FOUNDATION CALCULATION SHEET

TITLE DESCRIPTION
PROJECT/JOB NO. MSH155
PROJECT/JOB NAME RAFT FOUNDATION
CLIENT NAME PT. xxx
SITE NAME DMT SPLIT COMBAT GENBA
DOCUMENT NO.
REFERENCE NO.
STRUCTURE NAME MNR-62M
LOAD COMBINATION GROUP NAME
REV DATE DESCRIPTION PREP'D CHK'D APPR'D APPR'D

Copyright (c) GS E&C. All Rights Reserved


7/25/2016

Project Na. : RAFT FOUNDATION


Calculation Sheet
of Project No. : MSH155
Foundation Page 2

CONTENTS

1. GENERAL
1.1 CODE & STANDARD
1.2 MATERIALS & UNIT WEIGHT
1.3 SUBSOIL CONDITION & SAFETY FACTORS
1.4 LOAD COMBINATION

2. DRAWING
2.1 LOCATION PLAN & DETAIL SKETCH

3. FOUNDATION DATA
3.1 FOOTING AND SECTION DATA
3.2 PIER DATA
3.3 LOAD CASE
3.4 LOAD COMBINATION

4. CHECK OF STABILITY
4.1 CHECK OF SLIDING
4.2 CHECK OF OVERTURNING MOMENT
4.3 CHECK OF CONTACT PRESSURE

5. DESIGN OF FOOTING
5.1 DESIGN MOMENT AND SHEAR FORCE
5.2 REQUIRED REINFORCEMENT
5.3 ONE WAY SHEAR FORCE
5.4 TWO WAY SHEAR FORCE

Copyright (c) GS E&C. All Rights Reserved


7/25/2016

Project Na. : RAFT FOUNDATION


Calculation Sheet
of Project No. : MSH155
Foundation Page 3

1. GENERAL
1.1 CODE & STANDARD
Items Description
Design Code American Concrete Institute (ACI 318) [SI]
Horizontal Force for Wind UNIFORM BUILDING CODE (UBC-1997)
Horizontal Force for Seismic UNIFORM BUILDING CODE [UBC-1997]
Unit System Input : SI, Output : SI, Calculation Unit : SI

1.2 MATERIALS & UNIT WEIGHT


Items Value
2
Concrete (f'c : compressive strength) 18.600 N/mm
Lean Concrete (Lf'c : compressive strength) 15.000 N/mm2
Reinforcement (D10 ~ D16 , yield strength) 294.000 N/mm2
Reinforcement (D19 ~ , yield strength) 392.000 N/mm2
Rs (Soil unit weight) 14.700 kN/m3
Rc (Concrete unit weight) 24.000 kN/m3
Es (Steel Modulus of Elasticity) 196.130 kN/mm2
Ec (Concrete Modulus of Elasticity) 24.615 kN/mm2

- Soil Capacity
Items Value
Soil Name Unit-01
Footing List F3
Qa (Soil Bearing Capacity) 220.66 kN/m2
Buoyancy Not Consider
WL (Water Label from the EL = 0) 10000 mm
FD (Frost Depth from the EL = 0) 0 mm
Internal Friction Angle 30
Passive Soil Pressure Not Consider
Cu (Undrained cohesion) Clay , 0 kN/m2

1.3 SUBSOIL CONDITION & SAFETY FACTORS


Items Description
Allowable Increase of Soil (Wind) 33.33 %
Allowable Increase of Soil (Seismic) 33.33 %
Allowable Increase of Soil (Test) 20 %
Safety factor against overturning for OVM1(FO1) 1.5
Safety factor against overturning for OVM2(FO2) 1.5
Safety factor against sliding for the SL1(FS1) 1.5
Safety factor against sliding for the SL2(FS2) 1.5

Copyright (c) GS E&C. All Rights Reserved


7/25/2016

Project Na. : RAFT FOUNDATION


Calculation Sheet
of Project No. : MSH155
Foundation Page 4

Friction factor (m) 0.35

1.4 LOAD COMBINATION


Index Load Case Name Load Case Description
1 SW SELF WEIGHT
2 TR1 TOWER REACTION 1
3 TR2 TOWER REACTION 2
4 TR3 TOWER REACTION 3
5 TR4 TOWER REACTION 4

Comb . ID Load Combination for stability


1 1.0 SW + 1.0 TR1
2 1.0 SW + 1.0 TR2
3 1.0 SW + 1.0 TR3
4 1.0 SW + 1.0 TR4
Comb . ID Load Combination for Reinforcement
5 1.0 SW + 1.0 TR1
6 1.0 SW + 1.0 TR2
7 1.0 SW + 1.0 TR3
8 1.0 SW + 1.0 TR4

Copyright (c) GS E&C. All Rights Reserved


7/25/2016 Page 5

2. DRAWING REFERENCE DWGS


A01 NO. DWG NO. DWG TITLE

NOTES
* OUTPUT UNIT : mm

3 1

01

RAFT FOUNDATION PROJECT

FOUNDATION LOCATION PLAN


SST-62M
4 2

SQUAD CHECK
Y PROCESS PIPING VESSELS STRUCT. ELEC. INST.

F3

Z X SCALE JOB NO. MICROFILM NO.

AS SHOWN MSH115
7/25/2016 Page 6

2.2 DETAIL SKETCH

OUTPUT UNIT : mm
7/25/2016 Page 7

REFERENCE DWGS
NO. DWG NO. DWG TITLE
CL FOOTING

8200
1803.5 1803.5
4593
1803.5

NOTES
3 1 * OUTPUT UNIT : mm
CL FOOTING

8200

4593

RAFT FOUNDATION PROJECT

4 2
1803.5

FOUNDATION DETAIL FOR


F3

SQUAD CHECK
FOUNDATION PLAN

PROCESS PIPING VESSELS STRUCT. ELEC. INST.

SCALE JOB NO. MICROFILM NO.

REV. DATE DESCRIPTION DRWNCHKDAPPD APPD APPD


AS SHOWN MSH115
7/25/2016 Page 8

REFERENCE DWGS
NO. DWG NO. DWG TITLE

CL FOOTING

TOP BOTTOM

TYP.
50
NOTES
* OUTPUT UNIT : mm
D16@200

D16@200
RAFT FOUNDATION PROJECT

FOUNDATION DETAIL FOR


F3
D16@200
D16@200

SQUAD CHECK
REINFORCEMENT PLAN

PROCESS PIPING VESSELS STRUCT. ELEC. INST.

SCALE JOB NO. MICROFILM NO.

REV. DATE DESCRIPTION DRWNCHKDAPPD APPD APPD


AS SHOWN MSH115
7/25/2016 Page 9

4 2

3 1

800
400
4 2 LEAN CONC. 50 THK
CRUSHED STONE 100 THK
ELEVATION S1 - X

OUTPUT UNIT : mm
7/25/2016 F3 Item No. Page 10

1 2 3
650 650 650
50 50 50
TYP. TYP. TYP.
650

650

650
D10 D10 D10

24-D16 24-D16 24-D16

50

50

50
100

100

100
1500

1500

1500
@150

@150

@150
D10

D10

D10
D16 D16 D16
75

75

75
4
650
50
TYP.
650

D10

24-D16
50
100
1500

@150
D10

D16
75
7/25/2016

Project Na. : RAFT FOUNDATION


Calculation Sheet
of Project No. : MSH155
Foundation Page 11

3. FOUNDATION DATA
3.1 FOOTING AND SECTION DATA
( mm ) Ft. Name F3
Ft. Type MAT
8200 Area 67.240 m2
Ft. Thickness 400.00 mm
Ft. Volume 26.896 m3
650 650 650 650 Ft. Weight 645.504 kN
Soil Height 800.00 mm
3 1
Soil Volume 52.440 m3
Soil Weight 770.868 kN
8200

Buoyancy Not Consider


Self Weight (except Pr.SW) 1416.372 kN

650 650 650 650

4 2 1500
800

The Origin coordinate


400

The Center of gravity (0,0) mm

Section Data
( mm )
Ft.Name Direction Ft. Volume Soil Volume Pier Wt
3 3
F3 All Direct 26.896 m 52.440 m 60.840 kN

Sec.Name Section Area Ft. Weight Soil Weight Total Weight


2
S1 67.240 m 645.504 kN 770.868 kN 1477.212 kN

3.2 PIER DATA


Off X , Off Y is offset position from the Center of the footing
If Pier Shape is Circle or Circle wall, Pl is a Diameter. and Pw is a Inner Diameter
Area is pier concrete area
Weight is pier and inner soil weight in case circle wall except Tank1 Type(Circle Ring Footing Shape)
Unit( Length : mm , Weight : kN , Area : m2 )
Ft.Name Pr.Name Shape Pl Pw Ph Area Weight Off X Off Y
1 Rectangle 650.000 650.000 1500.000 0.423 15.210 2296.500 2296.500
2 Rectangle 650.000 650.000 1500.000 0.423 15.210 2296.500 -2296.500
F3
3 Rectangle 650.000 650.000 1500.000 0.423 15.210 -2296.500 2296.500
4 Rectangle 650.000 650.000 1500.000 0.423 15.210 -2296.500 -2296.500

Copyright (c) GS E&C. All Rights Reserved


7/25/2016

Project Na. : RAFT FOUNDATION


Calculation Sheet
of Project No. : MSH155
Foundation Page 12

3.3 LOAD CASE


Fz
Fy
Mz
Input the point loads in the global coordinate system direction. Positive directions of moments (shown in the sketch) are
My based on the right hand rule.
Fx
Mx

Index Load Case Name Load Case Description


1 SW SELF WEIGHT
2 TR1 TOWER REACTION 1
3 TR2 TOWER REACTION 2
4 TR3 TOWER REACTION 3
5 TR4 TOWER REACTION 4

Unit( kN , kN-m )
Ft.Name Pr.Name Load Case Fx Fy Fz Mx My
1 0 0 -15.21 0 0
2 -32.74 -31.95 -623.89 -0.36 0.34
1 3 -12.6 -10.73 -23.37 0.26 -0.22
4 -11.33 -13.55 -28.85 0.23 -0.28
5 -29.92 -30.68 571.67 -0.29 0.31
1 0 0 -15.21 0 0
2 -12.6 -10.73 -23.37 0.26 -0.22
2 3 -11.33 -13.55 -28.85 0.23 -0.28
4 -29.92 -30.68 571.67 -0.29 0.31
5 -32.74 -31.95 -623.89 -0.36 0.34
F3 1 0 0 -15.21 0 0
2 -11.33 -13.55 -28.85 0.23 -0.28
3 3 -29.92 -30.68 571.67 -0.29 0.31
4 -32.74 -31.95 -623.89 -0.36 0.34
5 -12.6 -10.73 -23.37 0.26 -0.22
1 0 0 -15.21 0 0
2 -29.92 -30.68 571.67 -0.29 0.31
4 3 -32.74 -31.95 -623.89 -0.36 0.34
4 -12.6 -10.73 -23.37 0.26 -0.22
5 -11.33 -13.55 -28.85 0.23 -0.28
Footing SW 0.000 0.000 -1416.372 0.000 0.000

Copyright (c) GS E&C. All Rights Reserved


7/25/2016

Project Na. : RAFT FOUNDATION


Calculation Sheet
of Project No. : MSH155
Foundation Page 13

3.4 LOAD COMBINATION


In Pier Top In Footing Bottom In Footing Bottom Center
without Self Weight with Pier Self Weight, with Pier & Footing Self Weight & Soil Weight,
But without Footing Self Weight, Case PileType
in centroid of Pile Group
Case NonPileType
in centroid of Footing

