Project H&S Plan Example
Project H&S Plan Example
This material, including documentation and any related computer programs, is protected by copyright controlled by
Nokia. All rights are reserved. Copying, including reproducing, storing, adapting or translating, any or all of this
material requires the prior written consent of Nokia. This material also contains confidential information, which
may not be disclosed to others without the prior written consent of Nokia.
All persons working on NOKIA projects are required to take into consideration the health and
safety of all persons involved in any activities performed during the execution of their duties
whether he is an internal staff, external staff, contractors or members of the public
This document will serve as a reference document to all matters relating to Health and Safety
during the implementation phase of the project.
It should be read in conjunction with the relevant NOKIA Safe Working Procedures, Project
Baseline Risk Assessment and NOKIA Health and Safety Specifications.
The below chart describes the steps (HOW is it done, WHEN to be done and WHO
does it) to meet the health and safety requirements in Customer Operation Projects in all
project life cycle, including the health and safety contractor management part
The steps for H&S Project Management for CO projects and associated tasks were
integrated with the CO Program Lifecycle Process (PLC).
NOKIA Nigeria will approach its activities in a manner that will ensure compliance to Country specific
Health, Safety and Environmental laws and regulations and this will be achieved by planning, use of
policies, and the development and implementation of effective procedures.
Nokia Nigeria maintains a legal register containing the Nigeria specfic laws and regulations that governs
Nokia activities
Outline Scope of work, with the list of all Products and Services delivered
Hashem, RAMY
CT Head ramy.hashem@nokia.com
Haithem BEN-HAMOUDA
CDM haithem.ben_hamouda@nokia.com
Julius OLUWOLE
OD julius.oluwole@nokia.com
Fadi ZUBA
PM fadi.zurba@nokia.com
Health and Safety Advisor / Rita AYENI
Support
Rita.emdin@nokia.com
PPM (Project Procurement Uchechukwu OSUOJI
Manager)
uchechukwu.osuoji@nokia.com
HSS/H&S Country
MCA (Marketing and Corporate Affairs)
18-02-2019 – NIG_QHS_Airtel_HSP04042019_v1.1 © Nokia 2018
Implementation of H&S standards and procedures specifically for the country, based on
Purpose
Nokia' Global Standards and local Laws
Assure the full implementation of H&S requirements within the country
Provides professional H&S support to all operations
Ensures the training is appropriate for the task/activity
Translates Nokia global requirements to meet local legislative requirements
Key Tasks
Lead the investigation into incidents
Set H&S expectations for suppliers based on the risk posed by the contract / project
Conduct assessment of suppliers H&S capability during RFI (via PPM)
Conduct assessment of project business compliance for H&S development (via COM)
Country H&S guidelines in local language
H&S assessments to Service Suppliers (via PPM)
Objectives H&S assessments to project business (via COM)
Support PMO during Quality Gate control (check H&S plan during project ramp-up)
5.3 Specialist Permitted Sub-Contracted Delivered Work – with Nokia Prior Approval
Workplace – Any physical location in which work related activities are performed under the control of this project
(e.g. National Project Office, regional Project Offices, Customer’s premise, Sites, Test-plant, etc.)
Hazard – Source, situation, or act with a potential for harm in terms of human injury or ill health, or a combination
of these
Risk – Combination of the likelihood of an occurrence of a hazardous event or exposure(s) and the severity of
injury or ill health that can be caused by the event or exposure(s)
Evaluating of risk arising from each hazard – Estimate and evaluate how likely it is that a hazard will cause
harm, how serious that harm is likely to be; how often (and how many) workers are exposed.
Likelihood
Descriptor Level Definition
Unlikely Level 1 Numerous control measures would have to be intentionally by-passed. Very
little chance of happening/not foreseeable
May Happen Level 2 Control measures may fail or may be defeated. Sometime in 100 years.
Likely Level 3 There is an even chance this may happen. Within 10 years.
Very Likely Level 4 Control measures depend on a person using them on every occasion e.g.
administrate controls alone, PPE only etc. Within 1 year.
Certain Level 5 Harm from the hazard is certain or imminent if no control measures are
provided. Next shift.
Severity
Descriptor Level Definition
Minor Level 1 Slight injury (small paper-cut). Slight damage to equipment. Minimal cost.
No downtime. Very slight spill/small scale contamination.
Appreciable Level 2 Minor injury or first aid. No lost time (sprain/cut). Minor damage/parts
replacement. Minor contamination.
Major Level 3 Hospital treatment or lost time (severe cut/fracture etc.) Localized damage.
Localized contamination/spill.
Severe Level 4 Permanent disability e.g. amputation, blindes etc. Major damage to
equipment. Large-scale contamination.
Catastrophic Level 5 Fatality/multiple fatalities. Extensive damage to property. Major uncontained
release.
Hazards
Descriptor Definition
Physical Hazard directly generating the potential for physical injury
Chemical Hazard generated by materials and substances
Risk Controls – Determining controls for reducing risks according to the following hierarchy:
Descriptor Definition
Elimination Complete remove the hazard (e.g. removal of hazardous substance from the workplace)
Substitution Change a work practice, substance or piece of equipment to provide a safer environment
(e.g. substitute old office chair to ergonomic chair to reduce the risk of ergonomic
injuries)
Engineering Modify the design of the workplace or plant and/or environmental conditions (e.g. the
use of fume extracting system to remove fumes generated by hazardous substance use in
labs)
Administrative Developing procedures and systems to control the interaction between people and
hazards (e.g. reducing the amount of time of exposure to hazards, like climb up a tower
to complete the antenna system integration)
Personal Implementing PPE to prevent physical contact between people and hazards (e.g. correct
protective footwear, gloves, etc.)
equipment
Working @ Height – Any work where, if there were no precautions in place, a person could fall a distance that
could cause personal injury.
Requirements:
- All employees and contractors will be medically fit to climb
Training:
Pole Climber Minimum 1 day; 6:1 60% of this must be Relevant Personal Fall Protection Equipment Pre-use
practical Formally inspection of PFPE Pre-climb structure / workplace
refreshed, minimum checks Site Safety - Drop zones, signage, security Correct
every 3 years. If not use of portable ladders Ascending and Descending Poles
climbing regularly Work Positioning Handling tools and equipment
(>3 times /month) Emergency procedures
then needs to be
refreshed annually
Tower 1 day - additional Annual test / Casualty Care - Suspension Trauma Rescue Procedures
Rescue and separate to all refresher as Equipment for Rescue
other courses 6:1 appropriate
- Type of work:
18-02-2019 – NIG_QHS_Airtel_HSP04042019_v1.1 © Nokia 2018
1. Rooftop Work – Everyone working on roof structures must be appropriately trained and put in place
suitable controls to prevent access to fragile surfaces and falls from unprotected edges. The following
controls shall be considered in order of preference:
Work within an area protected by a guard rail or parapet
Keep 2m from unprotected edges and fragile surfaces. Where necessary set out a safe working area by
establishing demarcation barriers a minimum of 2m from unprotected edges and fragile surfaces
Use a restraint system attached to suitable anchor/s to prevent a fall.
2. Climbing– Everyone who climbs as part of their business for Nokia must:
Hold a valid climbing certificate applicable to the task to be undertaken and the structure to be
accessed
Make sure that their certificate is available for inspection by Nokia or its partners at all times
Be trained and equipped to undertake a rescue at height
Be accompanied by a second suitably trained and equipped climber
Be continually attached to the structure by an approved fall protection system when not on a protected
platform
Use approved methods of lifting and carrying equipment and tools.
3. Pole Climbing – Everyone working on the Fixed Overhead Network must be appropriately trained and put
in place suitable controls. The following controls must be considered in order of preference:
MEWPs/Cherry Picker or similar. If this is not available or not suitable due to the type of terrain, then:
o Use ladder or steps on the pole. Appropriate restraint must be used both by the person and for
the ladder. If a ladder or steps cannot be used, then:
o Use spikes.
