Professional Documents
Culture Documents
net/publication/260712278
CITATIONS READS
39 928
2 authors:
Some of the authors of this publication are also working on these related projects:
Flashover Characteristics of Silicone Rubber Materials under Various Contaminated Conditions for Application in Outdoor Polymeric Insulators View project
All content following this page was uploaded by William Chisholm on 26 February 2015.
slower-front and shorter-tail 250/2,500 wave flashed over at Figure 3. Full-wave flashover for +1,610-kV 5/4,700 surge in
250 kV/m. These results, and the observation that flashover 4.9-m rod-to-plane gap [5].
stress decreased with increasing gap distance (Figure 4), were
important.
It was more effective to modify the power system by reducing The 50 years from 1963 to 2013 have shown an impressive
the magnitude of likely surge magnitudes than to increase improvement in our understanding and control of power-
clearances. In this way, improved switching-surge performance system switching-surge overvoltages, as demonstrated in IEEE
of power systems to match the relatively low switching-surge literature. This improvement was fundamental to successful
strength of insulators became the main preoccupation of any design and operation of overhead transmission lines and stations
utility adopting EHV technology. at EHV voltages, reaching 500 kV in the early 1960s and 735 kV
Switching-surge magnitudes are expressed using the per-unit in 1965. The technical achievement of switching-surge control
system (pu), in which 1 pu is the peak line-to-ground voltage, or started with measurement campaigns [13]. Digital computer
the system voltage multiplied by √2 /√3. Switching at the peak tools were developed, including the Electro Magnetic Transients
of an ac voltage wave, and reflection of the voltage transient at Program (EMTP/ATP) [14], [15]. After cross-calibration these
an open point, can lead to a 2-pu surge at the open terminal. eventually replaced analog computers and transient network
analyzers in modeling the statistical distributions of switching-
overvoltage waveshapes and amplitudes. The overall result
was that switching surges could be effectively predicted and
controlled to levels below 2 pu by combining closing resistors in
circuit breakers and carefully selected surge arresters.
Interest in icing flashover was limited to the IEEE technical
group on electrical insulation, chaired by Perkins starting in
Manitoba Hydro ±500-kV lines with 21 insulators (3.07 m dry Development of Specialized Indoor
arc). In both cases, insulator length was selected on the basis of
Laboratories
well-controlled switching-surge levels of 1.7 pu.
Figure 9. Collection of drip water from iced insulators naturally precontaminated with road salt
(December 1989) [18].
of the year and in addition did not allow precise control of suggests that the desired temperature transition from below to
temperature or relative humidity. As shown in Figures 7 and 8, above freezing, with high relative humidity, occurs infrequently
high relative humidity from a close match of ambient and dew- outdoors, and led to the development of a number of specialized
point temperature, both rising slowly to melting at 0°C, proved indoor icing-test laboratories and standard procedures [23].
to be critical conditions leading to flashovers under normal ac
operating voltage. Indoor Testing With Dry-Arc Distance of 0.5 to 2 m
Icing flashovers under dc conditions were studied by EPRI as In 1967 Khalifa and Morris [29] used a 4.5 m × 7.6 m ×
part of Project UHV in January and February 1982 [21]. Three 3.7 m refrigerated chamber to apply rime ice with density of about
types of insulators, P3, G1, and NC1, were dc-energized outdoors 0.4 g/cm3 to insulators with up to 1.3 m of dry-arc distance.
and coated with ice on one side using a fire hose (Figure 10). With a 200-kV source, they found that long rod insulators were
An accretion period of up to five hours at temperatures below inferior to equivalent strings of porcelain discs. This observation
−4°C was used, similar to the ice progressive stress approach was confirmed later when field experience showed that station
described in [22] and [23], so that flashover was achieved post insulators and bushings were inferior to overhead line
in most tests. Ice thicknesses were up to 10 cm. In order to insulation under the same icing conditions.
compare results with different insulator profiles, a so-called A HV and icing research laboratory was constructed
icing stress product (ISP) is defined as the product of the ice, at Tempere University, in Finland, consisting of a 3.3 m ×
snow, or frost layer mass per centimeter of length, multiplied by 2.8 m × 5 m climate room with minimum temperature of
the electrical conductivity of the layer when removed, melted −65°C, 300 kVac, 100 and 130 kVdc test-voltage sources, and a
and measured at a reference temperature of 20°C. The ISP
values for outdoor test results [21] were estimated using the ice
thickness, insulator diameter, and 0.9 g/cm3 density for glaze-
ice weight per centimenter of dry-arc distance. The ice weights
were multiplied by the specified applied water conductivity of
41.5 μS/cm corrected to 20°C.
Figure 11 shows the dispersion in the 1982 outdoor test
results [21], plotted as dc voltage stress (kV per m of dry-arc
distance) against ISP, with green diamonds for withstand results
and brown squares for flashovers. More recent test results
for HVDC, using a well-controlled laboratory method with
no melting phase [24], which achieves typically 4% relative
standard deviation in the critical flashover stress E50, are also
shown. The circles relate to five different water conductivities,
and the dashed curve represents consolidated ac and dc+ results
from a standard icing-test method that incorporates a melting
phase [18], [25]–[28]. This curve indicates lower stresses than
all the other test results, since melting yields the minimum
flashover level. Only 1 of the 44 outdoor flashover results Figure 11. Outdoor and indoor icing-test results for HVDC
from [21] coincides with this minimum level. This observation [18], [21], [24].