Professional Documents
Culture Documents
FOR
METHOD STATEMENT FOR FABRICATION OF STEEL GIRDERS
CLIENT/EMPLOYER
MUMBAI METROPOLITAN REGION DEVELOPMENT AUTHORITY
GENERAL CONSULTANT/ENGINEER
SYSTRA-CEG-SMCIPL CONSORTIUM
CONTRACTOR
J. KUMAR INFRAPROJECTS LTD.
Project: MMRDA/09/MMRP/CA48: DESIGN AND CONSTRUCTION OF ELEVATED VIADUCT AND NINE
(9) ELEVATED STATIONS (EXCLUDING ARCHITECTURAL FINISHES AND PEB ROOF STRUCTURE)
INCLUDING TWO (2) FLYOVERS, AND UNDERGROUND TWIN TUNNEL, CUT AND COVER, RAMP AND
ONE (1) UNDERGROUND STATION (INCLUDING ARCHITECTURAL FINISHES AND PEB STRUCTURES) FOR
CORRIDOR OF MUMBAI METRO LINE 9 i.e. EXTENSION OF LINE 7 FROM DAHISAR (EAST) TO MIRA
BHAYANDAR AND ANDHERI TO CSIA OF MUMBAI METRO RAIL PROJECT OF MMRDA.
INDEX
METHOD STATEMENT FOR FABRICATION
OF STEEL GIRDERS
Doc. No: JKIL/MMRDA/LINE09/79- (R0)
Contents
1. PURPOSE:...............................................................................................................................................3
2. REFERENCE:...........................................................................................................................................3
3. RESPONSIBILITIES..................................................................................................................................3
4. ORGANIZATION CHART..........................................................................................................................5
5. LIST OF EQUIPMENT..............................................................................................................................5
6. SEQUENCE OF WORK:-...........................................................................................................................6
7. MANDATORY SAFETY REQUIREMENTS................................................................................................18
8. ENCLOSURES........................................................................................................................................20
1. PURPOSE:
The objective of this method statement is to fabricate the steel girder as per IS
specifications. Work formulate as a summary of all quality related activities required to
Page 2 of 19
METHOD STATEMENT FOR FABRICATION
OF STEEL GIRDERS
Doc. No: JKIL/MMRDA/LINE09/79- (R0)
meet the terms of the contract as per the approved drawings & relevant technical
specifications.
2. REFERENCE:
Contract Specifications
IRS: Concrete Bridge Codes
Project SHE Plan
SHE conditions of contract
Approved Project Quality Management plan
Steel grade conforming to IS: 2062-2011
3. RESPONSIBILITIES
Following are the responsibilities and reporting structure of personnel involved in the scope of the
procedure:
Page 3 of 19
METHOD STATEMENT FOR FABRICATION
OF STEEL GIRDERS
Doc. No: JKIL/MMRDA/LINE09/79- (R0)
Page 4 of 19
METHOD STATEMENT FOR FABRICATION
OF STEEL GIRDERS
Doc. No: JKIL/MMRDA/LINE09/79- (R0)
4. ORGANIZATION CHART
Project Manager
Site
Safety
Engineer
Officer
Supervisior
5. LIST OF EQUIPMENT
Sr.
Description Quantity (In Nos) Remarks
No
1 Plasma Cutting Machine 2
2 Welding Machine 1
3 Drilling Machine 2
4 Paint Pump 2
5 Hydra 15 / 20 Ton 2 + 1*
6 Gantry 15/ 20/ 25 Ton 2 + 1*
7 Air Compressor 4 + 2*
8 Cutting Set 2 + 2*
9 Grinding Machine 10
Page 5 of 19
METHOD STATEMENT FOR FABRICATION
OF STEEL GIRDERS
Doc. No: JKIL/MMRDA/LINE09/79- (R0)
Sr.
Description Quantity (In Nos) Remarks
No
10 Stud Welding Machine 1
6. SEQUENCE OF WORK:-
Drawing Approval
Submission of QAP
Raw Material Procurement
Material Testing
Material Cutting
Bevelling the edges of the web
Fitting if Web & Flange
Arc Welding
Fitting of Gusset Plate & Stiffners
Testing
Cleaning of Drilling Holes
Shot Blasting / Metalizing & Painting
Stud Welding
6.1. Drawing approvals
1) Final and approved (signed and stamped by client) GAD will be required to start
the process.
