Cycle Time Takt Time Chart
Cycle Time Takt Time Chart
Cycle Time I
1.4
1.2
1
0.8
0.6
0.4
0.2
0
Step 1
Cycle Time Ideal Cycle Time (Min) Takt Time (Min)
1.4
1.2
1
0.8
0.6
0.4
0.2
0
Step 1 Step 2 Step 3 Step 4
Customer Demand 340 Units
Scheduled Time 340 MInutes
Takt Time 1 minutes
Actual time 280 minutes
Units run 280 units
Cycle Time 1 minutes
Downtime 60 minutes
Improved time 330 minutes
Units run 380 units
Cycle Time 2 0.868421 minutes 380 330
Downtime 5 40 6
Changeover time 1 20 4