3.4.1 Load Combination in Pier Top (Without SW)


Unit( kN , kN-m )
Ft.Name Pr.Name L.Comb. S Fx S Fy S Fz S Mx S My
1 -32.742 -31.946 -623.888 -0.356 0.343
2 -12.596 -10.730 -23.366 0.263 -0.219
3 -11.328 -13.548 -28.850 0.226 -0.281
4 -29.923 -30.678 571.672 -0.294 0.307
1
5 -32.742 -31.946 -623.888 -0.356 0.343
6 -12.596 -10.730 -23.366 0.263 -0.219
7 -11.328 -13.548 -28.850 0.226 -0.281
8 -29.923 -30.678 571.672 -0.294 0.307
1 -12.596 -10.730 -23.366 0.263 -0.219
2 -11.328 -13.548 -28.850 0.226 -0.281
3 -29.923 -30.678 571.672 -0.294 0.307
4 -32.742 -31.946 -623.888 -0.356 0.343
2
5 -12.596 -10.730 -23.366 0.263 -0.219
6 -11.328 -13.548 -28.850 0.226 -0.281
7 -29.923 -30.678 571.672 -0.294 0.307
8 -32.742 -31.946 -623.888 -0.356 0.343
F3
1 -11.328 -13.548 -28.850 0.226 -0.281
2 -29.923 -30.678 571.672 -0.294 0.307
3 -32.742 -31.946 -623.888 -0.356 0.343
4 -12.596 -10.730 -23.366 0.263 -0.219
3
5 -11.328 -13.548 -28.850 0.226 -0.281
6 -29.923 -30.678 571.672 -0.294 0.307
7 -32.742 -31.946 -623.888 -0.356 0.343
8 -12.596 -10.730 -23.366 0.263 -0.219
1 -29.923 -30.678 571.672 -0.294 0.307
2 -32.742 -31.946 -623.888 -0.356 0.343
3 -12.596 -10.730 -23.366 0.263 -0.219
4 -11.328 -13.548 -28.850 0.226 -0.281
4
5 -29.923 -30.678 571.672 -0.294 0.307
6 -32.742 -31.946 -623.888 -0.356 0.343
7 -12.596 -10.730 -23.366 0.263 -0.219
8 -11.328 -13.548 -28.850 0.226 -0.281

Copyright (c) GS E&C. All Rights Reserved


7/25/2016

Project Na. : RAFT FOUNDATION


Calculation Sheet
of Project No. : MSH155
Foundation Page 14

3.4.2 F3
Unit( kN , kN-m )
Ft.Name Pr.Name L.Comb. S Fx S Fy S Fz S Mx S My
1 -32.742 -31.946 -639.098 60.341 -61.867
2 -12.596 -10.730 -38.576 20.650 -24.151
3 -11.328 -13.548 -44.060 25.967 -21.804
4 -29.923 -30.678 556.462 57.994 -56.547
1
5 -32.742 -31.946 -639.098 47.563 -48.770
6 -12.596 -10.730 -38.576 16.358 -19.113
7 -11.328 -13.548 -44.060 20.548 -17.273
8 -29.923 -30.678 556.462 45.723 -44.578
1 -12.596 -10.730 -38.576 20.650 -24.151
2 -11.328 -13.548 -44.060 25.967 -21.804
3 -29.923 -30.678 556.462 57.994 -56.547
4 -32.742 -31.946 -639.098 60.341 -61.867
2
5 -12.596 -10.730 -38.576 16.358 -19.113
6 -11.328 -13.548 -44.060 20.548 -17.273
7 -29.923 -30.678 556.462 45.723 -44.578
8 -32.742 -31.946 -639.098 47.563 -48.770
F3
1 -11.328 -13.548 -44.060 25.967 -21.804
2 -29.923 -30.678 556.462 57.994 -56.547
3 -32.742 -31.946 -639.098 60.341 -61.867
4 -12.596 -10.730 -38.576 20.650 -24.151
3
5 -11.328 -13.548 -44.060 20.548 -17.273
6 -29.923 -30.678 556.462 45.723 -44.578
7 -32.742 -31.946 -639.098 47.563 -48.770
8 -12.596 -10.730 -38.576 16.358 -19.113
1 -29.923 -30.678 556.462 57.994 -56.547
2 -32.742 -31.946 -639.098 60.341 -61.867
3 -12.596 -10.730 -38.576 20.650 -24.151
4 -11.328 -13.548 -44.060 25.967 -21.804
4
5 -29.923 -30.678 556.462 45.723 -44.578
6 -32.742 -31.946 -639.098 47.563 -48.770
7 -12.596 -10.730 -38.576 16.358 -19.113
8 -11.328 -13.548 -44.060 20.548 -17.273

3.4.3 Load Combination in Footing Bottom Center (With Pier & Footing SW)
Load Combination of Elastic Condition
- C.G. of Load is coordinate from left bottom. Unit : mm Unit( kN , kN-m )
Ft.Name L.Comb. S Fx S Fy SFz S Mx S My C.G. of Loads
1 -86.589 -86.902 -1581.644 -2593.245 2568.640 5828.0 , 5843.9
2 -86.589 -86.902 -1581.644 2923.150 -164.369 4100.0 , 2356.1
F3
3 -86.589 -86.902 -1581.644 -2593.245 -2897.379 2372.0 , 5843.9
4 -86.589 -86.902 -1581.644 2923.150 -164.369 4100.0 , 2356.1

