Page 2 of 3 2 SURVEILLANCE ITINERARY AUDIT ISO 9001:2008 &
ASSESSMENT ITINERARY AUDIT OHSAS 18001:2008
0900 – 1000 hrs Top Management (Management Responsibility, Resources Management, Improvement, other relevant information)
1000 – 1200 hrs Operation (NDT, hydrostatic, pressure vessel, safety valve & inspection lifting gear and tubular goods certification)
Note : 1. The element 4, 5, 6, 8 and the understanding of Quality Policy & Objectives will be assessed simultaneously at the various
departments.
2. Kindly also ensure that at least ONE Management Review & Internal Audit covering the entire Quality Management System have
been conducted prior the assessment to proper.
3. Document and record control will be checked throughout the audit process in all departments being audited.
4. The above itinerary serves as general guideline. Changes in sequence and duration for each department may change depending on
situation during audit.