Finding an overview of the Project Leader 8th of March 2022 –6th of April
solution
Make estimated costs based on Sales Engineer 8th of March 2022 – 15th of
the client’s request and past March 2022
projects
Conducting secondary research Design Engineer 8th of March 2022 – 13th of
to meet client requirements March 2022
Design a solution based on the Design Engineer 13th of March 2022-20th of
client’s requirement and March 2022
situation
Identify possible limitations of Technical Engineer 20th of March 2022-23th of
the initial design March 2022
Conduct secondary research Technical Engineer 23th of March 2022-25th of
for the solution to the March 2022
limitation
Discuss the practicability, Design Engineer, Technical 26th of March 2022
improvement, and the budget Engineer, Sales Engineer
for design
Design Improvement Design Engineer, Technical 26th of March 2022-4th of April
Engineer 2022
The final design confirmation Design Engineer 5th of April 2022
Plan for testing Technical Engineer 6th of April 2022
Modify the cost based on the Sales Engineer 7th of April 2022-10th of April
final design and materials 2022
Plan for staff Training Sales Engineer 7th of April 2022-10th of April
2022
Making maintenance plans and Sales Engineer 7th of April 2022-10th of April
the after-sale service 2022