AC Hilltop Referigeration 7/11/2017 11/10/2017 123
7/11/2017 4/30/2022 1755 Total 1632 Sr. 1 Nature of Hinderance Items of work St. date Date of removal overlapping period Hinderance days % Hinderance Net hinderance which could allowed not be executed 8/28/2017 9/18/2017 22 22 8/28/2017 10/7/2017 22 19 11/7/2017 4/7/2018 152 152 11/22/2017 8/31/2018 137 146 146 5/8/2018 7/11/2018 165 Nil Nil 9/1/2018 9/30/2018 30 30 10/12/2018 12/10/2018 60 60 60 12/11/2018 9/23/2019 287 287 2/11/2020 5/31/2020 9/23/2019 6/17/2020 110 159 159 2/11/2020 5/5/2020 85 85 3/22/2020 5/31/2020 71 71 6/1/2020 7/31/2020 17 44 44
Non handover of rest portion of
GF area 8/15/2020 12/16/2020 124 124
Work withheld due to non
completion of false ceiling work. 12/19/2020 1/1/2021 14 14
Work withheld due to Covid 19
2nd wave which resulted in work hinderance due to scarcity of labour 4/1/2021 7/18/2021 109 109 Client has not vacated First floor lab area due to which work could not be started. 8/13/2021 10/19/2021 68 68
Non- completion of false ceiling
work and fire alarm work 10/19/2021 3/13/2022 114 32 32
Work withheld due to COVID-19
3rd wave of COVID-19 which resulted in work hinderance due to scarcity of labour
10/30/2021 2/20/2022 114 114
1536 1536 Extra work 96 96 Total Hinderance 1632 1632 281