Professional Documents
Culture Documents
Date: - _______________________
Contents
1. Executive summery ……………………………………………………………………………………………………………………2
2. Background Information......................................................................................................................4
2.13Project Performance……………………………………………………………………………..12
2.14 Environmental Issues.....................................................................................................................20
2.15 Organization, Management and Manpower................................................................................20
2.16 SWOT Analysis...............................................................................................................................25
2.17 Mitigation Measures.......................................................................................................................26
2.18 Conclusions and Recommendations............................................................................................27
The project originally established to process sheep and goat skin up to wet blue and
pickle stage with a total cost of Birr 10.9million of which Birr 6.9million was DBE loan
and the remaining 4million was the promoter’s equity contribution. The purpose of the
loan was to cover costs of building and construction, machineries and equipments,
vehicles, office furniture, power installation and to cover partial requirement of
working capital. After utilization of loan and equity, the project commenced operation
on July 2005.
After most of the machineries were installed, the promoter requested for the
second time an additional working capital loan of Birr 5 million. The Case
Team after a thorough analyses and discussion with the promoter, proposed
Birr 5 million and the loan was approved on exceptional bases to release in two
disbursement.
The bank has disbursed the first loan disbursement of Birr 2,526,783 as per
the agreement. Out of the total disbursed loan the Plc allotted Birr
1,342,713.41 for purchase of raw hides & skins and chemicals as per the plan
and the remaining Birr 746,000 expend on over head costs which were out of
plan. And out of the remaining birr 438,069.59 only birr 263,428.37 is spent
for purchase of chemical but the remaining amount is used for other
unplanned expenses again.
Relating with the production, out of the total 20,978 psc of purchased raw
materials there is only 4,925 psc of raw materials in different process stages.
This shows that the difference in between the two figures has been brought to
the market, but the promoter is not volunteer to show the sales of the
company.
As at December 29, 2014 the company has a total loan outstanding of Birr
20,002,075.20 of which Birr 17,969,940.58 is principal and Birr 2,032,134.62 is
Interest. Out of this Birr 4,820,829.96 is principal in arrears and Birr 1,851,601.97 is
interest in arrears. This shows that the company has left behind three installments as
per the terms and conditions set by the loan agreement and the next payment is on
January 31, 2015.
During last follow up it was observed that the project is performing under capacity due
major machineries are uninstalled. Due to that the second approved disbursement
Birr 2.5 million of working capital, which was conditioned by the finalization of the
above stated machineries, was not recommended to be disbursed. Instead the PLC
managers are told to finalize the installation for coming for the aforementioned
disbursement. Accordingly currently the installation of these machineries is finalized
and the project is under operation during field visit on November 24, 2014 of current
follow up.
Generally, at this time the installation of most of the machineries are finalized
and the company is under operation. But due to unwillingness of the PLC
managers to abide to the terms and conditions that was agreed between them
and the Bank and not to give the sales of the company and utilization of the
loan the project can’t rehabilitate as required. And therefore to rehabilitate the
project ones for most the bank should inform the promoter to submit the sales
of the company and its utilization unless to settle the loan in arrears before
second disbursement.
2.4 Objective of the project: To process finished hides and skins up.
2.5 Status of Business License
2.5.1 Date of original registration/issuance 20/10/1995
2.5.2 Date of Renewal:- _2005 E.C
2.5.3 Principal Registration Number:-09/2/13528/99
The time interval for insurance renewal and collateral valuation is one year. Business and
property mortgage registration is five and ten years, respectively. Land lease fee is
normally every year depending upon who gives the land use right. If the land is rented
from farmers’ arrangements may vary as per the negotiation between the concerned
parties.
Table 3: NPLs Classification as per NBE’ Standard (as of December 30, 2014)
Amount (Birr) Age in current
Classification/category
Arrears/principal status (days)
Pass
Special Mention 4,820,829.96
Comment on NPLs loan classification
As per the NBE’s classification the loan with less than 180 days in arrears is classified as
pass status but since the project is rescheduled and is found in PRLRP it is categorized
under substandard.
2.8.7 Loan Collections (in Birr):- 7,637,922.04
During the original loan, Birr 21,394 was reallocated from machinery to working
capital and also the client has invested additional Birr 277,269.60 for
procurement of vehicles because of purchase of truck.
During the first additional, for the construction of chemical store, it was planned
that, the promoter to contribute Birr 639,784.96 however, due to design change the
cost for chemical store construction decreased to Birr 381,002.44.
2.12 Actual project cost
NB: - The valuation of the project is out dated and should be evaluated as much as possible.
