PLANNING FOR THE MONTH OF OCTOBER - 2022


Sl No Location Activity Unit Total Quantity Week - 1 Week - 2 Week - 3 Week - 4 Area In-Charge Remarks

1 Roughing Mill - GR 08 Balance Slab at 0.00 m LVL Cum 215.00 215.00 Mr. V.C Mourya In between Grid D to E & Axis 3 to 2

Total (Only Concrete) 215.00 0.00 0.00 0.00 215.00

Slab at 0.00 m LVL Cum 675.00 337.50 337.50


2 Roughing Mill - GR 09 Mr. V.C Mourya
CT Wall Cum 20.00 10.00 10.00

Total (Only Concrete) 695.00 10.00 10.00 337.50 337.50

3 Roughing Mill - GR 10 2nd Lift of Mill Stand,MB slab Cum 255.00 101.00 154.00 Mr. V.C Mourya

Total (Only Concrete) 255.00 0.00 101.00 0.00 154.00

Motor Foundation - 1st lift Cum 110.00 110.00

4 Roughing Mill - GR 11 PCC Cum 14.40 14.40 Mr. V.C Mourya

Raft at (-)7.00 Mtr Lvl - Grid D to C & Axis 8 to 9 Cum 153.75 153.75

Total (Only Concrete) 278.15 0.00 14.40 0.00 263.75

Slab at 0.0 mtr Lvl towards D Grid (Axis 8 to 11) Cum 325.00 325.00 Mr. V.C Mourya Towards D Grid

5 Roughing Mill - GR 12 Slab at 0.0 mtr Lvl towards E Grid - 6 mtr Wide (Axis 8 to 9) Cum 80.00 80.00 Mr. S. Sinha Towards E Grid

Slab at 0.0 mtr Lvl towards D Grid (Axis 12 to 13) Cum 245.00 245.00 Mr. S. Sinha Towards D Grid

Total (Only Concrete) 650.00 0.00 0.00 405.00 245.00

6 Roughing Mill - GR 13 Slab from M.B Level to 0.0 mtr Lvl Cum Mr. S. Sinha

Total (Only Concrete) 0.00 0.00 0.00 0.00 0.00

CT Slab Cum 24.00 24.00

Column & Wall Cum 32.00 10.67 21.33


7 Roughing Mill - GR 15 Mr. Prasid Nag
Motor Bay - 2nd Lift Cum 110.00 110.00

CT Wall Cum 27.00 27.00

Total (Only Concrete) 193.00 34.67 21.33 27.00 110.00

Excavation Cum 550.00 250.00 300.00

CT Slab Cum 80.20 80.20

Wall (W80) Cum 23.52 23.52

8 Roughing Mill - GR 16 Raft (GR16 to GR18) Cum 581.00 581.00 Mr. Prasid Nag From Grid E to D & Axis 21 to 24

Raft - Flume Portion Cum 278.00 278.00 From Grid E to D & Axis 21 to 24

Raft Cum 126.00 126.00 From Grid D to C & Axis 23 to 24

Column & Wall Cum 185.00 61.67 61.67 61.67

Total (Only Concrete) 1273.72 581.00 61.67 339.67 291.39

Slab at (-)2.60 mtr LVL towards E Grid from M. Stand 5 to M. Stand 7 incl.
Cum 438.00 219.00 219.00 Slab from Flume to E grid
Mill Stand
Mr. Avik Sarkar &
9 Finishing Mill - GR 18
Slab at 0.0 mtr LVL towards D Grid - M. Stand1 to M. Stand 7 Cum 655.00 327.50 327.50 Mr. S. Poddar Slab towards D grid

Inverted Beam - M. Stand1 to M. Stand 4 Cum 247.73 247.73 Towards E grid

Total (Only Concrete) 1340.73 0.00 219.00 546.50 575.23

10 Reheating Furnace Column (2nd Lift) & Balance Slab Cum 155.50 15.00 25.00 115.50 Mr. V.C Mourya

Total (Only Concrete) 155.50 15.00 25.00 115.50 0.00

11 ECR Wall & Slab Cum 12.00 12.00 Mr. Prasid Nag

Total (Only Concrete) 12.00 0.00 12.00 0.00 0.00

12 Scale Pit Wall - West Side (2 lift) + Internal Wall Cum 350.00 120.00 70.00 50.00 110.00 Mr. Prasid Nag

Total (Only Concrete) 350.00 120.00 70.00 50.00 110.00

# Total Concrete Qty (Week Wise) Cum 5418 761 534 1821 2302

Grand Total

Excavation Cum 550


PCC Cum 14
RCC Cum 5404 5418