Professional Documents
Culture Documents
∑ Et
(1+k)t
Example
Possible net investment Probability
(4000) 0.3
(5000) 0.4
(6000) 0.3
1
________________________________________________________________________
Intermediate Finance Capital Budgeting under risk
City University College Department of Accounting & Finance
Et
Year 0 (5000)
Year 1 4000
Year 2 4400
If the risk free rate of return is 8 percent, the NPV statistics for this project
are calculated as follows. The expected NPV is computed as follows:
= 2,076
Project
X Project Y
Br.
Initial investment 10,000 Br.10,000
Annual Cash inflows
Outcome
Pessimistic 1500 0
Most likely 2000 2000
Optimistic 2500 4000
2
________________________________________________________________________
Intermediate Finance Capital Budgeting under risk
City University College Department of Accounting & Finance
∑ (et)xCFt
(1+Rf)
The equation shows that the project is adjusted for risk by first converting
the expected cash inflows to certain amounts, (et X CFt) and discounting
the cash inflows at Rf.
Example ABC company wishes to consider risk in the analysis of two
projects A and B. the cost of capital is 10% when considering risk. The
project cash flows are as follows.
Year Project A Project B
Initial Br. 42,000 Br. 45,000
investment
Cash flows
1 14,000 28,000
2 14,000 12,000
3 14,000 10,000
4 14,000 10,000
5 14,000 10,000
By ignoring risk differences and using NPV at 10% cost of capital, project A
is preferred over project B since its NPV of br. 11,074 is greater than B’s NPV
of birr 10,914. Assume however, that on further analysis the firm found that
project A is actually more risky than project B, to consider the deferring
risks; the firm estimated the certainty equivalent factors for each project’s
cash inflows for each year. Certainty equivalent for project A and B are as
follows:
Year Project A Project B
1 0.90 1.00
2 0.90 0.90
3 0.80 0.90
4 0.70 0.80
5 0.60 0.70
4
________________________________________________________________________
Intermediate Finance Capital Budgeting under risk
City University College Department of Accounting & Finance
be quite clear, the only difficulty lies in the need to make subjective
estimates of the certainty equivalent factors.
6
________________________________________________________________________
Intermediate Finance Capital Budgeting under risk
City University College Department of Accounting & Finance
7
________________________________________________________________________
Intermediate Finance Capital Budgeting under risk
City University College Department of Accounting & Finance
In Keymer Farm’s case, the cash flows are expressed in terms of the actual
dollars that will be received or paid at the relevant dates. Therefore, we
should discount them using the money rate of return.
TIME CASH FLOW DISOCUNT FACTOR PV
$ 40% $
0 (150,000) 1.000 (100,000)
1 90,000 0.714 64,260
2 80,000 0.510 40,800
3 70,000 0.364 25,480
30,540
The project has a positive net present value of $30,540, so Keymer Farm
should go ahead with the project. The future cash flows can be re-
expressed in terms of the value of the dollar at time 0 as follows, given
inflation at 30% a year.
8
________________________________________________________________________
Intermediate Finance Capital Budgeting under risk
City University College Department of Accounting & Finance
The case flows expressed in terms of the value of the dollar at time 0 can
now be discounted using the real value of 7.69%.
Inflation may be general, that is, affecting prices of all kids, or specific to
particular prices. Generalized inflation has the following effects.
a) Inflation will mean higher costs and higher selling prices. It is difficult
to predict the effect of higher selling prices on demand. A
company that raises its prices by 30%, because the general rate of
inflation is 30%, might suffer a serious fall in demand.
b) Inflation, as it affects financing needs, is also going to affect
gearing, and so the cost of capital.
9
________________________________________________________________________
Intermediate Finance Capital Budgeting under risk
City University College Department of Accounting & Finance
c) Since fixed assets and stocks will increase in money value, the same
quantities of assets must be financed by increasing amounts of
capital. If the future rate of inflation can be predicted with some
degree of accuracy, management can work out how much extra
finance the company will need and take steps to obtain it, e.g. by
increasing retention of earnings, or borrowing.
However, if the future rate of inflation cannot be predicted with a certain
amount of accuracy, then management should estimate what it will be
and make plans to obtain the extra finance accordingly. Provisions should
also be made to have access to contingency fund’s should the rate of
inflation exceed expectations, e.g a higher bank overdraft facility might
be arranged should the need arise.
Many different proposals have been made for accounting for inflation.
Two systems known as “Current purchasing power” (CPP) and “Current
cost accounting” (CCA) have been suggested.
CPP is a system of accounting which makes adjustments to income and
capital values to allow for the general rate of price inflation.
CCA is a system which takes account of specific price inflation 9i.e.
changes in the prices of specific assets or groups of assets), but not of
general price inflation. It involves adjusting accounts to reflect the current
values of assets owned and used.
At present, there is very little measure of agreement as to the best
approach to the problem of “accounting for inflation’. Both these
approaches are still being debated by the accountancy bodies
10
________________________________________________________________________
Intermediate Finance Capital Budgeting under risk