2) Shop/ fabrication drawing will be prepared based on above GAD and will be sent
to client for approval.
3) Once the fabrication drawings are approved by the client, these drawings will be
issued for fabrication to the shop floor.
4)
5)
6.2. Submission of QAP:
i) To ensure the proper Quality of fabrication Quality Assurance Plan (QAP) is prepared.
Page 6 of 19
METHOD STATEMENT FOR FABRICATION
OF STEEL GIRDERS
Doc. No: JKIL/MMRDA/LINE09/79- (R0)
Steel grade conforming to IS: 2062-2011 (with latest amendment), is proposed to be used for all
components for all spans as per approved drawings.
The steel shall comply in all respects with the requirements of approved drawings and relevant
codes and specifications and shall be procured from approved manufacturers only. It may be
noted that quality of steel used for fabrication shall be the essence of the contract & shall be
rigidly followed. Steel sections to be supplied by the manufacturers shall be ultrasonically tested
as per provisions at the manufacturer’s premises before dispatch. The Contractor on receipt of
supply in his factory premises/fabrication workshop shall carryout random USFD testing as per
standards laid down in various codes and verify them with the list received from manufacturers.
Only tested steel shall be used for fabrication.
Steel should be procured only from SAIL, RINL, TISCO or JINDAL such reputed steel
manufacturers only.
Page 7 of 19
METHOD STATEMENT FOR FABRICATION
OF STEEL GIRDERS
Doc. No: JKIL/MMRDA/LINE09/79- (R0)
From this Raw Material, a small cut-bits has to be sent to Certified Testing Laboratory or
government testing agencies for testing the properties of the metal. After testing the metal in
the Laboratory, they will give a clearance test certificate for the material for the Starting of
fabrication for the composite girders.
Page 8 of 19
METHOD STATEMENT FOR FABRICATION
OF STEEL GIRDERS
Doc. No: JKIL/MMRDA/LINE09/79- (R0)
We can eliminate over 90% of handling in parts to be drilled and profiled. High speed drilling
available with efficient plasma cutting offers improvements in output of +300%. Multi set-ups
materials are savings through better nesting on big plates. It can typically improve productivity
by three to five times, while introducing better accuracy, more flexibility and greater range. All
these aspects add up to lower cost parts.
Page 9 of 19
METHOD STATEMENT FOR FABRICATION
OF STEEL GIRDERS
Doc. No: JKIL/MMRDA/LINE09/79- (R0)
The Double layer run welding will be done on four positions of the girder. First layer i.e. root
layer will be done. And the second layer will be done on the root layer. As per the Standards the
depth of the Weld fillet must be = Thickness of web plate * 0.78.
6.9. Assembly of I-Beam Girders and Fit up of Web Stiffeners and Gusset plates:
After completing the Sub-merged arc welding the I-Beam Girders are assembled in platform and
after confirming the required camber will fit up the web stiffeners, Gusset Plates and at the same
time Splice Plates will be marked for Drilling.
Page 10 of 19
METHOD STATEMENT FOR FABRICATION
OF STEEL GIRDERS
Doc. No: JKIL/MMRDA/LINE09/79- (R0)
Note: Tolerances and limits in all levels are fallowed by as per RDSO standards.
6.10. MIG Welding for the fitted Stiffeners, Gusset plates and others:
After Making the Fit up of Web stiffeners and gusset plates, MIG welding will be done for
Stiffeners and gusset plates
Page 11 of 19
METHOD STATEMENT FOR FABRICATION
OF STEEL GIRDERS
Doc. No: JKIL/MMRDA/LINE09/79- (R0)
Page 12 of 19
METHOD STATEMENT FOR FABRICATION
OF STEEL GIRDERS
Doc. No: JKIL/MMRDA/LINE09/79- (R0)
Ultrasonic Inspection is a very useful and versatile NDT method. Some of the advantages of ultrasonic
inspection that are often cited include:
Page 13 of 19
METHOD STATEMENT FOR FABRICATION
OF STEEL GIRDERS
Doc. No: JKIL/MMRDA/LINE09/79- (R0)
2. We are using shot blasting for the girders and other structure, which is advanced
compare to sand blasting.
