CONDUITS LAYING ON WALL AND PEB BUILDING STRUCTURE (MAX. HEIGHT 14 MTR AT GIS HALL)
This Method Statement describes the specific safe working methods which will be used to carry out the
described work. It gives details of work procedure with control measures to counter health and safety
issues related to this work. The listed content of this Method Statement cannot be changed/ modified
subjected to job scope/customer specifications without the prior permission of Safety co-ordinator and
Project Manager. But task specific method statement once finalized & approved, that should not be
modified during work execution.
Scope of work: - Handling & Storage, laying, installation of conduit & PVC wires laying at PGCIL Malda project.
Location: - GIS Hall, CRP Room, ACDB Room and AHU Room.
Drawing References:- DRG. NO. - K2020T&DSS001A-01-DRG-037, REV-03 dated 1.06.23
Detail of Sub contractors Involved :- Satyanarayan Enterprises.
Signature Date
Method Statement
Prepared By:
Mr. Chandan Kumar- (Asst Manager) Electrical.
Mr. Neeraj joshi (HSE Officer)
Reviewed By: -
Mr. Susanta Bemal – HSE Manager
Approved By:-
Mr. Ravi Murugesan- Head, HSE – Domestic &
International Transmission & Distribution
1
2 METHOD STATEMENT OF CONDUIT (PVC & GI), WIRE LAYING
WITH FIXING OF SWITCH BOX AND LIGHT FITTINGS
2
3 METHOD STATEMENT OF CONDUIT (PVC & GI), WIRE LAYING
WITH FIXING OF SWITCH BOX AND LIGHT FITTINGS