Professional Documents
Culture Documents
A MICRO-PROJECT REPORT ON
2021-2022
SUBMITTED BY
award of
I would like to extend our thanks to all our professors, staff members
and all our friends who extended their co-operation to complete the
project.
Yours Sincerely,
Date: -
DECLARATION
The empirical findings in this project are based on the data collected in
this project is taken from Different sources.
Name Signature
MhadaColony,PachodRoad,ambad
Department Of Civil Engineering
TITLE OF MICRO-PROJECT :( Highway project costs estimating methods used in the planning stage
of project development)
Literature review
1. We have collected The Highway project costs estimating methods used in the
planning stage of project development
2. We take information of H i g h w a y p r o j e c t c o s t s e s t i m a t i n g
methods used in the planning stage of project
d e v e l o p m e n t in Nirali publication.
When estimating costs, this technique relies on the actual cost of previous, similar
projects as the basis for estimating the cost of the current project.
It is most reliable when the previous projects are similar in fact and not just in
appearance, and the project team members preparing the estimates have the
needed expertise.
• Most likely (M): The cost of the activity, based on realistic effort assessment for
the required work and any predicted expenses.
• Optimistic (O): The activity cost based on analysis of the best-case scenario for
the activity.
• Pessimistic (P): The activity cost based on analysis of the worst-case scenario for
the activity.
Depending on the assumed distribution of values within the range of the three
estimates the expected cost, cE, can be calculated using a formula. Two
commonly used formulas are triangular and beta distributions. The formulas are:
Triangular Distribution
E = (O+M+P)/3
Beta Distribution (from a traditional PERT analysis)
E = (O+4M+P)/6
Cost estimates based on three points with an assumed distribution provide an
expected cost and clarify the range of uncertainty around the expected cost.
The accuracy of single-point activity cost estimates may be improved by
considering estimation uncertainty and risk and using three estimates to define
an approximate range for an activity‘s cost:
• Most likely (M): The cost of the activity, based on realistic effort assessment for
the required work and any predicted expenses.
• Optimistic (O): The activity cost based on analysis of the best-case scenario for
the activity.
• Pessimistic (P): The activity cost based on analysis of the worst-case scenario for
the activity.
Depending on the assumed distribution of values within the range of the three
estimates the expected cost, cE, can be calculated using a formula. Two
commonly used formulas are triangular and beta distributions. The formulas are:
Triangular Distribution
E = (O+M+P)/3
Beta Distribution (from a traditional PERT analysis)
E = (O+4M+P)/6
Cost estimates based on three points with an assumed distribution provide an
expected cost and clarify the range of uncertainty around the expected cost.
The accuracy of single-point activity cost estimates may be improved by
considering estimation uncertainty and risk and using three estimates to define
an approximate range for an activity‘s cost:
• Most likely (M): The cost of the activity, based on realistic effort assessment for
the required work and any predicted expenses.
• Optimistic (O): The activity cost based on analysis of the best-case scenario for
the activity.
• Pessimistic (P): The activity cost based on analysis of the worst-case scenario for
the activity.
Depending on the assumed distribution of values within the range of the three
estimates the expected cost, cE, can be calculated using a formula. Two
commonly used formulas are triangular and beta distributions. The formulas are:
Triangular Distribution
E = (O+M+P)/3
Beta Distribution (from a traditional PERT analysis)
E = (O+4M+P)/6
Cost estimates based on three points with an assumed distribution provide an
expected cost and clarify the range of uncertainty around the expected cost.
8) Decision-Making Method
Some decision techniques are unanimity, majority, plurality, points allocation,
and dictatorship. For unanimity, everyone must agree; there is a shared
consensus. A majority or plurality is usually determined by a vote. For a majority,
the decision must be agreed to by more than half the participants.
Purpose of Construction Cost Estimation
Owner’s Purpose of Cost Estimation
-Making investment decision in the conceptual stage.
-Negotiate and finalize the contract at the implementation phase.
-To implement cost control measures.
-Ranking alternatives
-Evaluate economics and financial feasibility
-As a check on more detailed estimates
-We base our estimate on the cost of existing -projects that were built in the
past
-Price-level changes over time
-We need to project costs of future projects
-Many organizations publish construction cost data on regular basis.
2. Cost Indices
Used to update old cost information
Uses of Cost Indices
F = P (1 + i)n
F = future cost
P = present cost
i = predicted rate of cost escalation per period
1) Transport cost
Taxes
2) Labor supply and
3) local productivity
4) Codes and local
inspection
-Construction costs also vary in different regions of the USA.
-ENR and Means
publishes periodically
the indices of local
construction costs in
the major cities.
4. Project Size
Table 4.1 represents highway construction cost indices and inflation trends
based on data received from
MDT. STE calculated yearly inflation trends by evaluating the percent change in
cost index from one year
to the next.
Table 4.1 MDT Reported Highway Construction Cost Indices and STE
Calculated Inflation Rates
The ROCKS database was used for this research. This database contains road
works cost data from 65 developing countries. Among these countries Poland
and Thailand have a relatively large number of projects. For this reason they
were chosen in this study to investigate the relationship between project cost
and other variables such as work activity, terrain type, road parameters etc.
Rcc Models.
REFERENCES:
1. SEARCH IN INTERNET
2. TEACHERS HELP
1. NIRALI PUBLICATION
project development
a) understanding
C)Unity
d) team work
THANK YOU