1. Safety helmet
2. Safety boots
3. Gloves
4. Two-point full body harness
5. Four-point harness
6. Suspension harness
7. Twin tie back fall arrest lanyards
8. Restraint lanyard
9. Work positioning lanyard
10. Vertical fall arrest system traveler / sleeve
11. Temporary vertical lifeline
12. Self-reeling lifeline
13. Roof top restraint system
14. Temporary horizontal lifeline
15. Rope and pulley lifting rig
16. Karabiner connector
17. Anchor sling
18. Tower rescue kit
1. General Awareness
Everyone working for Nokia, whose role involves working on or coming into proximity of electrical
systems, circuits and installations must receive sufficient training related to the electrical risks to which
they are exposed.
The training must cover the risks arising from Nokia or customer electrical equipment and the
associated electrical installation i.e. fixed wiring, switches breakers, protective devices, power supplies,
or batteries, in the general vicinity.
The training must cover the defined rules, expected behaviors and controls detailed in this standard
The training must cover the “right to refuse” to work on something they believe is dangerous and the
escalation process to be followed for both unsafe practices and reporting unsafe installations
Live working is normally prohibited, however if it is not possible to isolate the circuits concerned, or
de-energizing them creates a greater hazard, an exception process must be established which ensures:
The reasons for the work needing to be conducted live are recorded.
A safe system of work is defined by a person competent in managing live working and the controls
necessary to reduce the very high risks involved.
There are at least two qualified persons present i.e. lone working is not permitted
Swapping out circuit boards or packs that are designed to be swapped out whilst the rack or unit is
powered up is not considered “live” working.
Requirements non-negotiables
1. Vehicle
Daily Pre-Use Check Sheets.
3 points Seat Belts and Head Rests.
Compartmentalization: The vehicle shall have appropriate load carrying capacity for tools and
material and a fixed segregation between load carrying areas and the passenger compartments.
Maintenance of Vehicles: All vehicles will be maintained in accordance and as prescribed by the
manufacturer of the said vehicle and be inspected as per the road traffic (motor vehicles, compulsory
inspection) rules.
“Fit for Purpose” – Suitable for use: The vehicle selected for use will be determined by the number of
people to be transported, the distances intended to be driven, the tools and materials that will be
transported and the nature of the roads that will be driven.
In-Vehicle Monitoring Systems (IVMS) installation and driver monitoring.
2. Driver
Driver must have a valid driving license.
Medical Requirements: Before being employed to undertake driving activities for Nokia all persons
expected to operate vehicles must be confirmed as being fit to drive.
All drivers shall be certified fit after undergoing an annual medical assessment. The medical
assessment shall be conducted by an Occupational Health Practitioner.
All Drivers must attend Defensive Driving course provided by certified training center.
3. Journey Management
The maximum amount of time that any one individual can drive for in any 24 hour period is 8 hours.
The maximum amount of work that any one individual is permitted to undertake, with driving
involved, is 12 hours.
No Night Driving on High ways or between cities.
Checking the weather conditions prior to starting the journey.
Considering security risks (e.g. theft or Harassment)
Consider the types of roads to be used.
Plan/consider alternative routes.
Always communicate any route changes to your manager, consider advising other persons about your
intended route (i.e. a family member, colleague)
Always wear a seat belt in ANY vehicle, all passengers should wear a seatbelt, anyone shall refuse to
drive or be driven in a vehicle with no seat belts.
Do not drive distracted or tired - take a break every 2hours. Distractions such as mobile phones shall be
avoided, Journeys should be planned to include breaks, and there shall be no driving in tired condition.
Always drive at a safe speed for road, traffic and weather conditions. Do not exceed the speed limit.
Speed limits for different types of road should be known Weather conditions should observe while
driving and speed slowed down accordingly. Journey should be planned to allow plenty of time.
Lift Supervisor
- A lift supervisor must be designated for all lifting activities.
