PUNCHLIST Revision :
CONTRACTOR : PT. Wasa Mitra Engineering CONTRACT No.:
BUILDING NAME : Housing Type B-2 AREA : BJP HOUSING
DRAWING NO : BJP-CD-16-B-AR-01 Sheet 1
PROJECT : BJP HOUSING FACILITY
DATE & TIME : 18 Desember - 19 Desember 2020 09.00 AM - 06 PM of 1
ITEM SIGNATURE
DESCRIPTION * CATEGORY REMARKS
No. WME BJP
1 Wall painting is untidy and finishing surface is untidy B Most of all section
Wastafel, Granite table, Shadow line, Door frame,
2 Gap on the object B Polycarbonate, Wardrobe, Credenza, TV cabinet,
Kitchen set, Shoes rack
Towel ring, Towel bar, Paper holder, Cylinder
3 Not properly installed B
cover, TV cabinet
Double robe hook, Shower curtain, Tumbler glass,
4 Not installed yet B Ceramic trap, Wardrobe, Rubber seal, TV cabinet,
Kitchen sink, Footing for AC bracket
Border of "coral sikat", Dividing wall, Ridge,
5 Crack on the object B Embosed wall, Ceramic floor, Wall, Roof deck,
Parapet
6 Wall painting is peeled off B Front Side Facade
Granite table, Wardrobe, Ceramic floor, Plint,
7 Chipped out B Canopy, TV cabinet, Wall, Roof tile, Door,
Parapet, Opening
8 Ceiling painting is uneven and finishing surface is untidy B Most of all section
Front Side Facade, Garden Facade, Roof deck,
9 Canopy finishing surface is untidy B
Terrace living room
Door frame, Window frame, BV1 frame,
10 Sealant application is untidy B
Polycarbonate
Door, Wardrobe, Polycarbonate, Wall, Credenza, TV
11 Dirty on the object C
cabinet, Shoes rack, Roof tile, Window
12 Ceramic tiles that porous and not fully grout A Most of all section
13 Paras jogja that porous and not cohesive A Front Side Facade, Back Side Facade
14 Scratches on the object B Door frame, Aluminium lattice
Door leaves accents, Door lattice, Water rope,
15 Finishing is not finished yet B
Wall
16 Suggest to add B Hole on the P4, Rubber seal
* Category A : Item that should be rectified as for requirement prior to milestone certificate issued
* Category B : Item that can be completed or corrected up to a week after the milestone or hand over certificate issued
* Category C : Minor Item that can be completed or corrected up to two (2) weeks after the milestone or handover certificate issued
Distribution : Client Commissioning System Ref.
No Date and Time Building/Work Item Section / Rooms Description Category Photograph
Housing
60 - Polycarbonate is dirty C
Terrace - Service
91 19/12/2020 - Wall surface is uneven B
Area
Terrace - Living
264 19/12/2020 - (PL1) Opening finishing surface is untidy B
Room
* Category A : Items that should be rectified as for requirement prior to milestone certificate issued.
* Category B : Items that can be completed or corrected up to a week after the milestone or handover certificate issued.
* Category C : Minor item that can be completed or corrected up to two (2) weeks after the milestone or handover certificate issued.