You are on page 1of 9

See discussions, stats, and author profiles for this publication at: https://www.researchgate.

net/publication/252044181

Voltage upgrading - An insulation coordination challenge

Article · June 2011


DOI: 10.1109/PTC.2011.6019174

CITATIONS READS
10 940

7 authors, including:

Sonja Monica Berlijn Kjell Halsan


KTH Royal Institute of Technology Statnett
42 PUBLICATIONS   202 CITATIONS    18 PUBLICATIONS   120 CITATIONS   

SEE PROFILE SEE PROFILE

Some of the authors of this publication are also working on these related projects:

Voltage Upgrading of 300 kV lines to 420 kV View project

Lightning Impulse evaluation View project

All content following this page was uploaded by Sonja Monica Berlijn on 27 May 2014.

The user has requested enhancement of the downloaded file.


1

Voltage Upgrading – an Insulation Coordination


Challenge
S. Berlijn, Member IEEE, K.Å. Halsan, A.T. Olsen, M. Runde
M. Hinteregger, T. Judendorfer, Student Member IEEE, M. Muhr, Senior Member IEEE

Abstract—When voltage upgrading, lightning-, switching- ice- II. TOWERS


and pollution performance of the insulators and airgaps in the The towers that have been used by Statnett in the 300 kV
overhead line play a very important role. The dimensioning
procedure is different and technically more challenging from the network have just enough space to make upgrading possible.
one used for new lines. Amongst others, the margins available in Depending on the load, this is wind-, ice-, and line
voltage upgrading are much smaller and therefore the temperature load, geography and line angles, in some towers
engineering needs to be done more precise. To be able to perform there is enough space to upgrade and in some towers it is tight
the required engineering for voltage upgrading Statnett has and special solutions have to be implemented. Already in the
performed and is busy performing a number of R&D projects.
beginning of the upgrading effort it became clear that most of
Different types of insulators have been studied, as well as
pollution and lightning performance of the most used glass the problems will occur in the middle phase.
insulator. The precise gapfactors have been determined In the two figures below, typical 300 kV towers are
theoretically and practically in full scale. Besides that, tools for presented both before and after upgrading.
the determination of the exact air clearances have been taken into
use. A tool for determination of the total line performance with
correct gapfactors and insulator performance has been and is
being developed.

Index Terms— High Voltage Techniques, Power Grids,


Availability, Voltage upgrading, Insulation coordination.

I. INTRODUCTION

T O be able to meet tomorrows demand on the power grid,


Statnett is busy upgrading a large part (5000 km) of its
300 kV network to 420 kV.
There are basically two different types of line
configurations that are of interest for upgrading, the simplex
lines (ca 3500 km) and the duplex lines (ca 1500 km). Each of Fig. 1 Typical 300 kV towers before upgrading. On the left hand side: duplex
arrangement with single I-strings. On the right hand side: simplex
the configurations has its own specific set of problems. The
arrangement.
problems that both line types have in common is the insulation
coordination challenge.
The insulation coordination challenge comprises different
parts, which are investigated on its own, but this paper focuses
on the interaction between all parts and has its main focus on
the required minimum air clearances.
The different parts that amongst others can be identified
when voltage upgrading are:
- The length and type of the insulator strings used
- The air clearances used
- The lightning performance
- The switching overvoltage profile and performance
- The actual wind load for the different load conditions Fig. 2 Typical 300 kV towers after upgrading. On the left hand side: upgraded
- Clearance to ground duplex arrangement with V-chains. The additional 4 insulator discs can be
seen by the difference in color in glass insulators. .
On the right hand side: the upgraded simplex arrangement from Fig 1. (now
duplex)
S. Berlijn, A. Olsen and K. Halsan are with Statnett, PB 5192, Majorstuen,
NO 0302 Oslo, Norway (e-mail: sonja.berlijn@statnett.no).
M. Hinteregger, T. Judendorfer and M. Muhr are with Graz University of
Technology, Graz, Austria (e-mail: thomas.judendorfer@tugraz.at) M. Runde
is with NTNU, Trondheim, Norge (e-mail: magne.runde@sintef.no)
2

