You are on page 1of 7

Arab J Sci Eng (2013) 38:3301–3307

DOI 10.1007/s13369-013-0641-y

RESEARCH ARTICLE - CIVIL ENGINEERING

Impact of Silt Excluder on Sediment Management of an Irrigation


Canal: A Case Study of D.G. Khan Canal, Pakistan
Muhammad Kaleem Sarwar · Muhammad Naveed Anjum ·
Sajid Mahmood

Received: 30 November 2011 / Accepted: 3 July 2013 / Published online: 6 September 2013
© King Fahd University of Petroleum and Minerals 2013

Abstract This study estimates the sediment transport capac- 1 Introduction


ity of D.G. Khan Canal and analyses the impact of silt
excluder on the sediment management of the canal. The aver- D.G. Khan Canal having a design discharge of 8,900 cusecs
age sediment load entering into the D.G. Khan Canal before off-takes from the right side of the Taunsa Barrage located
the silt excluder’s intervention was about 258 ppm which is on the river Indus, at latitude 30◦ 42 N and longitude 70◦
58 % more than the sediment transport capacity of the canal 50 E; 20 km northwest of KotAdu, Muzaffargarh District,
(163 ppm). However, the post-intervention average sediment Punjab Province of Pakistan Fig. 1. D.G. Khan Canal is a
load observed during 2006–2009 was 183 ppm which indi- non-perennial canal and flows from May to November which
cates that the intervention of silt excluder has reduced the are the months of high flows and excessive sediment load
sediment entry in the canal. variation in the river, and during these months siltation in
head reach of D.G. Khan Canal takes place.
Keywords Indus River · Taunsa barrage · Silt excluder · Sediment entry into D.G. Khan Canal has remained a
Sediment chronic problem since 1965. The oblique curve entry of river
flow into the Guide-Banks Zone is throwing the right pocket
and D.G. Khan Canal on the intrados of the approach curve
(Fig. 2) which results in increasing the sediment entry and
deposits in the right half of the barrage. The situation causes
imbalance in water levels across the barrage with lower pond
level on the right flank. The imbalance in the pond level and
increased sediment entry into the right pocket causes silting
up of the canal and reduction in its capacity. Therefore, the
D.G. Khan canal was provided with a silt ejector at RD-20800
for removing substantial quantity of sediment. However, the
ejector does not have any significant impact on the sediment
deposit in the head reach of D.G. Khan Canal, consequently
the idea of silt excluder was considered [5].
The fact that the bottom layers of a channel carry the major
part of the sediment load, has led to evolution of silt exclud-
ers for excluding excessive amount of sediments from the
water being diverted into canals off taking from barrages.
M. K. Sarwar (B) · M. N. Anjum · S. Mahmood Silt excluders divide the pocket into two portions by means
Centre of Excellence in Water Resources Engineering, of a horizontal diaphragm, the upper water layer enters into
University of Engineering and Technology, G.T. Road, the canal while heavier silt laden bottom water passes through
Lahore 54890, Pakistan
e-mail: eng_kaleem@yahoo.com the tunnels downstream of the under sluices [3].

123
3302 Arab J Sci Eng (2013) 38:3301–3307

Fig. 1 Location map of Taunsa Barrage

Using model studies it has been found that the tunnels regulator is 246.5 ft long while the last one farthest away
should be located at selected positions, rather than distrib- from the regulator is 24.5 ft long [5] (Figs. 3, 4).
uted uniformly over the entire length of head regulator. It
means that the position of tunnels is more important than
their number. It was found by experience at Khanki Barrage
in Punjab Province of Pakistan that three tunnels proved to 2 Background
be more efficient than six. Also, a smaller number of pocket
bays covered by the excluder, give better results as do the Ackers and White [1] noted that sediment transport is
openings of the tunnels confined to the mouth. expressed in terms of the dimensionless parameter dgr (sed-
At Taunsa barrage, it was decided to convert three out of iment size), Fcr (mobility parameter) and Gr (transport para-
total four bays of the under sluices on the right bank into silt meter). Baosheng et al. [4] evaluated the applicability of
excluders. The bays nos.64 and 65 were required to serve the sediment transport methods developed by Engelund and
D.G. Khan Canal while bay no. 63 was also provided with Hansen [6], Ackers and White, Yang et al. [13], and Van
short tunnels for additional affects. Each bay has been divided Rijn [11] together with the Wuhan method [14] for Yellow
into four tunnels of rectangular cross-section. Keeping the River China. The best results were obtained from the Yang
top level of tunnels at elevation 432 ft (i.e. 1.0 foot below method, the Wuhan method, and the modified Wuhan method
the existing and 2.0 foot below the raised canal crest level), by Wuhan and Long [12]. Reasonably good predictions were
the bottom level at elevation 425 ft (existing crest level of also provided by the Van Rijn method. Shakir and Khan [9]
the under sluices), and thickness of top slab 1.5 ft which estimated the sediment transport capacity of Marala Ravi
provides a clear tunnel height of 5.5 ft at exit and 11.5 ft Link Canal (MRL) and Upper Chenab Canal (UCC) as 199
elsewhere. Each of the two Bays (63 and 64) across the river and 356 ppm, respectively, by using Engelund and Hansen,
has 15 ft wide two outer tunnels and two inner tunnels of Ackers and White, Shen and Hung [10] and Yang’ method.
14.50 ft width with intervening 2-ft thick walls. Width of Ahmad et al. [2] discussed different sediment exclusion
the corresponding tunnels in the bay adjacent to the canal methods and devices at the intake of canals. They tested
head regulator (Bay no. 65) has, however, been kept as 13.75 the silt excluders for full supply discharge in power tun-
and 13.5 ft, respectively, in view of space available there. nel, where the river discharge was equal to 100,000 cusecs.
The tunnel immediately in front of DG Khan Canal head It was envisaged that an excluder of ejector type or vortex

123
Arab J Sci Eng (2013) 38:3301–3307 3303

Fig. 2 Schematic diagram of


hydraulic organs at Taunsa
Barrage, Pakistan

Fig. 3 Plans and section of silt


excluder

 
excluder will be efficient for exclusion of coarse silt from the Sc
Efficiency = 1 − × 100
power tunnel. The efficiency of silt excluder for coarse and So
medium sand was about 50 %, whereas the efficiency for total where Sc = sediment concentration in canal and So = sedi-
sediment passing through intake was 37 %, and established ment concentration in approach channel
the following relation for the calculation of silt excluder’s Haigh [7] described different factors affecting the effi-
efficiency. ciency of silt excluders. Sediment intensity decreases rapidly

123
3304 Arab J Sci Eng (2013) 38:3301–3307

Fig. 4 View of silt excluder at Taunsa Barrage

with depth, additional escape increases the efficiency but • Excessive sediment concentration in the right pocket and
slowly. The efficiency of silt excluder is affected by the D.G. Khan Canal intake being located on the inner side of
grade of material carried by the water. The excluder may the river approach curve.
be accepted to work more efficiently where the proportion of • Quite a few potent hill torrents discharging into the river
coarser silt is greater. On the other hand, coarser the grade from the right side a short distance on the upstream of the
of silt carried, the greater the slope and velocity will be, and barrage bring very heavy course sediment charge in the
consequently the less the concentration of silt in the lower right half of the river channel.
layers. It is well known that the coarser sediments must be in • Use of semi-still pond regulation, the right pocket used to
the lower layer of transport despite the velocity and slope. It get silted up frequently and DG Khan Canal received the
is the velocity that helps carrying the larger grain size. Width supply direct from the river channel with heavy concen-
and depth of the canal determine the amount of silt carried tration of sediment.
by the canal, while the velocity of water determines the grain
size.
Raju and Kothyari [8] explained the design principles of 4 Sediment Transport Capacity of D.G. Khancanal
two kinds of sediment withdrawal methods, namely; settling
basins, and vortex chambers. They accomplished that the vor- To analytically estimate the sediment transport capacity of
tex chamber has high efficiency as compared to settling basin D.G. Khan Canal, various sediment transport methods were
and require small flushing discharge. The negative aspect of reviewed. It was decided to make use of those methods
vortex chamber is that it is suitable for small channels only. which provide the estimate of total sediment load because
Shakir and Khan [9] indicated that there is slight differ- others methods may require more approximations for con-
ence in sediment intake as a result of raising the crest level verting results into total sediment load being transported in
of MRL canal, which was considered and supplemented by canal. Keeping in view the suitability following three meth-
physical model studies before implementation as one of the ods based on total sediment load approach were used.
most effective measure for controlling the sediment entry in
these canals. 1. Acker and White method
2. Enguland and Hansen method
3. Yang’s method
3 Reasons for Higher Silt Charge in D.G. Khan Canal
The Ackers and white [1] function to determine the total
Irrigation and Power Department, Punjab [5] found that the sediment transport is given as
 n
high sediment charge and grade in D.G. Khan Canal is due v
to: qs = G gr .s.d
u∗

