ORIX CONSTRUCTION AND DEVELOPMENT CORP.

ARCHITECTS - ENGINEERS - GENERAL CONSTRUCTION


Tel. Nos. (02) 8398-5954 / (02) 7621-0861

Project Name: ASMPH CONSTRUCTION OF PULLEY ASSEMBLY Date: 6/30/2022

Location: Ortigas Ave. Pasig City Site Supervisor / Safety: Lawrence Isidoro/Allan Lopez

Contractor: Orix Construction & Dev. Corp. Site Supervisor / Safety: Engr.Marlou Querubin

JUNE MONTH VOWD %


WORK PROGRESS
30 DATE 90%
Plan % 90% EVAL PTW%
Actual % 95% AHEAD 95%

Progress Pictures Work Description Major Tasks & Percentage

1. Chain block
installation on ceiling
slab. 2.
100%
Excess Hand Chain are
already cut and fixed on
the pulley structure.

1. Fully fabricated
overhead I-Beam for
pulley assembly
structure.
2. Installation of end to
end chain hoist .
100%
3. Fully Painted I-beam ,
Gray Color as specified
4. Restoration and
repainting of ceiling (
only on the affected
areas ).
1. Fully refurbished
cadaver tank lids,
completely installed eye
bolt for hoist and cable
connection.
2. Tank lid
reinforcement
95%
fabrication using angle
bars and flat bars.
3. Buffing and cleaning
of tank lids (only ) and
installation of cables to
assess movement of lid
and pulley

Number of Workers: 1 Supervisor


1 Safety Officer
1 Foreman
2 Labor
Total: 5 Workers

Prepared by:
Engr. Lawrence Rae M. Isidoro
Project Engineer
Orix Construction & Dev. Corp.