You are on page 1of 37

MARK CONFIDENTIAL IF TO BE SENT OUTSIDE

SITE EMERGENCY RESPONSE PLAN CM – S


Doc Number : Author : Rev No : Page No :
CM – S - P LAR 01 1 of 37

Origin Date : Origin Approver : Revision Date : Revision Approver :


PROCEDURE 20th July 2018 ABU - -
UNCONTROLLED COPY IF PRINTED IN HARD COPY

PLTMG MPP 50 MW KENDARI 

Jl. Poros Pltu Nii Tanasa, Desa Nii Tanasa, Kec. Lalonggasumeeto, Kabupaten Konawe, Sulawesi 

Tenggara 93351  
 
 
 
 
 
   
MARK CONFIDENTIAL IF TO BE SENT OUTSIDE

SITE EMERGENCY RESPONSE PLAN CM – S


Doc Number : Author : Rev No : Page No :
CM – S - P LAR 01 2 of 37

Origin Date : Origin Approver : Revision Date : Revision Approver :


PROCEDURE 20th July 2018 ABU - -
UNCONTROLLED COPY IF PRINTED IN HARD COPY

 
1.  Introduction to the Plant ........................................................................................................ 5 
2.  Profile ..................................................................................................................................... 5 
3.  Major Components................................................................................................................. 5 
4.  QEHS Policy ............................................................................................................................ 6 
5.  Transformation Basics ............................................................................................................ 7 
6.  Plant Facilities......................................................................................................................... 7 
6.1  Wartsia Gas Engine and Intake System ....................................................................... 7 
6.2  Water Circulation System ........................................................................................... 7 
6.3  Compressed Air System .............................................................................................. 8 
6.4  Plant Instrumentation & Control DCS System ............................................................. 8 
6.5  Power Evacuation & Transfer System ......................................................................... 8 
6.6  Ventilation System ...................................................................................................... 8 
7.  Utilities ................................................................................................................................... 8 
7.1  Water System ............................................................................................................. 8 
7.2  Switchyard and Power Evacuation System.................................................................. 9 
7.3  Water Treatment Plant – DM Plant ............................................................................ 9 
7.4  Environmental System ................................................................................................ 9 
7.5  Environmental Monitoring Program ........................................................................... 9 
7.6  Lube Oil Requirement and Waste Disposal ............................................................... 10 
8.  Storage Facilities................................................................................................................... 10 
8.1  Fire Fighting & Safety Measures in Storage Facilities ................................................ 10 
9.  Manpower Allocation ........................................................................................................... 10 
10.  Geographical Location .......................................................................................................... 11 
11.  Micro – Meteorological Data (Available on tender / project documents) ............................. 11 
11.1  Temperature............................................................................................................. 11 
11.2  Rainfall...................................................................................................................... 11 
11.3  Relative Humidity ..................................................................................................... 11 
11.4  Wind speed and wind direction ................................................................................ 11 
12.  Emergency Preparedness and Response Plan....................................................................... 11 
12.1  Definition .................................................................................................................. 11 
12.2  Need for Emergency Planning................................................................................... 12 
MARK CONFIDENTIAL IF TO BE SENT OUTSIDE

SITE EMERGENCY RESPONSE PLAN CM – S


Doc Number : Author : Rev No : Page No :
CM – S - P LAR 01 3 of 37

Origin Date : Origin Approver : Revision Date : Revision Approver :


PROCEDURE 20th July 2018 ABU - -
UNCONTROLLED COPY IF PRINTED IN HARD COPY

12.3  Objectives ................................................................................................................. 12 


13.  Risk Assessment ................................................................................................................... 12 
13.1  Risk Assessment due to Plant Process....................................................................... 12 
13.2  Potential accident ..................................................................................................... 13 
13.3  Environmental Incident ............................................................................................ 14 
13.4  Natural Disasters ...................................................................................................... 15 
13.5  Security..................................................................................................................... 16 
14.  Information of Premises and Personnel................................................................................ 16 
14.1  Number and Size of the Buildings and Area .............................................................. 16 
14.2  Numbers and locations of people (in each shift)....................................................... 16 
14.3  Contractors or Other Companies Working Permanently in the Location .................. 17 
14.4  Structural Fire Resistance of the Building, and Fire Class and Firewalls..................... 17 
14.5  Inventory of hazardous chemicals onsite .................................................................. 17 
14.6  Normal and emergency power sources .................................................................... 18 
14.7  Location of critical equipment .................................................................................. 19 
14.8  Location of pressure vessels and distribution systems.............................................. 19 
14.9  Hot work locations.................................................................................................... 21 
14.10  Sewage and rain water collection system ................................................................. 22 
14.11  Oil separators and spill control systems .................................................................... 22 
14.12  Possibility for helicopter landing in emergency......................................................... 23 
14.13  Security measures .................................................................................................... 23 
15.  Emergency organization and responsibilities ........................................................................ 23 
15.1  Internal emergency roles and responsibilities........................................................... 23 
15.1.1  Security chief .............................................................................................. 23 
15.1.2  Fire and rescue team .................................................................................. 24 
15.1.3  First aid man............................................................................................... 24 
15.1.4  Fire equipment service man ....................................................................... 24 
15.1.5  Watchmen.................................................................................................. 24 
15.2  List of key persons and contact information ............................................................. 25 
16.  Emergency services .............................................................................................................. 25 
16.1  Ambulance services .................................................................................................. 25 
16.2  City Fire Brigade Nearby........................................................................................... 25 
16.3  Response time in any emergency situations ............................................................. 25 
MARK CONFIDENTIAL IF TO BE SENT OUTSIDE

SITE EMERGENCY RESPONSE PLAN CM – S


Doc Number : Author : Rev No : Page No :
CM – S - P LAR 01 4 of 37

Origin Date : Origin Approver : Revision Date : Revision Approver :


PROCEDURE 20th July 2018 ABU - -
UNCONTROLLED COPY IF PRINTED IN HARD COPY

16.4  Contracted security and emergency services............................................................ 26 


17.  Fire protection and firefighting equipment .......................................................................... 26 
17.1  Location and type of fixed firefighting equipment .................................................... 26 
17.2  Location and type of portable firefighting equipment .............................................. 27 
17.3  Smoke and heat ventilation systems......................................................................... 28 
17.4  Fire and gas detection systems ................................................................................. 28 
18.  Evacuation arrangements ..................................................................................................... 29 
19.  First aid................................................................................................................................. 30 
19.1  First aid equipment and stretchers ........................................................................... 30 
19.2  Local Health care services ......................................................................................... 31 
20.  Crises communication .......................................................................................................... 32 
20.1  Internal crises communication model ....................................................................... 33 
20.2  External crises communication model ...................................................................... 33 
21.  Actions taken in the event of emergency ............................................................................. 33 
21.1  Fire or explosion ....................................................................................................... 33 
21.2  Chemical spill (liquid, gas or solid) ............................................................................ 34 
21.3  Earthquake, storm, flood, etc ................................................................................... 36 
21.3.1  Earthquake ................................................................................................. 36 
21.3.2  Flood .......................................................................................................... 36 
21.3.3  Hurricane / Strong Wind............................................................................. 36 
21.4  Epidemic or pandemic .............................................................................................. 36 
21.5  Civil disturbance, terrorism, sabotage, or workplace violence .................................. 37 
21.6  Traffic accident ......................................................................................................... 37 
21.7  Other emergency situations ..................................................................................... 37 
21.7.1  Snake‐bite .................................................................................................. 37 
22.  Training and drills ................................................................................................................. 37 
22.1  Training for dedicated emergency personnel ........................................................... 37 
22.2  Training for all personnel .......................................................................................... 37 
22.3  Periodic emergency drills.......................................................................................... 37 
 
   
MARK CONFIDENTIAL IF TO BE SENT OUTSIDE

SITE EMERGENCY RESPONSE PLAN CM – S


Doc Number : Author : Rev No : Page No :
CM – S - P LAR 01 5 of 37

Origin Date : Origin Approver : Revision Date : Revision Approver :


PROCEDURE 20th July 2018 ABU - -
UNCONTROLLED COPY IF PRINTED IN HARD COPY

1. Introduction to the Plant 
The Gas Engines based power generations are the most eco‐friendly process of electricity generation. 
More‐over, the engines are radiator cooled thus resulting in substantial conservation of water. 
 
The gas being sweet with insignificant Sulphur content, the impact due to SO2 in ambient environment 
is very negligible. The engines are also designed to limit NOX emissions to less than 50 PPM. Overall 
gas based power plants are most environment friendly subject to availability of natural gas. 
 