123
Arab J Sci Eng (2013) 38:3301–3307 3305

where Table 2 Data for the estimation of sediment transport capacity of D.G.
s Specific gravity of sediments Khan Canal by Enguland and Hansen method
G gr Transport parameter Full supply discharge 8,900 cusecs
d Representative particle diameter Average velocity 2.34 ft/s
ν Kinematic viscosity of sediments Specific gravity of sediments 2.65
n Exponent in dimensionless mobility parameter
Mean diameter 0.0007 ft
u∗ Shear velocity
Kinematic viscosity of sediments 1.315×105 ft/s
qs Total sediment transport
Gravitational acceleration (g) 32.2 ft/s2
In Enguland and Hansen method [6], total sediment trans- Flow depth 10 ft
port is expressed by:
0.05V 5
qs =
(S − 1)2 g0.5d50 C 3 Table 3 Data for the estimation of sediment transport capacity of D.G.
Khan Canal by Yang method
where in above equation
Full supply discharge 8,900 cusecs
qs Total sediment transport
Average velocity 2.34 ft/s
V Mean velocity
C Chezy coefficient Specific gravity of sediments 2.65
S Specific gravity of sediments Total sediment transport in ppm by mass 61.64 ppm
d50 Mean diameter Mean diameter 0.0007ft
g Gravitational acceleration Kinematic viscosity of sediments 1.315×105 ft/s
Flow depth 10 ft
Total sediment transport load by yang’s method [13] is
calculated as:-
Table 4 Estimated total sediment transport capacity of D.G. Khan
qs = 0.001ct .Vh Canal
where in above equation Ackers and White sediment transport formula 203 ppm
qs Total load transport Yang’s method 62 ppm
ct Total sediment transport in Enguland and Hansen method 223 ppm
ppm by mass Mean sediment transport capacity 163 ppm
V Velocity for initiation of motion
h Water depth
Tables 1, 2 and 3 show the experimental values of data
sediment characteristics and concentration. Table 4 gives the
collected from Irrigation and Power Department, Punjab for
calculated values of sediment transport capacity of the canal
the estimation of sediment transport capacity in D.G. Khan
by using collected data. Analysis of data for the year 2002 to
Canal. The Punjab irrigation and power department mea-
2009 regarding discharge and sediment load entering D.G.
sures water and sediment discharge twice a day at the head
Khan Canal indicated that the sediment load is maximum in
of the canal and at the upstream and downstream of the silt
the months of July and minimum in September while dis-
excluder. The sediment data is collected with the help of
charge of the canal is maximum during the months of July to
sediment samplers DA-59 and analyzed in the sediment lab-
September and minimum during the months of October and
oratory established at the barrage in order to find out the
November. Figure 5 shows that average annual sediment load
entering into D.G. Khan Canal varies in the range of 315 to
Table 1 Data for the estimation of sediment transport capacity of D.G. 165 ppm, while calculated mean sediment transport capacity
Khan Canal by Acker and White method is 163 ppm indicating that the sediment load entry in D.G.
Full supply discharge 8,900 cusecs Khan Canal is more than the sediment transport capacity of
Average velocity 2.34 ft/s the canal except in year 2008 where sediment concentra-
Specific gravity of sediments 2.65 tion value in canal is 127 ppm. Low sediment concentration
Transport parameter 0.26 in canal during the year 2008–2009 was recorded due to low
Representative particle diameter 0.0007 ft sediment intensity in river during that period. Figure 5 shows
Kinematic viscosity of sediments 1.315×105 ft/s
that in 2009 highest amount of water was diverted to canal
which may increase the velocity of flowing water in canal
Exponent in dimensionless mobility parameter 0.81
but in the presence of silt excluder, high velocity will not
Shear velocity 0.23 ft/s
increase the sediment entry in canal.

