Professional Documents
Culture Documents
11-Concrete Test Procedure Respecting A Suspended Slab
11-Concrete Test Procedure Respecting A Suspended Slab
Scope
1 Objective of this statement is to give an outlisne procedure wise, effected from stage of
cube test failure to complete rescue of concrete, involving all technical & procedural
steps in compliance to various codes, pertinent one 8th level plant room suspended slab of
a reinforced cement concrete eight storey building.
2 Slab was ordered in 1997 by Consulting Engineer to be demolished for reason of
achieving less than permissible cube test characteristics compressive strength of concrete,
but combined efforts by contractor & ready mix concrete supplier, along with help by
authorities, resulted into approval of slab past four months of issue of demolition order
date, proving that sometimes, faulty testing machines can jeopardize whole project &
erroneous test results may be disastrous.
3 Post twenty eight days curing, after issue of demolition order was also, applied to add to
replenish certain deficient chemical reaction in hardened concrete, which if possibly
could be a cause, based on advice of ready mix supplier’s material research engineer.
4 That time, effect of supplementary cementing material was not known clearly, which
accounted for such untoward testing results, while concrete achieved required strength
successfully.
Key Words
1 Cube test, Core Test, Loading, Characteristic Compressive strength, ACI (American
Concrete Institute), BS (British Standard), Engineer, Contractor, RMC Supplier
History
1 Commercial Building 8th slab core test resulted in failure of its cube compression tests on
7th day/28th days.
2 Matter was reported to Engineer on 8th & on 28th day, who advised for a core test
according to ACI provisions, when requested by contractor, but core test failed, since test
conducted by same laboratory that carried out cube test.
3 Consequently, Engineer ordered for removal of slab completely & reconstruct
accordingly.
4 Ready mix concrete supplier & contractor expressed procedural doubts about laboratory
testing equipment, as well as, core capping material, but laboratory claimed that its
machine was fully updated respecting calibration & core capping compound Sulpha,
being within its defined date of expiry.
5 Immediately, contractor conducted Schimdt or rebound hammer test, which slab
qualified, but Engineer did not approve slab.
6 Meanwhile, conducted another core test, which resulted better than previous test, but
engineer did not pay any attention to this plea.
Notes:
Since applications & communications transpired among various bodies are not available with
me, for in 1997, I did not know use of computers. I cannot actually recall my drafts, which I
wrote self. Many times long letters or applications, as formal communiqué were conducted & it
continued for 6 months durations. Parties on communiqué involved were Abu Dhabi
Municipality, Khalsa Contracting, Ardent Consultants, Al Fanar RMC. Lotus, Arab Material
Testing Laboratory & one more laboratory named by municipality
Hammer Test
1 Schmidt hammer test was conducted on June 28, 1997, which observed 34 N/mm^2
gauge reading indicating an equivalent of 40 N/mm^2 compressive strength
2 July 12, 1997, Engineer rejected slab & required removal & reconstruction (Order Copy)
a “Studied core test results taken from top of roof slab.
b Method of testing complied to BS 1881; part 120; 1983, applicable for
determination of compressive strength of concrete cores
c From laboratory tests results of concrete cores, it was found that equivalent cube
strength of all cores is about 50% or more lower than specified design strength of
concrete.
d Such poor results of concrete are unacceptable for structural safety.
Chemical Analysis
Chemical Analysis report by laboratory
1 Report # …..
2 Concrete core sample cement concrete analysis ASTM C 1084-1992
3 Sample description
4 4-inch dia. x 4-inch length cracked concrete core (core appeared to have already tested
for compression strength)
5 Identification Nil
6 Date received July 20, 1997
7 Date tested July 26, 1997
Results
1 Concrete dry density (as oven dry basis) 2340 kg/m^3
2 Cement content percentage 18.1 %
3 Cement content weight 424 kg/m^3
Conclusion-
1 It is an extremely rare example of concrete cubes failure in field that came across, but
provide an impetus to personnel belonging to contract, supervision & control parties to
have an opportunity of in depth study to practically, testing hardened concrete in all
respects/full range in line/according to internationally, acceptable set procedures applying
British & American codes.
2 Structural engineers supervising concrete working in construction field should be very
careful, while dealing with tests & technicalities involved, pertaining to dimensioning of
core.
3 Sulpha flaky capping compound should be within its shelf life period & must
demonstrate compressive strength more than proposed cube compression strength at least
1.5 times.
Load Deflection
Tonnes mm
First cycle Location
Loading 1 2 3 4 5 6 7
0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
68 0.03 0.01 0.00 0.36 0.00 0.00 0.19
119 0.07 0.15 0.03 0.77 0.00 0.02 0.14
170 0.15 0.12 0.12 1.25 0.10 0.10 0.83
221 0.25 0.01 0.16 1.71 0.22 0.14 1.22
0 hour
221 0.25 0.01 0.16 1.71 0.22 0.14 1.22
1 hour
Unloading
170 0.22 0.03 0.15 1.48 0.22 0.15 1.08
119 0.13 0.03 0.15 1.47 0.22 0.12 1.08
68 0.13 0.03 0.15 1.47 0.22 0.10 1.08
0 0.13 0.01 0.15 1.47 0.22 0.10 1.08
Second Location
cycle
Loading 1 2 3 4 5 6 7
0 0.13 0.01 0.15 1.47 0.22 0.10 1.08
68 0.24 0.10 0.23 1.47 0.34 0.29 1.09
119 0.25 0.12 0.23 1.50 0.38 0.32 1.12
170 0.29 0.14 0.24 1.92 0.41 0.32 1.15
221 0.30 0.17 0.25 2.35 0.42 0.33 1.45
0 hour
221 0.30 0.17 0.25 2.35 0.42 0.33 1.45
1 hour
Unloading
170 0.28 0.17 0.25 2.1 0.42 0.33 1.45