Professional Documents
Culture Documents
Presented By:
Muhammad Husnain
Dy. Director (M&S) WAPDA
135th MMC, WASC Islamabad
TO
My Beloved Mother
Here I shall also mention and appreciate guidance and support of my seniors
in Monitoring & Surveillance (M&S) who guided and helped to achieve my
tasks.
Muhammad Husnain
Dy. Director (Civil)
th
135 Middle Management Course
WASC, Islamabad.
PREFACE
This is the report of Individual Management Experience which is being presented
in the 135th middle management course at WASC in Islamabad on 14th of
November, 2022. At Tarbela 4th Ext Project, there are two major sides, one is
right bank colony and the other one is called left bank colony. Due to construction
of T4th HPP some additional Houses were constructed in right bank colony and
an additional Over Head Water Tank was to be constructed to meet the Water
demand of the residents.
CDO Water designed the OHWT and issued drawings in 2013, 02x No Drawings
were revised and the specifications were changed from 3000 PSI to 4000 PSI
Concrete and the steel was recommended 60 Grade in place of 40 Grade. When
the construction was started and the contractor was directed to construct as per
new specifications, he submitted a Variation Order No 1 with additional cost of
Rs 6.04 Million. Contractor submitted a new concrete Mix Design and
consequently, new Rate for 1 cubic Meter 4000 PSI concrete was estimated as
about 37000/- and was agreed on 3607 Rupee by the both parties. The work was
done and the payments were made to the contractor. In 2021-22, Audit observed
and highlighted the case. Hence an Inquiry Committee was constituted with the
approval of Member (Water) who inquired the case and submitted its
recommendations and fixed the responsibility for loss to the Authority. I was
member of that Inquiry Committee who during visit of site led a team, I planned
and organized the activity and got control by getting the relevant documents from
Project office.
TABLE OF CONTENTS
1. INTRODUCTION ....................................................................................................... 1
5. MANAGEMENT ......................................................................................................... 6
5.1 Planning............................................................................................................................ 6
7. CONCLUSIONS ...................................................................................................... 12
8. RECOMMENDATIONS ........................................................................................... 13
Muhammad Husnain, 135th MMC
1. INTRODUCTION
1.1 Self Introduction
Name: Muhammad Husnain
• Joined WAPDA in 2010 and got first posting at Tarbela Dam Project in PMO.
• Promoted as Sr. Engr (Civil) in M&S in Feb, 2017 and working till to date.
• Shared 2nd position in 121st JMC at WASC with Mr. Waqas Ahmad, Dy
Course Director of 135th MMC.
Page 1 of 13
Muhammad Husnain, 135th MMC
Chairman
WAPDA
GM(M&S)
Tech.
AD. Consult.
CE (M&S) (ADMN) Advisor
(Inq.) DBDP
Dir.
Dir. (MC) Dir. (MP) (Mont) Dir. (Inq) Dir. (Inv.)
DBDP
DD
Dy. Dir Dy. Dir. (Admn)
(03 Nos) Dy. Dir. (02 Nos.)
AD
(Admn)
Asst Dir
Asst. Dir.
(02 Nos) AD(Legl)
Page 2 of 13
Muhammad Husnain, 135th MMC
• During audit of Accounts' record of the Project Director, Tarbela 4th Extension
Hydro Power Project for the period from July, 2020 to June,2021, it was
noticed that the drawings for overhead water tank were containing concrete
compressive strength of 4000 PSI and steel yield strength of 60,000 SI was
approved by the office of General Manager (CDO) wide letter dated
September 17", 2013. After tendering during 2017, the work order for
construction of O&M Staff colony for including construction of water tank was
awarded to M/s Sahibzada Liaquat Ali Shah & CO on Feb 18, 2018 @
Page 3 of 13
Muhammad Husnain, 135th MMC
• The matter was taken up with the management in August 2021. The
management stated that detailed reply would be given after consultation of
record. No further progress was intimated.
• As per General Conditions of Contract (GCC) Clause 1(k) "The Contract price
is the Accepted Contract amount Stated in the Letter of Acceptance and
thereafter adjusted in accordance with the Contract. Hence, change in
Contract Price is evident through the word adjustment i.e. either it may
increase or decrease.
Page 4 of 13
Muhammad Husnain, 135th MMC
• All the variations issued so far are in accordance with the provisions of Sub-
Clause 38 of GCC as per site requirements and for obtaining the best value of
the investment being made by the Employer on the Works.
• It is highlighted that all the Contract Documents in the World has the
provisions for the variations in the works based on actual site requirements
during the execution of works.
• All changes have been made as per site requirements and not due to
discrepancies in the Bidding Documents.
• All the Contractors submitted the Bids and rates quoted were as per strength
of concrete/steel provided in the Bidding Documents. Most responsive and
economical bidder is selected for execution of Works. Thus a fair competition
has been experienced in the Bidding process.
• It is pointed out that rates are to be agreed between the parties otherwise the
matter goes into the dispute. So the parities were agreed at the rate of PKR
36,007.84 per cum depending assessment as per site conditions and
acknowledging the facts that no price adjustment was applicable in the
Contract.
• The Audit working of cost breakdown has no justification under the Law and
Contract as neither it is based on WAPDA Drafting Standards nor any
Page 5 of 13
Muhammad Husnain, 135th MMC
reference of rates used in the analysis have been provided. Further, it has not
been approved by any competent technical forum.
• After award of the Contract, Contract Provisions are the binding between the
parties not the general norms/ justifications etc.
• Keeping in view the above narrated facts, Audit is requested to drop the
observation please.
To reach the actual facts, a Fact Finding Inquiry Committee was constituted with the
approval of Member (Water) vides Office Order No.GM(C&M)W/D(A)W/Inq-229/E-
I/1383-89 dated 04.02.2022 to examine the proposed Draft Para No.235/2021-22 on
account of increase in contract cost due to change in specifications issued by CDO
WAPDA after Award of Contract-Rs.6.04 million in respect of T4 Wapda Tarbela.
The undersigned was nominated as member of the Inquiry Committee. The
constituted Inquiry Committee was as under.
5. MANAGEMENT
5.1 Planning
a. Relevant record/ information will be needed to reach the actual facts
Page 6 of 13
Muhammad Husnain, 135th MMC
b. Actual site will be visited to see the Overhead Water Tank and to collect
the information
e. The proceedings will be carried out to conclude the report well in time.
5.2 Organizing
a. Chief Engineer/PD Tarbela 4th Extension Project was requested to
provide information/data related to Draft Para and to nominate a focal
person to assist the Inquiry Committee vide letter dated 08.02.2022.
c. First meeting of the Inquiry Committee was called vide letter dated
16.02.2022 and held in the office of Chief Engineer (Dams)/Convener of
the Inquiry Committee on 18.02.2022.
Page 7 of 13
Muhammad Husnain, 135th MMC
g. Chief Engineer/PD Tarbela 4th HPP was requested vide letter dated
March 02, 2022 to provide the data at the earliest as the matter is most
urgent.
h. The Competent authority was requested to extend the given date for
completion of the inquiry which was accorded.
k. During scrutiny of the record some further information was sought from
the Project Office regarding rate analysis of 4000 Psi concrete vide letter
dated 25.03.2022.
5.3 Leading
During my site visit, I led a team of following members which was provided by
the Project office to search the relevant record;
a. Mr. Tanveer Ud Din, Sr Engineer TDP, Focal Person to the Inquiry Committee
b. Mr. Farooq Niazi, Junior Engineer T4th HPP
c. Mr . Tauseef Ur Rehman, Sub Engineer T4th HPP
Page 8 of 13
Muhammad Husnain, 135th MMC
6. FINDINGS / OBSERVATIONS
a. Initially CDO Water issued 20 Nos of drawings for construction of 20,000 gallons
overhead water tank to Chief Engineer(/PD(Tarbela) 4th extension HPP vide his
letter dated 15.08.2013.
b. After lapse of almost one month, 2 No Drawings i.e. 512-2-55 (R1) and 512-2-
56(R1) were revised and issued by CDO Water to Chief Engineer/PD T 4 th HPP
vide letter dated 17.09.2013 wherein concrete compressive strength was
changed from 3000 PSI to 4000 PSI and steel yield strength from 40 KSI to
60000 KSI.
d. Contractor submitted the rate of reinforced cement concrete work using course
sand including all labour and material except the cost of steel reinforcement and
its labour for bending and binding which will be paid separately for concrete ratio
1:2:4 as Rs.17000 per Cumec and providing & fabricating mild steel intermediate
grade 40,000 Psi (276 MP) yield for cement concreate including cost of cutting,
bending, laying, making joints as 122 Rupees per kg.
e. Chief Engineer/PD T 4th HPP requested CDO for confirmation of concrete and
steels strengths Vide a letter dated 09.07.2018 for which CDO vide letter dated
Page 9 of 13
Muhammad Husnain, 135th MMC
f. Contractor was directed to carry out the mixed design for the super structure of
overhead water tank as per CDO approved drawings i.e. 4000 PSI for concrete
vide project director letter dated 22.06.2018. Contractor vide his letter dated
17.08.2018 submitted concreted mixed design for 4,000 PSI strength for the
construction of overhead water tank.
g. Contractor vide his letter dated 24.07.2018 replied that the deviation of concrete
strength as well as steel from G-40 to G-60 as per approved design is a
compensation event as it stopped them from starting the construction of
overhead water tank and require proportionate increase in contract price.
h. Project office vide letter dated 06.09.2018 directed the contractor to submit
quotations for G-60 steel and 4,000 PSI concrete for which contractor submitted
the new rates of 4000 PSI concrete, 60,000 PSI steel, PVC Class-D blind pipe of
300 mm dia, PVC Class-D strainer pipe of 300 mm dia, MS pipeline with internal
100 mm dia etc/ vide his letter dated 15.10.2018
i. The strength of concrete and steel covered in the estimates were 3000 PSI and
40,000 PSI respectively while as per CDO the required strength of the same
material was 4000 PSI and 60,000 PSI due to which Variation Order(VO) was
approved. New rates for 4000 PSI strength concrete and 60,000 PSI yield steel
was given as Rs.36,007.84 per cumec and Rs.179.23 per kg respectively based
on market rates.
j. VO No.1 was submitted for approval vide note NO.9574 dated 16.11.2018 and
was approved on 29.01.2019 by GM(Power)Tarbelawhich is 14.53% of the actual
contract price as per Wapda Book of Financial Power Section-IV Clause F(ii) in
conjunction with general instructions/ix and was issued to the contractor vide
letter dated 06.02.2019 for which contractor agreed vide his letter dated
11.02.2019.
Page 10 of 13
Muhammad Husnain, 135th MMC
k. Committee gone through the concrete mix design submitted by the contractor as
well as the contents of rate analysis submitted for approval of competent
authority wherein a major discrepancy was noticed by the committee that the unit
of quantities used in the mix design do not match with unit of quantities used in
the rate analysis.
The same was shared with the project office for making correction in the rate
analysis vide letter dated 25-03-2022. In response, project office, submitted the
corrected rate analysis vide their letter dated 29.3-2022, which was authenticated
by the project office during the visit of committee to project site on 05-04-2022 to
the actual rate of the concrete having strength 4000 PSI was authenticated to be
Rs 21000 for 01m3 instead of Rs 36000/- as approved through Variation Order
No. 1.
The committee also confirm the total quantity of the concrete 4000 PSI used for
construction of overhead water tank to be 103.5 m3 This confirm the loss of
Rs153,299.25/- to the authority with regard to concrete of 4000 PSI strength.
However, no such discrepancy was noticed for 60000 Psi Steel. Estimated loss is
as;
=14,811.5
=153,299.25 Rupees.
Page 11 of 13
Muhammad Husnain, 135th MMC
7. CONCLUSIONS
ii. Revised drawings were not taken into account during preparation of BOQ and
award of contract by the Project Office inadvertently.
iii. The specifications of concrete steel and others were changed and the work was
executed on the revised specifications. The specifications were changed in the
interest of Project as if overhead water tank was constructed on 3000 PSI
concrete strength and 40,000 PSI steel strength, the results would have been
different in the form of life/usability of the structure.
iv. On the basis of concrete mix design for 4000 Psi concrete New rate demanded
by the contractor was Rs. 37871.40/- per cubec meter. The rate was analyzed by
the Project Office and was curtailed to 36007.84 PKR/m3.
v. Inquiry Committee thoroughly studied the rates quoted by the contractor and
formulated by the Civil Directorate and reached the result that the quantities
taken to formulate the rate of 1 cubec meter 4000 Psi concrete were wrong as
the quantities were taken from concrete mix design where the units were used as
liter and the same quantities were used with the unit cubec feet while formulating
the rate analysis which resulted in huge difference of amounts resulted in loss to
the Authority.
vi. Inquiry committee, calculated new rate for 1 cubec meter 4000 Psi concrete PKR
21,188.50 per cubec meter with correct quantities based on the rates quoted by
the Contractor while formulating the rate as 37871.40 PKR/cubec meter.
vii. The difference of the rates i.e. rate given to the contractor and the actual rate of 1
cubec meter 4000 Psi concrete is the loss to the Authority which may be
recovered from the contractor by the Project Office to recover the loss to the
Authority.
Page 12 of 13
Muhammad Husnain, 135th MMC
8. RECOMMENDATIONS
i. The difference of the rates i.e. rate given to the contractor and the actual rate of 1
cubec meter 4000 Psi concrete is the loss to the Authority which may be
recovered from the contractor by the Project Office to save the loss to the
Authority.
ii. If it is not possible to recover the loss from the contractor, Project Team involved
in approval of rate analysis as well as approval of VO No.1 may be held
responsible for the loss to the Authority.
iii. If the contractor has not been paid its final bill/retention money, the loss should
be recovered from the contractor and letter of displeasure should be issued to
the Project Team to avoid such mistakes in future.
(Muhammad Husnain)
Deputy Director (M&S) Wapda
Participant of 135th MMC
at WASC, Islamabad
Page 13 of 13