You are on page 1of 30

1 CHAPTER THREE

DISCUSSION, RECOMMENDATIONS AND CONCLUSION


1.1 Introduction
This chapter discusses about lessons learnt, comparison between site and class work and
challenges in the discussion, the recommendations to the university administration, the
organization and the trainee then finally the conclusion.
1.2 Discussion
1.2.1 Lessons learnt
1. Better interpretation of plans and drawings both architectural and structural.
2. Developing of rates needed for the different project activities.
3. Taking off using excel software and preparation of a bills of quantities.
4. Taking off using Plan swift software.
5. Preparation of valuations and interim certificates.
6. Basic office personnel relations and improved communication skills.

1.2.2 Comparison between site and class work


1. The trainee was able to analyze and compare what is taught in lecture rooms to what
actually goes on at the organization for example in class, we only consider the wall
plate to be on the external walls yet during the training, the wall plate is also on the
internal loading bearing walls because if it’s not there, it will lead to sagging of the
roof.
2. Calculating quantities for various elements in the construction process for example
the substructure, superstructure. The trainee was able to understand better what was
taught in class with a simpler method acquired during the training.
3. Quick measurement through the use of Plan Swift construction estimating takeoff
software. It calculates everything you need to get an estimate together, labor, square
metres, perimeters, volumes of simple or complex areas, beams among others. With
plan swift, you can easily take off as soon as you hear about the job.
4. At the organization, the trainee was able to physically make sense of certain
descriptions when the trainees visited the site in Kawempe for example descriptions
for excavation and disposal of water.

1
1.2.3 Challenges
Throughout the trainee’s training at Bikandema and Partners, the trainee faced a few
challenges and these include;
1. Many skills required in office especially with the billing process were those barely
taught in class. This created a great challenge in coping up with new skills barely
taught in class.
2. The outbreak of Ebola disease in the country that threatened most of citizens in the
country. This too, brought about fear of physical interaction amongst our trainers and
the fellow colleagues doing the training.
3. Limited time of interaction and career guidance from our supervisors. This was
because of the busy schedule of their works during the training period that minimized
the time of one-on-one interaction between the trainers and the trainees.

1.3 Conclusion
The training has been a great exposure to the quantity surveying field in specificity,
measurement, contract documentation, preparation of valuations and certificates among
others.
It has helped the trainee as a student to relate the general theory taught at the university to the
real work done in the field. Through this, the trainee acquired a couple of skills for example
taking off with excel and plan swift, time management, listening and interpersonal
communication skills, organizational skills, to mention but a few.
1.4 Recommendation
Internship training is implemented through partnership among three key stakeholders the
organization, the University and the students. All the three partners are responsible for
effectively, efficiently and sustainably implementing the internship program. Commitment to
this partnership rests on mutual benefits for all the key partners involved. The
recommendations to strengthen the internship program are categorized under the three stake
holders; the university administration, organization and the trainee.
1.4.1 The university administration
1. It should secure internship places with recognized companies for students to ease
monitoring them and also reduce the difficulty a student finds when looking for a
placement.
2. It should integrate internship program into the university curricular and have it
reviewed periodically for perfect improvements of the program.

2
3. It should also develop a more reliable monitoring and evaluation criteria for the
internship program including the code of conduct for students and staff involved both
at the university and at the field other than relying on logbooks.
4. The university should identify organizations that offer valuable learning experiences
to the students other than sending students with letters to look for sites for their
training and they resort to places that they are familiar with.
5. The university should source for funding from development partners and internally to
support implementation of the internship program. This mainly benefits the student
who may lack sufficient funds to go through the internship program.
6. It should also create platforms and mechanisms for sharing experience arising out the
internship program by the stakeholders for better improvement of the internship
program for example by issuing official communication to the organizations so that
they prepare themselves for the trainees.

1.4.2 The organization


1. It should provide feedback to the university on the experience of the student during
the internship period in order to make necessary improvements.
2. It should engage in a mutual learning exercise together with the students and staff of
Makerere University.
3. It should provide students undergoing internship program with a wide range of
experiences that go beyond technical skills.

3
REFERENCES

Brook, M. (2016). Estimating and Tendering for Construction Work (5 ed.). London:
Routledge.
Bukaliya, R. (2012, January). The Potential Benefits and Challenges of Internship
programmes in an ODL institution; A case for the Zimbabwe Open University.
International Journal on New Trends in Education and Their Implications, 3(1), 118-
133.
Carr, R. (1989). Cost-estimating principles. Journal of Construction Engineering and
Management, 4(115), 545-551.
Knouse, S. B. (2008). Benefits of business college internship. Journal of Employment
Counseling, 45(2), 61-66.
McGraw-Hill. (1992). Professional Construction Management (3 ed.). Newyork, USA:
Technical Publishing Services Company.
Mubarak, A. M. (2019). Changes in the unit price of work for reinforced concrete
construction based on building sites. The 8th Annual International Conference 2018
on Science and Engineering. 523, pp. 12-14. IOP Publishing Ltd.
Nicholson, D. (2000). Floor, Wall, and Ceiling Coverings. (1, Ed.) Montreal, USA:
RICS. (2012). NRM 2: Detailed measurement for building works. (1st, Ed.) Surveyor Court,
Westwood Business Park, UK: Royal Institution of Chartered Surveyors.
RICS. (2012). NRM 2: Detailed measurement for building works. (1st, Ed.) Surveyor court,
UK: Royal Institute of Chartered Surveyors.
RICS. (2012). RICS new rules of measurement NRM 1: Order of Cost estimating and cost
planning for capital building works. (2, Ed.) Surveyor Court, UK: Royal Institution of
Chartered Surveyors.

