You are on page 1of 11

A MICRO-PROJECT ON

“PREPARE DETAILED ESTIMATE OF CONSTRUCTION OF


SLABCULVERT ”

Submitted on 2021-2022

This micro-project work submitted in partial fulfilment of


requirement for the Award of diploma in Civil Engineering.

Under The Guidance Of

Miss:- payal barai mam


Lecture
(Dept. of Civil Engineering)

Submitted By:-

Pratik H. Meshram (17)

GOVERNMENT POLYTECHNIC, BRAMHAPURI, [2021-2022]


GOVERNMENT POLYTECHNIC, BRAMHAPURI DIST-
CHANDRAPUR
DEPARMENT OF CIVIL ENGINEERING

This is to certify that the following students of this institute have


carried out this micro-project work on “PREPARE DETAILED ESTIMATE OF CONSTRUCTION
OF SLABCULVERT ” under the guidance of Prof. Prof. Payal barai mam stability in the
Department of civil engineering during the session 2021-2022. This work has been done
in the partial fulfilment of the award for in civil engineering from Maharashtra State
Board of Technical Education, Mumbai.

SUBMITTED BY:-

Pratik H. Meshram (17)

Project Guide: Head of Department

Prof. Payal barai mam Dr. A. Pawde sir

GOVERNMENT POLYTECHNIC, BRAMHAPURI, [2020-2021]


GOVERNMENT POLYTECHNIC, BRAMHAPURI DIST-
CHANDRAPUR

We are the students of final year of Department of Civil Engineering,


humbly completed this Micro-project work for time to time as described in this
report by our own skill and study between the period from 2021-2022.
As per instruction and guidance Prof. Payal barai mam and following students
were associated with us for this work. However, quantum of our contribution has been
approved by the guide.

SUBMITTED BY

Pratik H. Meshram (17)

DATE: / / 2020 PLACE :BRAMHAPURI

GOVERNMENT POLYTECHNIC, BRAMHAPURI, [2021-2022]


PART-A

“PREPARE DETAILED ESTIMATE OF CONSTRUCTION OF SLABCULVERT ”

1. Aim of micro project:


1) To collect the information about detailed estimate.
2) To know the analysis of detailed estimate
3) To know the detailed estimate.

2. Course Outcomes:
■ prepare detailed estimate of a civil engineering works.

3. Proposed Methodology:

1) Search about information


2) Discuss the collected information and photos with the project guide and
group members.
3) Edit the collected information as per guide by project guide.
4) Study and present the collected information.
5) Prepare the hard copy of collected information.
6) Submit the prepare project to the department.

ACTION PLAN

Sr.N Details of activity Plans Plan Name &


o start finish Roll no.
date date
1. Discussion about // //
topic
2. Subtopic division // //
3. Collection of // // Pratik H
information Meshram
4. Arrange the // // (17)
information
5. Report showed to // //
project Guide
6. Report submission
date

RESOURCES REQUIRED

Sr. No. Materials Specifications Qty


1. Camera - 01
2. Notepad - 01

3. Books DSR Textbook 01


4. Internet Wikipedia -
PART :-B
“PREPARE REPORT ON DETAILED ESTIMATE AND COLLECT
IMFORMATION ABOUT IT”
Rational :
A detailed estimate is prepared after its complete set of
drawings are ready. The quantities of various items of work are worked out
from such drawings and are multiplied by the present rates of items of
works to arrive at the estimated cost of the work.
In Government Organisation, a detailed estimate is required for
obtaining technical sanction from the competent authorities for the proposed work. A
detailed estimate is also required for the preparation of contract (agreement)
document. The detailed estimates serve as a guide during the execution of the work.

Aim of Micro-project
1. To collect the information about detailed estimate.
2. To know the analysis of detailed estimate.
3. To know the detailed estimate.