After most of the machineries were installed, the promoter requested for the second
time an additional working capital loan of Birr 5 million. The Case Team after a
thorough analyses and discussion with the promoter, proposed Birr 5 million and
the loan was approved on exceptional bases. That was due to the inability of the
PLC to contribute the required equity contribution of Birr 9.5 million through cash
up front and/or in kind. The loan contract was signed on October 25, 2013, after
the promoter paid interest arrears. However, the registration of the loan contract at
Modjo Municipality was finalized on December 3, 2013.
The bank has disbursed the first loan disbursement of Birr 2,526,783 as per the
agreement. Out of the total disbursed loan the Plc allotted Birr 1,342,713.41 for
purchase of raw hides & skins and chemicals as per the plan and the remaining
Birr 746,000 expend on over head costs which were out of plan. And out of the
remaining birr 438,069.59 only birr 263,428.37 is spent for purchase of chemical but
the remaining amount is used for other unplanned expenses again.
It has to be note that out of Birr 5 million, Birr 2,200,000.00 was disbursed for the purchase
of raw hides and skins, and Birr 326,782.26 was disbursed for purchase of chemicals and
currently there is about Birr 2,473,217.38 in Commitment balance as of December 12,
2014.
Source:- which is the stock found in the company during field visit on November 24,2014.
The above figure shows that out of the total 20,978 psc of purchased raw materials there is only 4,925
psc of raw materials in different process stages. This shows that the difference in between the two
figures has been brought to the market, but the promoter is not volunteer to show the sales of the
N.B:- But by the letter dated 16/04/2007 E.C Ref.No. መግ/0991/07 the company reported
the stock of the project as follows.
3 Total 1,424,150.08
The company should finalize finishing part of primary treatment plant, even if it
started to use it;
The borrower should finalize the installation of the PP drum boiler and
measuring machine should be repaired;
The company should start to sale its products as much as possible, and repay
the due loan amount;
The case team should discuss with the management of the company before July
20,2014;
The Bank should communicate with stake holders like LIDI, Ministry of
Industry and the others regarding the specific problems of the company and
how to overcome them;
The company should be audited by an external auditor and summit the audit
report to the bank; and also it needs to submit provisional financial statement
monthly; and
If the project is not revitalized as per the plan after undertaking the above
measures the bank should think for other mitigating measures.
Additionally it was planned to take action according to the following action plan program
Call the promoters Before July 15, 2014 for discussion on the way to rehabilitate and bring the project
in normal truck and loan recovery.
Communicating with the stake holders like LIDI, Ministry of Industry Before August 31, 2014
regarding the company’s problem.
Installation of the PP drum, boiler, measuring machine and finalize finishing
part of primary treatment plant Before September 30, 2014.
Valuation of the company Before December 31, 2014.
Start to sale its products Before November 30, 2014.
Deliver audited financial statement Before September 30, 2014. And
The promoter has to give attention to successfully rehabilitate the project continuously.
The wastes that are released from the tannery factory are known to be highly toxic for human
health and animals unlike. Currently most of the demolished part of treatment plant is
maintained there were no significant leakages to the surrounding environment.
4.1. Organization
General
Manager
Additionally currently the company employed an Indian production manager with the
advice and support of LIDI which helps the company to manage its production quality and
overall production process of the company.
Comments on Variation (if any): The reduced amount is due to depreciation. Whereas
furniture and fixture are not evaluated by the engineers and the working capital is not
determined
Source: The projected fig is from Working capital loan and loan repayment Rescheduling
proposal dated October 2013 and the actual figure is from the Provisional financial
statement of companies report.
* Stands for profit before interest and tax** Stands for profit before tax
1. Qualification and experience of 2. Unable to fulfill preconditions set by the Bank to command on the
second disbursement
the general manager and finance
manager.
3. Improper use of the first disbursement and difficulty of rectifying it
4. Unable to complete the implementation as per the plan
2. Employing qualified production
manager 5. There is no export of finished leather
6. Low Employment creation
7. Lack of willingness to give information and audited financial
statements
8. Unavailability of systemized recording system
9. Low equity base
Opportunities Threats
The installation of all machineries that are purchased through Bank loan are believed to help produce
high quantity finished leather and expected to increase the sales volume of the company. The
company can operate properly and settle the loan beyond generating foreign currency to the country
and employee more labor power. But, the major machineries of the company has not yet installed.
Thus, the company has to install machineries properly as per the signed undertaking and discussing
openly with the Bank if any problem exists.
The company expected not to face problems regarding the market since Ethiopian leather products are
being expected at international market on the condition that the products have necessary quality. The
Plc should keep the financial and operational record of the company. It needs to avail the audited
financial statement to the Bank on time as per the agreement it entered with Bank. It needs to report
all problems that it might face in due course of operation.
Regarding the utilization of the disbursed loan the company is expected to submit the utilization of
loan unless the bank should take an immediate action.
As per the loan agreement held on December 06, 2013 the company has left three loan repayments
behind as per the agreed terms and conditions.