Because the length of the strings is mainly determined by


III. LENGTH AND TYPE OF INSULATORS the ice- and pollution performance of the insulators (as will be
The ‘typical insulators’ used in Statnett’s 300 kV lines are shown later), ice and pollution test on the most common used
glass insulators. Glass insulators were selected at that time, insulators have been performed [12]. The results of these
since they are the best choice considering maintenance and ice pollution- and ice tests will be used in the insulation
performance. coordination procedure that amongst others is using a special
Nowadays, there are many different types of insulators developed program called LPE (Line Performance Estimator)
which then also can be varied in length depending on the [9].
required performance. When upgrading there are two options:
a) replacing the existing insulator string by a different string
(arrangement) b) lengthening the existing string. Since it is
both the most practical and since it is difficult to get planned
outages for a long time on so many lines, the most cost
effective alternative is to lengthen the installed glass insulators
strings (where possible). However other alternatives are under
investigation. [7], [8]. Live data of this investigation can be
found on http://wap.stri.se.

Fig. 5 Results of pollution testing

Fig. 3 Three insulators that are monitored to be able to check the ice accretion
of insulators in real life, and to check swing angle calculations.

In typical 300 kV lines with duplex arrangement both I-


string and V-string arrangements are used. Typically the I- Fig. 6 Test set-up during ice testing
strings will be lengthened by 3 insulator discs (up to 17 discs)
and the V-strings with 4 insulator discs. Since in most cases the insulator will be lengthened live
Because of problems with space in the middle phase, it was line working is one possibility to be able to perform the
a question if it would be possible to lengthen the I-strings in changes necessary to upgrade the line. A number of R&D
there with only 2 discs (up to 16 discs). An investigation [10] activities have been performed at Statnett to investigate this
has shown that use of a shorter length can be allowed under possibility. In 2010/2011 all the suspension towers with V-
certain conditions. The total number of towers with this chains in one 300 kV line have been upgraded using this
solution should not exceed more than 25% of the total number method.
of towers, in case there is no heavy pollution and/or heavy
icing conditions.

Fig. 4 A typical I-string used in 300 kV lines. In 300 kV lines the number of
insulators is typically 14-15, but can be more in locations with heavy ice Fig. 7 Live line working in 300 kV lines. On the right hand side of the V-
loads. chain the 4 new inserted glass insulators can clearly be seen.
3

IV. LOAD CASES The requirement for the extreme wind condition that only
In [1] generally three load cases are considered: occurs for 2-5 seconds per 50 year, is of course that it can
1) Still wind conditions withstand AC overvoltages given by (3).
2) 3 year return time wind conditions The requirements (1), (2) and (3) only consider external
3) 50 year return time wind conditions clearances. Internal clearances might be decreased since they
For each of these conditions different air clearances are only have an effect on the system outages. Therefore internal
required, see next section for more details. clearances can be reduced.
The most frequently occurring load case will be the one in As can be seen from (1) the insulator length choosen will
between the three year return time and the still wind load case. have a direct effect on the required/needed air clearances. A
This will occur for 99,95% of the time. Wind over the three 15 cm shorter insulator, will result in a 15 cm shorter required
year return time will occur only for 0,05% of the time (around clearance and therefore 30 cm total distance will be gained.
4 hours per year). The 50 year return time represents extreme For new lines this is within the building uncertainty, but when
wind conditions (2-5 seconds per 50 years). voltage upgrading this will be the difference between feasible
The three load conditions and their distance requirements or not feasible.
are visualized in Fig. 8. For these three wind conditions the 1 K g _ ff _ is
swing angle of the lines/insulators will be different, as can be Del = ⋅ d is (1)
seen in the same figure. K a K g _ ff

1 ⎛⎜ 1080⋅K a ⋅K z _ sf ⋅K g _ sf ⎞
K cs ⋅U e 2% _ sf

Del = ⋅ e − 1⎟ (2)
0,46 ⎜ ⎟
⎝ ⎠
1 ⎛⎜ 750⋅ 3⋅K a ⋅K z _ pf ⋅K g _ pf ⎞
⋅U s

D pp = ⋅ e − 1⎟ (3)
0,55 ⎜ ⎟
⎝ ⎠

VI. DETERMINATION OF AIR CLEARANCE IN THE TOWERS


One important task is to determine the actual air clearance
Fig. 8 Sketch of a typical tower with the insulator in three different swing using a particular insulator configuration in each tower. At
angles (three different load cases)
Statnett this is done by using PLS CADD. A complete power
Experience with upgrading showed that most problems line model is made in PLS CADD using land and height
with clearances occur in the middle phase (ca 95%) in either profiles, results from helicopter scans that are made,
the still wind or three year return time wind condition. This photographs, detail tower drawings, string lengths etc. Studies
can be seen in the previous figure. Most of the other problems have been made towards the uncertainty of PLS CADD and
occur in the outer phases. the uncertainties between drawings and what is actually built.
First the tower model is made for the line as it is today.
V. DIFFERENT REQUIRED AIR CLEARANCES Then the insulator strings is lengthened by 50 cm. For this
configuration an initial check is made to find ‘problem
For each of the three load cases there are different
towers’. After these ‘problem towers’ are identified, different
requirements to the air clearance.
solutions are tried until the problem with the clearance has
According to [1] the minimum clearance for still wind
been solved.
condition is (1) or (2), whichever is greater. Since the ‘typical’
In Fig. 9 a tower and a part of the line are shown for the
line to be upgraded is 50 km long and the most frequent type
three load conditions. A) is the still wind condition, b), the
of switching is single phase auto recovery switching, the
three year return time wind condition and c) the 50 year return
switching overvoltages are not that high [11]. Besides,
time wind condition. In case of a tight tower, PLS CADD will
overvoltages can be limited by using surge arresters. And
mark this with a line and the results can be obtained by a
because of this, the overvoltage that should be used for the
reporting procedure in PLS CADD. It is however not so easy
dimensioning of voltage upgraded lines for still wind
to do this, since PLS CADD is not meant to be used for such
condition is lightning overvoltage.
precision electrical engineering.
Since the three year return time wind load condition only
occurs for less than 4 hours per year, the probability of
lightning to occur at the same time of the three year wind
condition is low [1]. So this means that the distance
requirement only considers switching overvoltages, i.e.
requirement given by (2).
4

even on the same line, is that lightning is a local phenomena.


Statnett prefers to have the lightning flashovers over the
insulator and not to the guy wire. With shorter insulators, the
distance required to prevent flashover to the guy wire is
shorter as well. However, the lightning performance of the line
might change. The external clearance requirement is based on
the longest insulator and remains untouched.
The first solution chosen is studied closer by using LPE
that besides the accurate distances obtained from PLS CADD
Fig. 9: The determination of the distances for the three load cases using PLS
CADD. in every tower is using, the real gap factors as found in the
study presented in the next chapters.
Let’s explain the procedure by an example. In Fig. 11 the
fault contribution of the different failure types and the
successful auto reclosing rate is presented for a line without
surge arresters. When the deviation from the selected insulator
length is zero (this means the standard length of insulator, e.g.
17 discs), 8% of the failures will be caused by ice flashovers,
Fig. 10 PLS CADD identifying the clearance problem. In this case for still 35% of the failures will be caused by pollution flashovers and
wind conditions. (the angle of the insulators is caused by the line having an 57% of the failures will be caused by lightning flashovers. The
angle) successful auto reclosing rate is 58%, which is unacceptable.

VII. INSULATION COORDINATION PROCEDURE


The procedure for determining which insulator length will
be used in a particular tower, which air clearance should be
used in the towers, whether or not surge arresters shall be
used, single phase or three phase switching, what an
acceptable level of outages is for icing outages, pollution Standard length
outages and lightning outages is very complicated. All
parameters will influence the other choices. Besides that a
very detailed and accurate engineering is necessary since the
margins available are small.
Quite often, a number of co-ordination procedures on the
same line are necessary to get everything on place. 1 insulator extra
Before starting, climatic loads, failure statistics and
lightning statistics are collected. This data is used to
‘calibrate’ LPE (Line Performance Estimator) and to be able
to calculate swing angles and future outage rates. Then a very
accurate model of the line is made in PLS CADD. In the first
model of the 420 kV line, the ‘standard’ solution of insulators
and insulator lengths is used. This is the lengthened glass
insulator string. The number of insulators used is depending Fig. 11 Failure contributions of the different failure types and the rate and
on the climatic conditions such as ice and pollution. Typically successful auto reclosing rate, with no surge arresters on the line
17 insulator discs are used. The required clearances for this
First of all, by lengthening the insulators, the total number
length of insulators are set, using the formulas (1,2 and 3).
of failures will be decreased. In this case from 2,5 to 1,5
Using these required clearances, problem towers are
failures per 100 km per year. From Fig. 11 it can be seen that
identified. Most of the problems will occur in still wind or
by lengthening the insulator string with one disc, the number
three year return time wind condition. For these towers, 16
of pollution and ice failures will decrease, while the failure
insulator discs might be used, using the required clearances for
contribution of lighting will increase (relatively). Lighting
16 insulators in still wind conditions and the same condition
failures are of short duration while outages because of ice and
for the three year return time wind condition.
pollution last longer, so this is positive. From the same figure
Most of the problems will be solved but in case some
it can be seen that lengthening the insulators have almost no
problems still exists, alternative solutions such as V-chains are
effect on the successful auto-reclosing rate. This problem can
considered. In some cases also smaller distances might be
be solved by placing surge arresters, as can be seen in Fig. 12.
accepted if the influence to the total line performance is not
significant.
The reason why the internal clearance requirements are
different for lightning impulses, with different insulator length
5

