Professional Documents
Culture Documents
The Extradosed pre-stress bridge concept is relatively new in the field of Structural
and Bridge Engineering. The first Extradosed Bridge was constructed by Japan in
1994. Since, it becomes a unique type of structure for its advantages over other
bridges. In this paper, detail study is carried out on historical context, origin and
exist worldwide. To replace the existing bridge along the Connecticut Turnpike in
U.S. with a new signature bridge with a 100-year service life expectancy the design
team was tasked with creating a “memorial quality” structure commemorating the
veterans of Pearl Harbor. The result was the final selection of a 10-lane Extradosed
bridge spanning New Haven Harbor. The contractors at the Pearl Harbor Memorial
Bridge in New Haven, Connecticut, have battled relentless winters to complete the
first Extradosed bridge in the United States. Their success hinged on detailed winter
concreting plans developed to work safely and efficiently during very cold weather.
The plans contain multiple concrete mix designs as well as specific heating
ranges necessary to produce quality concrete. The plans have shown to be effective,
1
1. INTRODUCTION
From 1994 to 2008, over fifty extradosed bridges have been constructed worldwide,
and the preferred proportions and cable arrangements have evolved. While there are
many articles available on the design of specific extradosed bridges, very little has
been published on their design from a general perspective. The intrados is defined as
the interior curve of an arch, or in the case of cantilever-constructed girder bridge, the
soffit of the girder. Similarly, the extrados is defined as the uppermost surface of the
arch. The term ‘extradosed’ was coined by Jacques Mathivat (1988) to appropriately
which external tendons were placed above the deck instead of within the cross-section
There is some debate over the boundary between cable-stayed and extradosed
bridges. Visually, extradosed bridges are most obviously distinguished from cable-
stayed bridges by their tower height in proportion to the main span. Extradosed
bridges typically have a tower height of less than one eighth of the main span,
Placing concrete in cold weather is problematic. The contractors at the Pearl Harbor
complete the first extradosed bridge in the United States. Their success hinged on
detailed winter concreting plans developed to work safely and efficiently during very
cold weather. The plans contain multiple concrete mix designs as well as specific
temperature ranges necessary to produce quality concrete. The plans have shown to
2
2. STRUCTURAL CHARACTERISTICS COMPARISON
A girder bridge is a basic, common type of bridge where the bridge deck is built on
top of such supporting beams, that have in turn been placed on piers and abutments
that support the span of the bridge. The types of beams used for girder bridges are
usually either I-beam girders or box girder beams that are made of steel or concrete
and shaped like an open box. Girder bridges are most commonly used for straight
bridges that are 10 m to 200 m long, such as light rail bridges, pedestrian overpasses,
or highway fly-overs. The load transmission is in a way that the stiff girder without
any stay cable carries all dead and live loads. The depth of the girder box will vary
Cable-stayed bridge, bridge form in which the weight of the deck is supported by a
number of nearly straight diagonal cables in tension running directly to one or more
vertical towers. The towers transfer the cable forces to the foundations through
vertical compression. The tensile forces in the cables also put the deck into horizontal
3
compression. The cable-stayed bridge ranks first for a span range approximately from
175 to 400 m. The ratio of pylon height to central span length in cable stayed bridge
is normally 1/5. In the case of cable stayed bridges, a major part of the dead and live
loads is carried by the stay cables. The depth of the bridge will be same at all sections.
An extradosed bridge employs a structure that combines the main elements of both
a girder bridge and a cable-stayed bridge. The extradosed bridge form is mostly
suited to medium-length spans between 80 m and 200 m. The ratio of pylon height to
central span length will be 1/9 to 1/10. An extradosed bridge possesses partial roots
from cable stayed bridges and girder bridges, in which the dead loads are distributed
between the stay cables and the girder, and a major part of the live load is carried by
the stiff girder. The depth variation will be based on the location and bridge
4
Table 1: Structural characteristics comparison
Ratio of
span length
DL&LL
LL -stiff
girder
stay cables
5
3. PEARL HARBOR MEMORIAL BRIDGE
When originally constructed in 1958, the existing six-lane Pearl Harbor Memorial
Bridge (locally known as the Q-Bridge) was the largest bridge along the Connecticut
Turnpike and included the longest plate girder span in the United States. However,
the existing bridge currently suffers from structural deficiencies and can no longer
accommodate today’s high-traffic volumes of over 160,000 vehicles per day, nearly
four times the volume of traffic it was originally designed to serve. As a result, a new
bridge was needed and planning for its replacement was initiated by the Connecticut
Pearl Harbor Memorial Bridge is the focal point of the $2.0 billion I-95 New Haven
bridge, the program includes operational, safety, and capacity improvements to 7.2
was made to replace the existing bridge with a new signature bridge with a 100-year
service life expectancy. The new bridge would continue to be named the Pearl Harbor
Memorial Bridge, and the design team was tasked with creating a “memorial quality”
structure commemorating the veterans of Pearl Harbor. The result was the final
bridges, behave differently and have several key distinctions. The extradosed design
6
utilizes shorter towers and a flatter stay-cable inclination than traditional cable-stayed
bridges, which results in the deck system being the primary resistance to dead and
live loads. For the New Haven Harbor crossing, the extradosed bridge design allowed
for increasing the main span to improve navigation and minimize environmental
impacts. The limited tower heights afforded by the extradosed design avoids
impacting air traffic from TweedNew Haven airport located east of the bridge,
whereas the taller towers of a traditional cable-stay bridge would have likely
infringed on FAA-required flight path clearances. The design was completed with bid
packages prepared for two alternatives for the main span; a three-span concrete
concrete alternate, which began in April 2008, with construction of the northbound
in-water foundations. The northbound bridge was recently completed and opened to
traffic in June 2012. It is the first extradosed bridge constructed in the United States.
