• This maximum Limit on 𝝉𝒗 ≤ 𝝉𝒄𝒎𝒂𝒙 is to avoid the failure 𝝉𝒄𝒎𝒂𝒙 1.8 1.9 2.2 2.3 2.5 WSM
of concrete due to crushing of concrete due to diagonal
compression failure.
M K SINGH MADE EASY - RCC - GATE / IES 5 M K SINGH MADE EASY - RCC - GATE / IES 6
1
11/9/2020
SHEAR 4. Design sHEAR strength of concrete 𝝉𝒄 SHEAR Value of 𝝉𝒄 - lsm – table -19 / p-73
M K SINGH MADE EASY - RCC - GATE / IES 7 M K SINGH MADE EASY - RCC - GATE / IES 8
M K SINGH MADE EASY - RCC - GATE / IES 9 M K SINGH MADE EASY - RCC - GATE / IES 10
M K SINGH MADE EASY - RCC - GATE / IES 11 M K SINGH MADE EASY - RCC - GATE / IES 12
2
11/9/2020
M K SINGH MADE EASY - RCC - GATE / IES 13 M K SINGH MADE EASY - RCC - GATE / IES 14
M K SINGH MADE EASY - RCC - GATE / IES 15 M K SINGH MADE EASY - RCC - GATE / IES 16
SHEAR Torsion
SHEAR
Cases of torsional moment
• 1. Beam with eccentric loading • Any Moment acting in transverse direction to
• 2. End Beams with slab Longitudinal axis of the member is called Torsional
• 3. Curved Beams in plan with any kind of loading Moment.
• 4. Fixed beams with secondary beams • If a Beam of size B x D (d) is to be designed for
• 5. Fixed beams with cantilever slab on one side of beam only 1 Bending Moment = Mu
2. Shear Force = Vu
3. Torsional Moment = Tu
M K SINGH MADE EASY - RCC - GATE / IES 17 M K SINGH MADE EASY - RCC - GATE / IES 18
3
11/9/2020
SHEAR SHEAR
1. Equivalent shear force
•(b) 41.3.2 ---- if 𝛕𝐯 < 𝛕𝐜 the beam does
•1. Equivalent Shear Force not need any shear reinforcement. In
1.6 Tu this case Minimum shear reinforcement
•Vue = Vu +
b shall be provided.
•2. Nominal shear stress
𝐕𝐮𝒆
𝛕𝐯 = ≤ 𝛕𝐜𝐦𝐚𝐱 •(c) 41.3.3 ----- if 𝛕𝐜𝐦𝐚𝐱 > 𝛕𝐯 > 𝛕𝐜
𝐁𝐝
(a) if 𝛕𝐯 > 𝛕𝐜𝐦𝐚𝐱 the beam shall be the beam shall be designed for Moment
redesigned. Size of beam shall be changed. and Shear both as per Pr 41.4
M K SINGH MADE EASY - RCC - GATE / IES 19 M K SINGH MADE EASY - RCC - GATE / IES 20
SHEAR
IS 456