Page 14 of 19
METHOD STATEMENT FOR FABRICATION
OF STEEL GIRDERS
Doc. No: JKIL/MMRDA/LINE09/79- (R0)
1. The Aluminum metal spraying should be carried out as soon as possible after the surface
preparation by shot blasting and in any case with in such period that the surface still
clean and without any visible oxidation. If deterioration, in the surface to be coated is
observed by comparison with strictly proposed stock surface, similar quantity
preparation treatment by shot blasting is repeated before the Aluminum spray is
applied.
2. Minimum thickness of metal coating applied shall be 115 microns and average thickness
shall be 150 microns. The metal coating shall be checked for thickness by approved
magnetic thickness measuring gauge. At least one reading for each sqm of area painted
shall be taken. The calibration of the gauge shall be checked against a standard of similar
thickness within an accuracy of 10%.
c) Painting :
Specification for Painting:
1. We maintain the paints and oils shall conform to IS specifications and shall be from
RDSO’s approved list of manufactures.
2. The paints used for the work shall confirm to the following specifications and the sample
should be tested at government authorized or NABL Laboratories.
Page 15 of 19
METHOD STATEMENT FOR FABRICATION
OF STEEL GIRDERS
Doc. No: JKIL/MMRDA/LINE09/79- (R0)
2. One coat of wash Etch primer to IS: 5666 shall be applied first. After 4 to 6 hours or the
application of the wash primer, one coat of Zinc chrome primer to IS: 104 with the
additional provision that Zinc Chromate shall be applied.
3. The third coat shall be by Aluminium paint conforming to IS: 2339. The girder parts shall
be dispatched to site after the third coat (i.e. first finishing coat or cover coat.
4. After assembling and launching at site, second finishing coat of Aluminium paint
conforming to IS: 2339 shall be applied after touching up the primer and first finishing
coat.
Page 16 of 19
METHOD STATEMENT FOR FABRICATION
OF STEEL GIRDERS
Doc. No: JKIL/MMRDA/LINE09/79- (R0)
In the stud welding process, the power source and the stud welding control system are set
control the amperage and the arc duration or time. The welding gun has the trigger activated circuit
to initiate the weld and a lifting mechanism to draw the stud away from the base material and
initiate the welding arc. The gun includes a stud holding chuck, two legs, a foot piece and a ferrule
grip to hold the ceramic ferrule (also called as an arc shield).
i) Stud and Ferrule are loaded into the Gun and properly positioned against the Base Plate.
ii) The Gun is pushed against base material taking up the plunge or stud length available for
burn off against the gun spring pressure. The trigger button is depressed to start the fully
controlled automatic sequence. This sequence consists of initiating the weld current, and
lifting the stud to create an arc by energizing the gun solenoid.
iii) The arc duration time is completed and the stud plunged into the molten pool by means of a
spring when the gun solenoid is de-energized and turning off the weld current at the time of
Page 17 of 19
METHOD STATEMENT FOR FABRICATION
OF STEEL GIRDERS
Doc. No: JKIL/MMRDA/LINE09/79- (R0)
weld cycle.
iv) The weld is completed and the gun is lifted off the stud and the ceramic ferrule removed.
The stud is inspected for weld Quality.
Page 18 of 19
METHOD STATEMENT FOR FABRICATION
OF STEEL GIRDERS
Doc. No: JKIL/MMRDA/LINE09/79- (R0)
The work methodology of the activity will be explained to all the key personnel and workmen
involved in that activity and standing instructions will be given.
TBT or Training shall be provided before starting the work.
Emergency contact numbers should be displayed.
Operator, Workmen and Foreman shall have adequate knowledge and experience.
Lifting Devices (Cranes & Tackles etc.) shall be inspected before operations to ensure safe
working condition.
Daily inspection checklist to be completed by site engineers and safety personnel before
starting the work.
Responsible Lifting Engineer/Supervisors must be available throughout the work activity and
close monitoring to be ensured.
Ensure that curing water should not fall on the road.
8. ENCLOSURES
ITP
Risk Assesment
GFC Drawing
Shop Drawing
Page 19 of 19