IX. GAP FACTORS IN UPGRADED TOWERS, THEORETICAL STUDY


The air space inside the tower window may be seen as
multiple air gaps with a strike length d. The tower window can
mainly be divided into three air gaps: conductor-cross arm,
conductor-tower pole and conductor-guy wire.

Fig. 12 Failure contributions of the different failure types and the rate and
successful auto reclosing rate, with two surge arresters

For voltage upgrading, however, it is not self-evident that


the failure rate decreases with increasing length of insulators.
This because the percentage of the failures caused by lightning Fig. 13 The different airgaps in the tower window and tower
will increase caused by the longer insulator and this causes
decreased air distances. Here is where accurate gap-factors When designing new transmission lines, it makes sense to
play an important role. use one common gap factor, which would be the lowest one of
It is not let to be unmentioned that due to the climatic the three, for the whole air space within the tower window as a
conditions of Statnett’s 300 kV network, longer insulators are conservative value. When it comes to voltage upgrading, the
preferred compared to large airgaps inside towers. air clearances within the tower is limited, making it interesting
to examine all relevant air gaps within the tower window to
VIII. THE IMPORTANCE OF GAP FACTORS get a more accurate description of the characteristics of the air
gap and hence the withstand strength.
When voltage upgrading it turned out that the gap factor The theoretical study performed by NTNU, showed that
will have a significant influence on the whole design previous performed tests (at STRI and at SINTEF) have
procedure, as mentioned in previous paragraphs. shown that the lightning performance of insulators is around
In [2] it is discussed that compacting towers (or upgrading 12% higher than the values obtained from the standard. The
towers) has a positive influence towards the real gap factors. Switching performance is about 5% better than the values
Since also the distances used in [1] where thought to be a obtained from the standard.
bit conservative and since Statnett didn’t want to take high Further it showed that when determining the gap factors
risk, a study was started to know the exact margins, or better accurately compared to using the standard values given in [1],
the right gap factors for the towers to be upgraded. First a the withstand strength of the air gap to the guy wire would be
theoretical study was performed. This study showed that there 7-8% better than the insulator strength, instead of being equal.
were margins in the gapfactor and therefore full scale tests This gave enough evidence to make it interesting to
have been performed in 2010. perform full scale tests. The reason to perform full scale test
That gapfactors play an important role as can be seen in (1) and not scaled tests, is that the insulators and accessories are
and (2). The required clearances are proportional to the difficult to scale down and besides that it might have influence
gapfactors. It was found that by using the correct gap factors, on the final results.
the distances can be reduced between 10-20% (this is 20-
35 cm or two insulator discs). When taking into account that X. GAP FACTORS IN UPGRADED TOWERS, FULL SCALE TEST
the requirement for lightning impulses is around 3 meters and
for switching impulses around 2 meters, one can deduce The practical full scale tests have been performed at the
directly that this is the difference in 1 insulator disc more in High Voltage Laboratory of the Graz University of
the string – meaning decreased number of faults caused by Technology [5]. Most of the problems in terms of insulation
pollution and ice or preventing mounting a V-chain coordination will occur at the centre phase of the steel tower.
configuration in the middle phase. Therefore, a full scale model of the centre phase of a relevant
tower has been designed and constructed in Graz (Fig. 14).
With this model it was possible to research specified distances
6

