At HVAC plant room call point should be added. Not required as per standard practices
7
At HT room / LT room /generator room is not covered
8 with any device. Noted & Revised (find enclosed drawing & BOQ)
9 At Fresh area roof Beam detector is missing. It will be added (find enclosed drawing & BOQ)
GR ramp/delivery doc devices are missing. Not required as it is an open area so smoke cannot be densed
or harzardous for fire prospoects.if there is any storage then
10 we may add but not recommended from our side.
LED displayed to import shop /PROMO area smoke
devices are not installed its high zone area. Devices are installed please review the design drawings or
11 specify the specific area
Cage for tegmental / DS doc all area devices are As this area is not accessable to us during site visit, if it is
missing. enclosed then detector must be required. Now we add the
12 devices (find enclosed drawing & BOQ)
13 The call point is not available at GR ramp area. Not required as per standard practices
14 All AHU areas call points missing. It will be added
15 The number of detailed devices is not mentioned. All mentioned in BOQ.
The consultant recommended a single end beam The recommendation is totally as per the standard compliance
detector which should be replaced with double end so kindly follow that. (If client may allow the double ended to
beam detector. few vendors due to their limitation in single ended.
16