123
3306 Arab J Sci Eng (2013) 38:3301–3307

Fig. 5 Sediment intake and


sediment transport capacity of
D.G. Khan Canal

5 Efficiency of Silt Excluder Table 5 Average efficiency of silt excluder during 2006–2009
Year Average Average discharge Average sediment
The reduction in canal water silt intensity as compare to efficiency (cusecs) intake of canal (ppm)
approach channel is termed as silt excluder’s efficiency which (%)
can be expressed mathematically as:
  2006 41 8,518 207
Ic 2007 45 8,544 236
Efficiency = 1 − × 100
If 2008 43 8,582 127

where 2009 49 8,518 162


Ic silt intensity in the canal (in ppm)
I f silt intensity in the approach channel (in ppm)
Following types of sediment data for 2006–2009(after
the silt excluder intervention) is shown in Fig. 6. The aver-
intervention of silt excluder) was used for computation of
age silt entry in the first four years (2002–2005) is about
silt excluder’s efficiencies.
258 ppm being highest in 2002 as 310 ppm and lowest in
(a) Sediment concentration at the head regulator of D.G. 2003 as 210 ppm. The average silt entry at the head of D.G
Khan Canal. Khan Canal after Silt Excluder intervention (2006–2009) is
(b) Sediment concentration at the upstream and downstream 183 ppm. This shows 29 % decrease in silt entry in compar-
of silt excluder. ison with previous four years (pre-silt excluder intervention
(c) Sediment load entry into the canal. conditions). In post-silt excluder intervention period, highest
recorded sediment concentration is 236 ppm and lowest is
Efficiency of silt excluder is high during high sediment bed 127 ppm in 2007 and 2008, respectively. Annual water vol-
loads as it excludes the sediment load which is near to the bed umes diverted to the D.G Khan canal for period 2002–2009
or on the bed while suspended sediment is diverted towards are also shown in Fig. 6 which indicates that the diversion of
the canal. At Taunsa Barrage, silt excluder’s efficiency was water in the post-intervention period (2006–2009) has been
noted high in the months of June to August and low in Sep- increased (18 %) as compared to the pre-intervention period
tember. The highest value of efficiency was observed as 72 % (2002–2005). This increase in water diversion reveals that
during August 11–20, 2008 while Table 5 shows that maxi- the canal capacity has been improved due to less sediment
mum efficiency of silt excluder is 49 %. It is clear from Table 5 entry into the canal after Silt Excluder’s interventions. It is
that the average efficiency of silt excluder is 45 % which is not noted that average sediment load entering into the D.G Khan
a good number and still required to eject the sediment which Canal before the Silt Excluder’s interventions is 258 ppm
is more than the transport capacity of D.G. Khan Canal. which is 58 % more than the sediment transport capacity of
canal, but the sediment load after the intervention is about
183 ppm which is only 12 % more than the sediment transport
6 Impact of Silt Excluder capacity of D.G. Kahn Canal. It shows that silt excluder has
reduced the sediment entry into the canal but still it is more
The sediment entry into D.G. Khan Canal for the eight years than the sediment transport capacity and this additional sed-
from 2002 to 2009 (four years before and four years after iment will cause the aggradation of canal bed.

