CONSTRUCTION DAILY REPORT

Company
Logo No. :

Project Name : BJP HOUSING FACILITY PROJECT Prepared by, Approved by,
Location : BOUNDARY FANCE
Department : PT. WME
Section :
Today Activities ( Actual ) Tomorrow Activities ( Planning )
Day / Date : 07-05-2021 Day / Date : 08-05-2021
Working Time : 13.00 - 17.00 Working Time : 08.00 - 22.00 Supervisor Site manager
Weather : Supervisor : SALMAN
Supervisor : SALMAN
Safety

Progress Progress Potensial


No. Description ManPower No. Description ManPower Job Nature Preventive Action
(Actual) (Target) Hazard

1 DEMPUL WOOD FENCE 1 1

2 CLEANING DINDING KAMPROT 1 2

3 3

4 4

5 5

6 6

7 7

Inspection Result : Inspection Item : - Safety Patrol : -


- -
- -
(Acknowledged by QC) (Acknowledged by Safety)
Obstruction During Construction ManPower Tools Consumables
Direct Labor Indirect Name Type Quantity Name Quantity
F/M S/M :
Survey : FHS :
Remarks S/K 1 STTY :
H/P S/V :
STP WLD : Staff :
Scaff : Op Exca :
TTL : TTL :
CONSTRUCTION DAILY REPORT
Company
Logo No. :

Project Name : BJP HOUSING FACILITY PROJECT Prepared by, Approved by,
Location : SECONDARY SECURITY POS
Department : PT. WME
Section :
Today Activities ( Actual ) Tomorrow Activities ( Planning )
Day / Date : 07-05-2021 Day / Date : 24-04-2021
Working Time : 08.00 - 22.00 Working Time : 08.00 - 22.00 Supervisor Site manager
Weather : Supervisor : SALMAN
Supervisor : SALMAN
Safety

Progress Progress Potensial


No. Description ManPower No. Description ManPower Job Nature Preventive Action
(Actual) (Target) Hazard

1 REPAIR DINDING KOPONG 1

2 REPAIR CRAMIK KOPONG 2 2

3 3

4 4

5 5

6 6

7 7

Inspection Result : Inspection Item : - Safety Patrol : -


- -
- -
(Acknowledged by QC) (Acknowledged by Safety)
Obstruction During Construction ManPower Tools Consumables
Direct Labor Indirect Name Type Quantity Name Quantity
F/M S/M :
Survey : FHS :
Remarks S/K 2 STTY :
H/P 1 S/V :
HENGKI WLD : Staff :
Scaff : Op Exca :
TTL : TTL :
CONSTRUCTION DAILY REPORT
Company
Logo No. :

Project Name : BJP HOUSING FACILITY PROJECT Prepared by, Approved by,
Location : MAIN SECURITY POS
Department : PT. WME
Section :
Today Activities ( Actual ) Tomorrow Activities ( Planning )
Day / Date : 28-04-2021 Day / Date : 24-04-2021
Working Time : 08.00 - 17.00 Working Time : 08.00 - 22.00 Supervisor Site manager
Weather : Supervisor : SALMAN
Supervisor : SALMAN
Safety

Progress Progress Potensial


No. Description ManPower No. Description ManPower Job Nature Preventive Action
(Actual) (Target) Hazard

1 REPAIR CRAMIK TOILET KOPONG 1 1

2 REPAIR DINDING ATAS 1 2

3 3

4 4

5 5

6 6

7 7

Inspection Result : Inspection Item : - Safety Patrol : -


- -
- -
(Acknowledged by QC) (Acknowledged by Safety)
Obstruction During Construction ManPower Tools Consumables
Direct Labor Indirect Name Type Quantity Name Quantity
F/M S/M :
Survey : FHS :
Remarks S/K 2 STTY :
H/P S/V :
STP WLD : Staff :
Scaff : Op Exca :
TTL : TTL :
: TYPE 1,2,3,4,5,6,12
PHOTOGRAPH
NO NO
ITEM ITEM

SIGN SIGN
PICTURE PICTURE

REPAIR CRAMIK TOILET KOPONG (MAIN SECURITY) REPAIR DINDING ATAS (MAIN SECURITY)
COMMENT COMMENT

ITEM ITEM
NO NO

SIGN SIGN
PICTURE PICTURE

CLEANING DINDING KAMPROT (BOUNDARY FENCE) REPAIR CRAMIK KOPONG (SECONDARY SECURITY)
COMMENT COMMENT

NO NO
ITEM ITEM

SIGN SIGN
PICTURE PICTURE

DEMPUL WOODEN FENCE (BOUNDARY FENCE)


COMMENT COMMENT

ITEM ITEM
NO NO

SIGN SIGN
PICTURE PICTURE

COMMENT COMMENT

REPAIR