 
2. Profile 
PLTMG 50 MW KENDARI is a 50 MW natural gas‐based power plant located at Kendari. 
 
The estimated Diesel fuel requirement is approximately 196632 Liters per day at 60.0% CF and an 
assumed Net Specific Energy of 42.76 MJ/kg. PT PLN has signed an agreement with PT Pertamina for 
supply of Diesel Fuel. 
 
3. Major Components  

S.No  Components  Description 

1  Gas Engine  Wartsila, 9780kW, 750rpm,  

2  Alternator  ABB, 11KV, 50Hz,750 rpm,  

3  Turbo Charger  Napier, NT1‐12 

4  Grid Power Transformer  Pauwels, 3 Phase, 2 x 40 MVA, 11/70 kV, 50Hz 

5  Auxiliary Transformer  Trafindo 2500, 3 phase, 2 x 2,5 MVA, 11/0,4 kV, 50 Hz  

6  LFO Feeder unit  ABB Motor, IMO Pump, 2 x 18 m3/h 

Motor Power: 4.5 kW, 4 radiators per engine, 4 cooling 
7  Radiator  fans per radiator 
 
 
 
 
 
 
 
MARK CONFIDENTIAL IF TO BE SENT OUTSIDE

SITE EMERGENCY RESPONSE PLAN CM – S


Doc Number : Author : Rev No : Page No :
CM – S - P LAR 01 6 of 37

Origin Date : Origin Approver : Revision Date : Revision Approver :


PROCEDURE 20th July 2018 ABU - -
UNCONTROLLED COPY IF PRINTED IN HARD COPY

4. QEHS Policy  

 
 
MARK CONFIDENTIAL IF TO BE SENT OUTSIDE

SITE EMERGENCY RESPONSE PLAN CM – S


Doc Number : Author : Rev No : Page No :
CM – S - P LAR 01 7 of 37

Origin Date : Origin Approver : Revision Date : Revision Approver :


PROCEDURE 20th July 2018 ABU - -
UNCONTROLLED COPY IF PRINTED IN HARD COPY

 
 
 

Pollution 

Exhaust Gas  Engine  Generator 


Combustion 
Torque 

Elec. Energy 
Mech. 
Heat loss  Loss 
Energy Loss 
(Flue Gas ) 

Thermal  Kinetic   Electrical 


Chemical 
Energy  Energy  Energy 
Energy 

5. Transformation Basics  

Gas  Electricity (Transformation Basics) 
 
6. Plant Facilities  

6.1 Wartsia Gas Engine and Intake System  
 Fuel is supplied by Pertamina 
 Engine inlet gas pressure 5‐8 bar 
 Gas filter pressure drop <0.5 bar 
 Pilot Fuel system is there for ignition to Main fuel as lean burn gas engine. 
 Gas regulator & Shut off valve is operated by control air 6 bar 
 
6.2 Water Circulation System  
 In Engine LT (low temperature) & HT (high temperature) closed water system is there. 
 LT & HT water pumps are Engine driven. 
 LT water temperature / pressure ‐40’c/3.5 bar 
 HT water temperature / pressure – 78’c/3.5 bar 
 LT water 3way valve used for maintaining LT water temp.‐35’c to 45 ‘c 
 HT water 3way valve used for maintaining Engine outlet water temp ‐85’c  
 Cooling water additive is NALCO 2000. 
MARK CONFIDENTIAL IF TO BE SENT OUTSIDE

SITE EMERGENCY RESPONSE PLAN CM – S


Doc Number : Author : Rev No : Page No :
CM – S - P LAR 01 8 of 37

Origin Date : Origin Approver : Revision Date : Revision Approver :


PROCEDURE 20th July 2018 ABU - -
UNCONTROLLED COPY IF PRINTED IN HARD COPY

 To cool the water radiator system is used. For one Engine 16 no. motors each 4.5 kW. 
 Radiator motor speed is controlled by variable frequency drive VACON. 
 
 
6.3 Compressed Air System 
 While Engine starting Engine is cranked by starting air which is 18 ‐25 bar     
 One starting air per engine is used. 
 One starting air bottle per engine is used for storage. 
 For control air to operate pneumatic valves (5‐6 Bar) 
 One Instrument air compressor per engine is used.  
 One instrument air bottle per engine is used for storage 
 
6.4 Plant Instrumentation & Control DCS System  
 Each  engine  has  UNIC  C3  (Unified  Control)  control  which  is  connected  to  PLC 
(Programming Logic Controller) via profile bus cable to CFC panel. 
 Through WOIS (Wartsila Operator Inter face System) all Engine parameters controlled. 
 WOIS is connected to PLC via Ethernet switch.  
 All engine CFC panel PLC connected to CFA panel PLC via Ethernet cable 
 
6.5 Power Evacuation & Transfer System  
 Three Engines connected to one Power transformer. 
 Each Power Transformer: 40 MVA, 11KV/70KV, PAUWELS Make. 
 Two Transformers connected to Common bus in the Switch yard. 
 
6.6 Ventilation System  
Engine  Cube  are  ventilated  with  3  number  of  pressurized  fans  located  Two  at  Engine  Cube 
Module Bay and other at Roof. 
 Two  Unit  of  inlet  ventilation  at  Engine  Cube  Module  Bay  (Manufacturer:  ZIEHL‐
ABEGG) Flow 20 m3/s, Motor Power 7.5 kW 
 One Unit of Outlet Ventilation fan at roof cube (Manufacturer: ZIEHL‐ABEGG) Flow 10 
m3/s, Motor Power 7.5 kW 
 
7. Utilities  

7.1 Water System  
The water requirements for PLTMG Kendari are covered under the following categories. 
 Raw water supply system 
 Water treatment (WT) system 
 Service water system 
 
MARK CONFIDENTIAL IF TO BE SENT OUTSIDE

SITE EMERGENCY RESPONSE PLAN CM – S


Doc Number : Author : Rev No : Page No :
CM – S - P LAR 01 9 of 37

Origin Date : Origin Approver : Revision Date : Revision Approver :


PROCEDURE 20th July 2018 ABU - -
UNCONTROLLED COPY IF PRINTED IN HARD COPY

7.2 Switchyard and Power Evacuation System  
70kV switchyard are provided for evacuation of power generated at the plant. Control and 
Protection  for  the  lines  is  provided  on  the  70kV  switchyard,  relay  and  control  panel.  The 
switchgear has:  
 Generator Transformers : 2 Units 
 Outgoing Feeder : 2 Units 
 
The switchyard is supplied and installed with all accessories to make the switchyard complete 
in all respects. The switchyard consists of: 
 70kV circuit breaker, isolators CT’s and PT’s 
 Lightning Arrestors 
 Bus bar material & accessories, insulator assemblies, clamps & connectors 
 Switchyard structures & support 
 Switchyard relay panels 
 Switchyard control panels 
 
7.3 Water Treatment Plant – DM Plant  
The water treatment plant provides make up water of the specified quality and quantity to 
meet  the  water  requirement  of  the  power  plant.  Water  treatment  plant  consists  of  pre‐
treatment plant and RO Unit.  
 
7.4 Environmental System  
The power plant is designed to meet the environmental requirements. The solid, liquid and 
gas  waste  are  either  recycled  or  disposed  off  in  accordance  with  the  Indonesian 
Environmental Department. 
 
7.5 Environmental Monitoring Program 
Sr No  Parameter  Frequency 
1  Ambient Air Quality   Twice  in  a  year  for  24  hours 
continuously to monitor SO2, NOx, CO, 
HC,  O3,  Lead,  Dust,  Temperature, 
Humidity levels. 
2  Source emissions  Continuous    On‐line    monitoring    for  
Particulate, CO, NO2, SO2, Opacity. 
3  Ground water quality  Once  in  a  month  except  for  heavy 
metals  which  will  be  monitored 
quarterly.  Monitoring  will  be  carried   
out   for   parameters   specified   under
IS: 10500:2012. 
4  Wastewater quality  Once in a month will be carried out for 
24  hours 
Continuously as per EPA Rules, 1986. 
5  Soil sample  Soil      samples    will    be      monitored   
quarterly for 
parameters specified by TNPCB. 
6  Ambient Noise Environment  Ambient  noise  environment  will  be 
monitored 
once in a half yearly. 
MARK CONFIDENTIAL IF TO BE SENT OUTSIDE

SITE EMERGENCY RESPONSE PLAN CM – S


Doc Number : Author : Rev No : Page No :
CM – S - P LAR 01 10 of 37

Origin Date : Origin Approver : Revision Date : Revision Approver :


PROCEDURE 20th July 2018 ABU - -
UNCONTROLLED COPY IF PRINTED IN HARD COPY

8  Occupational Health and safety  Qualified  doctors  carry    out  


pre‐employment  and      periodical   
medical   check‐up   of   all   the 
employees. 
 
