Professional Documents
Culture Documents
com
ADIS Question Paper & Answer – 2022 -- Sub code – 23110 -- 100 Marks
1. What are the safety measures to be taken, while working in tunnel? 8 Mark
Ans.
Tunneling is an underground activity, tunnels are required underground access for road-ways,
railways, through mountains. Tunnels are also used for irrigation of water, drainage, mining work
and defense installation.
2. What are the Hazards and their control measures in Excavation? 8 Marks.
Ans.
Hazards in Excavation: -
Ans.
Fall of person
Fall of materials
Fire & Explosion
Electrocutions
Failure of suspended load
Failure of winch machine
Failure of passenger lift
Communication gap
Slip/trip
Bad weather condition
4. What are the safety measures to be taken while handling construction machinery and
transport equipment? 5 Marks
Ans.
PPE (Personal protective equipment) are the safety equipment by which a person can prevent from
exposure to hazards by wearing it.
6. What are the safety precaution to be taken in store, handling and stacking of material in
construction? 5 Marks
Ans.
7. What are the hazards and control measure in construction of high rise buildings? 8 Marks
Ans.
Poor planning.
Cave-in i.e. collapse of soil.
Fall of person and material.
Failure of lifting tools.
Failure of man & material lift.
Lack of PPEs
Excessive dust and noise.
Lack of competency and safety training.
Lack of emergency planning.
Proper planning
Follow safe working procedure.
Implement effective emergency plan.
Provide proper training.
Proper inspection and certification of lifting tools must be done.
Provide adequate PPEs
Provide proper access egress.
Maintain good housekeeping.
Spray water to control dust.
8. What are the special safety precaution to be taken while working at silo? 5 Marks
Ans.
Silos should be erected on strong foundation and capable of bear load without any
damaging of walls, floors and parts.
Safe means of access must be provided such as ladder, stairs or hoists.
level indicator, notices, blockage remover and fire extinguishers should be provided and
available at work site.
www.safetymgmtstudy.com
ADIS Question Paper & Answer – 2022 -- Sub code – 23110 -- 100 Marks
Use flame proof electrical equipment and non-sparking tools where there is possibilities of
explosion and fire at silos.
Start work after valid work permit only.
Provide full body harness and lifeline.
Ans.
Ans.
Ans.
Demolition is the process of dismantling, razing, destroying or wrecking of any building or structure
or any part. Demolition is a very risky task it consists many hazardous activities, demolition hazards
are not limited it can be increase on situations.
12. What are the safety measures to be taken for scaffolding? 8 Marks
Ans.
Scaffold is a man-made temporary working platform use to support man and material during work at
height.
Ans.
Ans.
The cofferdam is a temporary structure use to exclude water from water-logged soil, because river
or the sea to enable the excavation and construction to be carried out in the dry. The cofferdam can
be made out of earth, concrete, sheet piles or sheet cell. The earthen cofferdam is possible in
shallow water with low velocity of current. The earthen bank is constructed 1 mt of the top water
level. Due to water seeping and leaking such dam can fail. Therefore, constant monitoring is
necessary. Sheet piled cofferdam can be constructed by using a floating structure with the help of
machinery and crew. All members of floating pile-driving crew must be trained to handle boats
safely. The interlocking sheet piles and bracing in a cellular form are placed through water. Fuel
tanks below deck of a floating pile-driving equipment should be vented to the outside air with flame
arresters. Workers handling piles should wear leather gloves. A competent person should constantly
supervise. After erecting the cofferdam, inside water is pumped out. The excavation is done in dry
soil up to a sound stratum, the foundation is laid down and the structure is built. The cofferdam is
dismantled thereafter.
Ans.
Demolition by hand Hand demolition is not a quick method, because only hand tools are used.
However, cranes and shear legs may be used to hold or lower beams during cutting. Chutes, or
crane-and-skip are usually used to get debris safely from the upper stories to the ground. Safe access
must be provided. If work cannot be carried out safely on the building, a scaffold or machine-lifted
platform should be used. Demolish only one storey at a time. It is usually safest to demolish the
building in the reverse order to building it, so the roof should go first. Next, part of each floor is
taken out so that the debris can fall through. On some jobs, the debris can be dropped down the lift
shaft, in which case, guardrails must be provided around openings. Debris must be removed
regularly and not allowed to pile up on floors. An overloaded floor could collapse onto the floor
below, which in turn, could collapse on the floor below it. Without propping from the floors, the
walls of the building could collapse. Walls could also collapse if debris is piled against them. If people
have to work in a place with a fall risk without guardrails or barriers to isolate them from a fall, other
protective measures must be implemented, including wearing a properly anchored safety harness.
Harnesses are only to be implemented if all other controls cannot be used. The employer shall need
to undertake a hazard assessment to effectively determine the appropriate controls beforehand. All
persons using any fall arrest systems must be fully trained in the correct and safe use of this
equipment. Guying or propping may be necessary to avoid hazards from wind or vibration. If only
part of the building is knocked down, make sure that what is left can stand safely.
Multi-storey demolition with ball and crane Demolition with the ball Most structures can be
demolished by balling, but it is a skilled practice that cannot be self-taught. Balling is a viable and
effective method of demolition when demolishing multi-storey structures that have suffered
structural damage, where all other methods have been considered, and a hazard assessment has
determined that this method is the most appropriate.