between the centre phase to the tower and guy wires


A. Results for lightning impulse tests
respectively, which occur at relevant swing angles.
The test program contained experiments with lightning The results for the lightning impulse tests are presented in
impulse voltages and switching impulse voltages. Furthermore Table I to Table III. With these test results, the gap factors can
switching impulse voltage tests have been conducted as wet be calculated. They are presented in Table IV and in Table V.
test with artificial rain also. The tests have been performed for With these gap factors, the required distances can be
several gaps to get a trend of withstand behaviour. In case of calculated and as one can see, this results in a distance
lightning impulse voltage testing, the area of occurrence of requirement that is ca 25-30 cm smaller.
flashovers inside the tower window was of particular interest. If one looks back to the paragraph about the line
The tower window has been divided into 6 areas and the performance one can see that this possible increase in insulator
flashovers have been photographed to assign them to the length has an impact on the line performance and also on the
appropriate area. The U90%-voltage has been determined lightning performance. And in case of upgrading it can make
beforehand and remained constant for all lightning impulse the difference between being able to use an I-String or not.
TABLE I CORRECTED U50%-VALUES AND U90%
tests. Type of Shortest Corrected voltage value in [kV]
The main target of the tests with switching impulse voltage corona ring striking U50% U90%
was to determine the U50%-voltage for several specified gaps distance in [m]
respectively swing angles. Similar to the tests with lightning 1 2.73 1515.62 1574.73
2 2.60 1483.44 1541.30
impulse voltage, the area of flashover occurrence has been
determined visually and with photographs. TABLE II RESULTS - CORONA RING TYPE 1
Within the impulse voltage test series, two different types Shortest striking Percentage of flashover
distance in [m] Along Insulator In air gap
of corona ring have been evaluated (Fig. 15). The first type of
2.60 100 0
corona ring consists of one horizontal ring, the second type of 2.50 70 30
two vertical rings. The total length of the insulator (number of 2.44 20 80
cap-and-pin insulators) is depending on the type of corona 2.35 0 100
ring. TABLE III RESULTS - CORONA RING TYPE 2
Shortest striking distance Percentage of flashover
in [m] Along In air gap
Insulator
2.45 100 0
2.35 95 5
2.28 0 100

TABLE IV COMPARISON OF GAP FACTORS FOR INSULATOR


STRENGTH
Type of Gap factor: Gap factor: Gap factor:
Fig. 14 Full scale test model used in Graz: simulated displacement of insulator corona ring Test TU Graz Standarda, b Literaturec,d
due to wind (left); dielectric wet test (right 1 1.052 1.07 (1.12) 0.99 (1.08) c;
1.10 d
2 1.081 1.07 (1.12) 0.99 (1.08) c;
1.10 d
a. Standard EN 50341-Part 1 [1]
b. Standard IEC 60071-Part 2 [13]
c. see [14] d. see [4]

TABLE V COMPARISON OF GAP FACTORS FOR AIRGAP


Type of Interpolation Gap factor Gap factor
corona ring striking Test TU Standarda,b
distance in Graz
[m]
1 2.476 1.15 1.07
Fig. 15 Corona ring – Type I (left) and type II (right) 2 2.317 1.21 1.07
a. Standard EN 50341-Part 1 [1]
b. Standard IEC 60071-Part 2 [13]
XI. EVALUATION OF THEORETICAL AND EXPERIMENTAL
TABLE VI COMPARISON OF REQUIRED DISTANCES
RESULTS
Type of corona Required Distance Required distance
The test results and the results from the theoretical study, ring Test TU Graz Standarda,b
which are explained in detail in [5] and [4] can be summarized 1 2.51 2.74 (2.87)
2 2.45 2.74 2.87)
as follows. a. Standard EN 50341-Part 1 [1]
b. Standard IEC 60071-Part 2 [13]
7

Table VII RESULTS OF BOTH CORONA RINGS (DRY TESTS) – insulator


strength
Type of Shortest Corrected voltage value in
corona ring striking [kV]
distance in [m] U50% U10%
1 2.73 1098.25 1012.59
2 2.60 1101.51 1015.59

