Start End Total days

AC Hilltop Referigeration 7/11/2017 11/10/2017 123


7/11/2017 4/30/2022 1755
Total 1632
Sr. 1 Nature of Hinderance Items of work St. date Date of removal overlapping period Hinderance days % Hinderance Net hinderance
which could allowed
not be
executed 8/28/2017 9/18/2017 22 22
8/28/2017 10/7/2017 22 19
11/7/2017 4/7/2018 152 152
11/22/2017 8/31/2018 137 146 146
5/8/2018 7/11/2018 165 Nil Nil
9/1/2018 9/30/2018 30 30
10/12/2018 12/10/2018 60 60 60
12/11/2018 9/23/2019 287 287
2/11/2020 5/31/2020 9/23/2019 6/17/2020 110 159 159
2/11/2020 5/5/2020 85 85
3/22/2020 5/31/2020 71 71
6/1/2020 7/31/2020 17 44 44

Non handover of rest portion of


GF area 8/15/2020 12/16/2020 124 124

Work withheld due to non


completion of false ceiling work. 12/19/2020 1/1/2021 14 14

Work withheld due to Covid 19


2nd wave which resulted in
work hinderance due to scarcity
of labour
4/1/2021 7/18/2021 109 109
Client has not vacated First floor
lab area due to which work could
not be started.
8/13/2021 10/19/2021 68 68

Non- completion of false ceiling


work and fire alarm work 10/19/2021 3/13/2022 114 32 32

Work withheld due to COVID-19


3rd wave of COVID-19 which
resulted in work hinderance due
to scarcity of labour

10/30/2021 2/20/2022 114 114


1536 1536
Extra work 96 96
Total Hinderance 1632 1632
281