Copyright (c) GS E&C. All Rights Reserved


7/25/2016

Project Na. : RAFT FOUNDATION


Calculation Sheet
of Project No. : MSH155
Foundation Page 15

Load Combination of Ultimate Condition


- C.G. of Load is coordinate from left bottom. Unit : mm Unit( kN , kN-m )
Ft.Name Sec.Nam L.Comb. S Fx S Fy S Fz S Mx S My C.G. of Loads
5 -86.589 -86.902 -1581.644 -2628.005 2603.276 5828.0 , 5843.9
6 -86.589 -86.902 -1581.644 2888.390 -129.734 4100.0 , 2356.1
F3 S1
7 -86.589 -86.902 -1581.644 -2628.006 -2862.743 2372.0 , 5843.9
8 -86.589 -86.902 -1581.644 2888.390 -129.733 4100.0 , 2356.1

Copyright (c) GS E&C. All Rights Reserved


7/25/2016

Project Na. : RAFT FOUNDATION


Calculation Sheet
of Project No. : MSH155
Foundation Page 16

4. CHECK OF STABILITY
4.1 CHECK OF SLIDING
mSFz + P.F
Formula : 2 2 > Fs -> OK (Bi-Axial)
SFx + SFy
P.F = Passive Force (apply only in case checked passive force, mark by P ) Unit ( kN )
2 2
Ft.Name Dir. L.Comb. ( mSFz + P.F ) / S Fx + SFy Fs(i) Result
F3 Bi-Axial 4 0.35 1581.64 / 122.68 = 4.51 1.5 OK

4.2 CHECK OF OVERTURNING MOMENT


Formula : (SMry / SMoy or SMrx / SMox) > OVM(i) -> OK Unit ( kN-m )
Ft.Name Dir. L.Comb. S Mry / S Moy = OVM or S Mrx / S Mox = OVM OVM(i) Result
X 2 -6484.74 / -164.37 = 39.45 1.5 OK
F3
Y 2 -6484.74 / -2923.15 = 2.22 1.5 OK

4.3 CHECK OF CONTACT PRESSURE


4.3.1 Contact Pressure Formula
'Handbook CONCRETE ENGINEERING' Second Edition edited by Mark Fintel

SFz SMy X(i) SMx Y(i)


q1,q2 =
Af Iy Ix
if q1 or q2 < 0 , than q1 and q2 will be recalculated
by following formula
L
q(x) width(x) X dx
Px = 0 L
0
q(x) width(x) dx
P = L0 q(x) width(x) dx

4.3.2 Input Data


2 4 4
Ft.Name Af (m ) Fl (m ) Fw (m ) Ix (m ) Iy (m )
F3 67.240 8.200 8.200 376.7682 376.7682

Copyright (c) GS E&C. All Rights Reserved


7/25/2016

Project Na. : RAFT FOUNDATION


Calculation Sheet
of Project No. : MSH155
Foundation Page 17

4.3.3 Pressure Check


- Qa = Soil bearing capacity
- Uc = Uplift Allowable capacity
- XY-Direction (Bi-Axial) Unit( kN , kN-m , kN/m2 )
Ft.Name L.Comb. q1 q2 ci cj Qmax Qa Cont.A.R Result
F3 3 0.000 105.763 4.878 11.579 105.8 294.2(gross) 64.39 % OK

Copyright (c) GS E&C. All Rights Reserved


7/25/2016

Project Na. : RAFT FOUNDATION


Calculation Sheet
of Project No. : MSH155
Foundation Page 18

5. DESIGN OF FOOTING
5.1 DESIGN MOMENT AND SHEAR FORCE
Footing design is in accordance with unltimate strength method at footing bottom.
Calculated total pier load as
SQ = SFz - Self Weight Factor (Soil Weight + Footing Weight)
Ft.Name : Footing Name , Sec.Name : Strip Name for Footing Reinforcement Design
Dir. : Direction , L.Comb. : Load Combination Index , Sl or Sw : Strip X or Y width

5.1.1 Data Unit( mm , kN , kN-m )


Ft.Name Sec.Nam Dir. L.Comb. Fl or Fw Sl or Sw S Fz SM SQ
5 8200.00 8200.00 1581.644 2603.28 165.272
6 8200.00 8200.00 1581.644 -129.73 165.272
S1 X
7 8200.00 8200.00 1581.644 -2862.74 165.272
8 8200.00 8200.00 1581.644 -129.73 165.272
F3
5 8200.00 8200.00 1581.644 -2628.005 165.272
6 8200.00 8200.00 1581.644 2888.390 165.272
S1 Y
7 8200.00 8200.00 1581.644 -2628.006 165.272
8 8200.00 8200.00 1581.644 2888.390 165.272

5.1.2 Design Parameters


Yield Strength - D10 ~ D16 : fy1 , D19 ~ : fy2
f_cl : Clear Cover for edge of footing reinforcement
f_clt : Clear Cover for top of footing reinforcement
f_clb : Clear Cover for bottom of footing reinforcement
Loc. : Location of Critical Point from left side of footing

Unit(N/mm2,mm)
f(Flexure) f(Shear) f'c fy1 fy2 f_cl f_clt f_clb
0.8 0.75 18.60 294.00 392.00 50.0 50.0 50.0

Copyright (c) GS E&C. All Rights Reserved


7/25/2016

Project Na. : RAFT FOUNDATION


Calculation Sheet
of Project No. : MSH155
Foundation Page 19

5.2 REQUIRED REINFORCEMENT


5.2.1 Reinforcement Formula
- Shrinkage and temperature reinforcement
As = fac b h , fac = 0.002 ---- USD99 CODE 5.7.2(1)
- Required Reinforcement by Analysis
As As2
- At every section of flexural members where tensile reinforcement is required
As As5
As As4
- The requirements of Eq (6.3.2) need not be applied, if every section As provided is
at least one -third greater than that required by analysis
As2 = r.req b d
As3 = 1.333 r.req b d
1.4
As4 = bd
fy
0.25 fck
As5 = bd
fy
Asmax = 0.75 rb b d
fck 0.003 Es
rb = 0.85 b 1 f 0.003 Es + fy
y

Selected As = Max ( As1 , As2 , Min ( As3 , Max ( As4 , As5 ) ) )


If Selected As < Using As < Asmax , then OK!!