TABLE VIII RESULTS OF BOTH CORONA RINGS (DRY TESTS) – AIRGAP


STRENGTH
Type of Shortest Corrected voltage value in
corona ring striking [kV]
distance in [m] U50% U10%
1 1.90 962.21 887.16
1 1.55 871.25 803.29
1 1.40 796.40 734.28
2 1.90 911.16 840.09

TABLE IX COMPARISON OF GAP FACTORS FOR INSULATOR


STRENGTH
Type of Shortest Gap factor Gap factor
corona ring striking Test TU Standarda,b
distance in Graz
[m]
1 2.73 1.26 1.25 (1.45)
2 2.60 1.31 1.25 (1.45)
a. Standard EN 50341-Part 1 [1]
b. Standard IEC 60071-Part 2 [13]
Fig. 16 Flashover from the conductor to the guy wire
TABLE X COMPARISON OF GAP FACTORS FOR THE AIR GAP
Type of Shortest Gap factor Gap factor
corona ring striking Test TU Standarda,b
distance in Graz
[m]
1 1.55 1.50 1.25
1 1.40 1.48 1.25
a. Standard EN 50341-Part 1 [1]
b. Standard IEC 60071-Part 2 [13]

XII. SUMMARY AND CONCLUSIONS


A very thorough investigation has been performed towards
the best insulation coordination possible for upgraded lines
and is presented in detail in this paper. The different load
cases and air clearance requirements have been discussed as
well as the procedure to determine the actual clearances of the
line to be upgraded as well as the procedure used for the
insulation coordination. The full scale test results have shown
that the air gap distances can be reduced significantly without
meaning any extra risk for failure. With significant it is meant
that the air gap clearances to the guy wires can be reduced
from 1,9 or 1,7 m to 1,4 m for switching impulse and from
2,8 m to 2,5 m for lightning impulse. This means that either
longer insulator strings can be used, that reduce the failure
Fig. 17 Flashover over the insulator string rate, or that use of different chain configurations are
prevented.
The results show that there is an enormous saving potential
B. Results for switching impulse tests
when doing accurate insulation coordination, without
The results for the switching impulse tests are presented in influencing the failure rate.
Table VII and Table VIII. With these test results, the gap For a 100 km line it meant a saving of 650 k Euro. When
factors can be calculated. They are presented in Table IX and
keeping in mind that Statnett has plans of upgrading 1500 km
in Table X. With these gap factors, the required distances can
duplex line, by keeping the same towers and increasing the
be calculated and for a required U50%-withstand voltage of
780,9 kV and can be reduced from 1,70 m to 1,36 m in case of insulation, one can calculate very easily that this project was
dry conditions. worth the trouble.
8

Anders OLSEN received his Master of Science in


Electrical Power Engineering from the Norwegian
XIII. ACKNOWLEDGMENT University of Science and Technology in Trondheim in
2010. During spring 2110 he wrote a thesis on voltage
The authors would gratefully acknowledge the upgrading. Since June 2010 he has been working at the
contributions of STRI – Igor Gutman, Jan Lundquist, Konrad overhead line department at Statnett, mainly on voltage
upgrading projects.
Kupisz and EFLA – Ragnhildur Jonsdottir for their work in
the described voltage upgrading effort.

