AFCM Work 

Programme Schedule
AF CONDITION MONITORING (M) SDN BHD

PO No. : PO727582 (Calibration Unit 4)

Task Target Date Duration No. Units


Acquire PTW and Vehicle Permit 24/Sep/2012 1 ‐
Dismantle, Verfication and Re‐install CWP Sensors  25/Sep/2012 2 4
Dismantle, Verification and Re‐Install GR Fans Sensors 27/Sep/2012 1 2
Dismantle, Verification and Re‐Install FD Sensors 28/Sep/2012 1 4
Dismantle, Verification and Re‐Install PA Fan Sensors 1/Oct/2012 1 4
Dismantle, Verification and Re‐Install IDF Sensors 2/Oct/2012 1 4
Dismantle, Verification and Re‐Install Mill sensors 3/Oct/2012 2 5
Dismantle, Verification and Re‐Install BFP sensors 4/Oct/2012 2 6
Reporting  8/Oct/2012 4
Printing  11/Oct/2012 1
Total (Target Days) 16
Total No. of Sensor (*lack 1 unit sensor) 29
Vibration Sensor and System Verification Test Programs
Target Date Duration

Acquire PTW and Vehicle Permit 24/9 1

Dismantle, Verfication and Re‐install CWP Sensors 25/9 2

Dismantle, Verification and Re‐Install GR Fans Sensors 27/9 1

Dismantle, Verification and Re‐Install FD Sensors 28/9 1

Dismantle, Verification and Re‐Install PA Fan Sensors 1/10 1

Dismantle, Verification and Re‐Install IDF Sensors 2/10 1

Dismantle, Verification and Re‐Install Mill sensors 3/10 2

Dismantle, Verification and Re‐Install BFP sensors 4/10 2

Reporting 8/10 4

Printing 11/10 1