MEKELLE UNIVERSITY

FACULTY OF SCIENCE AND TECHONOLOGY


DEPARTEMENT OF MECHANICAL ENGINEERING

PROPOSAL
ON
MANUFACTURING AND TESTING OF
PRESSURE TYPE TREADLE PUMP PROJECT

DONE BY: LIUL GIRMA FST/R352/96


MEWAEL GASHAW FST/R360/96

ADVISORS (MU): Dr. MULU BAYRAY (PHD)


Ir. FISSEHA MERESSA
Objective

 Verification of further improvements


 Manufacturing the prototype of pressure type treadle pump
 Test the prototype for several parameters (i.e., flow rate, suction head etc)
 Compare the improvement with the old prototypes
Methodology
 Study previous project reports
 Verify the correctness of the proposed designs
 Preparing workshop drawings
 Manufacturing the prototype
 Testing the prototype

Plan of activities
W W W W W W W W W W W W
No of activities 1 2 3 4 5 6 7 8 9 10 11 12

 literature review
 revising of the existing
design
 modifying the design if any
is found to be improved
 preparing part workshop
drawing & assembly
drawing
 preparing materials for
manufacturing
 arrangement of work shop
for manufacturing
-manufacturing of the pump
-testing of the pump for taking
necessary data
 comparing the data
 giving comments
-finalizing the report

Stationary
No. workmanship Qty Unit price Total price
1. Paper 80gm 4 50 200
2. Binding 5 20 100
3. For CD’s and burning 20 5 100
4. plotting 6 50 350
5. Typing 6 100 400
6. Printing 6 100 600
7. Photocopying 0.25 200
8. Internet 10 250
9. Transportation 2 300 600
10. Mobile cards 2 100 200
Total 3000