Kjell HALSAN received his Master of Science in


XIV. REFERENCES
Electrical Power Engineering from the Norwegian
[1] EN 50341-1: ‘Overhead Electrical Lines exceeding 45 kV part 1: University of Science and Technology in Trondheim in
General requirements – common specifications’ October 2001 1987. Involved in electrical engineering of transmission
[2] M. Kvarngren: ‘Screening of sharp points in compact transmission lines in Statnett since 1988. Active in various research
towers’ TRITA-EEA-9706 ISSN 1100-1593 projects on electrical components for transmission lines
[3] A.T. Olsen: ‘Voltage Upgrading of Overhead Lines’ Pre study Master and development of engineering tools for design of
thesis Dec 18. 2009 NTNU dept of electric power engineering transmission lines. He has been manager for section of
[4] A.T. Olsen: ‘Voltage Upgrading of Overhead Lines’ Master thesis June electro-mechanical design of transmission lines since
11. 2010 NTNU dept of electric power engineering year 2000. He is active in CIGRE and is Norwegian
[5] M. Hinteregger et al.: ‘Voltage withstand tests on a full-scale overhead National member of SC B2-Transmission Lines
tower model for line upgrading’, EIC 2011, Annapolis; to be published
[6] Sonja Berlijn et al., ‘Optimizing the electrical clearances in towers Magne RUNDE was born in Skien, Norway, in 1958.
voltage upgraded from 300 kV to 420 kV’, NORD-IS 2011, Tampere, He received a MSc degree in physics and a PhD degree
Finland; to be published in electrical power engineering from the Norwegian
[7] I Gutman, A. Dernfalk, K. Halsan, S. Berlijn, L Carlshem, M. Uehara, J. University of Science and Technology (NTNU) in
Seifert: ‘Flashover performance of line composite insulators with Trondheim, Norway in 1984 and 1987, respectively. He
different profiles intended for ice & snow environment’ , IWAIS 2009 has been with SINTEF Energy Research in Trondheim,
[8] S.M. Berlijn, I. Gutman, K.Å. Halsan, M. Eilertsten, I.Y.H. Gu: ‘ Norway since 1988. From 1996 on he is a professor in
Laboratory Tests and Web Based Surveillance to determine the Ice- and high-voltage technology at NTNU. He fields of interest
Snow Performance of Insulators’ IEEE DEIS 2007 include circuit-breakers and switchgear, electrical
[9] I. Gutman, J. Lundquist, K. Halsan, L. Wallin, E. Solomonik, W. contacts, power cables, diagnostic testing of power
Vosloo: “Line Performance Estimator Software: Calculations of apparatus, and power applications of superconductors.
Lightning, Pollution and Ice Failure Rates Compared with Service Michael HINTEREGGER is currently pursuing his
Records”, in Proc. of CIGRE Session 2006, B2-205 Dipl.-Ing. degree in electrical engineering at Graz
[10] Andreas Dernfalk ‘Effect on the pollution performance of an upgraded University of Technology. Since March 2009 he is also
OHL when reducing the insulator length in the middle phase. STRI with the Test Institution of High Voltage Engineering
report R10-698, 2010 Graz Ltd. and responsible for insulation coordination
[11] Jan Lundquist ‘Calculated overvoltages at line energization’ and and transient simulation studies.
Calculation of witching overvoltages STRI UTM09-327 and STRI
report R04-202, 2009 and 2004
[12] I. Gutman, A. Dernfalk, “Pollution flashover performance curve for NTP
33048 50 insulator”, STRI Technical Message, UTM09-332, 2009
[13] Standard IEC 60071 ‘Insulation coordination’ part 2 ‘application guide, Thomas JUDENDORFER received the Dipl.-Ing.
p.195, June 1996 degree from Graz University of Technology, Austria in
[14] A.R. Hileman, Insulation Coordination for Power Systems, New York: 2007. Since 2008 he is working as research assistant at
Dekker, 1999, p. 167. the Institute of High Voltage Engineering and System
Management at Graz University of Technology. His
major fields of research include insulation coordination,
insulation systems and high voltage overhead lines.
Furthermore he is pursuing his PhD in the field of oil-
XV. BIOGRAPHIES cellulose insulation systems for HVDC applications.
Michael MUHR is Professor and Vice Rector
Sonja BERLIJN received her M.Sc. degree from the Academics at the Graz University of Technology in
TUE, Eindhoven, the Netherlands in 1994, and her PhD Austria. He is the Head of the Institute of High Voltage
degree from TUG, Graz, Austria, in 2000. She has been Engineering and Managing Director of the Test
working at the High Voltage Laboratory of KEMA; the Institution of High Voltage Engineering Graz Ltd. He is
Netherlands, and at STRI in Sweden. Since 2008 she is also a member in national and international societies as
working at the overhead line department at Statnett and ÖVE, ÖGE, DKE, IEEE, IEC and convener of 5
she is responsible for a number of R&D activities. From working groups in CIGRE. He is supporting
1993-2008 she was a member of CIGRE WG D1.33 cooperation’s with institutes in several countries as well
¨High Voltage Testing and Measuring Techniques¨. as with national and international industry and utilities.
Since 2009 she is a member of TC 11 High voltage
power lines. In 1998 she got a Working Group
Recognition Award from PES IEEE and in 1999 she got
the prize paper award from ISH 99/Hydro-Quebec.

View publication stats

You might also like