Note : The reinforcement is calculated bases on the maximum moment under the foundation in each direction.
But, the 'ISO' , 'OCT' , 'HEX' , 'COMB' , 'TANK1' foundations are calaulated as face pier
Where,
Mu 0.85 fck 2Rn
Rn =
fbd
2 , f = 0.8 , r.req =
fy ( 1- 1-
0.85fck )
5.2.2 Check of Footing Reinforcement
Footing Name : F3 GroupType : Mat_Foundation
- X direction (Unit Width)

2
Sec.Name L.Comb. Using Bar (mm) Loc. (m) Width b (m) d (mm) As (mm )
5 top 5 - D16 @ 200 2.129 1.000 342.050 992.783
S1
5 botom 5 - D16 @ 200 6.072 1.000 342.050 992.783

Sec.Name L.Comb. Mu (kN-m) Rn r.Req


5 top 34.077 0.364 0.0013
S1
5 bottom 42.302 0.452 0.0016

2 2 2 2 2 2
Sec.Name L.Comb. As1(mm ) As2(mm ) As3(mm ) As4(mm ) As5(mm ) Asmax(mm )
5 top 400.000 428.572 571.286 1628.810 1254.408 7819.142
S1
5 bottom 400.000 533.555 711.228 1628.810 1254.408 7819.142

2 2
Sec.Name L.Comb. Using As(mm ) Select As(mm ) Result
5 top 992.783 571.286 OK
S1
5 bottom 992.783 711.228 OK

Copyright (c) GS E&C. All Rights Reserved


7/25/2016

Project Na. : RAFT FOUNDATION


Calculation Sheet
of Project No. : MSH155
Foundation Page 20

- Y direction (Unit Width)

2
Sec.Name L.Comb. Using Bar (mm) Loc. (m) Width b (m) d (mm) As (mm )
7 top 5 - D16 @ 200 2.129 1.000 326.150 992.783
S1
7 botom 5 - D16 @ 200 6.072 1.000 326.150 992.783

Sec.Name L.Comb. Mu (kN-m) Rn r.Req


7 top 34.151 0.401 0.0014
S1
7 bottom 42.722 0.502 0.0017
2 2 2 2 2 2
Sec.Name L.Comb. As1(mm ) As2(mm ) As3(mm ) As4(mm ) As5(mm ) Asmax(mm )
7 top 400.000 450.992 601.172 1553.095 1196.097 7455.673
S1
7 bottom 400.000 566.060 754.558 1553.095 1196.097 7455.673
2 2
Sec.Name L.Comb. Using As(mm ) Select As(mm ) Result
7 top 992.783 601.172 OK
S1
7 bottom 992.783 754.558 OK

Copyright (c) GS E&C. All Rights Reserved


7/25/2016

Project Na. : RAFT FOUNDATION


Calculation Sheet
of Project No. : MSH155
Foundation Page 21

5.3 ONE WAY SHEAR FORCE


5.3.1 One-Way Shear Formula
- f Vc = 0.75 1/6 fck B'w d
- Vu <= f Vc , then OK!!

5.3.2 Check of One-Way Shear


Footing Name : F3 GroupType : Mat_Foundation PileType : False

Unit : mm
8200

3 1
8200

4 2
1137

1137

- X direction One-Way Shear (Unit Width)


Sec.Name L.Comb. Loc. (mm) d (mm) Bw (mm) fVc (kN) Vu (kN) Result
S1 7 1137 342 1000 184.398 35.122 OK
- Y direction One-Way Shear (Unit Width)
Sec.Name L.Comb. Loc. (mm) d (mm) Bw (mm) fVc (kN) Vu (kN) Result
S1 6 1137 326.1 1000 175.826 35.51 OK

Copyright (c) GS E&C. All Rights Reserved


7/25/2016

Project Na. : RAFT FOUNDATION


Calculation Sheet
of Project No. : MSH155
Foundation Page 22

5.4 TWO WAY SHEAR FORCE


5.4.1 Two-Way Shear Formula
Vu = SFz Shade Ratio
f Vc1 = 0.75 1/6 (1 + 2/ b c) fck bo d
f Vc2 = 0.75 1/6 (1 + as d / 2 bo) fck bo d
f Vc3 = 0.75 1/3 fck bo d
f Vc = Min(f Vc1 , f Vc2 , f Vc3)
Vu f Vc , then OK
where
b c = ratio of long side to short side of the column, concentrated load or reaction area
as = 40 for interior colimns
= 30 for edge columns
= 20 for corner columns
bo = perimeter of critical section
Footing Area - Punching Area
Shade Ratio =
Footing Area

5.4.2 Check of Two-WayShear

Ft.Name F3 Punching Area 984163.000 mm2

8200 Pr.Name 2 Ratio Shade 0.985

Shape Rectangle f Vc1 2195.184 kN

3 1 L.Comb. 8 f Vc2 1993.194 kN


8200

Pl 650 mm f Vc3 1463.456 kN

Pw 650 mm f Vc 1463.456 kN
4 2

bo / d 3968.2 / 342.05 mm Vu 629.744 kN

b c / as 1 / 40 Result OK

Copyright (c) GS E&C. All Rights Reserved


7/25/2016

Project Na. : RAFT FOUNDATION


Calculation Sheet
of Project No. : MSH155
Foundation Page 1

SUMMARY REPORT FOR FOUNDATION DESIGN

Project Information
Project Name RAFT FOUNDATION
Structure Name SST-62M

1. CHECK OF STABILITY
1.1 Check of Sliding Force (Bi-Axial)
Ft.Name # L/C Fs Allowable Result
1 4.512 1.5 OK
2 4.512 1.5 OK
F3
3 4.512 1.5 OK
4 4.512 1.5 OK

