The document is an audit report on new site builds and installations prepared by Kiyingi Ivan for MTN. It summarizes case studies on new site builds in Ntare, Kigoyera, and Kibiito Blue. It also provides guidelines on proper cable routing, equipment setup and positioning in the cabinet and on ground. Specifically, it addresses cabinet installation, GPS surge arrestor positioning, cable routing and termination, RRU positioning, grounding, power installation and labeling. The report appreciates the MTN quality assurance team for their recommendations to achieve absolute quality in project deliverables.
The document is an audit report on new site builds and installations prepared by Kiyingi Ivan for MTN. It summarizes case studies on new site builds in Ntare, Kigoyera, and Kibiito Blue. It also provides guidelines on proper cable routing, equipment setup and positioning in the cabinet and on ground. Specifically, it addresses cabinet installation, GPS surge arrestor positioning, cable routing and termination, RRU positioning, grounding, power installation and labeling. The report appreciates the MTN quality assurance team for their recommendations to achieve absolute quality in project deliverables.
The document is an audit report on new site builds and installations prepared by Kiyingi Ivan for MTN. It summarizes case studies on new site builds in Ntare, Kigoyera, and Kibiito Blue. It also provides guidelines on proper cable routing, equipment setup and positioning in the cabinet and on ground. Specifically, it addresses cabinet installation, GPS surge arrestor positioning, cable routing and termination, RRU positioning, grounding, power installation and labeling. The report appreciates the MTN quality assurance team for their recommendations to achieve absolute quality in project deliverables.
8/25/2022 Modernization & New Site Build Installation Quality Audit 2 Training Manual New site builds (Cable routing, RRU On Ground) Cabinet Installation (Positioning, New Cabinet Installation and Equipment Setup) MTS3900 Huawei Cabinet Structure and Equipment Setup (for a 9 RRUs configuration)
Cables routed in accordance with
direction of entry of cables for easy maintenance (for a 9 RRUs configuration)
Space left to create work area for
the BBU cabling e.g. sagging CPRIs
Plastic label extended from the
blue/black part of the RRU power cable to prevent cutting during cable tie cutting
Only paper labels are installed at
the blue/black part The RRUs on ground should be raised leaving not more than half a foot Prepared by Kiyingi Ivan, i84042998 2022 MTN RAN of the pole 8/25/2022 Modernization & New Site Build Installation Quality Audit 3 Training Manual New site builds (Cable routing, RRU On Ground) Cabinet Installation (Positioning, New Cabinet Installation and Equipment Setup) MTS3900 Huawei Cabinet Structure and Equipment Setup (for a 6 RRUs configuration)
Cables routed in accordance with
direction of entry of cables for easy maintenance (for a 6 RRUs configuration)
Prepared by Kiyingi Ivan, i84042998 2022 MTN RAN
8/25/2022 Modernization & New Site Build Installation Quality Audit 4 Training Manual New site builds (Cable routing, RRU On Ground) Cabinet Installation (GPS Surge arrestor positioning and installation)
GPS Surge arrestor should be fastened at
this point and all grounding cables fastened properly
Prepared by Kiyingi Ivan, i84042998 2022 MTN RAN
8/25/2022 Modernization & New Site Build Installation Quality Audit 5 Training Manual New site builds (Cable routing, RRU On Ground) Cabinet Installation (CPRI cable routing)
Wrong: The CPRI Cables scattered and
are blocking the slots
Correct: The CPRI Cable are bound
together
Prepared by Kiyingi Ivan, i84042998 2022 MTN RAN
8/25/2022 Modernization & New Site Build Installation Quality Audit 6 Training Manual New site builds (Cabinet grounding)
Main cabinet grounding
should be installed here then WRONG RIGHT cascade the cage bus bar from here
The cabinet should be
grounded At this point
Prepared by Kiyingi Ivan, i84042998 2022 MTN RAN
8/25/2022 Modernization & New Site Build Installation Quality Audit 7 Training Manual New site builds (Cable routing, RRU On Ground) RRU On ground(Positioning and cable routing) RRU5905 installed on the ground with feeder cables running along side the CPRI cable that enter the cabinet directly
RRUs on ground extended up the pole
leaving not more than 15 cm, with in which the GPS can be installed
The RRUs on ground CPRI cables are
secured firmly on the pole in such a way not to interfere with Jumpers
Prepared by Kiyingi Ivan, i84042998 2022 MTN RAN
8/25/2022 Modernization & New Site Build Installation Quality Audit 8 Training Manual New site builds (Cable routing, RRU On Ground) RRU On ground(Positioning and cable routing) Feeder / CPRI cables along the cable tray revisions
Clamps installed at the
corners of the cable tray to prevent cable damaging
All jumper cables are well clamped as
they enter the cabinet leaving no cable suspended Feeder connectors are terminated at the same level at a place not less than 15 cm
Prepared by Kiyingi Ivan, i84042998 2022 MTN RAN
8/25/2022 Modernization & New Site Build Installation Quality Audit 9 Training Manual New site builds (Power installation) Labeling and Cable Termination
Wrong: The power cable
has exposed copper which causes sparks that may lead to MCB tripping after heating up
DCDUs and power cable to be
labeled (NPL or PL), this helps MS team during troubleshooting and swaps by easy identification
Correct Cable terminated firmly
Prepared by Kiyingi Ivan, i84042998 2022 MTN RAN
8/25/2022 Modernization & New Site Build Installation Quality Audit 10 Training Manual Appreciation Thanks To The MTN Quality Assurance Team; • Hassan Kintu • Jacob Lukwago • Philip Katongole
• For the recommendations As Summarized Jointly In This Report, Let’s
Continue To Work Together To Achieve Absolute Quality In The All Project Deliverables
Prepared by Kiyingi Ivan, i84042998 2022 MTN RAN
8/25/2022 Modernization & New Site Build Installation Quality Audit 11 Training Manual