Professional Documents
Culture Documents
Sprint
Requirement ID Epic Feature User Story Title
1
MTE-010-010-01 ManufactureMTE-010:
to Execute
Production Master
Sprint 1 MTE-010-010:
Data Production Master Data
MTE-020-020-01 ManufactureMTE-020:
to Execute
Production Order
Sprint 1 MTE-020-020: Manage Discrete Manufacturing
MTE-020-020-02 ManufactureMTE-020:
to Execute
Production Order
Sprint 1 MTE-020-020: Manage Discrete Manufacturing
MTE-020-020-03 ManufactureMTE-020:
to Execute
Production Order
Sprint 1 MTE-020-020: Manage Discrete Manufacturing
MTE-020-020-04 ManufactureMTE-020:
to Execute
Production Order
Sprint 1 MTE-020-020: Manage Discrete Manufacturing
MTE-020-020-05 ManufactureMTE-020:
to Execute
Production Order
Sprint 1 MTE-020-020: Manage Discrete Manufacturing
MTE-020-020-06 ManufactureMTE-020:
to Execute
Production Order
Sprint 1 MTE-020-020: Manage Discrete Manufacturing
MTE-020-020-07 ManufactureMTE-020:
to Execute
Production Order
Sprint 1 MTE-020-020: Manage Discrete Manufacturing
MTE-020-020-08 ManufactureMTE-020:
to Execute
Production Order
Sprint 1 MTE-020-020: Manage Discrete Manufacturing
MTE-020-020-09 ManufactureMTE-020:
to Execute
Production Order
Sprint 1 MTE-020-020: Manage Discrete Manufacturing
MTE-020-020-10 ManufactureMTE-020:
to Execute
Production Order
Sprint 1 MTE-020-020: Manage Discrete Manufacturing
MTE-020-020-11 ManufactureMTE-020:
to Execute
Production Order
Sprint 1 MTE-020-020: Manage Discrete Manufacturing
MTE-020-020-12 ManufactureMTE-020:
to Execute
Production Order
Sprint 1 MTE-020-020: Manage Discrete Manufacturing
MTE-020-020-13 ManufactureMTE-020:
to Execute
Production Order
Sprint 1 MTE-020-020: Manage Discrete Manufacturing
MTE-020-030-01 ManufactureMTE-020:
to Execute
Production Order
Sprint 1 MTE-020-030: Manage Repetitive Manufacturi
MTE-020-030-02 ManufactureMTE-020:
to Execute
Production Order
Sprint 1 MTE-020-030: Manage Repetitive Manufacturi
MTE-020-030-03 ManufactureMTE-020:
to Execute
Production Order
Sprint 1 MTE-020-030: Manage Repetitive Manufacturi
MTE-020-030-04 ManufactureMTE-020:
to Execute
Production Order
Sprint 1 MTE-020-030: Manage Repetitive Manufacturi
MTE-020-030-05 ManufactureMTE-020:
to Execute
Production Order
Sprint 1 MTE-020-030: Manage Repetitive Manufacturi
MTE-020-030-06 ManufactureMTE-020:
to Execute
Production Order
Sprint 1 MTE-020-030: Manage Repetitive Manufacturi
MTE-020-030-07 ManufactureMTE-020:
to Execute
Production Order
Sprint 1 MTE-020-030: Manage Repetitive Manufacturi
MTE-020-030-08 ManufactureMTE-020:
to Execute
Production Order
Sprint 1 MTE-020-030: Manage Repetitive Manufacturi
MTE-010-010-02 ManufactureMTE-010:
to Execute
Production Master
Sprint 1 MTE-010-010:
Data Production Master Data
MTE-010-010-03 ManufactureMTE-010:
to Execute
Production Master
Sprint 1 MTE-010-010:
Data Production Master Data
MTE-010-010-04 ManufactureMTE-010:
to Execute
Production Master
Sprint 1 MTE-010-010:
Data Production Master Data
MTE-010-010-05 ManufactureMTE-010:
to Execute
Production Master
Sprint 1 MTE-010-010:
Data Production Master Data
MTE-010-010-06 ManufactureMTE-010:
to Execute
Production Master
Sprint 1 MTE-010-010:
Data Production Master Data
MTE-010-010-07 ManufactureMTE-010:
to Execute
Production Master
Sprint 1 MTE-010-010:
Data Production Master Data
MTE-010-010-08 ManufactureMTE-010:
to Execute
Production Master
Sprint 1 MTE-010-010:
Data Production Master Data
MTE-010-010-09 ManufactureMTE-010:
to Execute
Production Master
Sprint 1 MTE-010-010:
Data Production Master Data
MTE-010-010-11 ManufactureMTE-010:
to Execute
Production Master
Sprint 1 MTE-010-010:
Data Production Master Data
MTE-010-010-12 ManufactureMTE-010:
to Execute
Production Master
Sprint 1 MTE-010-010:
Data Production Master Data
MTE-020-030-09 ManufactureMTE-020:
to Execute
Production Order
Sprint 1 MTE-020-030: Manage Repetitive Manufacturi
MTE-020-030-10 ManufactureMTE-020:
to Execute
Production Order
Sprint 1 MTE-020-030: Manage Repetitive Manufacturi
MTE-020-030-11 ManufactureMTE-020:
to Execute
Production Order
Sprint 1 MTE-020-030: Manage Repetitive Manufacturi
MTE-020-030-12 ManufactureMTE-020:
to Execute
Production Order
Sprint 1 MTE-020-030: Manage Repetitive Manufacturi
MTE-020-030-13 ManufactureMTE-020:
to Execute
Production Order
Sprint 1 MTE-020-030: Manage Repetitive Manufacturi
MTE-020-030-14 ManufactureMTE-020:
to Execute
Production Order
Sprint 1 MTE-020-030: Manage Repetitive Manufacturi
MTE-020-030-15 ManufactureMTE-020:
to Execute
Production Order
Sprint 1 MTE-020-030: Manage Repetitive Manufacturi
MTE-020-030-16 ManufactureMTE-020:
to Execute
Production Order
Sprint 1 MTE-020-030: Manage Repetitive Manufacturi
MTE-020-030-17 ManufactureMTE-020:
to Execute
Production Order
Sprint 1 MTE-020-030: Manage Repetitive Manufacturi
MTE-020-030-18 ManufactureMTE-020:
to Execute
Production Order
Sprint 1 MTE-020-030: Manage Repetitive Manufacturi
MTE-020-030-19 ManufactureMTE-020:
to Execute
Production Order
Sprint 1 MTE-020-030: Manage Repetitive Manufacturi
MTE-020-030-20 ManufactureMTE-020:
to Execute
Production Order
Sprint 1 MTE-020-030: Manage Repetitive Manufacturi
MTE-020-030-21 ManufactureMTE-020:
to Execute
Production Order
Sprint 1 MTE-020-030: Manage Repetitive Manufacturi
MTE-020-030-22 ManufactureMTE-020:
to Execute
Production Order
Sprint 1 MTE-020-030: Manage Repetitive Manufacturi
MTE-020-030-23 ManufactureMTE-020:
to Execute
Production Order
Sprint 1 MTE-020-030: Manage Repetitive Manufacturi
MTE-020-030-24 ManufactureMTE-020:
to Execute
Production Order
Sprint 1 MTE-020-030: Manage Repetitive Manufacturi
MTE-020-030-25 ManufactureMTE-020:
to Execute
Production Order
Sprint 1 MTE-020-030: Manage Repetitive Manufacturi
MTE-020-030-26 ManufactureMTE-020:
to Execute
Production Order
Sprint 1 MTE-020-030: Manage Repetitive Manufacturi
MTE-020-010-01 ManufactureMTE-020:
to Execute
PrSprint 1 MTE-020-010: Schedule Production/ Planned
MTE-020-010-02 ManufactureMTE-020:
to Execute
PrSprint 1 MTE-020-010: Schedule Production/ Planned
MTE-020-010-03 ManufactureMTE-020:
to Execute
PrSprint 1 MTE-020-010: Schedule Production/ Planned
MTE-020-010-04 ManufactureMTE-020:
to Execute
PrSprint 1 MTE-020-010: Schedule Production/ Planned
MTE-020-010-05 ManufactureMTE-020:
to Execute
PrSprint 1 MTE-020-010: Schedule Production/ Planned
MTE-020-010-06 ManufactureMTE-020:
to Execute
PrSprint 1 MTE-020-010: Schedule Production/ Planned
MTE-020-010-07 ManufactureMTE-020:
to Execute
PrSprint 1 MTE-020-010: Schedule Production/ Planned
MTE-020-030-27 ManufactureMTE-020:
to Execute
Production Order
Sprint 1 MTE-020-030: Manage Repetitive Manufacturi
MTE-020-030-28 ManufactureMTE-020:
to Execute
Production Order
Sprint 1 MTE-020-030: Manage Repetitive Manufacturi
MTE-020-030-29 ManufactureMTE-020:
to Execute
Production Order
Sprint 1 MTE-020-030: Manage Repetitive Manufacturi
MTE-020-010-08 ManufactureMTE-020:
to Execute
PrSprint 1 MTE-020-010: Schedule Production/ Planned
MTE-020-030-30 ManufactureMTE-020:
to Execute
Production Order
Sprint 1 MTE-020-030: Manage Repetitive Manufacturi
MTE-020-030-31 ManufactureMTE-020:
to Execute
Production Order
Sprint 1 MTE-020-030: Manage Repetitive Manufacturi
MTE-020-030-32 ManufactureMTE-020:
to Execute
Production Order
Sprint 1 MTE-020-030: Manage Repetitive Manufacturi
MTE-020-030-33 ManufactureMTE-020:
to Execute
Production Order
Sprint 1 MTE-020-030: Manage Repetitive Manufacturi
MTE-020-030-34 ManufactureMTE-020:
to Execute
Production Order
Sprint 1 MTE-020-030: Manage Repetitive Manufacturi
MTE-020-030-35 ManufactureMTE-020:
to Execute
Production Order
Sprint 1 MTE-020-030: Manage Repetitive Manufacturi
MTE-010-010-14
ManufactureMTE-010:
to Execute
PrSprint 1 MTE-010-010: Production Master Data
MTE-020-030-36 ManufactureMTE-020:
to Execute
Production Order
Sprint 1 MTE-020-030: Manage Repetitive Manufacturi
MTE-020-030-37 ManufactureMTE-020:
to Execute
Production Order
Sprint 1 MTE-020-030: Manage Repetitive Manufacturi
MTE-020-030-38 ManufactureMTE-020:
to Execute
Production Order
Sprint 1 MTE-020-030: Manage Repetitive Manufacturi
MTE-020-030-39 ManufactureMTE-020:
to Execute
Production Order
Sprint 1 MTE-020-030: Manage Repetitive Manufacturi
MTE-020-030-40 ManufactureMTE-020:
to Execute
Production Order
Sprint 1 MTE-020-030: Manage Repetitive Manufacturi
MTE-020-030-41 ManufactureMTE-020:
to Execute
Production Order
Sprint 1 MTE-020-030: Manage Repetitive Manufacturi
MTE-020-030-42 ManufactureMTE-020:
to Execute
Production Order
Sprint 1 MTE-020-030: Manage Repetitive Manufacturi
MTE-020-030-43 ManufactureMTE-020:
to Execute
Production Order
Sprint 1 MTE-020-030: Manage Repetitive Manufacturi
MTE-020-030-44 ManufactureMTE-020:
to Execute
Production Order
Sprint 1 MTE-020-030: Manage Repetitive Manufacturi
MTE-020-030-45 ManufactureMTE-020:
to Execute
Production Order
Sprint 1 MTE-020-030: Manage Repetitive Manufacturi
MTE-020-030-46 ManufactureMTE-020:
to Execute
Production Order
Sprint 1 MTE-020-030: Manage Repetitive Manufacturi
MTE-020-030-47 ManufactureMTE-020:
to Execute
Production Order
Sprint 1 MTE-020-030: Manage Repetitive Manufacturi
MTE-020-030-48 ManufactureMTE-020:
to Execute
Production Order
Sprint 1 MTE-020-030: Manage Repetitive Manufacturi
MTE-020-030-49 ManufactureMTE-020:
to Execute
Production Order
Sprint 1 MTE-020-030: Manage Repetitive Manufacturi
MTE-020-030-50 ManufactureMTE-020:
to Execute
Production Order
Sprint 1 MTE-020-030: Manage Repetitive Manufacturi
MTE-020-030-51 ManufactureMTE-020:
to Execute
Production Order
Sprint 1 MTE-020-030: Manage Repetitive Manufacturi
MTE-020-030-52 ManufactureMTE-020:
to Execute
Production Order
Sprint 1 MTE-020-030: Manage Repetitive Manufacturi
MTE-020-030-53 ManufactureMTE-020:
to Execute
Production Order
Sprint 1 MTE-020-030: Manage Repetitive Manufacturi
MTE-020-030-54 ManufactureMTE-020:
to Execute
Production Order
Sprint 1 MTE-020-030: Manage Repetitive Manufacturi
MTE-020-030-55 ManufactureMTE-020:
to Execute
Production Order
Sprint 1 MTE-020-030: Manage Repetitive Manufacturi
MTE-020-030-56 ManufactureMTE-020:
to Execute
Production Order
Sprint 1 MTE-020-030: Manage Repetitive Manufacturi
ManufactureMTE-010:
to Execute
Production Master Data
MTE-020-030-62 ManufactureMTE-020:
to Execute
Production Order
Sprint 1 MTE-020-030: Manage Repetitive Manufacturi
MTE-020-030-63 ManufactureMTE-020:
to Execute
Production Order
Sprint 1 MTE-020-030: Manage Repetitive Manufacturi
MTE-020-020: Manage Discrete
Manufacturing
MTE-020-020-14 ManufactureMTE-020:
to Execute
Production Order
Sprint 1
MTE-020-020: Manage Discrete
Manufacturing
MTE-020-020-15 ManufactureMTE-020:
to Execute
Production Order
Sprint 1
MTE-020-020: Manage Discrete
Manufacturing
MTE-020-020-16 ManufactureMTE-020:
to Execute
Production Order
Sprint 1
MTE-020-020: Manage Discrete
Manufacturing
MTE-020-020-17 ManufactureMTE-020:
to Execute
Production Order
Sprint 1
MTE-020-020: Manage Discrete
Manufacturing
MTE-020-020-18 ManufactureMTE-020:
to Execute
Production Order
Sprint 1
MTE-020-020: Manage Discrete
Manufacturing
MTE-020-020-19 ManufactureMTE-020:
to Execute
Production Order
Sprint 1
MTE-020-020: Manage Discrete
MTE-020-020-20 ManufactureMTE-020:
to Execute Sprint 1 Manufacturing
Production Order
MTE-020-020: Manage Discrete
Manufacturing
MTE-020-020-21 ManufactureMTE-020:
to Execute
Production Order
Sprint 1
MTE-020-020: Manage Discrete
Manufacturing
MTE-020-020-22 ManufactureMTE-020:
to Execute
Production Order
Sprint 1
MTE-020-020: Manage Discrete
Manufacturing
MTE-020-020-23 ManufactureMTE-020:
to Execute
Production Order
Sprint 1
MTE-020-020: Manage Discrete
Manufacturing
MTE-020-020-24 ManufactureMTE-020:
to Execute
Production Order
Sprint 1
MTE-020-020: Manage Discrete
Manufacturing
MTE-020-020-25 ManufactureMTE-020:
to Execute
Production Order
Sprint 1
MTE-020-020: Manage Discrete
Manufacturing
MTE-020-020-26 ManufactureMTE-020:
to Execute
Production Order
Sprint 1
MTE-020-020: Manage Discrete
Manufacturing
MTE-020-020-27 ManufactureMTE-020:
to Execute
Production Order
Sprint 1
MTE-020-020: Manage Discrete
Manufacturing
MTE-020-020-29 ManufactureMTE-020:
to Execute
Production Order
Sprint 1
MTE-020-020: Manage Discrete
Manufacturing
MTE-020-020-30 ManufactureMTE-020:
to Execute
Production Order
Sprint 1
MTE-020-020: Manage Discrete
Manufacturing
MTE-020-020-31 ManufactureMTE-020:
to Execute
Production Order
Sprint 1
MTE-020-020: Manage Discrete
Manufacturing
MTE-020-020-32 ManufactureMTE-020:
to Execute
Production Order
Sprint 1
MTE-020-020: Manage Discrete
Manufacturing
MTE-020-020-33 ManufactureMTE-020:
to Execute
Production Order
Sprint 1
MTE-020-020: Manage Discrete
Manufacturing
MTE-020-020-34 ManufactureMTE-020:
to Execute
Production Order
Sprint 1
MTE-020-020: Manage Discrete
Manufacturing
MTE-020-020-35 ManufactureMTE-020:
to Execute
Production Order
Sprint 1
MTE-020-020: Manage Discrete
Manufacturing
MTE-020-020-36 ManufactureMTE-020:
to Execute
Production Order
Sprint 1
MTE-020-020: Manage Discrete
Manufacturing
MTE-020-020-37 ManufactureMTE-020:
to Execute
Production Order
Sprint 1
MTE-020-020: Manage Discrete
Manufacturing
MTE-020-020-38 ManufactureMTE-020:
to Execute
Production Order
Sprint 1
MTE-020-020: Manage Discrete
Manufacturing
MTE-020-020-39 ManufactureMTE-020:
to Execute
Production Order
Sprint 1
MTE-010-010-16 Sprint 1 MTE-010-010: Production Master Data
ManufactureMTE-010:
to Execute
Production Master Data
MTE-020-020: Manage Discrete
Sprint 1
Manufacturing
MTE-020-020-40 ManufactureMTE-010:
to Execute
Production Master Data
Sprint 1
MTE-010-010-33 ManufactureMTE-020:
to Execute
Production Order
MTE-010-010: Production Master Data
Sprint 1 MTE-010-010: Production Master Data
MTE-010-010-34 ManufactureMTE-010:
to Execute
Production Master Data
MTE-020-030-64 ManufactureMTE-020:
to Execute
Production Order
Sprint 1 MTE-020-030: Manage Repetitive Manufacturi
MTE-020-030-65 ManufactureMTE-020:
to Execute
Production Order
Sprint 1 MTE-020-030: Manage Repetitive Manufacturi
MTE-020-030-66 ManufactureMTE-020:
to Execute
Production Order
Sprint 1 MTE-020-030: Manage Repetitive Manufacturi
MTE-020-030-67 ManufactureMTE-020:
to Execute
Production Order
Sprint 1 MTE-020-030: Manage Repetitive Manufacturi
MTE-020-030-68 ManufactureMTE-020:
to Execute
Production Order
Sprint 1 MTE-020-030: Manage Repetitive Manufacturi
MTE-020-030-69 ManufactureMTE-020:
to Execute
Production Order
Sprint 1 MTE-020-030: Manage Repetitive Manufacturi
MTE-020-030-70 ManufactureMTE-020:
to Execute
Production Order
Sprint 1 MTE-020-030: Manage Repetitive Manufacturi
MTE-020-030-71 ManufactureMTE-020:
to Execute
Production Order
Sprint 1 MTE-020-030: Manage Repetitive Manufacturi
MTE-010-010-35 ManufactureMTE-020:
to Execute
Production Order
Sprint 1 MTE-010-010: Production Master Data
MTE-020-030-72 ManufactureMTE-020:
to Execute
Production Order
Sprint 1 MTE-020-030: Manage Repetitive Manufacturi
MTE-020-030-73 ManufactureMTE-020:
to Execute
Production Order
Sprint 1 MTE-020-030: Manage Repetitive Manufacturi
MTE-020-030-74 ManufactureMTE-020:
to Execute
Production Order
Sprint 1 MTE-020-030: Manage Repetitive Manufacturi
MTE-020-030-75 ManufactureMTE-020:
to Execute
Production Order
Sprint 1 MTE-020-030: Manage Repetitive Manufacturi
MTE-020-030-76 ManufactureMTE-020:
to Execute
Production Order
Sprint 1 MTE-020-030: Manage Repetitive Manufacturi
MTE-020-030-77 ManufactureMTE-020:
to Execute
Production Order
Sprint 1 MTE-020-030: Manage Repetitive Manufacturi
MTE-020-030: Manage Repetitive
MTE-020-030-87 ManufactureMTE-020:
to Execute
Production Order
Sprint 1 Manufacturing
MTE-020-030-88 ManufactureMTE-020:
to Execute
Production Order
Sprint 1 MTE-020-030: Manage Repetitive Manufacturi
MTE-020-030-89 ManufactureMTE-020:
to Execute
Production Order
Sprint 1 MTE-020-030: Manage Repetitive Manufacturi
MTE-020-030-90 ManufactureMTE-020:
to Execute
Production Order
Sprint 1 MTE-020-030: Manage Repetitive Manufacturi
MTE-020-030-91 ManufactureMTE-020:
to Execute
Production Order
Sprint 1 MTE-020-030: Manage Repetitive Manufacturi
MTE-020-030-92 ManufactureMTE-020:
to Execute
Production Order
Sprint 1 MTE-020-030: Manage Repetitive Manufacturi
MTE-020-030-93 ManufactureMTE-020:
to Execute
Production Order
Sprint 1 MTE-020-030: Manage Repetitive Manufacturi
MTE-020-030-94 ManufactureMTE-020:
to Execute
Production Order
Sprint 1 MTE-020-030: Manage Repetitive Manufacturi
MTE-020-030-95 ManufactureMTE-020:
to Execute
Production Order
Sprint 1 MTE-020-030: Manage Repetitive Manufacturi
MTE-020-030-96 ManufactureMTE-020:
to Execute
Production Order
Sprint 1 MTE-020-030: Manage Repetitive Manufacturi
MTE-020-030-97 ManufactureMTE-020:
to Execute
Production Order
Sprint 1 MTE-020-030: Manage Repetitive Manufacturi
MTE-010-010-37 ManufactureMTE-010:
to Execute
PrSprint 1 MTE-010-010: Production Master Data
MTE-010-010-38 ManufactureMTE-010:
to Execute
PrSprint 1 MTE-010-010: Production Master Data
Sprint 1 MTE-010-010: Production Master Data
MTE-010-010-39 ManufactureMTE-010:
to Execute
Production Master Data
MTE-020-020: Manage Discrete
Manufacturing
MTE-020-020-42 ManufactureMTE-020:
to Execute
Production Order
Sprint 1
MTE-020-020: Manage Discrete
Manufacturing
MTE-020-020-43 ManufactureMTE-020:
to Execute
Production Order
Sprint 1
MTE-020-020: Manage Discrete
Manufacturing
MTE-020-020-44 ManufactureMTE-020:
to Execute
Production Order
Sprint 1
MTE-020-020: Manage Discrete
Manufacturing
MTE-020-020-45 ManufactureMTE-020:
to Execute
Production Order
Sprint 1
MTE-020-020: Manage Discrete
Manufacturing
MTE-020-020-46 ManufactureMTE-020:
to Execute
Production Order
Sprint 1
MTE-020-020: Manage Discrete
Manufacturing
MTE-020-020-47 ManufactureMTE-020:
to Execute
Production Order
Sprint 1
MTE-020-020: Manage Discrete
Manufacturing
MTE-020-020-48 ManufactureMTE-020:
to Execute
Production Order
Sprint 1
MTE-020-020: Manage Discrete
Manufacturing
MTE-020-020-49 ManufactureMTE-020:
to Execute
Production Order
Sprint 1
MTE-020-020: Manage Discrete
MTE-020-020-50 ManufactureMTE-020:
to Execute Sprint 1 Manufacturing
Production Order
MTE-020-020: Manage Discrete
MTE-020-020-51 ManufactureMTE-020:
to Execute Sprint 1 Manufacturing
Production Order
MTE-020-030-99 ManufactureMTE-020:
to Execute
Production Order
Sprint 1
MTE-020-020: Manage Discrete
MTE-020-020-52 ManufactureMTE-020:
to Execute Sprint 1 Manufacturing
Production Order
Sprint 1 MTE-010-010: Production Master Data
MTE-010-010-40 ManufactureMTE-010:
to Execute
Production Master Data
Sprint 1 MTE-010-010: Production Master Data
MTE-010-010-41 ManufactureMTE-010:
to Execute
Production Master Data
MTE-010-010-42 ManufactureMTE-010:
to Execute
Production Master Data
MTE-010-010-43 ManufactureMTE-010:
to Execute
Production Master Data
Sprint 1 MTE-010-010: Production Master Data
MTE-010-010-44 ManufactureMTE-010:
to Execute
Production Master Data
Sprint 1 MTE-010-010: Production Master Data
MTE-010-010-45 ManufactureMTE-010:
to Execute
Production Master Data
Sprint 1 MTE-010-010: Production Master Data
MTE-010-010-46 ManufactureMTE-010:
to Execute
Production Master Data
MTE-010-010-50 ManufactureMTE-010:
to Execute
Production Master Data
Sprint 1 MTE-010-010: Production Master Data
MTE-010-010-51 ManufactureMTE-010:
to Execute
Production Master Data
MTE-010-010-52 ManufactureMTE-010:
to Execute
Production Master Data
Sprint 1 MTE-010-010: Production Master Data
MTE-010-010-53 ManufactureMTE-010:
to Execute
Production Master Data
MTE-010-010-64 ManufactureMTE-010:
to Execute
Production Master Data
Sprint 1 MTE-010-010: Production Master Data
MTE-010-010-65 ManufactureMTE-010:
to Execute
Production Master Data
Sprint 1 MTE-010-010: Production Master Data
MTE-010-010-66 ManufactureMTE-010:
to Execute
Production Master Data
Sprint 1 MTE-010-010: Production Master Data
MTE-010-010-67 ManufactureMTE-010:
to Execute
Production Master Data
Sprint 1 MTE-010-010: Production Master Data
MTE-010-010-68 ManufactureMTE-010:
to Execute
Production Master Data
Sprint 1 MTE-010-010: Production Master Data
MTE-010-010-69 ManufactureMTE-010:
to Execute
Production Master Data
Sprint 1 MTE-010-010: Production Master Data
MTE-010-010-70 ManufactureMTE-010:
to Execute
Production Master Data
MTE-020-030-102 ManufactureMTE-020:
to Execute
Production Order
Sprint 1
MTE-010-010-79 ManufactureMTE-010:
to Execute
Production Master
MTE-010-010:
Data Production Master Data
Sprint 1
MTE-010-010-80 ManufactureMTE-010:
to Execute
Production Master
MTE-010-010:
Data Production Master Data
Sprint 1
MTE-010-010-81 ManufactureMTE-010:
to Execute
Production Master
MTE-010-010:
Data Production Master Data
Sprint 1
MTE-010-010-82 ManufactureMTE-010:
to Execute
Production Master
MTE-010-010:
Data Production Master Data
Sprint 1
MTE-010-010-83 ManufactureMTE-010:
to Execute
Production Master
MTE-010-010:
Data Production Master Data
Sprint 1
MTE-010-010-84 ManufactureMTE-010:
to Execute
Production Master
MTE-010-010:
Data Production Master Data
Sprint 1
MTE-010-010-85 ManufactureMTE-010:
to Execute
Production Master
MTE-010-010:
Data Production Master Data
Sprint 1
MTE-010-010-86 ManufactureMTE-010:
to Execute
Production Master
MTE-010-010:
Data Production Master Data
MTE-020-020: Manage Discrete
Manufacturing
MTE-020-020-53 ManufactureMTE-020:
to Execute
Production Order
Sprint 1
MTE-020-020: Manage Discrete
Manufacturing
MTE-020-020-54 ManufactureMTE-020:
to Execute
Production Order
Sprint 1
MTE-020-020: Manage Discrete
Manufacturing
MTE-020-020-55 ManufactureMTE-020:
to Execute
Production Order
Sprint 1
Sprint 1
MTE-010-010-87 ManufactureMTE-010:
to Execute
Production Master
MTE-010-010:
Data Production Master Data
Manufactur MTE-020:
e Production MTE-020-020: Manage Discrete
MTE-020-020-56 to Execute Order Sprint 4 Manufacturing
Manufactur MTE-020:
e Production MTE-020-020: Manage Discrete
MTE-020-020-57 to Execute Order Sprint 1 Manufacturing
Manufactur MTE-020:
e Production MTE-020-020: Manage Discrete
MTE-020-020-58 to Execute Order Sprint 1 Manufacturing
Manufactur MTE-020:
e Production MTE-020-020: Manage Discrete
MTE-020-020-59 to Execute Order Sprint 1 Manufacturing
Manufactur MTE-020:
e Production MTE-020-020: Manage Discrete
MTE-020-020-60 to Execute Order Sprint 1 Manufacturing
Manufactur MTE-020:
e Production MTE-020-020: Manage Discrete
MTE-020-020-61 to Execute Order Sprint 1 Manufacturing
MTE-020-030: Manage Repetitive
MTE-020-030-110 ManufactureMTE-020:
to Execute
Production Order
Sprint 1 Manufacturing
MTE-020-030: Manage Repetitive
MTE-020-030-111 ManufactureMTE-020:
to Execute
Production Order
Sprint 1 Manufacturing
MTE-020-030: Manage Repetitive
MTE-020-030-112 ManufactureMTE-020:
to Execute
Production Order
Sprint 1 Manufacturing
MTE-020-030: Manage Repetitive
MTE-020-030-113 ManufactureMTE-020:
to Execute
Production Order
Sprint 1 Manufacturing
MTE-020-030: Manage Repetitive
MTE-020-030-114 ManufactureMTE-020:
to Execute
Production Order
Sprint 1 Manufacturing
MTE-020-030: Manage Repetitive
MTE-020-030-115 ManufactureMTE-020:
to Execute
Production Order
Sprint 1 Manufacturing
MTE-020-030: Manage Repetitive
MTE-020-030-116 ManufactureMTE-020:
to Execute
Production Order
Sprint 1 Manufacturing
MTE-020-030: Manage Repetitive
MTE-020-030-118 ManufactureMTE-020:
to Execute
Production Order
Sprint 1 Manufacturing
MTE-020-030: Manage Repetitive
MTE-020-030-119 ManufactureMTE-020:
to Execute
Production Order
Sprint 1 Manufacturing
MTE-020-030-132
Sprint 1
MTE-010-010-89 ManufactureMTE-010:
to Execute
Production Master
MTE-010-010:
Data Production Master Data
Sprint 1
MTE-010-010-90 ManufactureMTE-010:
to Execute
Production Master
MTE-010-010:
Data Production Master Data
Sprint 1
MTE-010-010-91 ManufactureMTE-010:
to Execute
Production Master
MTE-010-010:
Data Production Master Data
Sprint 1
MTE-010-010-92 ManufactureMTE-010:
to Execute
Production Master
MTE-010-010:
Data Production Master Data
rint 1 user stories provided by Nguyen Ngoc Anh for the purpose Approvals only. Please refer to this link for Sprint 1 user stories
Required
Role Capability
Production Planner This is unique for bench ( mold life is number of usages)
As a production planner, I want ability to view the WIP sty by
Production Planner each work center
As a material planner, I want system can auto update ETA base
on latest confirmation from vendors. Advanced Shipping
Material Planner notification from Vendor
Production Planner Able to see available mold stock at Mold Shop area in SAP
Possibility to see mtd Yield on each work center (A grade, % re-
Production Planner Fire and % loss ) in real-time
As a production planner, I want to have the ability to create a
supply and inventory plan for new products and phase out
Production Planner products
Production planner should have ability to confirm estimated time
to departure to customer orders in system, and this should be
linked with packing plan when system generates packing
Production Planner proposal
Global Manufacturing L As a as a global MTE leader, I want the ability to visualize and
compare each factory's standard cost per SKU broken down by
manufacturing process, globally.
As a global MTE leader, I want the ability to visualize the
production plan vs actual progress in each factory by
Global Manufacturing L manufacturing process, globally.
As a as a global MTE leader, I want the ability to visualize and
compare each factory's failure rate broken by manufacturing
process, globally. And automatically calculate as TCL (Total
Global Manufacturing L cost lost) by cost
Production Planner As a Production Planner I'd like to see the critical path in terms
of capacities and material availability (mutli level) in order to
avoid capacity and availability issues.
Production Planner As a Production Planner I'd like to work with various production
scenarios and their verification with regard to capacity utilization
and the identification of capacity bottlenecks
Production Planner
As a production planner I'd like to work with finite capacities in
order to create a constrained based production program.
As a production planner I'd like to get support from the system in
Production Planner order to schedule the sequence of the shop floor orders in the
most efficient sequence e.g. shortest total lead time. Need a
way to propose most optimized scheduling considering
optimization of set up time
Production Planner As a Production Planner I'd like to get support in resolving multi-
level planning conflicts by the system.
Production Planner
As Production Planner I'd like to get an alert in case of critical
situations of the production plan realization (even after order is
released)
Production Planner
As Production Planner I'd like to get a guidance by the system
to solve capacity issues with alternative work centers.
Production Planner
As a Production Planner I'd like to work with different Company
Calendar in order to simulate closing periods and the impact on
the production program (e.g. company closing between
Christmas eve and new year)
Production Planner As a Production Controller for assembly I'd like to have a report
based on work centers to release shop floor orders according
the material availability. (release of orders)
As the Production Controller for assembly, I'd like to have a
Production Planner report of the released nondelivered and partially delivered shop
floor orders with the remaining workload in hours per work
center in order to harmonize the workload and to identify
capacity bottleneck
Production Planner
As a Production planner, I want the ability to monitor work
center daily production schedule with SKU and quantity listed
Production Planner
Pegging relationship should be established between purchase
orders and production orders. Pegging should be dynamic.
Any SKU's that is on the frozen plan but could not be produced
for any reason, should be automatically included in the first
Production Planner immediate week after the frozen period. Production planner
should have rights to over-ride any frozen plan at any time.
Overrides to the production plan within the frozen period should
be recorded separately
As a production supervisor, I want the ability to execute post
Production Planner processing of errors raised during backflush posting, so that I
am able to post components at later stage to right production
orders
Production Planner
As a production planner I like to give additional note (text field)
to the shop floor when releasing a prod. order
Master data specialist As a Master data specialist, I want the ability to create and
manage Sales Bill of Materials and Production BOM
Master data specialist As a Master data specialist, I want the ability to change tax
classification field for ROH & HALB materials at the plant level in
the Material Master
As a Master data specialist, I want the ability to change the
Master data specialist Delivering Plant in the Sales Org data 1 view in the Material
Master
As a Master data specialist, I want the ability to extend ROH &
Master data specialist HALB materials to certain sales and distribution channels within
our company code.
*As a Master data specialist, I want the ability to create and
Master data specialist change Material Master Purchasing and MRP views including
plant-specific configurations
Master data specialist *As a Master data specialist, I want the ability to create and
manage Production Bill of Materials
Master data specialist *As a master data specialist, I want the ability to create and
manage Rate Routing master
Master data specialist
*As a Master data specialist, I want the ability to create and
manage Work centers
Master data specialist As a Master data specialist, I want the ability to receive updated
Production master data from SAP to other systems
Master data specialist As a Master data specialist, I want the ability to create and
manage dependencies in the super BOM and Super Routing
As a Master data specialist, I want the ability to create and
Master data specialist change Accounting/Costing views in Material Master at plant
level
As a Master data specialist, I want the ability to create and
Master data specialist manage material Subcontract info records and subcontracting
BoMs
Master data specialist As a Master data specialist, I want the ability to create and
manage Phantom Assembly BOM's
Master data specialist As a Master data specialist, I want the ability to create &
manage material Vendor info records
Master data specialist As a Master data specialist, I want the ability to maintain
supplier source list
As a Master data specialist, I want the ability to manually force
Master data specialist back flushing (and substitution backflush) of BOM components
in repetitive manufacturing
Master data specialist *As a Master data specialist, I want the ability to execute mass
change transactions in Material Master
As a Production Planning I would like to get frozen schedule
Production Planner production with commit dates from SAP.
Production
Planner/Scheduler As a production planner, I would like the ability to view in SAP
(from Tranxfer) final SKU after scanned at Pack operation.
Production
Planner/Scheduler As a production planner I want the ability to pull data from
customized production planning report (ZPROD) by date range.
Production As a production planner I want the ability to print orders in bulk
Planner/Scheduler from report (ZPROD)
Production As a production planner I want the ability to print orders by date
Planner/Scheduler range
As Master data specialist, I want the ability for MRP to run and
suggest planned order for the product that have production in
multiple plants.
Master Data Specialist For example: 1 SKU produced in 2 Production Plant, Sales
Order and Forecast placed in 1 plant. However, Procurement
type have to set as "E" in both production plant, so when MRP
run, there is no link between both plants, planner have to
manual check and manual create STO to move inventory to
fulfill the order.
Master Data Specialist As a Master data specialist, I want the ability to create and
manage Production versions
Master Data Specialist As a Master data specialist, I want the ability to create and
manage operation time in Routing
Master Data Specialist As a Master data Specialist, I want the ability to create multiple
BOM for a single sku
Master Data Specialist As Master Data Specialist, I want the ability to create and
manage Production versions for each SKU at factory level.
Master Data Specialist As Master Data Specialist, I need a report for Routing review. In
there, we can input plant, Material, MRP type, MRP controller,
and routing information (Type, status, valid.) to get data.
As Master Data Specialist, I need the report for BOM review. In
Master Data Specialist there, we can input plant, Material, Material type, Material Group
and BOM information (Usage, Alt BOM, BOM level, Valid.) to
get data.
Master Data Specialist As a Master data specialist, I want the ability to auto calculate
Kiln routing cost (Average of 1st fired, and 2nd fired)
Master Data Specialist As a Master data specialist, I want the ability to auto calculate
AOP Work content
Master Data Specialist As a Master data specialist, I want the ability to manage
Material Master views plan Scrap %
Master Data Specialist As a Master data specialist, I want the ability to manage
Material Master views Actual Scrap %
Master Data Specialist As a Master data specialist, I want the ability to mass export
Material master
As a Master data specialist, I want the ability to have BOM
Master Data Specialist included Costing BOM & Production BOM. Also have BOM for
each process in production (example: BOM for Slip/Glaze; BOM
for casting/spraying/firing/packing)
Master Data Specialist As a Master data specialist, I want the ability to mass
create/change/extend BOM
Master Data Specialist As a Master data specialist, I want the ability to mass export
BOM
As a Master data specialist, I want the ability to have Routing
Master Data Specialist included Costing Routing & Production Routing. Also have
Routing for each process in production (example: Routing for
Slip/Glaze; Routing for casting/spraying/firing/packing)
Master Data Specialist As a Master data specialist, I want the ability to mass
create/change/extend Routing
Master Data Specialist As a Master data specialist, I want the ability to mass export
Routing
Master Data Specialist As a Master data specialist, I want the ability to create
Production version
Master Data Specialist As a Master data specialist, I want the ability to mass export
Production version
Master Data Specialist As a Master data specialist, I want the ability to Backflush
activity
Master Data Specialist As a Master data specialist, I want the ability to release Product
Cost Collector for Production version
Master Data Specialist As a Master data specialist, I want the ability to auto calculate
Kiln routing costing (Average of 1st fired, and 2nd fired)
Master Data Specialist As a Master data specialist, I want the ability to auto calculate
AOP Work content
Master Data Specialist As a Master data specialist, I want the ability to distinguish
between in-house product, trading product
As a Master data specialist, I want the ability to relate in house
Master Data Specialist product with same product code also want to ability to
distinguish which plant produce this product
Master Data Specialist As a Key user, I want Increase the number of blank rows to 100
rows when creating a new PR. Currently only 10 rows at a time
Master Data Specialist As a Key user, I want to be able to delete all lines items or
release all line items in PReq. Currently its line by line
Master Data Specialist As a Key user, I want to split the cost center into 2 in the same
department in a plant
Master Data Specialist As a master Data Specialist, I want the ability to combine the
data fields of two T_code is MB51 and Zvn_pp_prdrpt
Production Planner
fixed periods
FG`s in 0201 with 3 months
FG`s in plant 0301 with 10 days
Production Planner released production orders in assembly with 48 hours
Must Have /
Outcome Entered By
Nice to Have
So that I am able to
1. Authorize shop floor to begin production process.
2. Arrange components, tools and machine setup to begin
production process (includes all orders scheduled to begin in next
few days) Must Have PwC
So that I can quickly see and manage any variances that occur Must Have
so that I can make schedule by each casting line and facility Must Have Alex Wu
so that plant team can know detailed plan for each process in
system Must Have Alex Wu
so that I can identify the bottleneck and opportunities Must Have Alex Wu
so that this plan can be shared to production team once I confirm it Must Have Alex Wu
so that I can evaluate the potential risk of supply to customer orders Must Have Alex Wu
so that I can make mold change plan accordingly Must Have Alex Wu
so that I can easily know the production situation in workshop and
confirm supply plan to customer in positive way Must Have Alex Wu
so that I can evaluate our supply ability to customer order Must Have Alex Wu
so that vendor can prepare capacity/RM base on my forecast Must Have Alex Wu
so that I can make mid term supply plan accordingly Must Have Alex Wu
so that I can identify the fluctuation of marketing forecast Must Have Alex Wu
so that I can manage the production plan with each factory leader Must Have Alex Wu
So that top management team can check without requesting report Must Have Alex Wu
so that I can take right action to meet sale plan Must Have Alex Wu
so that each process team can receive my plan from system and
arrange resources accordingly Must Have Alex Wu
so that I can use it to negotiate it with plant team when there's a big
gap happen Must Have Alex Wu
so that I can negotiate it with each market when our inventory
increase Must Have Alex Wu
so that I can identify the bottleneck for production Must Have Alex Wu
so that I can know whether my packing plan can be executed or not Must Have Alex Wu
so that I can negotiate it with plant team when they have a poor
performance on it and to give alert to plant manager for that, and
also I can utilize this information when I doing the production plan Must Have Alex Wu
so that CS could not place the order more than production capacity Must Have Alex Wu
so that plant team can know detailed schedule at model level(same
mold but different hole/different color) Must Have Alex Wu
so that my plan for casting will be more accuracy Must Have Alex Wu
so that I can track the fulfill rate to customer orders Must Have Alex Wu
so that we can manage components parts and WIP properly Must Have Alex Wu
so that we can adjust production plan properly to avoid
manufacturing shutdown from lack of raw material Must Have Alex Wu
so that I can have a real time tracking on my plan. Must Have Alex Wu
so that I can optimize the plan with manufacturing team Must Have Alex Wu
so that I can easily track the executions for planning and outputs Must Have Alex Wu
so that I can how much glaze I should request for stock transfer from
WH to production area Must Have Alex Wu
special process to
produce a finished
good out of
several colored
Must Have
components
(chrome plated
components) in
one production lot
M K. Müller
M K. Müller
M K. Müller
M K. Müller
M K. Müller
M K. Müller
So that I am able to identify Critical situation by looking a report
about production status for shortage of capacity and material.
This is must have requirement: Need a visibility of work center M K. Müller
unavailability due to component shortage, capacity shortage,
machine breakdown, quality notification or any such triggers in the
form of dashboard preferably
M K. Müller
M K. Müller
M K. Müller
M K. Müller
M K. Müller
M K. Müller
M K. Müller
M K. Müller
Measure the performance of plant. We have started in US and need
to rollover another region. Currently there is custom report available M
to calculate this.
Action: Shahu will share this sample report. Probal Basu
M
Probal Basu
M
Probal Basu
M
Probal Basu
Probal Basu
M
Mario
So that I am able to add Long text in production order which are
managed manually to address specific instructions to sop floor M R. May
before orders are printed
So that I am able to monitor no-production labor BoMs in order to Must Have T. Rhynes
maintain inventory levels
so that I am able to maintain data consistency at the plant level, and Must have T. Rhynes
sales or repair/warranty orders are relieving materials.
so that I am able to maintain master data for Super BOMs and that Must have T. Rhynes
the MRP process runs correctly.
So that the MRP process is accurate, dependent requirements are Must have T. Rhynes
created and components are consumed properly prior to pack.
Must Have T. Rhynes
So that I am able to use them consistently in production process
Must have T. Rhynes
So that I am able to use them consistently in the production process
So that I am able to maintain data consistency across various Nice to have T. Rhynes
systems
So that I am able to maintain data consistency at the plant level Must have T. Rhynes
within the production process.
So that I am able to maintain data consistency at the plant level for Must have T. Rhynes
SKUs in preparation for plant controller to run costs for SKU set up.
Master Data
IT Gerardo Orta
Production Planner
Materials Management Gerardo Orta
Production Planner
Materials Management Gerardo Orta
so that I can know the shortage situation of the planning order and
make adjustment accordingly. must have Annie Tang
so that I won’t plan for phase out SKU. must have Annie Tang
so that I can plan stock properly and reduce manual job. must have Annie Tang
so that I can nominate phase out list. must have Annie Tang
so that I know what's the rework rate. must have Annie Tang
so that I can know that free stock material situation. must have Annie Tang
so that I can tracking for the shortage material with vendor. must have Annie Tang
so that Finance can get the right product cost of the material. nice to have Annie Tang
so that I can choose the right one while backflush. nice to have Annie Tang
so that we know the subassembly part required to produce the must have Annie Tang
Finished good
T.Rhynes/
so that I am able to plan the order of production from open sales must have
E.Henderson
orders.
T.Rhynes/
to increase production line efficiency and maintain steady labor flow must have E.Henderson
throughout the production floor
T.Rhynes/
must have
E.Henderson
T.Rhynes/
must have
E.Henderson
so that I know if there are any issues causing delay in the weekly
schedule
T.Rhynes/
must have
E.Henderson
so that I can confirm completion of packed units
T.Rhynes/
nice to have
E.Henderson
T.Rhynes/
nice to have
E.Henderson
T.Rhynes/
Need a walkthrough of the ZPROD tcode & its special functionalities. must have E.Henderson
Action: Americas need to arrange a session
Need a walkthrough of the ZPROD tcode & its special functionalities. nice to have T.Rhynes/
Action: Americas need to arrange a session E.Henderson
T.Rhynes/
nice to have
so that I can release best production plan E.Henderson
T.Rhynes/
nice to have
E.Henderson
so that they can get material from WH base on planned order must have Annie Tang
must have Annop
So that I can control profit by plant and understand which plant are must have Anh
good performance.
so that more information can be found in finding the error-free data must have Anh
entry
So that we can make LCL10PJ weekly/monthly report automatically. must have Yamashita
So that I don't have to ask for glaze type. must have Yamashita
So that I can compare Work contents of different plants must have Yamashita
So that we can save time and implement best practice easily must have Yamashita
So that I can see the whole link between SKU must have Yamashita
so that the rework activity can be recorded in system. Nice to have Zhang Hua
so that I know the key components stock information in time. Nice to have Zhang Hua
so that we can save some time in order confirmation. Nice to have Zhang Hua
so that we don’t need to change location during material issue. Nice to have Zhang Hua
PwC
Robert May
Kanban production demand for the next day -> reduced Kanban
area
Robert May
This is established in Lahr in SAP in order to produce not against
FC, production if defined Kanban’s are empty
Robert May
Fixed period in assembly with 48 h is necessary to produce in
Kanban needed pre-assemblies and have time for preparation
Ngoc
Ngoc
Ngoc
Ngoc
Ngoc
Ngoc
Ngoc
Ngoc
Ngoc
Ngoc
Ngoc
Ngoc
Anh
so that I can report and control it easily.
Anh
so that I can report and control it easily.
Anh
So that we can improve first in first out in processes.
Anh
So that we can adjust next production plan.
Anh
So that I can confirm volume schedule (total actual/total plan)
Anh
so that I can apply shortage countermeasure early
Anh
so that I take the action to meet sales plan.
Anh
so that I take the action to meet sales plan.
Anh
so that I can control supply and inventory.
Anh
so that I can adjust supply plan.
Anh
so that I can checking supplying status.
Anh
so that I can decide priority of orders.
Anh
so that I will see overview of production status.
Anh
so that I can adjust production plan.
Anh
So that I can align production plan and packing plan.
Anh
So that I can supply trading items for sales department on time.
Nga
so that I can analyze and make the changes as needed
Nga
So, I can restrict any changes in short-term planning (3-4 weeks)
Nga
Alex Wu
so that I can follow right way to get concerned master data updated
in SAP
so that I am able to interface master data values from SAP to MES Alex Wu
system
For LIXIL work stream Feature owner Optional
Approved
Approved
Approved
Approved
Approved
Approved To be discussed
Approved To be discussed
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved The capacity profile of the work centers are maintained by the productio
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved SAP is host of master data. Export of the data to other systems ok.
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Material staging process w EWM
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
Approved
For BPO / Core team use Region Applicability
Business Review Status (In Scope - yes / No) BPO Approved Americas APAC EMENA Africa
re captured in SAP.
he work centers are maintained by the production planning team. The capacity utilization factor is also maintained by the prod
be defined for master data maintenance.
MTE MTE
MTE MTE
MTE MTE
MTE MTE
MTE MTE
MTE FIT
Gap
Gap
Need to validate the
actual requirement of
mass change
MTE-Scheduling MTE-Scheduling
MTE-Scheduling MTE-Scheduling
MTE-Scheduling MTE-Scheduling
MTE-Scheduling MTE-Scheduling
MTE-Scheduling MTE-Scheduling
MTE-Scheduling MTE-Scheduling
Gap
Gap
STP STP
STP STP
FTP FTP
FTP FTP
FTP FTP
FTP FTP
ITD ITD
MTE-Scheduling MTE-Scheduling
MTE MTE
STP STP
MTE MTE
MTE MTE
MTE MTE
FTP FTP
MTE-Scheduling MTE-Scheduling
MTE-Scheduling MTE-Scheduling
MTE MTE
OTC OTC
MDG MDG
PLM PLM
MTE-Scheduling MTE-Scheduling
MTE MTE
MTE-Scheduling MTE-Scheduling
MTE MTE
MTE MTE
RTR RTR
MTE-Scheduling MTE-Scheduling
MTE-Scheduling MTE-Scheduling
MTE-Scheduling MTE-Scheduling
MTE-Scheduling MTE-Scheduling
MTE-Scheduling MTE-Scheduling
MTE-Scheduling MTE-Scheduling
MTE-Scheduling MTE-Scheduling
MTE GAP
MTE-Scheduling MTE-Scheduling
MTE-Scheduling MTE-Scheduling
MTE-Scheduling MTE-Scheduling
MTE-Scheduling MTE-Scheduling
MTE-Scheduling MTE-Scheduling
MTE-Scheduling MTE-Scheduling
MTE-Scheduling MTE-Scheduling
MTE-Scheduling MTE-Scheduling
MTE-Scheduling MTE-Scheduling GAP
MTE-Scheduling MTE-Scheduling
MTE-Scheduling MTE-Scheduling
MTE Fit
MTE Fit
MTE
MDG
MDG
OTC
MDG MDG
MDG
MDG
MTE Fit
MTE
MTE Fit
MTE
MTE Fit
MTE
MTE MTE
Fit
MTE Fit
MTE
MTE Fit
MTE
STP STP
MTE Fit
MTE
STP STP
STP STP
MTE Fit
MTE
MDG MDG
MTE-Scheduling MTE-Scheduling
MTE MTE
MDG MDG
MDG MDG
MDG MDG
FTP FTP
MDG MDG
MDG MDG
MTE-Scheduling MTE-Scheduling
STP STP
STP STP
MTE-Scheduling MTE-Scheduling
FTP FTP
MTE-Scheduling Deep Dive required
MTE-Scheduling MTE-Scheduling
MTE-Scheduling MTE-Scheduling
FTP FTP
FTP FTP
FTP FTP
FTP FTP
MTE Repetition
MTE
MTE GAP
MTE-Scheduling MTE-Scheduling
MTE GAP
MTE GAP
MTE
MTE Fit
MTE MTE GAP
Fit
MDG MDG
FTP FTP
MTE Repetition
MTE
MTE repetition
MTE
MTE repetition
MTE
MTE GAP
MTE NA
MTE repetition
MTE
MTE repetition
MTE
MTE repetition
MTE
MTE repetition
MTE
MTE NA
MTE NA
MTE
Fit
MTE
Fit
MTE Fit
MTE
MTE Fit
MTE
MTE Repetition
MTE
MTE repetition
MTE
MTE Gap
MTE Gap
MTE Repetition
MTE
Gap
MTE Gap
MTE repetition
MTE
MTE Gap
MTE repetition
MTE
RTR RTR
MTE repetition
MTE
MTE repetition
MTE
MTE Fit
MTE
MTE Fit
MTE
STP STP
STP STP
RTR RTR
MTE Gap
KPI GAP
MTE
RTR RTR
RTR Please clarify the report details GAP
MTE
Fit
MTE NA
MTE-Scheduling
MTE-Scheduling MTE-Scheduling
ITD ITD
MTE-Scheduling MTE-Scheduling
MTE-Scheduling MTE-Scheduling
FTP FTP
MTE-Scheduling
MTE-Scheduling
MTE-Scheduling
MTE-Scheduling
MTE-Scheduling MTE-Scheduling
Fit
MTE MTE
Fit
MTE MTE
Fit
MTE
Fit
MTE MTE
Fit
MTE MTE
Fit
MTE MTE
Fit
MTE MTE
Fit
MTE
MTE
Fit
MTE
Fit
MTE
Fit
MTE GAP
MTE GAP
MTE
Fit
MTE
Fit
MTE
Fit
MTE-Scheduling MTE-Scheduling
Fit
MTE MTE
Fit
MTE MDG
Fit
MTE MTE GAP
Disposition Description WRICEF Complexity WRICEF Type
Interface
Report
Report
Decision between
- Continue to use TM3 OR
- Development
enhancement in SAP Enhancement
Report
Report
Report
Report
Report
Report
Report
Report
Report
Interface
Report
Decision between
- Continue to use TM3 OR
- Development
enhancement in SAP
Decision between
- Continue to use TM3 OR
- Development
enhancement in SAP
Report
Decision between
- Continue to use TM3 OR
- Development
enhancement in SAP
Report
Report
Report
Report
Enhancement Enhancement
Enhancement
enhancement
Interface
Report
Report
Enhancement
Report
Report
Report
Report
Report
Report
Report
Report
Following tcodes can be
used to achieve this
requirement
- COOIS in combination of
MIGO
Interface
Interface
Enhancement
Interface
SAP mapping /
SAP mapping / solution
Process step solution
APP Name
TCODE
S_ALR_8701312
RTR 7
Confirm Repetitive
60 Record Backflush MFBF Manufacturing
RTR
MTE-Scheduling
MTE-Scheduling
MTE-Scheduling
MTE-Scheduling
MTE-Scheduling
MTE-Scheduling
MTE-Scheduling
MTE-Scheduling
120 Review Inventory MMBE Stock Multiple Material
STP
STP
FTP
FTP
FTP
FTP
MTE MTE-Scheduling
MTE MTE-Scheduling
MTE MTE-Scheduling
OTC
MTE MTE-Scheduling
MTE MTE-Scheduling
MTE MTE-Scheduling
MTE-Scheduling
ITD
FTP
MTE-Scheduling
FTP
FTP
Monitor Production / Planned
40 Report Daily / Weekly order schedule COOIS Order
STP
Master Data
MTE-Scheduling
Monitor Production / Planned
40 Report Daily / Weekly order schedule COOIS Order
FTP
MTE-Scheduling
MTE-Scheduling
FTP
OTC
MDG
PLM
MTE-Scheduling
Monitor Production / Planned
30 Planned order Missing List MDVP / COOIS Order
MTE-Scheduling
MTE-Scheduling
RTR
MTE-Scheduling
MTE-Scheduling
MTE-Scheduling
MTE-Scheduling
MTE-Scheduling
MTE-Scheduling
MTE-Scheduling
Display Production Order
160 Review / Report Post production CO03 Monitor Production / Planned
orders COOIS Order
MTE-Scheduling
MTE-Scheduling
MTE-Scheduling
MTE-Scheduling
MTE-Scheduling
MTE-Scheduling
MTE-Scheduling
MTE-Scheduling
MTE-Scheduling
MTE-Scheduling
MTE-Scheduling
MDG
MDG
MDG
MDG
Master Data
CS21 Create Rate Routing
Production Master Data
Production Master Data CR01 Create Work center
MDG
STP
MMBE
200 Review Inventory MB52 Stock Single Material
STP
MDG
MDG
FTP
MTE-Scheduling
MDG
MDG
MTE-Scheduling
STP
STP
MTE-Scheduling
FTP
MTE-Scheduling
MTE-Scheduling
MTE-Scheduling
FTP
FTP
FTP
FTP
Master Data
Monitor Production / Planned
30 Planned order Missing List MDVP / COOIS Order
Confirm Repetitive
60 Record Backflush MFBF Manufacturing
MTE-Scheduling
Routing / Rate
Production Master Data Routing Create Routing
Mass Processing Production
70 Release Production Order COHV Order
MDG
FTP
Master Data
Master Data
Master Data
Master Data
Master Data
Master Data
Master Data
Master Data
Master Data
Production Master Data CS20 Maintain Bill of Material
Master Data
Production Master Data
Master Data
RTR
Master Data
Master Data
CS03 Display Bill of Material
Production Master Data
STP
STP
RTR
RTR
RTR
RTR
MTE-Scheduling
ITD
MTE-Scheduling
Monitor Production / Planned
10 Constrained Planned Orders COOIS Order
MTE-Scheduling
FTP
MTE-Scheduling
MTE-Scheduling
MTE-Scheduling
COOIS in
combination of
110 Post Goods Issue MIGO Post Goods Movement
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
Yes 12/31/2020
12/31/2020
Yes 12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
Yes 12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
Yes 12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
Yes 12/31/2020
Yes 12/31/2020
Yes 12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
Yes 12/31/2020
Yes 12/31/2020
Yes 12/31/2020
Yes 12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
Yes 12/31/2020
Yes 12/31/2020
Yes 12/31/2020
12/31/2020
Yes 12/31/2020
Yes 12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
Yes
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
nufacturing (MFBF)
12/31/2020
12/31/2020
Yes 12/31/2020
Yes 12/31/2020
12/31/2020
Yes 12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
Yes 12/31/2020
12/31/2020
Yes 12/31/2020
Yes 12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
Yes
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
both plants
12/31/2020
12/31/2020
12/31/2020
Yes
12/31/2020
Yes
12/31/2020
Yes
12/31/2020
12/31/2020
12/31/2020
12/31/2020
Yes
12/31/2020
Yes
12/31/2020
Yes
12/31/2020
Yes
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
Yes
12/31/2020
Yes
12/31/2020
12/31/2020
12/31/2020
Yes
12/31/2020
Yes
12/31/2020
12/31/2020
Yes
12/31/2020
12/31/2020
Yes
12/31/2020
12/31/2020
Yes
12/31/2020
Yes
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
12/31/2020
01/05/2021
01/05/2021
01/05/2021
01/05/2021
01/05/2021
01/05/2021
12/31/2020
01/11/2021
01/11/2021
01/11/2021
01/13/2021
01/13/2021
01/13/2021
01/13/2021
01/13/2021
01/13/2021
01/13/2021
01/13/2021
01/13/2021
01/13/2021
01/13/2021
01/13/2021
01/13/2021
01/19/2021
01/19/2021
01/19/2021
01/19/2021
01/19/2021