PUNCHLIST Revision :
CONTRACTOR : PT. Wasa Mitra Engineering CONTRACT No. :
BUILDING NAME : Housing Type B-4 AREA : BJP HOUSING
DRAWING NO : BJP-CD-16-B-AR-01 Sheet 1
PROJECT : BJP HOUSING FACILITY
DATE & TIME : 20 Desember - 21 Desember 2020 09.00 AM - 06 PM of 1
ITEM SIGNATURE
DESCRIPTION * CATEGORY REMARKS
No. WME BJP
Gas Storage, Foyer, Corridor Pantry, Pantry, Master
1 Wall painting is uneven and finishing surface is untidy B Bedroom, Bedroom 2, Bedroom 1, Facade Garden,
Living and Dining Room
Door, Wardrobe, Kitchen set, TV cabinet, Frame,
2 Gap on the object B Shadow line, Shoe rack, Credenza, Kitchen set,
Wastafel, Lavatory cabinet
Door handle, Cylinder cover, Hinge, Paper holder,
3 Not properly installed B
Towel bar, Lock case
Curtain hook, Double robe hook, Mini bar, Home
4 Not installed yet B
appliances, Granite table, Wardrobe
Parapet, Embosed wall, Ridge, Wall, Opening, Door,
5 Crack on the object B
Pedestal column, Border of "koral sikat"
Gas storage, Foyer, Corridor, Master bedroom,
6 Wall painting is peeled off B Master bathroom, Bedroom 2, Bedroom 1, Garden
facade, Living and dining room, Back side facade
Parapet, Wall, Roof tile, Opening, Ceramic,
7 Chipped out B Credenza, Canopy, Dividing wall, Border of "koral
sikat"
Roof tile, Entrance, Pantry, Master bedroom,
8 Ceiling painting is uneven and finishing surface is untidy B Bedroom 1, Living and dining room, Terrace living
room
9 Sealant application is untidy B Door frame, Window frame, Wastafel, BV1, Mirror
Roof tile, Wall, Dividing wall, Door, Kitchen set,
10 Dirty on the object C
TV cabinet, AC split unit
11 Ceramic floor/wall tiles that porous and not fully grout A Most of all section
12 Paras jogja that porous and not cohesive A Front side facade, Back side facade
13 Installation is not align B Drop ceiling, Wall, Opening
Aluminium lattice, Wardrobe, Window frame, Door
14 Scratches on the object B
frame
Skirting, Water rope, Door leaves accents, Pergola,
15 Finishing surface is untidy B
Canopy
* Category A : Item that should be rectified as for requirement prior to milestone certificate issued
* Category B : Item that can be completed or corrected up to a week after the milestone or hand over certificate issued
* Category C : Minor Item that can be completed or corrected up to two (2) weeks after the milestone or handover certificate issued
Distribution : Client Commissioning System Ref.
No Date and Time Building/Work Item Section / Rooms Description Category Photograph
Housing
24 - Wall is dirty C
42 - Polycarbonate is dirty C
63 - Aluminium is dirty C
76 - Floor is dirty C
77 - Gap between shadow line and wall B
Terrace - Living
440 21/12/2020 - (PL1) Opening is uneven and uneven painting B
Room
* Category A : Items that should be rectified as for requirement prior to milestone certificate issued.
* Category B : Items that can be completed or corrected up to a week after the milestone or handover certificate issued.
* Category C : Minor item that can be completed or corrected up to two (2) weeks after the milestone or handover certificate issued.