PUNCHLIST Revision :
CONTRACTOR : PT. Wasa Mitra Engineering CONTRACT No.:
BUILDING NAME : Housing Type B-11 AREA : BJP HOUSING
DRAWING NO : BJP-CD-16-B-AR-01 Sheet 1
PROJECT : BJP HOUSING FACILITY
DATE & TIME : 22 Desember - 23 Desember 2020 09.00 AM - 06 PM of 1
ITEM SIGNATURE
DESCRIPTION * CATEGORY REMARKS
No. WME BJP
1 Sealant application is untidy B Window, Door, Granite table, BV1
Foyer, Corridor, Bedroom 2, Terrace-living
room, Facade, Living and dining room, Kitchen,
2 Wall painting is uneven B
Service area, Carport, Roof deck, Gas storage,
Terrace-service area
Wardrobe, Shadow line, Frame, Shoe rack, TV
3 There is a gaps B cabinet, Credenza, Lavatory table, Kitchen
set, Pergola
Wall, Opening, Gutter, Border of "koral
4 Crack on the object B
sikat", Dividing wall, Parapet, Ridge
HPL surface, Shadow line, Border of "koral
sikat", Water rope of "koral sikat", Opening,
5 Finishing is untidy, Not finished yet B Wall, Ceiling, Dividing wall, Fence, Gutter,
Canopy, Column, Parapet, Embosed wall, Fascia
board
Door, Granite table, Polycarbonate, Roof tile,
6 Dirty C
Gas storage
Window frame, Towel bar, Closet, AC split
7 Remove seal, remove plastic cover C
unit, Door frame
Wardrobe, Curtain, Credenza rack, Tumbler
8 Not installed yet B glass, Shower curtain, Sink, Stove, Kitchen
set rack, Granite table
9 Ceramic floor/wall tiles that porous and not fully grout A Most of all section
11 Not properly installed B Lock case, Cylinder cover, Shower faucet
12 Scratches B Door leaves, TV cabinet
Opening, Wall, Wardrobe, Ceramic, Parapet,
13 Chipped out on the object B Dividing wall, Column, Border of "koral
sikat", Embosed wall, Roof tile
14 Paras jogja that porous and not cohesive A Facade (front and back side)
15 Painting is peeled off B Dividing wall, Door opening
* Category A : Item that should be rectified as for requirement prior to milestone certificate issued
* Category B : Item that can be completed or corrected up to a week after the milestone or hand over certificate issued
* Category C : Minor Item that can be completed or corrected up to two (2) weeks after the milestone or handover certificate issued
Distribution : Client Commissioning System Ref.
No Date and Time Building/Work Item Section / Rooms Description Category Photograph
Housing
1 22/12/2020 Type B-11 Master Bedroom - (P2) Opening finishing surface is untidy B
Terrace - Living - There are 11 ceramic floor tiles that porous and
139 12/23/2020 A
Room not fully grout
Terrace - Service
398 23/12/2020 - Wall finishing surface is untidy B
Area
* Category A : Items that should be rectified as for requirement prior to milestone certificate issued.
* Category B : Items that can be completed or corrected up to a week after the milestone or handover certificate issued.
* Category C : Minor item that can be completed or corrected up to two (2) weeks after the milestone or handover certificate issued.