 
7.6 Lube Oil Requirement and Waste Disposal 
Two main oil requirements in the plant are for the oil circulation for Gas Engine operation and 
for the transformer operation. Lube oil is stored in 20 kL tank for each Gas Engine operation. 
The quantity of transformer oil includes 40 kL( x 2 nos) in the main two transformers and 4kL 
(x 2 nos) at the online tap changers.  
 
Wastage of 2‐5% per annum of lube oil is expected. These arise due to spills, leaks during the 
course  of  the  circulation  and  will  be  collected  as  oil  sludge  and  sent  to  certified  sludge 
transporter and recycler. Spent oil due to deterioration at transformer will be totally replaced 
and disposed as per TNPCB norms. 
 
 
 
8. Storage Facilities  
There are two tanks for storage of Lubricating oil. These are: 
 One New Lube Oil Tanks of capacity 20 KL for storing new lube oil. 
 One Used Lube Oil Tank, capacity 20 KL for storing dirty engine oil which is not suitable for further 
use. 
 
MSDS for HSD is given in Appendix II 
 
8.1 Fire Fighting & Safety Measures in Storage Facilities 
Risk for storage units depends not only the extent of the consequence, but also on the probability 
of the failure of the safety measures and provisions provided. Following table describes the safety 
measures provided in storage facilities. 
 
Acts in case of oil tank fire: 
 Make fire alarm 
 Stop the process 
 Use portable extinguisher in case of small fire 
 Use mobile foam units from the power house or fuel treatment house in case of large fire.  
 Burning oil tank and other oil tanks can be cooled by water jets 
 Oil from burning oil tank or others can be tried to pump away 
 Be careful with burning oil leakage 
 Resist oil or oil soiled fire water leakage to the river or drains, which have not oil 
 Follow local fire brigade’s orders 
 
 
 
 
9. Manpower Allocation  
The existing manpower is 49.  
MARK CONFIDENTIAL IF TO BE SENT OUTSIDE

SITE EMERGENCY RESPONSE PLAN CM – S


Doc Number : Author : Rev No : Page No :
CM – S - P LAR 01 11 of 37

Origin Date : Origin Approver : Revision Date : Revision Approver :


PROCEDURE 20th July 2018 ABU - -
UNCONTROLLED COPY IF PRINTED IN HARD COPY

 
10. Geographical Location  
Plant Address : JL. Poros PLTU Nii Tanasa, Desa Nii Tanasa, Kec. Lalonggasumeeto, Kab. Konawe, South 
East Sulawesi 93351 
Location Coordinates : 3°53'40.4"S 122°32'21.4"E 
 
11. Micro – Meteorological Data (Available on tender / project documents) 
Climate    : Coastal 
Rainfall    : 265 mm (Average) 
Temperature  : 25°C – 33°C Max.  
Wind Speed  : 12 Km/Hr 
Min. Wind Speed  : 0.5 Km/Hr 
Wind Direction  : North West 
 
11.1 Temperature  
The district has a tropical climate temperature ranging from 25 C (min) to 33 C (max) and the 
relative humidity is at 77% on an average and it ranges between 71% to 83% in coastal areas. 
 
11.2 Rainfall 
Based on available data, it is observed that maximum rainfall is in April and minimum is in 
September. 
 
11.3 Relative Humidity 
Humidity is generally high in 77%. During January to August comparatively it is very high and 
goes to a maximum of about 83% during May and June. October has been found as the driest 
month with maximum humidity of 97% and minimum humidity of 46%. 
 
11.4 Wind speed and wind direction 
Wind  speed  determines  the  rate  of  diffusion  and  travel  time  of  pollutants,  while  direction 
determines direction of transport of pollutants. Based on the data, it is found that in this area 
wind speed is maximum in October and minimum in March. Wind direction predominantly is 
towards west followed by North West. 
 
12. Emergency Preparedness and Response Plan  
Major  Accidents  can  occur  in  any  industry  in  spite  of  the  best effort  to  prevent  them.  Apart  from 
providing safe facilities it is necessary to have an action plan prepared in anticipation of an emergency 
to prevent losses and to restore the normality at the earliest. 
It aims at controlling the emergency and mitigating the adverse effects of a major accident. 
12.1 Definition  
Incidents/ Occurrence that may affect several departments within the works and cause 
serious injury and loss of life, extensive damage to property or serious disruption of work 
and require the use of combined resources are termed as Emergency. 
 
MARK CONFIDENTIAL IF TO BE SENT OUTSIDE

SITE EMERGENCY RESPONSE PLAN CM – S


Doc Number : Author : Rev No : Page No :
CM – S - P LAR 01 12 of 37

Origin Date : Origin Approver : Revision Date : Revision Approver :


PROCEDURE 20th July 2018 ABU - -
UNCONTROLLED COPY IF PRINTED IN HARD COPY

12.2 Need for Emergency Planning  
Every  industry  has  to  prepare  the  detailed  plan  to  show  its  competence  to  manage  the 
possible hazards. It is a statutory requirement under PT Wartsila Indonesia. 
 
12.3 Objectives 
 To contain and control accidents. 
 To  effect  maximum  use  of  the  combined  resources  in  the  plant  and  outside  for 
minimizing loss. 
 To fix responsibility of individuals in order to avoid confusion. 
 To  prevent  delay  in  emergency  actions  such  as  evacuation,  rescue,  Fire  fighting, 
mitigation of effect of toxic release, medical relief etc. 
 To restore normalcy at the earliest. 
 
13. Risk Assessment  
PLTMG 50 MW Kendari has carried out risk analysis studies to assess potential to cause accident. In 
most cases, proactive systems are in place and the probability of incidents is low. To govern the safety 
during Maintenance activities, effective Work Permit System is in place, in addition to permit system, 
Protocol & JSA is in place to take care of most critical activities, new erection & first time jobs. 
 
13.1 Risk Assessment due to Plant Process  
 
Sl.  Activity/  Explosion  Fire  Toxic release  Spill 
No.  Unit 
1  Usage  of  Explosion  Fire   Vapor  of  natural    
Natural  Gas  when leak and  gas 
as  engine  reaches 
fuel  explosion 
temperature   
2  Storage  of  Explosion  Fire hazard due  ‐  Spill  to  Drainage 
B20  when leak and  to  leakage  of  system  and 
reaches  oil.  Contaminate 
explosion  surrounding 
temperature    environment. 
3  Storage  of  ‐  ‐  Sharp  smell  could  Major spills of acid in 
Sulphur acid  lead to respiration  to bund will result in 
damage  localized  formation  
of acid  mist/fumes 
4  70kV/  Explosion  of  Possibility  of  Aerosols  –  Smoke  ‐ 
11kV  breakers,  fire  due  to  and CO 
Transformer  transformers  overheating  of 
or capacitor  transformer oil 
5  Cable  cellar  ‐  Fire  PVC  cables  emit  ‐ 
room  toxic gases 
7  MV Building  Explosion  of  Possibility  of       
Breaker  short circuit  
8  Workshop    Possibility  Smoke  from  Spill  of  equipment 
electric  short  welding process  cleaning activity 
circuit, Welding 
MARK CONFIDENTIAL IF TO BE SENT OUTSIDE

SITE EMERGENCY RESPONSE PLAN CM – S


Doc Number : Author : Rev No : Page No :
CM – S - P LAR 01 13 of 37

Origin Date : Origin Approver : Revision Date : Revision Approver :


PROCEDURE 20th July 2018 ABU - -
UNCONTROLLED COPY IF PRINTED IN HARD COPY

and  Grinding 
Process 
 
13.2 Potential accident  
 

Emergency Situation  Impact  Containment / Mitigation Measures 

Bring down the victim (if he is working at   
height) 
without  panic.
Injury  with  or  without  
Fall of person  fracture,  loss  of  body  parts  due  to  Administer the first aid for any injury on 
non‐ adherence to safe practices.        the  spot.
 
Shift  the  victim  to  the  Occupational 
health centre at the earliest. 
Bring down the victim (if he is working at   
height)  without  panic. 
Injury  with  or  without  
Fall of object  fracture, loss of body parts   due   to    Administer  the  first  aid  on  the  spot. 
non ‐ adherence to safe practices.   
Shift  the  victim  to  the  Occupational 
health centre at the earliest. 
Cut  off  the  supply
 
If it is not possible to isolate to electrical 
supply, remove   the   victim   with   the 
help  of  insulating  material  e.g.  dry 
Electrocution,  burn  injury,  muscle 
wooden stick by ensuring personal safety
Electrocution  dissipation, loss of body part due to 
 
non‐adherence to safe practices. 
Administer  the  first  aid  (CPR  –  Cardio 
Pulmonary  Resuscitation)  on  the  spot.
 