Literature Review
of the firms have tried to achieve the maximum
Most
sufficiently of cost estimate in bedding stage as well as the success
detailed estimate avoid the firms the failure in the market. Furthermore, the
knowledge of construction cost estimate support the detailed cost
estimate, because this knowledge were ignored and not understood by
most estimators in the field of construction industry in Yemen. Cost is one
of the three main challenges for the construction manager, where the
success of a project is according to the criteria of cost with budget,
schedule on time, and quality .
Resources Required:-
S. Name Specifications Qty. Remark
No. of
Resour
ce
1. 1 Reading

2. Internet Give As per To get more


sufficient require information about
information d Project.
3. Digital Camera High Req. To take photographs
resolution 13
mega pixels..

Actual Procedure Followed:

1. The given collect the information by Google.


2. Sub-topics are distributed to the me
3. The information is collected by Google
4. The information is arranged by Google

INFORMATION ABOUT MICRO-PROJECT:-

Slab culvert, also known as bridge culverts, can be three-sided, or


simply a deck slab embedded in the soil on either side, providing a bridge over the
distance. Usually, a series of slabs are laid to form a bridge-like structure, and a
pavement surface is placed on top to serve as the road.
The slab culverts are constructed for a span of maximum 2.5 m in
width. To construct the slab culvert, a stone or R.C.C slab is directly placed over
the simply supported beam on piers or aboutments.The culvert, having its
superstructure consisting of RCC slab which carries the bridge floor, is known as
slab culvert. In this type of culvert, the RCC slab of suitable thickness is provided
as simply supported over abutments and piers which are constructed of any
suitable type of masonry.
■ Following are the types of culverts generally used in construction:
● Pipe Culvert (Single or Multiple) Pipe culverts are widely used culverts and rounded in shape.
● Pipe Arch Culvert (Single or Multiple)
● Box Culvert (Single or Multiple)
● Arch Culvert.
● Bridge Culvert.
■ PIPE CULVERT:- When a pipe is placed in an excavated trench to move water away, it is known as
pipe culvert. It is the most commonly used drainage feature ... Pipe culverts are found in different
shapes such as circular, elliptical, pipe arch etc. Generally, the shape depends on site conditions
and constraints.

■ PIPE ARCH CULVERT:-Pipe arch culverts means nothing but they looks like half circle shaped
culverts. Pipe arch culverts are suitable for larger water flows but the flow should be stable. Because
of arch shape fishes or sewage in the drainage easily carried to the outlet without stocking at the inlet
or bottom of channel

■ BOX CULVERT:- Box Culverts are used for drainage purposes. They are also used to make
tunnels and used for storage as well as material handling. Some culverts act as bridges. They easily
accommodate both pedestrian and vehicular traffic.
■ ARCH CULVERT:-It defines an arch culvert a: 'The most common form of culvert construction for
river, road, canal, and railway culverts until the mid-19th century. Can be arched, or egg-shaped. For
smaller widths, these may be masonry/brick channel side walls capped with a simply-supported slab
roof.

8) Skill Developed/ Learning outcome of this Micro- project:

• Communication skill
• Presentation skill
• Preparation of report

9) Application Of This Micro-Project: It is used as a mould for a structure in which


fresh concrete is poured only to harden subsequently.
Slabculvert construction good quality of materials.
Micro Project Evolution Sheet
Name of student:Pratik Hemant Meshram Enrollment No. :

1915970025 Name of program: - Civil Engineering Semester: -

5th Sem Course title: - Estimating and Costing Code: -

22503

Title of Micro-Project: - Prepare a detailed estimate of


construction of slab culvart

Course Outcomes Achieved:-


Prepare detailed estimate of a civil engineering works .

(A) Process and Product Assessment (Convert above total


marks out of 6 marks)

Sr. Characteristics Poor Averag Good Excellen Sub


No. to be assessed (mark e (mark t (marks Tot
s 1-3) (marks s 6-8) 9- al
4-5 ) 10)
1. Relevance to
the course

2. Literature
review/informati
on collection

3. Completion of
the target as
per project
proposal
4 Analysis of data
and
representation

5 Quality of
prototype/mod
el
6. Report
preparation

(B)Individual presentation / via (concept above total marks out of 4


marks)

7. Presentation

8. Viva

(A) (B) Total


Process Individual
and presentati marks 10
product on
Assessmen /viva (4 marks)
t (6 mark)

Name and designation of the teacher: Mrs. Payal Barai mam

Dated signature: