M.Waqas(20-IE-12)
Arslan Ashraf(20-IE-13)
M .Hssaan(20-IE-14)
1
Introduction
Work and time study is a
techniques that tell about
Business efficiency technique
Use for the measurement of
repetitive work
Normally used an attempt to
increase output
Productivity is the ratio of an
aggregate output to a single
input.
2
Techniques to improve
productivity:
o By reducing work content .
o By reducing non valve added
time.
o Proper planning of man,
material and machine.
3
Purpose:
Improve productivity of men machine and material
4
Existing layout
5
Methodology
o Initially plant visit was made and discussions made with manager and observations made
during the visit.
o The ineffective time related with the manufacturing and assembly plant layout was found
to be more.
o The existing methods involved in gate valve body manufacturing and assembly
workstation were studied and finding improved methods using work study techniques.
o Bottle necks were identified at various stages of the existing layout. Flow process chart
was drawn through several orientation visits to the plant and getting familiar with the
different work elements.
6
o Flow process chart was drawn for both existing and proposed
system.
o With the work study, results of both existing as well as
proposed method were compared which results in reduction in
total cycle time to manufacture and assemble one gate
assembly.
7
07/17/2023 8
Proposed Layout:
9
07/17/2023 10
3.1.1 Comparison of existing layout and proposed layout
Operation 10 10
inspection 3 0
transportation 6 5
delays - -
storage 2 1
Value added time 325 333
Non value added time 125 44
Distance travelled 400 270
11
Comparison of Work elements of existing and Proposed Layouts
500
458
450
400
400
377
350 333
325
300
270
250
200
150
125
100
44
50
11 10 8 6
0
Total VAs VAs Time Distance Travelled(m) Total NVas NVAs Time Lead TIme
Before After
13