4
APPENDICES
Appendix 1: Rate Analysis for walling
  Description 200mm thick clay brick wall bedded jointed in cement sand
mortar mix 1:3 complete with hoop iron in horizontal alternate
  BRICK WALLING courses; in header bond.
Item Details       Analysis  
S/ Materia T/port Unit
N Description Qty Unit Rate l Labour & Plant Rate

1.0 Cost of materials              


  For 1.0m of Brick wall
2
             
Bag 35,00
  Cement 0.314 s 0 10,990 -    
45,00
  Sand 0.047 Ton 0 2,115      

  Bricks 54 No 300 16,200      

          29,305 - 2,931  

Include
  Allow for wastage (10%)       d      
               

  Materials cost for 1.0m2 of Brick wall       29,305   2,931 32,236


                 

2.0 Labour              
  For laying 1.0m2 of brick wall              
 
        - - -  
 
        - - -  

  Labour Cost for 1.0m2 of Brick wall 25%       -   8,059


                 
Unit Rate for supply and laying 1.0m2
3.0 of Brick wall             40,294
                 
Net Unit Rate for supply and laying
4.0 1m2 of brick wall             40,294
                 
Add: Mark-up for Contractor's P & 40,29
5.0 Overheads 10%   4       4,029

                44,324

  Rounding – Off             1
Gross Unit Rate for supply and laying
6.0 1.0m2 of Brick wall 1 m2         44,325

5
Appendix 2: Rate analysis for concrete
  Description
GRADE 25 -
  CONCRETE GRADE 25 - CONCRETE
Item Details       Analysis  
T/
port
&
S/ Qt Un Mater Lab Plan Unit
N Description y it Rate ial our t Rate

1.0 Cost of materials              


For 1.0m3 of
  Concrete              

5.7 Ba 35,00 201,6


  Cement 6 gs 0 00 -    

0.4 To 45,00 20,25


  Sand 5 n 0 0      

0.9 To 85,00 81,60


  Aggregate 6 n 0 0      

303,4 30,3
          50 - 45  
Allow for wastage Inclu
  (10%)       ded      
               

Materials cost for 303,4 30,3 333,7


  1.0m3 of Concrete       50   45 95
                 

2.0 Labour              
  For laying 1.0m3 of
concrete              
 
        - - -  
 
        - - -  

Labour Cost for 25 83,44


  1.0m3 of Concrete %       -   9
                 
Unit Rate for
supply and laying 417,2
3.0 1.0m3 of Concrete             44
                 
Net Unit Rate for
supply and laying 417,2
4.0 1m3 of concrete             44
                 
Add: Mark-up for 10   417,2      

6
Contractor's P & 41,72
5.0 Overheads % 44 4

458,9
                68

  Rounding – Off             2
Gross Unit Rate
for supply and
laying 1.0m3 of 458,9
6.0 Concrete 1 m3         70

  Description
  STEEL REINFORCEMENT STEEL REINFORCEMENT
Item Details       Analysis  
T/port Unit
S/N Description Qty Unit Rate Material Labour & Plant Rate

1.0 Cost of materials              


  For 1Kg of Steel              

  T16 bar 1 Kg 4,747 4,747 -    

  Sundry Items say; binding wire 5% Item   237      

          4,984 - 548  

  Allow for wastage (10%) - off cuts       498      


               

  Materials cost for 1Kg of steel bar       5,483   548 6,031


                 

2.0 Labour              
  For laying 1Kg of steel bar              
 
        - - -  
 
        - - -  

  Labour Cost for 1Kg of steel bar 5%       -   603


                 
Unit Rate for supply and laying 1Kg of
3.0 steel bar             6,634
                 
Net Unit Rate for supply and laying 1Kg
4.0 of steel bar             6,634
                 
Add: Mark-up for Contractor's P &
5.0 Overheads 10%   6,634       663

                7,297

  Rounding – Off             3

7
Gross Unit Rate for supply and laying
6.0 1Kg of steel bar 1 Kg         7,300
Appendix 3: Rate analysis for steel

  Description
  FORWORK SAWN FORMWORK
Item Details       Analysis  
Materia T/port Unit
S/N Description Qty Unit Rate l Labour & Plant Rate

1.0 Cost of materials              


  For 1.0m2 of Formwork              

  Kirundu boards 1.11 No 9,000 9,990 -    

  Sundry Items 5% Item   500      

          10,490 - 1,154  

  Allow for wastage (10%)       1,049      


               

