Professional Documents
Culture Documents
GEOTECHNICAL PARAMETERS
TABLE OF CONTENT
7. Piles settlement.
Appendix A
Figure No.2 Relationship Bet. Standard Penetration Test N-values and Angle
of Shearing Resistance
Page 1/13
1. Allowable Bearing Pressure of Isolated / Strip Footings on Sand.
qnet(all) = 16 N kd (1-1)
qnet(all) = 10 N kd (1-2)
CN = 9.78
Df = footings depth, m
B = Footings width, m.
The above equations (1-1) and (1-2) are to be multiplies by 0.5 in case of
existence of shallow water table.
Page 2/13
2. Allowable Bearing Pressure of Raft Foundations on Sand.
(usually S = 50mm)
Notes:
1) The above equations (1-1), (1-2) and (2-1) are the average
between Meyerhof (1956) and Bowles.
qnet(all) = (3-1)
Page 3/13
4. Allowable Bearing Pressure of Raft Foundations on Rock.
qo = (4-1)
I1, I2 & If: factors depend on length of raft, width of raft and thickness of
influenced rock strata below raft = 2B (Table No.1 for I1 and I2
and Figure No.1 for If are attached).
F.S. = (4-2)
if F.S. <5, qo =
H = 4 qo B If (4-4)
Page 4/13
5. Piles Capacity on Sand
Qu = Qp + Qf (5-1)
Where:
According to the Tomlinson (1987), the following equations are used for the
case of cohesionless soils:
Qp = Nq vo Ab (5-2)
Where:
Qu
Qall = -------
F.S.
Page 5/13
6. Piles Capacity on Rock
Q = Qp + Qf (6-1)
Qf = Af . Fs
Qp = Ap . qb
qb = 4.5 quc
B = Pile Diameter
Page 6/13
7. Piles Settlement
= + . . (7-
1)
Where,
= Pile Settlement
L = Shat Length
B = Pile diameter
= Poisson’s ratio
For a poisson’s ratio of 0 to 0.25 and L/B > 5, Ip is taken as 0.5, the last term
approximates to 0.5Wb / BEb, so
= + (7-2)
Page 7/13
8. Allowable Bearing Pressure for Shallow Foundations on Sand Based on
CPT
8.1 Meyerhof
B = Width of footing, m
qnet(all) in kN/m2
qc = Average CPT end bearing resistance in the zone of 2B, kN/m2
8-2 Schmertmann
Page 8/13
9. Electrical Resistivity
A) Apparent Resistivity
S=2 a R (9-1)
Where,
S = Apparent Resistivity
a = Electrode spacing, m
R = Soil resistance,
F = 2t
t = Layer thickness, m
Page 9/13
10.1 Scope
10.1.1 The work to be done shall comprise the drilling and pressure
grouting of the fill and / or cavities. The work shall include
among others, the following items: drilling and grouting of
holes and testing. Casing and or other grouting tubes may
be required to prevent holes collapse during drilling and
grouting.
10.2 Grouting
10.2.3 Grout nipples at the collars of grout holes shall be placed into
fill a minimum of 40cm to prevent leakage between the pipe
or casing and fill.
10.2.6 If, during the grouting of any hole, grout is found to flow from
adjacent grout holes, the contractor shall be prepared to
make an immediate hook up to the flowing holes for
Page 10/13
simultaneous grouting of up to a total of 3 holes. Additional
holes continue to flow so as to interface seriously with the
grouting operations or to cause more than 25 litres/hour loss
of grout, such connections shall be capped and a pressure
gauge installed to monitor the pressure on the capping.
10.2.8 All grout holes shall be backfilled from the bottom up with 1:1
by volume water cement slurry grout or dry packed upon
completion of grouting.
10.2.9 During the grouting operations, the contractor shall take due
precautionary measures to prevent uplifting of the ground
slabs or footings due to excessive grouting pressure.
The injection of grout into any hole shall be continued until the
hole takes a 4:1 water-cement grout at the rate of less than 0.027m3 in
20 minutes, at the specified grouting pressure.
10.4.1 General
Page 11/13
All drilling equipment shall produce a smooth, round
hole, free of irregularities.
a. Water
b. Cement
c. Sand
Page 12/13
Whenever sand is added to the grout it shall consist of
clean, durable stone particles, free from lumps of clay and
objectionable foreign matter and shall conform to the following
grading requirements:
10.6 Drilling
Page 13/13
APPENDIX A
Page 14/13