Construction of the southbound bridge will occur following demolition of the existing
configuration of the bridge’s harbor crossing consists of a 157-m-long (515 ft) main
span with adjacent 75.85-m-long (249 ft) approach spans, providing 19.5 m (64 ft) of
vertical clearance over the approximately 73-m-wide (240 ft) navigation channel.
Beyond the main 308.7-m-long (1013 ft) harbor crossing, approach spans extend 484
m (1588 ft) to the west, and another 624 m (2047 ft) to the east, for an overall bridge
7
Figure 5: Pearl Harbor Memorial Bridge
Segmental construction of the main span superstructure was performed utilizing the
segments are typically 4.36 m (14.3 ft) long, range from 29.9 to 33.6 m (98 to 110 ft)
wide, and have a nominal depth of 3.5 m (11.5 ft) that increases to 5 m (16 ft) at the
featuring Type III cement for high early strength, a design compressive strength of 41
MPa (6.0 ksi), and 7% silica fume to decrease permeability. The northbound and
southbound concrete box-girder segments will each ultimately carry five 3.6-m-wide
(12 ft) lanes of traffic, an auxiliary lane varying in width, and two 3.6-m-wide (12 ft)
southbound bridge, the northbound segments will temporarily carry three lanes of
traffic in both directions. The initial concrete segments located at the tower piers are
referred to as “pier tables,” and contain internal diaphragms that transfer the
8
superstructure loads to disk bearings supported on the tower pier strut beams. The
pier tables were lengthened to 15.9 m (52 ft) during construction to include the first
pair of typical segments, creating additional deck area to ease installation of form
travelers on both ends of the pier table. Four travelers were employed, allowing for
The 54,500 kN (12,300 kip) bearings beneath the pier tables are the world’s largest
external tendons at stay-cable locations that are deflected through the two central
vertical webs of the section. ASTM A416M, Grade 1860, low-relaxation strands are
utilized throughout. The four longitudinal cantilever tendons anchoring in the top slab
of both the back span and main-span segments were stressed after segments achieved
ft). The 19-strand draped transverse external tendons were provided to transfer
superstructure forces to the stay-cables, and were stressed after casting the stay
9
3.2. Stay-Cable System
The northbound and southbound main span superstructures are each carried by a
series of 64 individual stay cables parallel to each other in a “harp” pattern. The stays
anchor in pairs to the edge beams of the cast-in-place concrete segments and to the
steel anchor boxes within the tower legs. Each stay consists of 48 individual 15.2-
mm-diameter (0.6 in.), 7-wire, low-relaxation strands up to 66.5 m (218 ft) in length,
coating for corrosion protection during the strand manufacturing process. These 48
strands are, in turn, encased in a co-extruded HDPE sheathing pipe with an outer
diameter of 225 mm (9 in.) that remains ungrouted during its service life. Stay-cable
strand installation was performed using the elongation method to control variations in
individual strand force, and then stressed to 60% maximum ultimate tensile strength
(MUTS) from within the tower anchor boxes using monostrand jacks. The 60%
MUTS limit for the cable strands is higher for the extrodosed bridge design than in
conventional cable stayed bridges, which utilize an upper stress limit of 45% MUTS.
Because of the geometric layout of the stay-cables and the relatively large stiffness of
the box girder superstructure, the stress range and overall contribution to staycable
force from live loads is significantly less than that of a typical cable-stayed structure,
therefore justifying the use of the higher allowable cable stresses on the new
extradosed bridge. Strand stressing was typically performed in three steps. First,
strands were installed and stressed individually to a force level equivalent to 15%
MUTS. This low force level allowed internal “cheese plate” type strand centering
damper assemblies to be slid down the galvanized steel guide pipes near each
anchorage and bolted in their final position. The second stage of tensioning was
performed to approximately 50% of the final stay-cable force. A final, third stage of
10
strand tensioning was then performed to fine-tune the strand forces to closely match
the target stay force value. The adjustable anchorages were then capped and greased.
