You are on page 1of 2

Jubilant Infrastructure Limited-Bharuch

Annexure-6
JOB SAFETY ANALYSIS

JSA NO. Department / Routine/ Non


Job Title: New/ Revised
Activity/ No… Routine
JOB SAFETY
ANALYSIS Reference work Supervisor:
Prepared By:
Permit no:
Department: Project Plant Location:
Reviewed By:
Job Description: Lifting work from chain pulley block
Approved By:

SEQUENCE OF TASK POTENIAL HAZARDS PREVENTIVE MEASURES

 Lifting work  Failure of chain block  Before starting lifting operations check the chain pulley block
(Use of chain block)  Fall of man/chain position.
pulley block  Proper capacity of chain pulley block must be used and safety
 Damage to lifting latch must be checked before installing.
equipment since  Check the physical condition of chain pulley block.
inspection  Chain pulley block must be inspected by competent person and
 Personnel having body put color code of the month.
part trapped by load  All rigging work done by competent person.
 Moving load hit the  Proper access to be provided work man to go for anchoring the
people & injured the chain pulley block.
person.  Third party certificated chain block must be used and softener
 Material lifted too high must be provided while anchoring the chain pulley block on the
permanent structure.
 All persons to be made aware of danger through tool box talk
 Tag line to be attached to the load to prevent swinging
 Good housekeeping to be maintained.
 No one should stand under the load during lifting.

Day-1 Day-2 Day-3

Permit issuer

Permit acceptor

Prepared by- Permit Issuer and Permit Acceptor Reviewed by-Plant Manager/ Safety officer

Approved By HOD

Page 1 of 2
Format No.: EHS-006/F06-00 Effective Date:
Jubilant Infrastructure Limited-Bharuch

Annexure-6
JOB SAFETY ANALYSIS

Page 2 of 2
Format No.: EHS-006/F06-00 Effective Date:

You might also like