We are pleased to submit herewith our construction proposal for the above mentioned
project.
OPTION 1
Description Qty Unit Cost Total
A. MOBILIZATION 1 lot
C. 60x80CM LAMINATED OFFICE 71 sets 5,310.00 377,010.00
TABLES
D. FRONT AND SIDE PANELS 1 lot 110,500.00 114,750.00
(120mm height, Laminated with
aluminum endtrims To match
with the existing office tables)
E. 45X60CM CLEAR GLASS PANELS 60 pcs 1250.00 75,000.00
(10mm thick with fine edge to
match with the existing)
TOTAL PROJECT AMOUNT = Php 566,760.00
*Note:
*Project duration
Fabrication 1-2nd week
Installation - 3rd to 5th week maximum
Indent time may vary whatever may effect the schedule