Shift the victim to the medical centre at 
the earliest. 
Stop  the  machine  in  which  the  victim  is 
trapped.  Disengage  the  victim  from  the 
nip  point  of  the  machine.
Injury with or without fracture, loss 
Caught   
of body parts due to non‐adherence 
between/Entrapment  Administer  the  first  aid  on  the  spot.
to safe practices. 
 
Shift  the  victim  to  the  Occupational 
health centre at the earliest. 
Collision  with  truck/ 
Injury with or without fracture, loss 
tanker/  front  end  Remove  the  victim  from  the  accident 
of body parts due to non‐ adherence   
loader and any   other   spot. Administer the first aid on the spot.
to   safe practices. 
mobile vehicle 
MARK CONFIDENTIAL IF TO BE SENT OUTSIDE

SITE EMERGENCY RESPONSE PLAN CM – S


Doc Number : Author : Rev No : Page No :
CM – S - P LAR 01 14 of 37

Origin Date : Origin Approver : Revision Date : Revision Approver :


PROCEDURE 20th July 2018 ABU - -
UNCONTROLLED COPY IF PRINTED IN HARD COPY

Administer  the  first  aid  with  plenty  of 


water  for  15  minutes  on  the  spot.
Contact  with  hot  Burn injury due to non‐adherence 
 
water  to safe practices. 
Shift  the  victim  to  the  Occupational 
health centre at the earliest. 
Remove  the  victim  from  the  accident 
spot. 
 
Fainting  due  to  Fainting  due  to  release  of  gas  in  Administer  the  first  aid  (Mouth  to 
suffocation  the area due to poor maintenance. Mouth  respiration)  on  the  spot.
 
Shift  the  victim  to  the  Occupational 
health centre at the earliest. 
Remove  the  victim  with  the  help  of 
personnel  available  who  can  swim.
 
If  required  wear  necessary  protective 
clothing such as PVC suits, Acid splash 
goggles, etc. Use of long rope available 
with  maintenance  department  is 
advisable. 
Drowning in water  Falling into water ponds.   
Dewater  the  victim  if  he/she  has 
swallowed  water.
 
Administer  first  aid  (Mouth  to  Mouth 
respiration,  if  required)  on  the  spot.
 
Shift  the  victim  to  the  OHC 
immediately. 
Administer  the  first  aid  with  plenty  of 
water  for  15  minutes  on  the  spot.
 
Acid  burn  injury  due  to  non‐ Apply safety gels if Sulphuric acid burn 
Acid splash 
adherence to safe practices.  injury. 
 
Shift  the  victim  to  the  Occupational 
health centre at the earliest. 
 
13.3 Environmental Incident  
Emergency Situation  Impact  Containment / Mitigation Measures 

Oil Spill   Polluting  nearby  Isolate the spill area using sawdust. 


environment   Remove remaining oil spill to oil sump pit. 
 
Mitigation: the surrounding unit should be built a 
containment  wall  to  isolate  the  unit  from  the 
MARK CONFIDENTIAL IF TO BE SENT OUTSIDE

SITE EMERGENCY RESPONSE PLAN CM – S


Doc Number : Author : Rev No : Page No :
CM – S - P LAR 01 15 of 37

Origin Date : Origin Approver : Revision Date : Revision Approver :


PROCEDURE 20th July 2018 ABU - -
UNCONTROLLED COPY IF PRINTED IN HARD COPY

environment. 

Soil  Polluting nearby soil  Remove  the  contaminated  soil  to  Hazardous 


Waste  Area  and  contact  certified  hazardous 
waste  disposal  company  to  handle  the 
contaminated soil. 
 
Mitigation:  Isolate/build  the  containment  wall 
surrounding the area. 
Air emission   Polluting nearby air  Stop  the  operating  unit.  Do  the  inspection  to 
analyze the cause of the high emission. 

Mitigation: Continuously Monitor the Emission of 
the unit. 
Water  pollution Damaging  the  nearby  Isolate  the  contaminated  area.  Remove  the 
discharge  from  Fuel  and
environment  contaminated water to waste water treatment to 
Lube  Oil  Treatment
system   neutralize the waste. 

Mitigation:  Continuously  monitor  the  waste 


water product quality before moving them to the 
drainage system. 
 
 
13.4 Natural Disasters 
Emergency Situation  Impact  Containment / Mitigation Measures 

Earthquake   Construction  and  Emergency Plant Shutdown 


Facility Damage  Relocate all personnel to the master point 

Flood   Construction  and  Emergency Plant Shutdown 


Facility Damage 
Relocate all personnel to higher landscape 
Tsunami   Construction  and  Emergency Plant Shutdown 
Facility Damage 
Relocate all personnel to higher landscape 
 
 
MARK CONFIDENTIAL IF TO BE SENT OUTSIDE

SITE EMERGENCY RESPONSE PLAN CM – S


Doc Number : Author : Rev No : Page No :
CM – S - P LAR 01 16 of 37

Origin Date : Origin Approver : Revision Date : Revision Approver :


PROCEDURE 20th July 2018 ABU - -
UNCONTROLLED COPY IF PRINTED IN HARD COPY

13.5 Security 
Emergency Situation  Impact  Containment / Mitigation Measures 

Civil Disturbance  Access  Blockade  to  Plant Emergency Shutdown 


PLTMG  Call nearby Police Department 
Evacuation for all personnel 
Terrorism   Endanger  Personnel  Plant Emergency Shutdown 
Life and could lead to  Call nearby Police Department 
Facility destruction  Evacuation for all personnel 

Sabotage   Distract the operation  Call nearby Police Department 


of Power plant 

Workplace Violence   Distract the operation  Call nearby Police department 


of Power plant 
Call  the  guard  to  isolate  the  involved 
personnel/suspect 
 
 

14. Information of Premises and Personnel 
14.1 Number and Size of the Buildings and Area 
Description of PLTMG 50 MW Kendari 
Buildings / Areas  Number (s)  Size 
Power House   1   
Electrical Equipment Building   1   
Fuel Treatment Area   1   
Workshop & Warehouse   1   
Fuel Unloading Station   1   
Oily Water Collecting Pit  7   
Lub Oil Shelter   1   
Block Station Transformer   2   
Waste Water Treatment Plant  1   
 
14.2 Numbers and locations of people (in each shift) 
PLTMG 50 MW Kendari 
Buildings / Areas  Numbers of people (in each shift)  Remarks  
Shift 1  Shift 2  Shift 3 
Power  House  &  2  2  2  2  personnel 
Electrical  Equipment  off 
Building 
Fuel Treatment House          
MARK CONFIDENTIAL IF TO BE SENT OUTSIDE

SITE EMERGENCY RESPONSE PLAN CM – S


Doc Number : Author : Rev No : Page No :
CM – S - P LAR 01 17 of 37

Origin Date : Origin Approver : Revision Date : Revision Approver :


PROCEDURE 20th July 2018 ABU - -
UNCONTROLLED COPY IF PRINTED IN HARD COPY

Workshop  &  3       
Warehouse  
Fuel  Unloading  2       
Station  
Oily  Water  Collecting         
Pit 
Lub Oil Shelter          
Block  Station         
Transformer  
Office  8       
Waste  Water  1       
Treatment Plant 
 
14.3 Contractors or Other Companies Working Permanently in the Location 
PLTMG 50 MW Kendari 
Name of Contractors or Other Companies  Number of Personnel 
Nawakara  17 
Supraco CS  7 
Supraco Driver  5 
 
 
14.4 Structural Fire Resistance of the Building, and Fire Class and Firewalls 
In the power plant area there is a power house, where in the same building is a utility block, 
and  some  smaller  buildings.  The  buildings  are  normally  made  of  steel.  The  fire  resistance 
category of frame structures, external walls and roof are of non‐combustible material.    
 
Floor area           
Engine hall         : 693.5 m² 
Administration & social facility building  : 230.5 m² 
Electrical equipment building    : 266.5 m² 
Fuel pump house           : 91.0 m² 
Workshop & warehouse       : 150.0 m² 
Guard house        : 16.0 m² 
 
14.5 Inventory of hazardous chemicals onsite 
All  hazardous  substance  which  will  be  used  for  supporting  activities  in  Wartsila  shall  be 
completed  with  MSDS.  Responsible  Department  Manager  is  responsible  to  ensure  all 
hazardous substance bought and deliver to Wartsila Indonesia completed with MSDS. 
 
Department that use chemical shall retains one copy of each chemical that used in operational 
activities 
 
Storage of chemical must follow applicable regulation, client/customer policy and MSDS of 
chemical. It is minimum recommendation guidance for handling and storage of chemical as 
following but not limited to: 
 Storage area of flammable liquids such as diesel oil, lube oil, paint, thinner, gasoline, glues 
and solvents is recommended provide separately 
 Storage  areas  shall  be  in  open  room  or  has  well  ventilated  by  means  of  natural 
MARK CONFIDENTIAL IF TO BE SENT OUTSIDE

SITE EMERGENCY RESPONSE PLAN CM – S


Doc Number : Author : Rev No : Page No :
CM – S - P LAR 01 18 of 37

Origin Date : Origin Approver : Revision Date : Revision Approver :


PROCEDURE 20th July 2018 ABU - -
UNCONTROLLED COPY IF PRINTED IN HARD COPY

ventilation. 
 Storage area shall be marked appropriately as chemical area or room  
 There  shall  be  no  smoking  or  open  flames  within  the  vicinity  of  a  flammable  liquids 
storage area. 
 Appropriate fire extinguishers and eyewash station shall be mounted in the immediate 
vicinity of each storage area. 
 Chemical container shall be closed condition 
 Use recommended personal protective equipment  
 As possible do not handle or store around the domestic drainage 
 

 
 
14.6 Normal and emergency power sources 
For emergency power sources like black out or other incident, this site use black start unit 
that located near E‐house 
MARK CONFIDENTIAL IF TO BE SENT OUTSIDE

SITE EMERGENCY RESPONSE PLAN CM – S


Doc Number : Author : Rev No : Page No :
CM – S - P LAR 01 19 of 37

Origin Date : Origin Approver : Revision Date : Revision Approver :


PROCEDURE 20th July 2018 ABU - -
UNCONTROLLED COPY IF PRINTED IN HARD COPY

14.7 Location of critical equipment  

 
 
 
     
14.8 Location of pressure vessels and distribution systems 
Air compressed system consist of Starting air (30 bar) and Instrument air (7 bar). There are one
starting air system (include its pressure vessel) and one instrument air system (include its pressure
vessel) in each engine cube. Also there is a compressor for maintenance purpose located in
workshop. Instrument air and Starting air system can be operated individually for its engine cube
or it can be shared to other engine using common line air system. This common line air system
also used for air supply in Feeder unit pump, Diaphragm pumps (Sump Pit), Lube oil Separator
and Fuel Oil Separator.
MARK CONFIDENTIAL IF TO BE SENT OUTSIDE

SITE EMERGENCY RESPONSE PLAN CM – S


Doc Number : Author : Rev No : Page No :
CM – S - P LAR 01 20 of 37

Origin Date : Origin Approver : Revision Date : Revision Approver :


PROCEDURE 20th July 2018 ABU - -
UNCONTROLLED COPY IF PRINTED IN HARD COPY

 
 
 
 
 
 
 
   
MARK CONFIDENTIAL IF TO BE SENT OUTSIDE

SITE EMERGENCY RESPONSE PLAN CM – S


Doc Number : Author : Rev No : Page No :
CM – S - P LAR 01 21 of 37

Origin Date : Origin Approver : Revision Date : Revision Approver :


PROCEDURE 20th July 2018 ABU - -
UNCONTROLLED COPY IF PRINTED IN HARD COPY

14.9 Hot work locations 
At the Site, hotwork such as welding, machining is done in the workshop area 
 

 
MARK CONFIDENTIAL IF TO BE SENT OUTSIDE

SITE EMERGENCY RESPONSE PLAN CM – S


Doc Number : Author : Rev No : Page No :
CM – S - P LAR 01 22 of 37

Origin Date : Origin Approver : Revision Date : Revision Approver :


PROCEDURE 20th July 2018 ABU - -
UNCONTROLLED COPY IF PRINTED IN HARD COPY

14.10 Sewage and rain water collection system 

 
14.11 Oil separators and spill control systems 
There two kinds of separator in PLTMG 50 MW Kendari, There are Fuel Oil Separator and six
Lube Oil Separators, Lube Oil separator is used to purify lube oil in each unit of engine. The
clean oil is discharged back to the engine, while the dirty oil is discharged to oil sump pit.
MARK CONFIDENTIAL IF TO BE SENT OUTSIDE

SITE EMERGENCY RESPONSE PLAN CM – S


Doc Number : Author : Rev No : Page No :
CM – S - P LAR 01 23 of 37

Origin Date : Origin Approver : Revision Date : Revision Approver :


PROCEDURE 20th July 2018 ABU - -
UNCONTROLLED COPY IF PRINTED IN HARD COPY

 
 
14.12 Possibility for helicopter landing in emergency 
There is no possibility for helicopter landing in the site. 
 
14.13 Security measures  
The Site is completely surrounded by fences and also equipped with barbed wire to minimize 
the possibility of animals get through to site. 
 
 

15. Emergency organization and responsibilities 
15.1 Internal emergency roles and responsibilities  
15.1.1 Security chief 
Security chief is a leader of the power plant. His deputies are leaders of shifts. 
Duties of the security chief are: 
 Fire and accident prevention management in the power plant 
 Leading fire protection and rescue work in case of accident before the Arrival of 
the local fire brigade 
 Making fire and safety inspections regularly in the power plant 
 Controlling the condition of fire prevention systems and equipment 
 Controlling housekeeping and tidiness 
 Controlling the smoking rules 
 Controlling cutting, welding and hot works. Giving permissions to those works 
MARK CONFIDENTIAL IF TO BE SENT OUTSIDE

SITE EMERGENCY RESPONSE PLAN CM – S


Doc Number : Author : Rev No : Page No :
CM – S - P LAR 01 24 of 37

Origin Date : Origin Approver : Revision Date : Revision Approver :


PROCEDURE 20th July 2018 ABU - -
UNCONTROLLED COPY IF PRINTED IN HARD COPY

 Taking care of education and training of fire prevention and safety  
 Organization.  He  can  use  experts  to  give  education,  for  instance  local  Fire 
prevention authorities 
 Contacting the fire prevention and safety authorities 
 Contacting  the  own  superior  in  safety  matters.  Giving  suggestions  for  better 
safety and new safety equipment acquiring 
 Maintenance of the safety plan 
Polsek Lalonggasumeeto 082293201997 
 
15.1.2 Fire and rescue team 
Every worker in the power plant belongs to the fire and rescue team. Security chief is 
leader of the fire and rescue team. His deputies are leaders of the shifts. 
Duties of the fire and rescue team are: 
 Making emergency call 
 Fire protection and rescue work independently or in the co‐operation with local 
fire brigade 
 Extinguishing by using portable extinguishers, hose equipment and mobile foam 
units 
 Resisting spreading of fire by closing doors and windows and carrying possible 
gas bottles etc. away 
 Rescuing and evacuating 
 Prevention of oil leaks 
 Guiding and helping local fire brigade 
Kendari Fire Brigade 04013122113 
 
 
15.1.3 First aid man 
In every shift there should be at least one first aid man and Duties of first aid men are 
 Making emergency call or ordering someone to do it 
 Giving first aid in case of accident or illness. 
 Giving especially emergency first aid (lifesaving first aid) 
 Giving first aid independently or in co‐operation with paramedics 
 Maintenance of first aid equipment 
Ambulance Santa Anna 04013123092 
15.1.4 Fire equipment service man 
In the power plant there  should be at  least one fire prevention  equipment service 
man. Duties of fire prevention equipment service man: 
 Maintenance and testing of automatically fire detection system 
 Maintenance and testing of fire pumps 
 Maintenance of hose equipment, mobile foam units and portable extinguishers 
 Maintenance of safety and exit lights and signs 
 Maintenance of other fire prevention and safety signs 
 Maintenance of fire water system, pumps and hydrants 
 Maintenance of fire doors and fire walls 
 Testing ventilation fire dampers manually 

15.1.5 Watchmen  
In every shift there are __watchmen. Duties of watchmen 
MARK CONFIDENTIAL IF TO BE SENT OUTSIDE

SITE EMERGENCY RESPONSE PLAN CM – S


Doc Number : Author : Rev No : Page No :
CM – S - P LAR 01 25 of 37

Origin Date : Origin Approver : Revision Date : Revision Approver :


PROCEDURE 20th July 2018 ABU - -
UNCONTROLLED COPY IF PRINTED IN HARD COPY

 Controlling passage in the power plant area 
 Keeping outsiders away from the power plant area 
 Being security guards 
 Guiding of local fire brigade in case of fire 
 Taking part of fire fighting and rescue work if necessary 
 Other watchman duties 
 
15.2 List of key persons and contact information 

POSITION  NAME and TITLE  PHONE 


    Cell phone: +6281260095223 
Designated responsible official  Arief Budiman 
(leader of power plant) 
Alternate:  Cell phone: +6281379212228 
Budiono Iwan S 

  Yulianus  Cell phone: +6281288977107 
Emergency coordinator 
 (leader of the shift) 
Alternate:  Cell phone: 
Beni H  +628122791444 
Alexsander P  +6281342540617 
Oscar B  +6285241545643 
    Cell phone: +6285341620324 
Guard  Yusuf 
 
  Latif W  Cell phone: +6282116098310 
Watchmen  

M Fahman Yusuf  Cell phone: +6282114664956 
First Aider 

Ridwar Sanjaya  Cell Phone: +6285213883822 
Rescuer 

Ruslan  Cell phone: +6285242388207 
Fire Fighter 

16. Emergency services  
16.1 Ambulance services 
Santa Anna Hospital (04013123092) 
16.2 City Fire Brigade Nearby 
Kendari Fire Brigade (04013122113) 
16.3 Response time in any emergency situations  
Access to nearby city is about a half hour 
MARK CONFIDENTIAL IF TO BE SENT OUTSIDE

SITE EMERGENCY RESPONSE PLAN CM – S


Doc Number : Author : Rev No : Page No :
CM – S - P LAR 01 26 of 37

Origin Date : Origin Approver : Revision Date : Revision Approver :


PROCEDURE 20th July 2018 ABU - -
UNCONTROLLED COPY IF PRINTED IN HARD COPY

16.4 Contracted security and emergency services 
Nearby Police Department (082293201997) 
 

17. Fire protection and firefighting equipment  
The power plant’s fire protection consists of structural solutions, fire extinguishing system and fire 
alarm  system.  The  basic  fire  protection  system  consists  of  the fire  main  network  with  fire  pumps, 
water tanks, distribution pipelines, sprinkler system, hydrants, hose reels, hose equipment, mobile 
foam units and portable extinguishers 
 
17.1 Location and type of fixed firefighting equipment 
There are two fire pumps, one is electric and the other is diesel engine driven. The pumps 
supply fire main network. Water is coming from Fire water tank, size 700 m3. Fire water tank 
has capacity for two hours. 
 
The pumps and control panels are located in the fire pump container/house. The pumps and 
water tanks are located so that the suction pipes and pumps are always filled with water. 
 
The diesel engine is equipped with an approved automatic auxiliary start. The diesel pump has 
a fuel tank containing sufficient fuel to enable the pump to run a full load for at least 2 hours. 
 
The electric jockey pump system will maintain system pressure in the fire line. If the jockey 
pump cannot keep the pressure in the system the fire pumps starts automatically. The fire 
pumps are stopped manually. A common fault alarm from the fire pumps is led to the control 
room. 
 
The number and position of the hydrants are such that spray from at least two hoses with 
combined jet and water fog nozzles may reach any part of engine hall or auxiliary room and 
spray from one combined jet and water fog nozzles may reach any part of other places. Each 
hydrant is fit with a stop valve. 
 
The fire water tank must be continuality kept full of water. Maintenance and testing of fire 
water system, pumps and hydrants must be done regularly. 
 
Fire  hose  cabinets  on  site  area  are  equipped  with  two  fire  hoses  and  a  branch  pipe  with 
combined jet and water fog nozzle.  
 
The fire hose coupling standard is of type BS336. Fire hoses are oil‐resistant and approved 
material. Hose connections are made of a copper alloy approval material. The hose length for 
outside hydrants is 20 m, 65mm and designed for 10 bar pressure. Inside power house the 
hoses are of size 38mm. 
 
Hose reels are located in accommodation spaces. The hose reels are permanently connected 
to the fire water piping system under constant water pressure. The hose reels are placed and 
arranged in such a way that any point in the accommodation spaces may be reached with a 
spray from at least one hose reel.  
 
The hose reel is 30 m in length per reel. The hose that has an internal diameter of 25 mm is 
equipped with a nozzle for both spray and solid jet. 
MARK CONFIDENTIAL IF TO BE SENT OUTSIDE

SITE EMERGENCY RESPONSE PLAN CM – S


Doc Number : Author : Rev No : Page No :
CM – S - P LAR 01 27 of 37

Origin Date : Origin Approver : Revision Date : Revision Approver :


PROCEDURE 20th July 2018 ABU - -
UNCONTROLLED COPY IF PRINTED IN HARD COPY

 
Fire hose equipment and hose reels are very powerful in firefighting. Workers must train to 
use fire hose equipment and hose reel. 
 
Location of the fire pumps, pipes, water tank and hydrants are shown in the emergency layout 
PLTMG 50 MW Kendari. 

 
 
     
17.2 Location and type of portable firefighting equipment 
 Mobile foam units 
Water must not be used to extinguish oil fires and therefore mobile foam units are used 
for that purpose. The foam unit is considered to be ideal for the protection of small oil 
storage  and  unloading  terminals,  boiler  rooms,  engine  rooms,  process  areas  and  all 
similar areas. It has been designed for one‐man foam deployment to be easily operable 
by one person.  
 
A mobile foam unit consist of a low expansion foam branch pipe, inductor, 100 liter foam 
tank and two 20 m lengths of 65 mm fire hose with coupling’s type suitable to connect 
to the fire main hydrants. The unit requires only a connection to a suitable pressurized 
water supply (min. 5 bar). 
 
The mobile foam units must be tested regularly and foam liquid must not be expired. 
Workers should be trained to use the mobile foam unit 
MARK CONFIDENTIAL IF TO BE SENT OUTSIDE

SITE EMERGENCY RESPONSE PLAN CM – S


Doc Number : Author : Rev No : Page No :
CM – S - P LAR 01 28 of 37

Origin Date : Origin Approver : Revision Date : Revision Approver :


PROCEDURE 20th July 2018 ABU - -
UNCONTROLLED COPY IF PRINTED IN HARD COPY

 
 Portable extinguishers  
In  the  power  plant  area  there  are  portable  CO2  (5  kg)  and  dry  powder  (12  kg,  ABC) 
extinguishers.  CO2  is  useful  especially  against  electrical  and  liquid  fires  inside  the 
building. Dry powder is useful against solid material, liquid and electrical fires. CO2 is a 
suffocating  gas.  The  room  must  be  evacuated  immediately  after  usage  of  CO2 
extinguishers. 
 
Maintenance  of  extinguishers  must  be  done  regularly.  Workers  must  train  to  use 
portable extinguishers. 
 
Fire extinguishers are divided into categories, based on different types of fires. 
 
Class  A  extinguishers  are  for  ordinary  combustible  materials  such  as  paper,  wood, 
cardboard, and most plastics.   
 
Class B fires involve flammable or combustible liquids such as gasoline, kerosene, grease 
and oil.  
 
Class C fires involve electrical equipment, such as appliances, wiring, circuit breakers and 
outlets. Never use water to extinguish class C fires ‐ the risk of electrical shock is far too 
great! 
 
17.3 Smoke and heat ventilation systems 
There is no automatic smoke ventilation system in the power plant. Smoke ventilation will be 
done by using windows and doors. Smoke ventilation will be done by local fire brigade. In case 
of plant emergency shut down the whole ventilation system is stopped. Roof monitors are 
mainly used in Power Plants with large engine halls and preferably in climates above 0°C. In 
cold conditions there are closable roof monitors. 
 
17.4 Fire and gas detection systems 
The power plant is supplied with an automatic fire detection system. Workers may also make 
manual alarm by using the push button. Push buttons are installed at critical points and escape 
routes. Alarm transmits to the control panel of fire detection system in the control room and 
fire bells and sirens start to ring. The fire bells and sirens are located so that the fire alarm can 
be heard everywhere. Flashing lights are installed in engine hall because of the high noise 
level. 
 
Engine hall is supplied with open path gas detectors, Administration building and social facility 
rooms, Switchgear room, control room are provided with smoke detectors. Compressor room 
& Kitchen has heat detectors. On the other hand, toilets and washrooms smaller than 4m2 
and without loose fire load need not be equipped with fire detectors. 
 
When the system cannot be repaired and returned to full operation, the following precautions 
should be implemented:  
 Notify the Fire Department of the system status.  
 Have a person remain at the premises until the system is fully operable. 
 Watchman shall make inspection rounds of all areas of the building every half hour, 24 
hours per day.  
MARK CONFIDENTIAL IF TO BE SENT OUTSIDE

SITE EMERGENCY RESPONSE PLAN CM – S


Doc Number : Author : Rev No : Page No :
CM – S - P LAR 01 29 of 37

Origin Date : Origin Approver : Revision Date : Revision Approver :


PROCEDURE 20th July 2018 ABU - -
UNCONTROLLED COPY IF PRINTED IN HARD COPY

 Watchman shall remain on the property between rounds. 
 

 
 

18. Evacuation arrangements  
 Threatening event 
If initial fire or accident seems to be threatening, the power plant building must be evacuated. 
Normally evacuation will be done by using emergency exits. 
 
 Leaving the building 
Every worker must know all emergency exit routes well. Workers should be able to leave building 
fast, also in exceptional cases like during electrical failure. 
 
 Behavior of workers 
Calm and purposeful behaviour prevents panic. 
 
 Evacuation of workers 
After evacuation workers must gather at the assembly point, unless security chief, his deputy or 
local fire fighters order otherwise. Security chief must check that no person has remained in the 
building. 
MARK CONFIDENTIAL IF TO BE SENT OUTSIDE

SITE EMERGENCY RESPONSE PLAN CM – S


Doc Number : Author : Rev No : Page No :
CM – S - P LAR 01 30 of 37

Origin Date : Origin Approver : Revision Date : Revision Approver :


PROCEDURE 20th July 2018 ABU - -
UNCONTROLLED COPY IF PRINTED IN HARD COPY

19. First aid 
19.1 First aid equipment and stretchers 
No  Items  Qty 
1  Sterile Gauze (Kasa steril terbungkus)  20 
2  Adhesive Bandages 5cm (Perban)  2 
3  Adhesive Bandages 10cm (Perban)  2 
4  Adhesive Tape 1,25cm (Plester)   2 
5  Adhesive Tape (Plester Cepat)  10 
6  Cotton Wool 25gram (Kapas)  1 
7  Triangular Bandage (Kain segitiga/mittela)  2 
8  Scissor (Gunting)  1 
9  Safety Pins (Peniti)  12 
10  Pair of Impervious Disposable Gloves (Sarung tangan sekali pakai)  2 
11  Mask (Masker)  1 
12  Tweezers (Pinset)  1 
13  Flashlight (Lampu senter)  1 
14  Eye wash (Gelas untuk cuci mata)  1 
15  Plastic bag that can be sealed (Kantong plastik bersih)  1 
16  Aquades (100 ml lar.Saline)   1 
MARK CONFIDENTIAL IF TO BE SENT OUTSIDE

SITE EMERGENCY RESPONSE PLAN CM – S


Doc Number : Author : Rev No : Page No :
CM – S - P LAR 01 31 of 37

Origin Date : Origin Approver : Revision Date : Revision Approver :


PROCEDURE 20th July 2018 ABU - -
UNCONTROLLED COPY IF PRINTED IN HARD COPY

17  Povidone Iodine 60ml (Povidon Iodin)  1 
18  Alcohol 70% (Alkohol)  1 
19  First Aid Guidance Leaflet (Buku panduan P3K di tempat kerja)  1 
20  First Aid Content List (Buku catatan daftar isi kotak)  1 
21  Stretchers    
 

 
19.2 Local Health care services 

Hospital Name  Rumah Sakit St. Anna 
Type of Facility  Public Hospital 
Address  Jl.  Dr.  Moh.  Hatta  No.  65A,  Sanua,  Kendari 
Barat,  Sanua,  Kendari  Bar.,  Kota  Kendari, 
Sulawesi Tenggara 
General Contact Details  (0401) 3123092 
Website: rssantaanna.com 
Open: 24 Hours 
Appropriate use   This  hospital  according  to  government 
standard.  It  is  operated  by  PT.  Citra  Ratna 
Nirmala.  It  capabilities  include  some 
disciplines, emergency care and ambulance, 
ICU  and  MCU  and  specialist  clinics, 
Laboratory. Radiology, etc 
MARK CONFIDENTIAL IF TO BE SENT OUTSIDE

SITE EMERGENCY RESPONSE PLAN CM – S


Doc Number : Author : Rev No : Page No :
CM – S - P LAR 01 32 of 37

Origin Date : Origin Approver : Revision Date : Revision Approver :


PROCEDURE 20th July 2018 ABU - -
UNCONTROLLED COPY IF PRINTED IN HARD COPY

 Location 
The only access from site to the hospital is by road. It can take about an hour to reach 
the hospital. The road access to hospital is quite good but sometimes we find torturous 
and wavy road due to hill and forest area.  
 
The Location of Nearby Hospital 

 
 

 
 
 
20. Crises communication 
Crisis communication takes place when the reputation of an organisation is at stake. Through crisis 
communications  we  aim  to  protect  Wartsila  brand  and  our  standing  within  the  industries  of  our 
operations. 
 
One of the important task in crisis communications is to minimize insecurity by being responsive. In 
all  crisis  situations,  communication  should  always  be  quick,  proactive,  open,  honest,  relevant  and 
consistent as well as strictly based on careful consideration and situation analysis. 
 
MARK CONFIDENTIAL IF TO BE SENT OUTSIDE

SITE EMERGENCY RESPONSE PLAN CM – S


Doc Number : Author : Rev No : Page No :
CM – S - P LAR 01 33 of 37

Origin Date : Origin Approver : Revision Date : Revision Approver :


PROCEDURE 20th July 2018 ABU - -
UNCONTROLLED COPY IF PRINTED IN HARD COPY

Country‐based Local Crisis Management Team is responsible for crisis communications in every site 
in  the  country.  Every  employee  in  every  site  is  responsible  for  reporting  a  potential  crisis  to  their 
supervisors or Local Security Manager. They will inform Local Crisis Management Team and involve 
Global Crisis Management Team if necessary. 

Supervisor/Security 
Local Crisis  Global Crisis 
Employee Manager/Site 
Management Team  Management Team 
Manager

 
When you report a crisis or an incident be prepared to tell: 
 What has happened? 
 Where? 
 When? (Date and Time) 
 Who and what were involved? (People, assets, etc.) 
 How did it/could it happen? 
 Who currently manages the situation? 
 
20.1 Internal crises communication model 
In all matters concerning internal communication please contact: 
Name    : Agung Hary Yudhanto 
Title    : Director HRD  
Wärtsilä office  : Wartsila Indonesia  
Email    : AgungHary.Yudhanto@wartsila.com  
Phone    : +6281320685650 
 
20.2 External crises communication model  
All  external  communication  in  this  matter  is  to  go  through  the  appointed  external 
spokespersons: Wärtsilä is assessing the situation and we should not speculate, only provide 
neutral information 
 
In all matters concerning local [Country] communication please contact: 
Name    : Cahyanul Uswah  
Title    : Director HRD  
Wärtsilä office  : Wartsila Indonesia  
Email    : cahyanul.uswah@wartsila.com  
Phone    : +62811823750 
 
21. Actions taken in the event of emergency 
21.1 Fire or explosion 

Pre Event Activity/Control 
 The particular storage area is identified and highlighted by painted demarcation line for 
maintaining a safe zone from other working areas. 
 Only trained persons are allowed to transport and handle empty or filled Gas cylinders. 
 The sources of ignition are always avoided or controlled in the area by : 
1. Regular check of gas cylinder hose/tubing used, 
2. Ensuring Regular Inspection of protective caps provided on gas cylinders by shop 
Supervisor, 
MARK CONFIDENTIAL IF TO BE SENT OUTSIDE

SITE EMERGENCY RESPONSE PLAN CM – S


Doc Number : Author : Rev No : Page No :
CM – S - P LAR 01 34 of 37

Origin Date : Origin Approver : Revision Date : Revision Approver :


PROCEDURE 20th July 2018 ABU - -
UNCONTROLLED COPY IF PRINTED IN HARD COPY

3. Prohibiting smoking & open flames,  
4. Implementing & complying to work permit system while conducting any job 
involving hot work like welding/cutting, ensuring all precautions of safety.  
5. Ensure proper labeling of all Gas cylinders with warning sign. 
6. Ensure timely check of cylinder pressure. 
7. Make sure that all liquefiable gas cylinders are kept upright position. 
 A provision should be there for storage of empty and filled gas cylinders. 
 Ensure all Gas cylinders are equipped with Flash Back Arresters/NRV/Pressure 
regulators in working condition. 
 Ensure that Gas cylinders avoid direct sun light by safe roofing of storage place. 
 Fire extinguishers (CO2 Type) are provided and are regularly inspected for proper 
functioning during emergency. 
 The Emergency Telephone numbers are displayed on nearby wall and are regularly 
reviewed for changes. 
 Training on Emergency Preparedness is imparted to the concerned employees 
 Regular Mock‐Drills (during day & night time) are conducted and CA/PA & 
recommendation thereon are implemented. 
 Storage is restricted in open areas or very well ventilated. 
 