1.2 Check of Overturning Moment


Ft.Name # L/C X - OVM Y - OVM Allowable Result
1 2.52 2.5 1.5 OK / OK
2 39.45 2.22 1.5 OK / OK
F3
3 2.24 2.5 1.5 OK / OK
4 39.45 2.22 1.5 OK / OK

1.3 Check of Bearing Pressure (Bi-Axial)


2
Ft.Name # L/C Qu(kN/m ) Allowable Result
1 96.64 294.21 OK
2 59.06 294.21 OK
F3
3 105.76 294.21 OK
4 59.06 294.21 OK

2. DESIGN OF FOOTING
2.1 Check of Reinforcement
(Unit : mm2)
Ft.Name Sec.Nam # L/C Req.As top / bottom Used.As top / bottom Result
5 571.29 / 711.23 992.78 / 992.78 OK / OK
6 400.00 / 400.00 992.78 / 992.78 OK / OK
S1 (X)
7 400.00 / 578.11 992.78 / 992.78 OK / OK
8 400.00 / 400.00 992.78 / 992.78 OK / OK
F3
5 601.17 / 754.56 992.78 / 992.78 OK / OK
6 403.25 / 613.87 992.78 / 992.78 OK / OK
S1 (Y)
7 601.17 / 754.56 992.78 / 992.78 OK / OK
8 403.25 / 613.87 992.78 / 992.78 OK / OK

Copyright (c) GS E&C. All Rights Reserved


7/25/2016

Project Na. : RAFT FOUNDATION


Calculation Sheet
of Project No. : MSH155
Foundation Page 2

2.2 Check of One Way Shear (Unit : kN)


Ft.Name Sec.Nam # L/C fVc Vu Result
5 184.40 30.56 OK
6 184.40 7.09 OK
S1 (X)
7 184.40 35.12 OK
8 184.40 7.09 OK
F3
5 175.83 30.87 OK
6 175.83 35.51 OK
S1 (Y)
7 175.83 30.87 OK
8 175.83 35.51 OK

2.3 Check of Two Way Shear (Unit : kN)


Ft.Name # L/C Ct. Pr.Name fVc Vu Result
5 1 1463.456 629.744 OK
6 4 1463.456 629.744 OK
F3
7 3 1463.456 629.744 OK
8 2 1463.456 629.744 OK

Copyright (c) GS E&C. All Rights Reserved


7/25/2016

COLUMN CALCULATION SHEET

TITLE DESCRIPTION
PROJECT/JOB NO. MSH155
PROJECT/JOB NAME RAFT FOUNDATION
CLIENT NAME PT. XX
SITE NAME DMT SPLIT COMBAT GENBA
DOCUMENT NO.
REFERENCE NO.
STRUCTURE NAME MNR-62M
GROUP NAME
LOADCOMBINATION GROUP NAME
REV DATE DESCRIPTION PREP'D CHK'D APPR'D APPR'D

Copyright (c) GS E&C. All Rights Reserved


7/25/2016

Project Na. : RAFT FOUNDATION


Calculation Sheet
of Project No. : MSH155
Pier Page 1

CONTENTS

1. INPUT DATA
1.1 GENERAL
1.2 PIER DATA
1.3 LOADING DATA
2. CANTIL BEAM DESIGN
2.1 FORMULA
2.2 CANTIL BEAM DESIGN
3. ONE-WAY SHEAR
3.1 FORMULA
3.2 ONE-WAY SHEAR

Copyright (c) GS E&C. All Rights Reserved


7/25/2016

Project Na. : RAFT FOUNDATION


Calculation Sheet
of Project No. : MSH155
Pier Page 2

1. INPUT DATA
1.1 General
Design Code American Concrete Institute (ACI 318) [SI]

Input Unit SI Output Unit SI

f Bending f Axial f Sprial reinf. f Tied reinf. f Shear


0.8 0.8 0.7 0.65 0.75

f'c fy (D10 ~ D16) fy (D19 ~) Ec Es Steel Db Cover


2 2 2 2 2
18.6 N/mm 294 N/mm 392 N/mm 24.61 kN/mm 196.13 kN/mm JIS G3112 (D) 50 mm

1.2 Pier Data


650 Pier Name 1 Ver Bar D16, 7 7 EA
50
Pier Shape Rectangle Tie Bar D10 @ 150 mm

Width 650 mm f'c 18.6 N/mm2


650

Length 650 mm fy 294 N/mm2

Height 1500 mm Using As 4765.35 mm2

dx 582.52 mm dy 582.52 mm

650 Pier Name 2 Ver Bar D16, 7 7 EA


50
Pier Shape Rectangle Tie Bar D10 @ 150 mm

Width 650 mm f'c 18.6 N/mm2


650

Length 650 mm fy 294 N/mm2

Height 1500 mm Using As 4765.35 mm2

dx 582.52 mm dy 582.52 mm

650 Pier Name 3 Ver Bar D16, 7 7 EA


50
Pier Shape Rectangle Tie Bar D10 @ 150 mm

Width 650 mm f'c 18.6 N/mm2


650

Length 650 mm fy 294 N/mm2

Height 1500 mm Using As 4765.35 mm2

dx 582.52 mm dy 582.52 mm

650 Pier Name 4 Ver Bar D16, 7 7 EA


50
Pier Shape Rectangle Tie Bar D10 @ 150 mm

Width 650 mm f'c 18.6 N/mm2


650

Length 650 mm fy 294 N/mm2

Height 1500 mm Using As 4765.35 mm2

dx 582.52 mm dy 582.52 mm

Copyright (c) GS E&C. All Rights Reserved


7/25/2016

Project Na. : RAFT FOUNDATION


Calculation Sheet
of Project No. : MSH155
Pier Page 3

1.3 Loading Data


1.3.1 Load Case Unit( kN , kN-m )
Pier Name Name Fx Fy Fz Mx My
SW 0 0 -15.21 0 0
TR1 -32.742 -31.946 -623.888 -0.356 0.343
1 TR2 -12.596 -10.73 -23.366 0.263 -0.219
TR3 -11.328 -13.548 -28.85 0.226 -0.281
TR4 -29.923 -30.678 571.672 -0.294 0.307
SW 0 0 -15.21 0 0
TR1 -12.596 -10.73 -23.366 0.263 -0.219
2 TR2 -11.328 -13.548 -28.85 0.226 -0.281
TR3 -29.923 -30.678 571.672 -0.294 0.307
TR4 -32.742 -31.946 -623.888 -0.356 0.343
SW 0 0 -15.21 0 0
TR1 -11.328 -13.548 -28.85 0.226 -0.281
3 TR2 -29.923 -30.678 571.672 -0.294 0.307
TR3 -32.742 -31.946 -623.888 -0.356 0.343
TR4 -12.596 -10.73 -23.366 0.263 -0.219
SW 0 0 -15.21 0 0
TR1 -29.923 -30.678 571.672 -0.294 0.307
4 TR2 -32.742 -31.946 -623.888 -0.356 0.343
TR3 -12.596 -10.73 -23.366 0.263 -0.219
TR4 -11.328 -13.548 -28.85 0.226 -0.281

1.3.2 Load Combination List


Comb . ID Load Combination for Reinforcement
5 1.0 SW + 1.0 TR1
6 1.0 SW + 1.0 TR2
7 1.0 SW + 1.0 TR3
8 1.0 SW + 1.0 TR4

1.3.3 In Pier Top Unit( kN , kN-m )


P. Name LC# S Fx S Fy S Fz S Mx S My
5 -32.742 -31.946 -623.888 -0.356 0.343
6 -12.596 -10.73 -23.366 0.263 -0.219
1
7 -11.328 -13.548 -28.85 0.226 -0.281
8 -29.923 -30.678 571.672 -0.294 0.307
5 -12.596 -10.73 -23.366 0.263 -0.219
6 -11.328 -13.548 -28.85 0.226 -0.281
2
7 -29.923 -30.678 571.672 -0.294 0.307
8 -32.742 -31.946 -623.888 -0.356 0.343
5 -11.328 -13.548 -28.85 0.226 -0.281
3 6 -29.923 -30.678 571.672 -0.294 0.307
7 -32.742 -31.946 -623.888 -0.356 0.343

Copyright (c) GS E&C. All Rights Reserved


7/25/2016

Project Na. : RAFT FOUNDATION


Calculation Sheet
of Project No. : MSH155
Pier Page 4

8 -12.596 -10.73 -23.366 0.263 -0.219


5 -29.923 -30.678 571.672 -0.294 0.307
6 -32.742 -31.946 -623.888 -0.356 0.343
4
7 -12.596 -10.73 -23.366 0.263 -0.219
8 -11.328 -13.548 -28.85 0.226 -0.281

1.3.4 In Pier Bottom Unit( kN , kN-m )


P. Name LC# S Fx S Fy S Fz S Mx S My
5 -32.742 -31.946 -639.098 34.785 -35.673
6 -12.596 -10.73 -38.576 12.066 -14.075
1
7 -11.328 -13.548 -44.06 15.129 -12.742
8 -29.923 -30.678 556.462 33.452 -32.608
5 -12.596 -10.73 -38.576 12.066 -14.075
6 -11.328 -13.548 -44.06 15.129 -12.742
2
7 -29.923 -30.678 556.462 33.452 -32.608
8 -32.742 -31.946 -639.098 34.785 -35.673
5 -11.328 -13.548 -44.06 15.129 -12.742
6 -29.923 -30.678 556.462 33.452 -32.608
3
7 -32.742 -31.946 -639.098 34.785 -35.673
8 -12.596 -10.73 -38.576 12.066 -14.075
5 -29.923 -30.678 556.462 33.452 -32.608
6 -32.742 -31.946 -639.098 34.785 -35.673
4
7 -12.596 -10.73 -38.576 12.066 -14.075
8 -11.328 -13.548 -44.06 15.129 -12.742

Copyright (c) GS E&C. All Rights Reserved


7/25/2016

Project Na. : RAFT FOUNDATION


Calculation Sheet
of Project No. : MSH155
Pier Page 5

2. CANTIL BEAM DESIGN


2.1 FORMULA
- Shrinkage and temperature reinforcement
As = fac b h , fac = 0.002 ---- USD99 CODE 5.7.2(1)
- Required Reinforcement by Analysis
As As2
- At every section of flexural members where tensile reinforcement is required
As As5
As As4
- The requirements of Eq (6.3.2) need not be applied, if every section As provided is
at least one -third greater than that required by analysis
As2 = r.req b d
As3 = 1.333 r.req b d
1.4
As4 = bd
fy
0.25 fck
As5 = bd
fy
Asmax = 0.75 rb b d
fck 0.003 Es
rb = 0.85 b 1 f 0.003 Es + fy
y

Selected As = Max ( As1 , As2 , Min ( As3 , Max ( As4 , As5 ) ) )


If Selected As < Using As < Asmax , then OK!!

Note : The reinforcement is calculated bases on the maximum moment under the foundation in each direction.
But, the 'ISO' , 'OCT' , 'HEX' , 'COMB' , 'TANK1' foundations are calaulated as face pier
Where,
Mu 0.85 fck 2Rn
Rn =
fbd
2 , f = 0.8 , r.req =
fy ( 1- 1-
0.85fck )

2.2 CANTIL BEAM DESIGN Unit( mm )


P.Name bx by dx dy
1 650 650 582.52 582.52
2 650 650 582.52 582.52
3 650 650 582.52 582.52
4 650 650 582.52 582.52

Unit(mm2)
P.Name Pier As temp. As (As1) Using As (All) Result
1 4765.35 845 4765.35 OK
2 4765.35 845 4765.35 OK
3 4765.35 845 4765.35 OK
4 4765.35 845 4765.35 OK

Unit(mm2)
P.Name Dir LC# UsingAs As2 As3 As4 As5 AsSelect Result
5 1389.9 262.06 349.32 1803.04 1388.59 349.32 OK
1 X
6 1389.9 102.99 137.28 1803.04 1388.59 137.28 OK

Copyright (c) GS E&C. All Rights Reserved


7/25/2016

Project Na. : RAFT FOUNDATION


Calculation Sheet
of Project No. : MSH155
Pier Page 6

7 1389.9 93.21 124.25 1803.04 1388.59 124.25 OK


X
8 1389.9 239.41 319.13 1803.04 1388.59 319.13 OK
5 1389.9 255.49 340.57 1803.04 1388.59 340.57 OK
6 1389.9 88.26 117.65 1803.04 1388.59 117.65 OK
Y
7 1389.9 110.72 147.59 1803.04 1388.59 147.59 OK
8 1389.9 245.64 327.44 1803.04 1388.59 327.44 OK
5 1389.9 102.99 137.28 1803.04 1388.59 137.28 OK
6 1389.9 93.21 124.25 1803.04 1388.59 124.25 OK
X
7 1389.9 239.41 319.13 1803.04 1388.59 319.13 OK
8 1389.9 262.06 349.32 1803.04 1388.59 349.32 OK
2
5 1389.9 88.26 117.65 1803.04 1388.59 117.65 OK
6 1389.9 110.72 147.59 1803.04 1388.59 147.59 OK
Y
7 1389.9 245.64 327.44 1803.04 1388.59 327.44 OK
8 1389.9 255.49 340.57 1803.04 1388.59 340.57 OK
5 1389.9 93.21 124.25 1803.04 1388.59 124.25 OK
6 1389.9 239.41 319.13 1803.04 1388.59 319.13 OK
X
7 1389.9 262.06 349.32 1803.04 1388.59 349.32 OK
8 1389.9 102.99 137.28 1803.04 1388.59 137.28 OK
3
5 1389.9 110.72 147.59 1803.04 1388.59 147.59 OK
6 1389.9 245.64 327.44 1803.04 1388.59 327.44 OK
Y
7 1389.9 255.49 340.57 1803.04 1388.59 340.57 OK
8 1389.9 88.26 117.65 1803.04 1388.59 117.65 OK
5 1389.9 239.41 319.13 1803.04 1388.59 319.13 OK
6 1389.9 262.06 349.32 1803.04 1388.59 349.32 OK
X
7 1389.9 102.99 137.28 1803.04 1388.59 137.28 OK
8 1389.9 93.21 124.25 1803.04 1388.59 124.25 OK
4
5 1389.9 245.64 327.44 1803.04 1388.59 327.44 OK
6 1389.9 255.49 340.57 1803.04 1388.59 340.57 OK
Y
7 1389.9 88.26 117.65 1803.04 1388.59 117.65 OK
8 1389.9 110.72 147.59 1803.04 1388.59 147.59 OK

3. ONE-WAY SHEAR
3.1 FORMULA
- Vc = 1/6 fck Bw d
Av fy d
- Vs =
s
- Vu <= f Vc + f Vs , f = 0.75
- When, Value of f Vs shall not exceed f 2/3 fck Bw d (Vs max)

Copyright (c) GS E&C. All Rights Reserved


7/25/2016

Project Na. : RAFT FOUNDATION


Calculation Sheet
of Project No. : MSH155
Pier Page 7

3.2 ONE-WAY SHEAR Unit(kN)


P. Name Dir. LC# fVc fVs fVs max Vu Result
5 204.531 244.323 818.123 32.742 OK
6 204.531 244.323 818.123 12.596 OK
X
7 204.531 244.323 818.123 11.328 OK
8 204.531 244.323 818.123 29.923 OK
1
5 204.531 244.323 818.123 31.946 OK
6 204.531 244.323 818.123 10.73 OK
Y
7 204.531 244.323 818.123 13.548 OK
8 204.531 244.323 818.123 30.678 OK
5 204.531 244.323 818.123 12.596 OK
6 204.531 244.323 818.123 11.328 OK
X
7 204.531 244.323 818.123 29.923 OK
8 204.531 244.323 818.123 32.742 OK
2
5 204.531 244.323 818.123 10.73 OK
6 204.531 244.323 818.123 13.548 OK
Y
7 204.531 244.323 818.123 30.678 OK
8 204.531 244.323 818.123 31.946 OK
5 204.531 244.323 818.123 11.328 OK
6 204.531 244.323 818.123 29.923 OK
X
7 204.531 244.323 818.123 32.742 OK
8 204.531 244.323 818.123 12.596 OK
3
5 204.531 244.323 818.123 13.548 OK
6 204.531 244.323 818.123 30.678 OK
Y
7 204.531 244.323 818.123 31.946 OK
8 204.531 244.323 818.123 10.73 OK
5 204.531 244.323 818.123 29.923 OK
6 204.531 244.323 818.123 32.742 OK
X
7 204.531 244.323 818.123 12.596 OK
8 204.531 244.323 818.123 11.328 OK
4
5 204.531 244.323 818.123 30.678 OK
6 204.531 244.323 818.123 31.946 OK
Y
7 204.531 244.323 818.123 10.73 OK
8 204.531 244.323 818.123 13.548 OK