Professional Documents
Culture Documents
No :
CLIENT : EMAAR PROPERTIES PJSC Rev. No : 0
CONSULTANT : HIDI RAE CONSULTING ENGINEERS INC Date : 13 NOV 2022
CONTRACTOR : DUBCO CONSTRUCTION LLC Page No : Page 1 of 8
Index
1. Introduction 3
3. Standards 4
5. Test Execution 6
6. Demonstration Procedures 8
SERVE POINT ENERGY TECHNICAL SERVICES LLC, PO Box 13334 , Dubai UAE
.
PROJECT: SOCIO PARK HEIGHTS III
PROJECT : SOCIO PARK HEIGHTS III Doc. No :
CLIENT : EMAAR PROPERTIES PJSC Rev. No : 0
CONSULTANT : HIDI RAE CONSULTING ENGINEERS INC Date : 13 NOV 2022
CONTRACTOR : DUBCO CONSTRUCTION LLC Page No : Page 3 of 8
METHOD STATEMENT
Fan Coil Unit Testing
1. INTRODUCTION
1.1 The following test procedure has been prepared to lay down the minimum
specification for the site testing and commissioning of Fan Coil Units (FCU) .
1.2 The objective of this procedure is to verify that the installation and operation of the
FCU is as per design intent.
1.3 The tests proposed in this document shall be read in conjunction with the
Consultant Technical Specification and are not exhaustive, nor are they to be
considered an acceptable alternative to the standard site tests performed by the
manufacturer.
2.3 The following test instrumentation & tools shall be required to undertake the tests
detailed within this procedure:
SERVE POINT ENERGY TECHNICAL SERVICES LLC, PO Box 13334 , Dubai UAE
.
PROJECT: SOCIO PARK HEIGHTS III
PROJECT : SOCIO PARK HEIGHTS III Doc. No :
CLIENT : EMAAR PROPERTIES PJSC Rev. No : 0
CONSULTANT : HIDI RAE CONSULTING ENGINEERS INC Date : 13 NOV 2022
CONTRACTOR : DUBCO CONSTRUCTION LLC Page No : Page 4 of 8
3. STANDARDS
3.1 The following standards have been referenced when preparing these test
procedures:
1. Confirm all packing material has been removed from unit and that air inlets
and discharges are free from obstruction.
2. Confirm there is no visual damage to the external casing of the unit or
damage to the internal parts.
3. Confirm all transit bolts, wedges etc. have been removed from Fan, Motor’s
and isolation mountings and that they are free to move.
5. Confirm the electrical connections are correct and that the unit is isolated.
6. Check power supply is present at the unit at the correct voltage. Verify
circuit has been tested and approved by the electrical contractor.
8. Check that fresh air supply (where applicable) is installed in room and
confirm that airflow has been set to the correct value.
SERVE POINT ENERGY TECHNICAL SERVICES LLC, PO Box 13334 , Dubai UAE
.
PROJECT: SOCIO PARK HEIGHTS III
PROJECT : SOCIO PARK HEIGHTS III Doc. No :
CLIENT : EMAAR PROPERTIES PJSC Rev. No : 0
CONSULTANT : HIDI RAE CONSULTING ENGINEERS INC Date : 13 NOV 2022
CONTRACTOR : DUBCO CONSTRUCTION LLC Page No : Page 5 of 8
Confirm chilled water systems and coils have been hydrostatically tested in
accordance with the commissioning & testing specification and that there is no
evidence of leakage at joints or valves.
SERVE POINT ENERGY TECHNICAL SERVICES LLC, PO Box 13334 , Dubai UAE
.
PROJECT: SOCIO PARK HEIGHTS III
PROJECT : SOCIO PARK HEIGHTS III Doc. No :
CLIENT : EMAAR PROPERTIES PJSC Rev. No : 0
CONSULTANT : HIDI RAE CONSULTING ENGINEERS INC Date : 13 NOV 2022
CONTRACTOR : DUBCO CONSTRUCTION LLC Page No : Page 6 of 8
5. TEST EXECUTION
Perform the following Commissioning/Performance Test for each fan coil unit:
A. Static Checks
Check and Test Sheets for ducted fan coil unit will be completed
by the Serve Point Site Engineer.
SERVE POINT ENERGY TECHNICAL SERVICES LLC, PO Box 13334 , Dubai UAE
.
PROJECT: SOCIO PARK HEIGHTS III
PROJECT : SOCIO PARK HEIGHTS III Doc. No :
CLIENT : EMAAR PROPERTIES PJSC Rev. No : 0
CONSULTANT : HIDI RAE CONSULTING ENGINEERS INC Date : 13 NOV 2022
CONTRACTOR : DUBCO CONSTRUCTION LLC Page No : Page 7 of 8
SERVE POINT ENERGY TECHNICAL SERVICES LLC, PO Box 13334 , Dubai UAE
.
PROJECT: SOCIO PARK HEIGHTS III
PROJECT : SOCIO PARK HEIGHTS III Doc. No :
CLIENT : EMAAR PROPERTIES PJSC Rev. No : 0
CONSULTANT : HIDI RAE CONSULTING ENGINEERS INC Date : 13 NOV 2022
CONTRACTOR : DUBCO CONSTRUCTION LLC Page No : Page 8 of 8
6. DEMONSTRATION PROCEDURES
The commissioning engineer will ensure that the following works are carried out:
6.1 The final tested and balanced results are demonstrated to the accepting authority
on a random spot check basis, and that repeatability of readings is proven within
the accepted tolerance.
6.2 Submittal of all records of data obtained during testing, adjusting and balancing in
accordance with, and on, the approved forms.
SERVE POINT ENERGY TECHNICAL SERVICES LLC, PO Box 13334 , Dubai UAE
.
PROJECT: SOCIO PARK HEIGHTS III