Professional Documents
Culture Documents
PROPOSAL
ON
MANUFACTURING AND TESTING OF
PRESSURE TYPE TREADLE PUMP PROJECT
Plan of activities
W W W W W W W W W W W W
No of activities 1 2 3 4 5 6 7 8 9 10 11 12
literature review
revising of the existing
design
modifying the design if any
is found to be improved
preparing part workshop
drawing & assembly
drawing
preparing materials for
manufacturing
arrangement of work shop
for manufacturing
-manufacturing of the pump
-testing of the pump for taking
necessary data
comparing the data
giving comments
-finalizing the report
Stationary
No. workmanship Qty Unit price Total price
1. Paper 80gm 4 50 200
2. Binding 5 20 100
3. For CD’s and burning 20 5 100
4. plotting 6 50 350
5. Typing 6 100 400
6. Printing 6 100 600
7. Photocopying 0.25 200
8. Internet 10 250
9. Transportation 2 300 600
10. Mobile cards 2 100 200
Total 3000