A RCC Hume Pipe of 200mm Inner diameter for one length 200 Material 1 Excavation Cum 10.381 250 2595.15 2 PCC Cum 0.117 6000 702
Supply of Pipe (Length of each pipe is 2.5
and required pipe length is 7 m so 3 considering 7.5m) Rmt 7.5 500 3750 4 Backfilling Cum 10.2222 200 2044.438 5 Mortar used on collar for Jointning Cum 0 Cement Bags 0.529364 320 169.3965 Sand MT 0.052936 2500 132.341 6 Concrete used over collar for Jointning Cum 0.052936 6000 317.6185 Labour 7 Mason(For 8hours) MD 1 800 800 8 Helper(For 8 Hours ) MD 1 700 700 Sub Total 11210.94 Tools & Tackles @2% 224.2189 Contengencies @3% 336.3283 Rtae per 7 rm 11771.49 Rate per RMT RMT 1681.642
B RCC Hume Pipe of 300mm Diameter for one Length 300
1 Excavation Cum 12.028 250 3006.9 2 PCC Cum 0.162 6000 972
Supply of Pipe (Length of each pipe is 2.5
and required pipe length is 7 m so 3 considering 7.5m) Rmt 7.5 630 4725 4 Backfilling Cum 11.8242 200 2364.838 5 Mortar used on collar for Jointning Cum 0 Cement Bags 0.671885 320 215.0033 Sand MT 0.067189 2500 167.9713 Concrete used over collar for Jointning Cum 0.067189 6000 403.1312 Labour 7 Mason(For 8hours) MD 1 800 800 8 Helper(For 8 Hours ) MD 1.5 700 1050 Sub Total 13704.84 Tools & Tackles @2% 274.0969 Contengencies @3% 411.1453 Rtae per 7 rm 14390.09 rate per RMT RMT 2055.726
C RCC Hume Pipe of 450mm Diameter for one Length 450
1 Excavation Cum 16.519 250 4129.65 2 PCC Cum 0.230 6000 1377
Supply of Pipe (Length of each pipe is 2.5
and required pipe length is 7 m so 3 considering 7.5m) Rmt 7.5 900 6750 4 Backfilling Cum 16.2477 200 3249.538 5 Mortar used on collar for Jointning Cum 0 Cement Bags 0.977288 320 312.7321 Sand MT 0.097729 2500 244.3219 Concrete used over collar for Jointning Cum 0.097729 6000 586.3726 Labour 7 Mason(For 8hours) MD 1.2 800 960 8 Helper(For 8 Hours ) MD 2.5 700 1750 Sub Total 19359.61 Tools & Tackles @2% 387.1923 Contengencies @3% 580.7884 Rtae per 7 rm 20327.59 rate per RMT RMT 2903.942
D RCC Hume Pipe of 600 mm Diameter for one Length 600
1 Excavation Cum 21.701 250 5425.125 2 PCC Cum 0.293 6000 1755
Supply of Pipe (Length of each pipe is 2.5
and required pipe length is 7 m so 3 considering 7.5m) Rmt 7.5 1300 9750 4 Backfilling Cum 21.3666 200 4273.318 5 Mortar used on collar for Jointning Cum 0 Cement Bags 1.32341 320 423.4913 Sand MT 0.132341 2500 330.8526 Concrete used over collar for Jointning Cum 0.132341 6000 794.0462 Labour 7 Mason(For 8hours) MD 1.5 800 1200 8 Helper(For 8 Hours ) MD 2.5 700 1750 Sub Total 25701.83 Tools & Tackles @2% 514.0367 Contengencies @3% 771.055 Rtae per 7 rm 26986.92 rate per RMT RMT 3855.275
E RCC Hume Pipe of 750 mm Diameter for one Length 750
1 Excavation Cum 23.460 250 5865 2 PCC Cum 0.360 6000 2160
Supply of Pipe (Length of each pipe is 2.5
and required pipe length is 7 m so 3 considering 7.5m) Rmt 7.5 1600 12000 4 Backfilling Cum 23.0586 200 4611.718 5 Mortar used on collar for Jointning Cum 0 Cement Bags 1.628813 320 521.2201 Sand MT 0.162881 2500 407.2032 Concrete used over collar for Jointning Cum 0.162881 6000 977.2877 Labour 7 Mason(For 8hours) MD 2 800 1600 8 Helper(For 8 Hours ) MD 3 700 2100 Sub Total 30242.43 Tools & Tackles @2% 604.8486 Contengencies @3% 907.2729 Rtae per 7 rm 31754.55 rate per RMT RMT 4536.364 Nos L B H QTY