Annexure-6
JOB SAFETY ANALYSIS
Page 1 of 2
Format No.: EHS-006/F06-00 Effective Date:
Jubilant Infrastructure Limited-Bharuch
Annexure-6
JOB SAFETY ANALYSIS
Steel Bending of Physical cut injury due Ensure industrial plug and cable condition properly checked
Reinforcement to sharp edge. before starting the work. Ensure rated ELCB / RCCB properly
Electric shock due to checked before starting the work
use damage cable use All electrical cable to be laying over head up to 2 mtrs.
at site. Ensure competent/ designated person will perform this activity.
Damage equipment Ensure inspection tag must be displayed to the machine
Slip & trip hazards Use proper PPE
Area to be barricaded
Housekeeping Slip, trip hazards Slip, Ensure entire area shall be cleaned after the completion of job.
trip hazards Remove unwanted / scrap material from the site after close the
job.
In Case of Emergency Confusion Emergency assembly point, emergency access should be defined &
always free from any obstructions.
Emergency contact details to be displayed at prominent locations
of site.
Emergency vehicle must be available at work locations during all
working hours.
All workers shall aware / trained about site emergency procedure.
Permit issuer
Permit acceptor
Prepared by- Permit Issuer and Permit Acceptor Reviewed by-Plant Manager/ Safety officer
Approved By HOD
Page 2 of 2
Format No.: EHS-006/F06-00 Effective Date: