JOB SAFETY ANALYSIS
Reference work
JOB SAFETY Permit no:
ANALYSIS Supervisor:
Prepared By:
Mobilization of Unskilled workers, Site safety induction should be provided to all new
Manpower Unauthorized entry employees.
Deploy experienced trained skilled worker for specific jobs.
Job specific training should be given
TBT to be taken on daily basis prior to start the job
Mandatory
PPE’s should be provided viz. safety helmet, safety shoes,
reflective jacket etc.
Safety Awareness/motivational programs shall be conducted
to workmen for more awareness on safety.
Medical fitness is must for all workers.
Gate pass compliance (As per JIL HR Dept) shall be complied.
Storage of shuttering Slip, trip & fall All shuttering material should be stored properly with
material hazards may arise due sufficient stacking height.
to improper Properly secure or tie store shuttering material
housekeeping at Shuttering yard areas to be demarcated and barricaded.
shuttering material
storage area
Manual handling of Sharp edge or Use mandatory PPEs safety shoes, helmet, gloves & goggles
shuttering material protruding nails etc.
Lifting of excess Bend / remove unwanted protruding nails. Use proper tool
weight to remove embedded nails, nails to be collected in proper
Material falling on box, maintain good housekeeping.
feet. Supervisor shall be ensure that no workman will lift more
Slippery surface & than 20 kg for manually handling loads more than 20kg,
tripping hazard. deploy a team of required manpower.
Wrong posture. Provide shoulder pad for material shifting.
Ensure obstruction free accesses to work place.
Ensure proper packing is provided below the stacked
Page 1 of 4
Format No.: EHS-006/F06-00 Effective Date:
Jubliant Infrastructure Limited-Bharuch
Annexure-6
JOB SAFETY ANALYSIS
material
PPEs safety shoes with steel toe shall be provided.
Shuttering material stack height to be limited to 1.2 mtr.
Shuttering frame Inadequate designed, Skilled carpenter & fitter to be deployed for shuttering work.
making/formwork fabricated, and Continue supervision to be provided.
supported form work. Ensure proper tying or fixing of shuttering.
Cut hazard Support formwork or shuttering secured with both ends.
Dust The vertical supports shall be adequately braced or
Trapping and pinching otherwise secured in position.
Inadequate tying of Avoid excessive stacking on shuttering material.
frames. Provide the rubber / PVC insulated sleeve for the hammer.
Rusted or spoiled nuts After assembling the basic unit, adjustment screw shall be
and bolts. set to their approximate final adjustment.
Protruding nails. The centring frames shall be tied together with sufficient
Uneven ground. braces to make rigid and solid.
Do not used rusted or spoiled threaded nuts & bolts.
Use of adequate PPE's are provided, proper communication
amongst crew.
Ply wood cutting for Wrong operation of Ensure only valid & inspected ply cutter machine should be
shuttering work ply cutter machine. used by competent person.
Dust Inspect work locations and ensure closure of observations.
Flying of small Inspect hand tools before use, use right tool for right job.
particles. Use of dust mask/Nose mask.
Electrical shock All electrical connection given through ELCB (capacity 30
Defective hand tools mA).
Flying Nail leading to Electrical connection shall be taken only through authorized
bodily injury electrician.
Ensure joint free cable is used for the electrical connection
and protection
Maintain good housekeeping in the area.
Deploy trained persons, use of adequate PPE's.
Access way should be free from obstacles.
Electric supply cable should be having industrial/waterproof
pin top.
Tool box talk conducted by concerned engineer or
supervisor before start of work.
Work permit should be taken before start the work,
Only skilled person are allowed to execute ply wood cutting
work.
Use of safety glasses, Hand gloves, Appropriate PPES, restrict
unauthorized person at workplace.
Manual De Failure of scaffolding. Ensure continuous supervision during deshuttering work.
shuttering of Fall of shuttering Proper inspection of scaffolding by certified inspector,
material material required strengthening, supporting before start of work.
Page 2 of 4
Format No.: EHS-006/F06-00 Effective Date:
Jubliant Infrastructure Limited-Bharuch
Annexure-6
JOB SAFETY ANALYSIS
Permit issuer
Permit acceptor
Prepared by- Permit Issuer and Permit Acceptor Reviewed by-Plant Manager/ Safety
officer
Page 3 of 4
Format No.: EHS-006/F06-00 Effective Date:
Jubliant Infrastructure Limited-Bharuch
Annexure-6
JOB SAFETY ANALYSIS
Approved By HOD
Page 4 of 4
Format No.: EHS-006/F06-00 Effective Date: