INITIAL PRESSURE:
FINAL PRESSURE:
TIME INTERVAL:
TIME STARTED:
TIME FINISHED:
MAKE:
CAPACITY:
DATE:
TESTING AREA: DCS and HEAT EXCHANGER AREAS
SYSTEM: CHILLED WATER LINE (ALL)
TESTING MEASURE: PRESSURIZED WATER TESTING
READING:
START: __________________ FINISHED: _________________
DATE:
TESTING AREA: HOTEL HEX
SYSTEM: CHILLED WATER LINE ( SUPPLY )
TESTING MEASURE: AIR PRESSURE TESTING
READING:
START: __________________ FINISHED: _________________
DATE:
TESTING AREA: BPO2 HEX
SYSTEM: CHILLED WATER LINE ( RETURN )
TESTING MEASURE: AIR PRESSURE TESTING
READING:
START: __________________ FINISHED: _________________
DATE:
TESTING AREA: G2 HEX
SYSTEM: CHILLED WATER LINE ( RETURN )
TESTING MEASURE: AIR PRESSURE TESTING
READING:
START: __________________ FINISHED: _________________
DATE:
TESTING AREA: G2 HEX
SYSTEM: CHILLED WATER LINE ( SUPPLY )
TESTING MEASURE: AIR PRESSURE TESTING
READING:
START: __________________ FINISHED: _________________