.

4 '21-6/a+ Making earthen embankment with earth


1-1/ a to j taken from approved borrow pits i/c cost of
excavation , placing in layers not exceeding 9"
(230 mm) in depth i/c dressing top and sides of
the bank within a lift of 5ft (1.5 m) and
lead upto (10 Km). (Excluding the royality of 960.00 Cum 660.11 633,705.60
earth , Compaction and its carriage) in all
kind of soil except gravelly, murum, wet silt ,
clay or mud including carraige of earth from 10
Km.
5 21-9-1 Compaction of earthen embankments to full depth
and width below sub grade level by
mechanical means in layers not exceeding 8"
(200 mm) in depth at optimum moisture
content i/c watering and mixing by mechanical
960.00 Cum 208.10 199,776.00
means. The sub grade embankment shall be
compacted to at least 95% modified AASHTO
maximum dry density for their full depth and
width.

6 21-15/b+ Providing ang laying piturn gravel in sub base


1-1/a to k or base course of any thicness to required grade
and camber i/c watering and compacting with
1,308.00 Cum 1,955.28 2,557,506.24
road roller with all lead and lift. (compacted
thickness to be measured)
3

BILL OF QUANTITIES

Client/ Owner : Gwadar Development Authority (GDA) Baluchistan.

Name of Project : Rehabilitation of Old Town Gwadar (Phase-1) - Road works (Package-1G)
Name of Work CONSTRUCTION /BLACK TOPPING OF ROAD FROM C&W OFFICE TO RCDC GWADAR

Sr. Item Ref:- Rate (Rs)


No. # Description Qty Unit In Figure In Words Amount (Rs)

A7
- Road21-17+
Works. Supplying and laying graded aggregated
1-1 base course of crushed stone of approved
quality, i/c placing , mixing, spreading,
watering, and compacteing base course to
required depth, camber and grade to achieve
100% max modified AASHTO dry density
conforming to AASHTO classification T-180
with mechanical means and with all lead and lift 1,308.00 Cum 2,704.22 3,537,119.76
.(Carriage of crushed stone is included in the
rate within 5 km of project premises.)
Carraige from 6th to 10th Km and from 11th to
170th km (475.7+2704/ 2.83=1123.57)

8 21-23-1/a Providing and applying prime coat of liquid asphalt


(cut back) of any approved grade using asphalt
( cut back) i/c cleaning and brooming of 7,320.00 Sqm 226.45 1,657,614.00
road surface.

9 21-32/ c- Providing and laying hot mix bituminous concrete


21-24-1/a in road pavement laid with mechanical paver and
mixed in central mixing plant in required thickness
and density , rolled hot with different types of
rollers complete as per specification and job 7,320.00 Sqm 1,236.95 9,054,474.00
mix formula and design in single layer in 2"
(50mm) compected thickness.

Sub-Total (A) Schedule Items 20,176,115.60


Add 60% premium on Bitumen (Item No- 08 & 09) 6,427,252.80
Sub-Total (A) Schedule Items 26,603,368.40
4

BILL OF QUANTITIES

Client/ Owner : Gwadar Development Authority (GDA) Baluchistan.

Name of Project : Rehabilitation of Old Town Gwadar (Phase-1) - Road works (Package-1G)
Name of Work CONSTRUCTION /BLACK TOPPING OF ROAD FROM C&W OFFICE TO RCDC GWADAR

Sr. Item Ref:- Rate (Rs)


No. # Description Qty Unit In Figure In Words Amount (Rs)

A - Road
Part Works.
B - Non Schedule Items
Solar Street Lights
LIGHTING POLES DOUBLE ARM
10 NSI Supply, installation, testing and commissioning of 8 m
high Fiber Reinforced Plastic single arm street lighting
poles. Including base plate anchor bolt, nuts and
washer, etc. with atleast 15 years company warranty.
10.00 Nos
Complete in all respects as per specification and
drawings.
SOLAR LIGHT FIXTURES COMPLETE SYSTEM
11 NSI Supply, installation testing and commissioning of solar
LED street lights 120W suitable for the project
requirement with minimum lumen output 15600 Lm at
maximum brightness setting with plug and play
connectors arrangement. Fully IP66 with corrosion
resistant diecast aluminum housing silicon gasket,
thermally hardened glass. Light distribution of luminaire 10.00 Nos
should be symmetric and optics should be anti dust
exposed lenses. With built in Lithium Ferro Phosphate
(LifePO4) battery and time and brightness control
intelligent charge controller to operate dusk to dawn.
with at least 2 rainy day backup.

WRAP TYPE SOLAR PANELS


12 NSI Supply, installation testing and commissioning of wrap
type (vertical) 140W solar panel with monoperc cells,
tempered glass material, aluminum alloy and weather
resistant nylone frame structure and fully weather proof 40.00 Nos
including DC cables, connectors and other related
accessories.

Utilities
13 NSI Supply installation connection testing
and commissioning galvanized electric poles
having height of 36 ft in R.c.c foundation
2x2x4 and HT cable and L.T bus tie duct 10.00 Nos
termination arragement terminals etc complete
in all respect as per engineer incharge.