 
21.2 Chemical spill (liquid, gas or solid)  
 Equipment for oil  
In case of oil leakage, equipment such as suction material, plastic pails and tubs, plastic 
bags, spades, brushes, wooden stoppers, wedges etc. is to be used to stop the oil from 
spreading to a bigger area. When the oil is gathered, pump it to a tank truck. 
 
 Small oil spill 
Small leaks from pipelines or tanks can be stopped by closing valves or using wooden 
stoppers etc. There are risks that leaked oil ignites.  
In case of leaked oil do the following: 
1. Notify the security chief 
2. Remove immediately leaked oil 
3. Cover with foam 
 
 Lube oil spill 
Maintenance of oil tanks and pipes must be done according to producer’s instructions. 
The impounding walls will retain leaking oil from the biggest oil tank +10% (220 m³). If 
drains are not equipped with oil separators, oil leakage must be prevented. In case of 
fire, there is a risk of oil spreading to the drains with fire water. Note that the flash point 
of the lubrication oil is typically about 200 °C so it cannot be ignited by a spark if there 
would be small spillage.  
In case of oil‐leakage do the following: 
1. Close the valves  
2. Make casual dams made of sand 
3. Cover with foam 
4. Pump the oil to a tank truck 
 
 Small Chemical Spill  
1. Notify the security chief   
MARK CONFIDENTIAL IF TO BE SENT OUTSIDE

SITE EMERGENCY RESPONSE PLAN CM – S


Doc Number : Author : Rev No : Page No :
CM – S - P LAR 01 35 of 37

Origin Date : Origin Approver : Revision Date : Revision Approver :


PROCEDURE 20th July 2018 ABU - -
UNCONTROLLED COPY IF PRINTED IN HARD COPY

2. If toxic fumes are present, secure the area (with caution tapes or cones) to prevent 
other personnel from entering   
3. Handel with the spill in accordance with the instructions described in the MSDS 
4. Small spills must be handled in a safe way, while wearing the proper PPE 
5. Review the general spill clean‐up procedures 
 
 Large Chemical Spill  
1. Notify the security chief 
2. Contain the spill with available equipment (e.g., pads, booms, absorbent powder, 
etc.)   
3. Secure the area and alert other site personnel 
4. Do not attempt to clean the spill unless trained to do so. 
5. Attend to injured personnel and call the medical emergency number, if required. 
6. Call a spill cleanup company or the Fire Department (if arrangement has been made) 
to perform a large chemical (e.g., mercury) spill cleanup 
7. Evacuate building as necessary 
Name of Spill Cleanup Company: PT Sultra Alam Perkasa 
Phone Number: Pak Hasrim (+6285242036831) 
 
 Fuel Gas Leakage  
A fuel gas leakage into a building may lead to a gas fire and explosion. Therefore, it is 
important to prevent any leaks by examining regularly and carefully the fuel gas system 
for leakage. This should be done using a leak detection liquid and/or a gas detector. If 
any of the connections in the fuel gas system is opened, new sealing should be used when 
reassembling. 
 
The following safety instructions shall be distributed to all personnel working at the Lean 
burn gas engine power plant, to ensure that proper and safe counter measures are taken 
in case of a fuel gas leak or fire. The instructions should also be posted in a visible place 
in the plant. 
 
In case of fire or gas leak: 
1. Close the main gas valve (or any valve upstream the fire). For main gas shut‐off valve 
location refer to emergency layout. This will stop the fuel gas leak and eventually 
extinguish the gas fire. In case of fire, do NOT close valves on both sides of a pipe 
caught in the fire. This would cause the pressure to rise and eventually the pipe to 
explode.  If  the  fuel  gas  supply  system  contains  a  gas  compressor,  press  the  gas 
compressor emergency button to close down and ventilate the compressor. 
2. Do NOT put out a gas fire with water or fire extinguisher. A gas fire should be put 
out EXCLUSIVELY by shutting off the gas supply. If a gas fire is extinguished by other 
means, a gas explosion may occur when the out flowing gas makes contact with hot 
residues. 
3. Evacuate the affected area. Evacuate people from fire or gas explosion risk areas. 
4. Arrange proper ventilation. Open doors and windows, avoid using electrical switches 
and equipment, do not smoke. Natural gas in high concentration has a slight narcotic 
effect that disappears when breathing fresh air. Carbon monoxide possibly created 
in  a  fire  is  highly  poisonous,  causes  first  dizziness  and  headache  then  quickly 
paralyses,  and  leads  to  death.  If  a  person  is  suspected  to  have  inhaled  carbon 
monoxide, bring him out into fresh air and call for medical attention immediately. 
MARK CONFIDENTIAL IF TO BE SENT OUTSIDE

SITE EMERGENCY RESPONSE PLAN CM – S


Doc Number : Author : Rev No : Page No :
CM – S - P LAR 01 36 of 37

Origin Date : Origin Approver : Revision Date : Revision Approver :


PROCEDURE 20th July 2018 ABU - -
UNCONTROLLED COPY IF PRINTED IN HARD COPY

5. Call local emergency number. Inform authorities of the fire or gas leak so that proper 
measures may be taken. 
 
All Lean burn gas engine power plants provided by Wärtsilä are equipped with suitable 
detection and alarm system for fuel gas leaks and fire. 
 
21.3 Earthquake, storm, flood, etc 

21.3.1 Earthquake  
Stay calm and await instructions from the Emergency Coordinator or the designated 
official: 
 Keep away from overhead fixtures, windows, filing cabinets, and electrical power 
 Assist people with disabilities in finding a safe place. 
 Evacuate  as  instructed  by  the  Emergency  Coordinator  and/or  the  designated 
official 

21.3.2 Flood 
If indoors 
•  Be  ready  to  evacuate  as  directed  by  the  Emergency  Coordinator  and/or  the 
designated official   
•  Follow the recommended primary or secondary evacuation routes 
If outdoors: 
•  Climb to high ground and stay there   
•  Avoid walking or driving through flood water 
 
21.3.3 Hurricane / Strong Wind  
The nature of a hurricane provides for more warning than other natural and 
weather  disasters.  A  hurricane  watch  issued  when  a  hurricane  becomes  a 
threat to a coastal area.  A hurricane warning is issued when hurricane winds 
of 74 mph or higher, or a combination of dangerously high water and rough 
seas, are expected in the area within 24 hours. 
 
Once a hurricane watch has been issued: 
•  Stay calm and await instructions from the Emergency Coordinator or the 
designated official 
Once a hurricane warning has been issued: 
•  Be ready to evacuate as directed by the Emergency Coordinator and/or the 
designated official 
•  Leave areas that might be affected by storm tide or stream flooding. 
During a hurricane: 
•  Remain indoors and consider the following: 
•  Small interior rooms on the lowest floor and without windows 
•  Stay away from outside walls and windows 
 
21.4 Epidemic or pandemic  
Procedure  
 Isolate the victim 
MARK CONFIDENTIAL IF TO BE SENT OUTSIDE

SITE EMERGENCY RESPONSE PLAN CM – S


Doc Number : Author : Rev No : Page No :
CM – S - P LAR 01 37 of 37

Origin Date : Origin Approver : Revision Date : Revision Approver :


PROCEDURE 20th July 2018 ABU - -
UNCONTROLLED COPY IF PRINTED IN HARD COPY

 Call ambulance and bring to the Hospital 
21.5 Civil disturbance, terrorism, sabotage, or workplace violence 
Procedure 
 Keep Calm 
 Hide to safe area,  
 Coordinate with Security and try to call Polsek for immediate back up 
 
21.6 Traffic accident 
Procedure  
 Locate the victim to safe place, call ambulance for immediate help 
 Give first aid treatment 
 Bring the victim to hospital 
 
21.7 Other emergency situations  
21.7.1 Snake‐bite 
A. Pre Event Activity/control:   
 The  regular  housekeeping  is  done  to  keep  things  on  designated  place  and 
cleaning (sweeping) for removal of unwanted materials. 
 Regular grass cutting 
 Provision of tarred or concreted roads to access all the workplaces. 
 Adequate Lighting at the workplace and on the access roads. 
 Safety shoes to operators & staff Safety Gum boots to gardening and security 
men. 
 Provision of torch to the security for patrolling during night time. 
 Maintain a stock of Antidote for snakebite. 
 
22. Training and drills 
22.1 Training for dedicated emergency personnel 
First Aid Training 
 
22.2 Training for all personnel 
Fire Drill and Evacuation simulation 
 
22.3 Periodic emergency drills 
Once a month, PLTMG 50 MW Kendari planned to hold Fire Drill 
 

You might also like