SEWER PIPELINE REPORT AS AT 12th, SEP 2022

Pipe Manhole pipeline laid Manhole


Total Total
S/No Work Item Complete Completed to in preciding done in
Length,(M) manholes to date date week preciding
week
1.   Bus Station Line 1,500 30 1,360 24 0 0
2 Market Line 2,926 60 2,354 43 0 0
3 Main Line 18,844 377 16,192 323 190 5
4 Kiaritha Line 4,706 98 4,272 96 100 3
5 Effort Boys 4,265 98 3717 81 0 0
TOTAL 32,241 663 27,895 567 290 8

TOTAL PIPELINE (m) 32,241


TOTAL PIPELINE
INSTALLED (m) 27,895
%COMPLETED 87%

TOTAL MANHOLES 663


TOTAL COMPLETED 567
%COMPLETED 86%
%

91%
80%
86%
91%
87%
80%
WATER PIPELINE REPORT AS AT 12th, SEP 2022
Work done in
Total Delivered to
Pipe Size, mm Installed, m Preceding %done
Length,m site, m
week
KIRINGA RAW WATER MAINS
DN 450, GRP 1700 1812.8 1658 0 98%

THIBA RAW WATER MAINS


DN 300, GRP 4300 4300 4050 0 94%

TREATED WATER GRAVITY MAINS+A7:F9


DN 500, GRP 4,200 4,186.30 4,156 54 99%
DN 400, GRP 9,350 9238.5 8,658 0 93%
DN 300, GRP 21,750 21,501.90 11,890 1,575 55%
DN 250, GRP – To 7,800 3431 3968 331 51%
Kutus
DN 250, GRP – To
8,400 6533.9 5,146 0 61%
Kerugoya
DN 140, HDPE 6,300 6,300 6,215 0 99%
TOTAL 57,700 51,192 40,033 1,906 69%

TOTAL PIPELINE 63,700


TOTAL DELIVERED 57,304
TOTAL DONE FROM
6TH september TO 1,906
12th SEPTEMBER
TOTAL INSTALLED M 45,741
% WORK DONE 72%