The project was originally established to process sheep and goat skin up to wet blue and
pickle stage for export market. The total cost of the project is Birr 10.9 million, of which
Birr 6.9 million is DBE loan and the remaining Birr 4 million is the promoter’s equity
contribution. The purpose of the loan was to cover costs of building and construction,
machineries and equipments, vehicles, office furniture, power installation and to cover
partial requirement of working capital. After utilization of loan and equity, the project
commenced operation on July 2005.
The government of Ethiopia has imposed 150% tax on export of semi-processed hides
and skins, which required the PLC to upgrade its final product from wet blue and pickle
to finished leather. But that has created a financial problem on the PLC. To minimize
the financial problem, the promoter requested an additional loan to upgrade the finished
leather and leather products.
By appraising the request of the promoter, the Bank approved Birr 11.5million for the
purchase of machineries on the loan contract signed on October 2011 in order to cover
the production of crust, as an additional loan, and from the promoter equity it was
planned to construct an additional building for chemical store and for the purchase of
some machineries from local market. All the required machineries were purchased and
the planned construction for chemical store also constructed. Currently, all of the
required machineries are purchased and installed except PP dyeing & re-tanning drum,
and boiler.
Since its establishment, the Bank injected two additional loans and allowed
three loan repayment rescheduling. On the other hand, the total loan collection
of the project is Birr 7.6 million and currently the project is three loan
repayments behind schedule and the next payment is going to due on January,
2015.
By a loan contract signed on October 25, 2014 the bank approved the second
additional working capital loan of Birr 5 million. Which was planned to be
Starting from January 2014 up to June 2014 the company bought around
14,377.70 pcs of raw hides and skins, out of which, 586, 12,053 and 1739 pcs
are Number of hides and sheep and goat skins respectively, which the company
paid a total of Birr 1,013,821.60 for the same. But after February 2014 onwards
there is no information regarding purchase of raw materials, and a chemical of
Birr 681,487.98 is bought within the same period.
As of November 24, 2014 the stock balance of the company is 1500 pcs of raw
hides at wet blue stage and 1343 pcs of goat and sheep skin at wet blue stage.
Additionally there are about 982 and 1100 number of pickle and shave sheep
skins, respectively.
Regarding the management and manpower, the company has qualified and
experienced personnel, and currently, they have opened employment opportunity
for 49 workers. Additionally the company has got an Indian production Manger
by the support of LIDI.
The company didn’t submit the audited financial statement due to this reason it
is difficult to compare the financial status of the company in relation with the
planned financial statement of the project. Even if the provisional financial
statement of the company has submitted since its reliability is in question and
most of the report is out of reality it is difficult to take it as real financial
statement of the company.
As of December 30, 2014 the total outstanding loan balance of the company is
Birr 20,002,075.20, of which Birr 13,149,110.62 is undue principal, Birr
180,532.65 is undue interest and, Birr 4,820,829.96 and 1,851,601.97 are
due principal and interest, respectively.
On the other hand, the evaluation of collateral of the project was done before a year on
July 2013, as per this valuation the collateral coverage of the project is 87% ((fixed
On the other hand on the last follow up to rehabilitate the project and to bring it
to the right track It was planned to communicate with the stake holders and the promoters to
discuss on the way to rehabilitate and bring the project in normal truck and loan recovery. Accordingly the
case team has discussed with the promoters and LIDI with the specified time limit as a result the promoters
agreed to take actions according to the action plan set by the follow up.
During last follow up it was observed that the project is performing under capacity due
major machineries are uninstalled. Due to that the second approved disbursement Birr
2.5 million of working capital, which was conditioned by the finalization of the above
stated machineries, will not recommended to be disbursed. The PLC managers are told
to finalize the installation for coming for the aforementioned disbursement. But currently
the installation of these machineries is finalized and the project is under operation
during field visit on November 24, 2014 of current follow up.
Generally, even if the installation most of the machineries are finalized company
is operating under performance and not performing as per the plan, and the bank
has exerted the possible maximum effort to rehabilitate the project but due to
unwillingness of the PLC managers to abide to the terms and conditions that was
agreed between them and the Bank the project cant rehabilitate as required. In
addition to this the promoters are not willing to give appropriate information to
the bank which hinders the rehabilitation of the company.
The responsible case team after checking the current condition of the company and
discussed on the details of this follow-up report, it recommended the following:
The company should give appropriate information relating to the sales of the
company product and the general utilization of first disbursed loan.
The company should be audited by an external auditor and summit the audit
report to the bank; and also it needs to submit provisional financial statement
monthly; and
The valuation of the project should be done before December 31, 2014.
If the project is not revitalized as per the above recommendations it is not
recommended to release the requested second disbursement and the bank
should think for other mitigating measures.