The contractor at the Pearl Harbor Memorial Bridge developed a cold weather
concreting plan especially for the expected cold winters of Connecticut. This plan was
modified to meet all types of concrete placements necessary during the job. As
defined in the documents submitted to the Connecticut DOT, cold weather concreting
3.3.1.Placement Area
The contractor’s cold weather concreting plan required all contact surfaces of the
11
placements, the approved methods included the use of heaters, glycol tubing, and
insulating blankets Portable heaters were used for the Q Bridge project. They proved
to be very effective and durable. The models used ran on kerosene or diesel, had a
maximum output just under 316,517 kJ(300,000 Btu/h) and an airflow rate of 70
needed to be monitored. For this reason, the heaters were always placed outside the
formwork, and the hot air was transmitted into the forms through a hose system.
A portable heater does a good job of heating the material contained within the
formwork, but the formwork itself must reach the required 1.70C (350F). For heating
the formwork to the required temperature, glycol tubing was used. The tubing is
wrapped along the exterior of the formwork and secured in place by the insulating
blankets. At this jobsite, hydronic ground heaters were used. The term hydronic
simply means heat transfer by means of a circulation fluid. With these construction
hydronic heaters, the unit’s boiler heats a propylene glycol mixture; this mixture is
similar to a food-grade antifreeze that effectively conducts heat. The warm fluid is
then pumped through long loops of heater hose. The heater used at the Q Bridge
operated with 83% efficiency with an output of over 316,517 kJ (300,000 Btu/h).
Although these heaters run on diesel fuel, they have 914 m (3,000 ft) of hose,
allowing the machine to be positioned where exhaust is not an issue. Even with
hydronic heaters, gaining the necessary temperature would not have been possible
without the use of insulating blankets. The blankets were woven, reinforced high-
(0.493 Btu/h.ft2.0F). The cold weather concreting plan required, as a minimum, that
the formwork be double wrapped to ensure that all seams were enclosed and exterior
12
airflow avoided. Although the R-value of the blankets being used is not exceptional,
in combination with this requirement, hydronic heaters, and air heaters, the blankets
system allows for a gradual cooling process after the required concrete strength has
been reached.
Figure 9 : Hydronic heater tubes (foreground) are wrapped around the column formwork
inside the insulating blanket
13
4. ADVANTAGES
This new typology, generally recognized as an intermediate solution between cable
these take advantages of design and constructions methods of the other two
bridges is that this ratio can be accommodated depending upon site constraints
without many impacts. As the structure is similar to Girder Bridge and looks similar
to cable stayed bridge increases the aesthetic quality of extradosed bridges. The
superstructure is simpler and lower tower height than cable stayed bridges the
construction become more easier. Less material consumption of super structure and
less loading on foundation increases the saving and the cost will be less.
14
5. EXTRADOSED BRIDGES IN INDIA
bridge completed 2007 over Hooghly River connecting Howrah with Kolkata,
old Vivekananda Setu opened in 1932. The bridge is named after Sister Nivedita, the
112, Dumdum/Kolkata Airport and northern parts of Kolkata passes over the bridge.
15
5.2. 3rd Narmada bridge
The New Narmada Bridge (or the 3rd Narmada Bridge) is an extra dosed bridge,
constructed at Bharuch, India. It is a 1,344 m (4,409 ft) long bridge, built over
river Narmada on NH-8. The four-lane bridge is a part of larger project involving six
laning of a section of NH-8 between Vadodara and Surat. It runs parallel to Sardar
Bridge. It is the extradosed bridge with the longest spans in India, 144 m (472 ft)
long. The bridge was constructed by Larsen & Toubro and Dywidag Systems
to ₹452 crore or US$57 million in 2020). This bridge was inaugurated by Indian
16
5.3. Arrah-Chhapra bridge
span extradosed bridge in the world with a main bridge length of 1,920 m (6,300 ft).
connecting Arrah in Bhojpur district to Chhapra in Saran district of Bihar state. The
bridge provides a roadway link between the northern and southern parts of Bihar. The
bridge opened for public use on 11 June 2017. As of April 2021, it is the 9th longest
17
6. CONCLUSION
Though extradosed bridges are the extension of girder bridges, have striking visual
resemblance to cable stay bridges. Thus it imbibes the ease of design and construction
associated with girder bridges while giving the option to the designer of enhancing
the aesthetic factors. There is an urgent need to define and clearly distinguish between
extradosed cable system from that of stay cable system. In the absence of the same,
there is a clear danger of adopting stay cable technology for extradosed bridges which
18
7. REFERENCES
1. Foley, T., & Schexnayder, C. (2015). Placing winter concrete: pearl harbor
04014037.
2. Meng, X., & Zhang, C. (2014). Extradosed and intradosed cable-stayed bridges
3. Merritt Jr, R., Bonzon, W. S., & Dunham, J. S. (2012). Pearl Harbor Memorial
Bridge.
dissertation).
5. Ali, K., Katsuchi, H., & Yamada, H. (2021). Comparative study on structural
19