- The lift supervisor must be trained in the requirements of the role, which as a minimum mean that they
must be:
• Trained as detailed in Nokia Global Work at Height Standard
• Responsible for the accuracy of the lift plan
• Responsible for the development of the risk assessment and method statement that supports the
lift plan
• Responsible for the delivery of the works in line with the lift plan
• Responsible for ensuring everyone working on the lift is appropriately trained, has the correct
equipment and understands their role in the lifting process
• Responsible for assessing the safety of the site before lifting starts, stopping work should any
concerns arise during the lift and making sure that the customer / site owner / operator is made
aware
- The lift supervisor must be competent as detailed in applicable legislation. These requirements must be
met as a minimum.
Working at Height
Considered as Manual Working at Height
Up to 10Kg Standard -Non-
Handling Standard
Negotiable
Working at Height
Considered as Simple Working at Height
Between 10kg and up to 50kg Standard -Non-
Rigging Standard
Negotiable
Working at Height
Standard -Non-
Considered as Rigging
Negotiable Rigging and
Between 50kg and up to 100kg requiring the use of Rigging and Lifting
lifting standard -
Capstan winch
Principles must be
reviewed and used
Working at Height
Standard -Non-
Considered as complex
Over 100kg Rigging and Lifting Negotiable Rigging and
Rigging
Lifting Standard - Non-
Negotiable
Climbing,
legal Legal Life Superviso First Aid Risk
Induction Fire Working at Electrical
Profile Basic Advanced Saving rs Tool & Basic Assessme Safe Driving
(Awareness) Fighting heights & Safety
OHS OHS Rules Kit CPR nt
Rescue
Safety Auditor X X X X X X X X X
Quality Auditor X X X X X X
Implementation Manager X X X X X X
Project Coordinator X X X X X X
Site Supervisor X X X X X X
Site Engineer X X X X X X X X
Site Technicians Team
X X X X X X X
Leaders
Site Technicians (Riggers) X X X X
Site Technicians
X X X X
(Electrician)
Driver X X X
Induction
and frequent
One
FREQUENCY One Time at least Yearly Yearly 2 years 2 years 2 years 2 years 2 years 2 years
Time
every 2
months
8.1.1 Supervision:
Site Supervision
Profile Training Supervision Report Recipients
%
Site Supervisor Refer to section-7 100% HSE Team & Project Team
Site Engineer Refer to section-7 100% HSE Team & Project Team
Site Technicians Team Leaders Refer to section-7 100% HSE Team & Project Team
8.1.2 Monitoring:
Site Monitoring
Profile Training Supervision Report Recipients
Frequency
Implantation Manager Refer to section-7 Monthly HSE Team & Project Team
Project Coordinator/ROM/PM Refer to section-7 Monthly HSE Team & Project Team
Senior Leader Quarterly HSE Team & Project Team
8.1.3 Auditing:
Meeting Frequency
Suppliers Meeting Weekly
Project Roll-Out Meeting Weekly
Project Operational Review Meeting Monthly
H&S Performance Review Monthly
Market Unit Services Meeting NA
Customer H&S Meeting NA
The customer team performances for H&S are “externally” reported and reviewed then with the Head of Market
Unit Services Kareem Shammaa during the Business Operational Review (BOR) meetings.
All related records are stored in Meetings Records.
All incidents – Near Misses, Fatal, Critical or Hipo cases to be reported to the project QHS respondible using the
Nokia Incident reporting form and other means of communication.
Nokia aim to involve both contractors and the customer in the investigation where appropriate and report sent to all
parties.
NOKIA will promptly report any HSE incident, injury, lost time incidents and near misses to Airtel
Within a reasonable period a report is to be provided to Airtel containing details of the incident,
contributing factors and corrective actions.
NOKIA will ensure reports are prepared within the timeline and will be submitted to Airtel by the Project
Manager.
In addition to the formal reporting requirements outlined below, NOKIA will verbally inform Airtel of
significant incidents, should they occur, to effectively keep it informed of situations or events particularly
if there is an impact on or involvement with stakeholders.
Additionally, once per year, a specific High-Risk Project H&S Implementation Assessment (HRPIA) is
performed to objectively identify possible improvements. All related records are stored in HRPIA