Sub-Total (B) (Non-Schedule Items)

Total Amount of (Part A + Part B)

(Rupees )
In Words

CONTRACTOR GWADAR DEVELOPMENT AUTHORITY (GDA)


BILL OF QUANTITIES 5

Client/ Owner : Gwadar Development Authority (GDA) Baluchistan.


Name of Project : Rehabilitation of Old Town Gwadar (Phase-1) - Road works (Package-1G)

Name of Work :CONSTRUCTION /BLACK TOPPING OF ROAD FROM C&W OFFICE TO RCDC GWADAR

Sr. Item Ref:- Rate (Rs)


No. # Description Qty Unit Amount (Rs)
In Figure In Words
B - Civil Works.
Part A - Schedule Items
1 3-21/ B ii Excavation in foundation of buildings and
bridges including layout, dressing, refilling around
structures with excavated earth, watering & 3,604.19 Cum 242.10 872,575.37
ramming lead upto 100 ft. (30m) & lift upto 5 ft.
(1.5m) with machinery
2 5-5/c Providing and laying plain machine mixed
1:4:8 cement concrete using coarse sand and
crushed aggregate having maximum size up to 38 39.39 Cum 6,544.05 257,776.67
mm & down gauge in foundation i/c levelling,
compacting and curing
3 5-8/b Providing and laying 1:1.5:3 cement concrete
using coarse sand and crushed aggregate having
maximum size up to 19 mm & down gauge in
foundation i/c levelling, compacting and curing

a Bed for man Hole 62.37 Cum 9,745.95 607,840.28


b For pipes 106.22 Cum 9,745.95 1,035,227.57
4 5-13/b Providing and laying 1:1.5:3 cement concrete in
walls and piers using coarse sand and crushed
aggregate having maximum size up to 19 mm & 218.99 Cum 11,423.35 2,501,576.57
down gauge in foundation i/c levelling, compacting
and curing
5 5-17/bi+ Providing and laying 1:1.5:3 cement concrete
5-24 using coarse sand and crushed aggregate 3/4"
(19mm) and down gauge in slabs including
formwork and its removal, compacting and 44.36 Cum 11,673.15 517,815.10
curing upto 12" (300 mm) thick slab.

6 5-65/a Providing, fabricating and laying deformed Grade


60 steel reinforcement (deformed bar) for all
kinds of R.C.C work in foundation, plinth and
ground floor including the cost of
straightening,removal of rust, cutting, bending,
binding, wastage and providing such over-laps as
46.694 Ton 130,426.05 6,090,113.98
are not shown on the drawings. The cost of binding
wire and cement concrete spacer blocks or chairs
for binding and holding the reinforcement in
position is inclusive upto 15 ft. (5m) height .

Extra for providing and using Sulphate


7 5-30/a resisting cement other than ordinary portland
cement.
a Lean Concrete 1:4:8 6.50 Tonne 1,200.00 7,796.82
b Concrete 1:1.5:3 150.8404 Tonne 1,200.00 181,008.49
8 Providing and applying two coats of hot bitumen
(maxphalt 80/100 or equivalent) using 1.22 kg. per
sq.metre for first coat and 1.0 kg. per Sq.m. for 2nd
5-35-1 coat including cleaning the surface, heating and 22.296 Sqm 244.85 5,459.18
spraying the asphalt on concrete faces.
BILL OF QUANTITIES 6

Client/ Owner : Gwadar Development Authority (GDA) Baluchistan.


Name of Project : Rehabilitation of Old Town Gwadar (Phase-1) - Road works (Package-1G)

Name of Work :CONSTRUCTION /BLACK TOPPING OF ROAD FROM C&W OFFICE TO RCDC GWADAR

Sr. Item Ref:- Rate (Rs)


No. # Description Qty Unit Amount (Rs)
In Figure In Words
B -9Civil Works. Providing ang laying piturn gravel in sub base or
base course of any thicness to required grade and
21-15/b)+(1-
camber i/c watering and compacting with road roller 135.00 Cum 1,955.28 263,962.80
1/a to k)
with all lead and lift. (compacted thickness to be
measured)
10 25-1/b vi Providing and laying cement concrete pipes
moulded with cement concret 1:1.5:3 with SR
cement with spigot socket or collar joint as
specified in trenches to correct alignment and
grade, jointing with jointing materials including
cutting pipes where necessary, finishing and
testing. R.C.C pipe with bell & spigot or tongued &
grooved joint conforming to ASTM C-76 class II
wall B or BS 3911 Part I class M including
cost of reinforcement.

a 18" (450 mm) inner dia 274.20 RM 1904.05 522,090.51


b b vi 24" (600 mm) inner dia 970.00 RM 2895.75 2,808,877.50

Sub-Total (B) Schedule Items 15,672,120.84


Add _____% premium on Steel (Item No-11)

Add _____% premium on Cement/Concrete (Item No-02, 03, 04, 05, 07&10)

Sub-Total (B) Schedule Items

(Rupees )
In Words

CONTRACTOR GWADAR DEVELOPMENT AUTHORITY (GDA)