You are on page 1of 2

Page 1

BILL OF QUANTITIES

Date: 23/08/2022

Job Ref:

Client:

Tel:

Project Description: Construction of a Fence

Project Location: Nema Fula Kunda

Project Value: 177,180

Page 1
Page 2

Description Quantity Unit Rate Dalasi

SITE CLEARANCE fence perimeter area = 65mts


Demolished and clear all debris around area of fence. 36 m2 75 2,700

EXCAVATION AND FILLINGS


Excavating to receive foundation:

Trenches 450 wide x 600mm depth. 21.6 m3 300 6,480

Filling to excavations with materials arising from excavation:

Trenches. 15 m3 100 1,500

CONCRETE
Reinforced in-situ concrete; 25 N/mm2 20mm
aggregate size, red wash stone

Foundation trenches, 150mm thick. 5.4 m3 7,500 40,500

MASONRY
Blockwork 130mm thick to solid walls @ 2.4mts high 192 m2 500 96,000

Metal Gates 1 Nr 30,000

CARRIED TO COLLECTION 177,180

Page 2

You might also like