123
Arab J Sci Eng (2013) 38:3301–3307 3307

Fig. 6 Annual sediment intake


of D.G. Khan Canal before and
after silt excluder’s intervention
(2002–2009)

7 Conclusions and Recommendations 2. Ahmad, M.; Ali., M.; Khaliq, A.: Sediment exclusion methods and
devices at the intake of canals. Pak. Engg. Congr. 341, 1–63 (1960)
3. Ali, I.: Irrigation and hydraulic structures theory design and prac-
The analysis of data regarding sediment entry at the head
tice. Allied Book Company, Lahore, Pakistan (2007)
of the canal and comparison of water diversions in the post 4. Baosheng, W.U.; Van Maren, D.S.; Lingyun, L.: Predictability of
intervention period (2006–2009) and pre intervention (2002– sediment transport in the yellow river using selected transport for-
2005) period indicated that the construction of silt excluder mulae. J. Sediment Research, 23, 283–298 (2008). ISSN 1001-
6279
has reduced the sediment intake and increased the discharge 5. Consultant, N.D.; Pakistan, N.E.S.: ATKINS: Punjab barrages
of D.G. Khan Canal but still it is more than the sediment rehabilitation project, phase-1. Irrigation and Power Department,
transport capacity of the canal, consequently aggradation Government of Punjab, Pakistan (2005)
of canal bed will reduce its design discharge capacity. The 6. Engelund, F.; Hansen, E.: A monograph on sediment transport
in alluvial streams.Teknish Forlag, Technical Press, Copenhagen,
data analysis of cross sections and longitudinal sections in Denmark, p. 62 (1967)
upper reaches of the canal is required to study the changes in 7. Haigh, F.F.: Silt excluders. Pak. Engg. Congr. 211, 1–51 Lahore
canal bed levels due to silt excluder intervention. To exclude (1938)
the maximum quantity of sediment load from canal flows, 8. Raju, K.G.R.; Kothyari, U.C.: Sediment management in hydro-
electric projects. Proceedings of ninth international symposium on
the operation and management authority of barrage should river sedimentation, Yichang, China (2004)
ensure that no turbulence occur at silt excluder tunnel in-takes 9. Shakir, A.S.; Khan, N.M.: Impact of structural intervention on sed-
or in the close upstream proximity. The closure of excluder iment management of large canals, acase study of Marala Barrage,
tunnels is not suggested in any case except during dire emer- Pakistan. J. W. Resour. Manag. 23, 3149–3163 (2009). ISSN 0920-
4741
gency and for a short period and a minimum discharge of 10. Shen, H.W.; Hung, C.S.: An engineering approach to total bed-
1,000 cusecs should always be escaped through the excluder material load by regression analysis. In: Sedimentation Symposium
tunnels in order to keep them operative. to honour Professor Einstein HA (ed. by H.W. Shen), 14/1-14/7.
Colorado State University, Fort Collins, Colorado (1972)
Acknowledgments Authors are thankful to Irrigation and Power 11. Van Rijn, L.C.: Sediment transport, Part-I: Bed load transport. J.
Department for the access of data and to the Centre of Excellence Hydr. Engg. 110 (10), 1431–1456. ISSN: 0733–9429
in Water Resources Engineering, Engineering University Lahore for 12. Wuhan, B.S.; Long,Y.Q.: Several modifications for sediment trans-
providing the required facilities to conduct the study. port capacity formulae of Yellow River. Yellow River. 95, No.(07)
(1993)
13. Yang, C.T.; Molinas, A.; Wu, B.S.: Sediment transport in Yellow
River. J. Hydr. Engg. 122 (5), 237–244 (1996). ISSN: 0733-9429
References 14. Zhang, R.J.: A study of the sediment transport capacity of the mid-
dle and lower Yangzte River.J. Sediment Rese 04, (02) (1959).
1. Ackers, P.; White, W.R.: Sediment transport, new approach and ISSN 1001–6279
analysis. J. Hydr. Div. 99, (1973). ISSN: 0044–796X

123

You might also like