  Materials cost for 1.0m2 of Formwork       11,538   1,154 12,692


                 

2.0 Labour              
  For laying 1.0m2 of Formwork              
 
        - - -  
 
        - - -  

  Labour Cost for 1.0m2 of Formwork 25%       -   3,173


                 
Unit Rate for supply and laying 1.0m2
3.0 of Formwork             15,865
                 
Net Unit Rate for supply and laying
4.0 1m2 of Formwork             15,865
                 
Add: Mark-up for Contractor's P &
5.0 Overheads 10%   15,865       1,587

                17,452

  Rounding – Off             (2)

8
Gross Unit Rate for supply and laying
6.0 1.0m2 of Formwork 1 m2         17,450
Appendix 4: Rate analysis for formwork

Appendix 5: Abstract for the roof


ITE UNI
M DESCRIPTION T TIMESING/DIMENSION SQUARING
      A B C D    
           
           
A (50X100) mm treated soft wood wall plate in m  
one piece over 52m not exceeding 53m with    
scarfed joints.
  Add:   1 1 1 53 53 53
  Deduct:   1 1 1 0 0 0
          53
           
           
B (50x100) mm soft wood treated ridge beam m      
  Add:   1 1 1 10 10 10
  Deduct:   1 1 1 0 0 0
          10
           
           
C (225x25) mm softwood treated Berge board m      
  Add:   1 1 1 57.5 57.5 58
  Deduct:   1 1 1 0 0 0
          58
           
D (50x100) mm softwood treated purlins m      
  Add:   1 1 1 90.6 90.6 91
  Deduct:   1 1 1 0 0 0
          91
           
E (225x25) mm wrought fascial board m      
  Add:   1 1 1 36.8 36.8 37
  Deduct:   1 1 1 0 0 0
          37

9
           
F (50x100) mm principal/ half truss softwood m  
   
treated tie beam
40.0
40.05 40
  Add:   1 1 1 5
  Deduct:   1 1 1 0 0 0
          40
           
G (50x100) mm softwood treated rafter m      
           
89.4
89.48 89
  Add:   1 1 1 8
  Deduct:   1 1 1 0 0 0
          89
           
H (50x100) mm softwood treated struts and ties m      
31.4
2 31
Girl Add:   1 1 1 9
  Deduct:   1 1 1 0 0 0
          31
           
B 26mm gauge Aluzinc IT4 troughed roofing m2  
manufactured by …... fixed with galvanised    
nails
           
81.8
81.88 82
  Add:   1 1 1 8
  Deduct:   1 1 1 0 0 0
          82
           
J …. wide diameter purpose made hip Aluzinc m  
   
IT4 troughed roofing
           
12.3
12.31 12
  Add:   1 1 1 1
  Deduct:   1 1 1 0 0 0
          12
           
           
K Ridge caping IT4 troughed roofing m      
           
  Add:   1 1 1 10 10 10
  Deduct:   1 1 1 0 0 0
          10
           
L Raking cutting 26-gauge Aluzinc IT4 troughed m  
   
roofing at hips
  Add   1 1 1 24.6 24.61 25

10
1
  Deduct:   1 1 1 0 0 0
          75
           
M 80mm diameter uPVC down pipes with m  
soldered connections in running length fixed
with mild steel holder bats at … mm centres to    
backgrounds
           
  Add   1 1 3 3 9 9
  Deduct:   1 1 1 0 0 0
          9
           
           
N Extra over pipe for shoes No.      
           
  Add   1 1 1 3 3 3
  Deduct:   1 1 1 0 0 0
          3
           
O Extra over pipe for bends m      
           
  Add   1 1 1 3 3 3
  Deduct:   1 1 1 0 0 0
          3
           
P 112mm H/R uPVC gutter m      
           
Add   40.6
40.68 41
  1 1 1 8
Deduct:   0 0
  1 1 1 0
          41
           
Q Extra over gutter for bends No.      
           
  Add   1 1 1 1 1 1
Deduct:   0 0
  1 1 1 0
          1
           
R Extra over mild steel gutter for outlet to suit No.  
80mm diameter down pipe    

           
  Add   1 1 1 3 3 3
Deduct:   0 0
  1 1 1 0

11
          3
           
S Extra over gutter for corners No.      
           
  Add   1 1 1 5 5 5
Deduct:   0 0
  1 1 1 0
          5
           
T Extra over gutter outlet No.      
           
  Add   1 1 1 1 1 1
Deduct:   0 0
  1 1 1 0
          1
           

12
Appendix 6: Preliminaries
Contract Valuation
Item Description Amount Initial Running Running Cost Final Cost Amount Accum.
(USHS) Cost Cost Accum Initial+Running Cost

RENOVATION OF THE MEETING CHAMBERS OF


BUNYORO - KITARA KINGDOM - HOIMA DISTRICT.

BILL NO. 1

PRELIMINARIES

1/1A DEFINITIONS AND ABBREVIATIONS


1/2E COST OF SECURITIES AND INSURANCE
MATERIALS, GOODS AND WORKMANSHIP TO
1/3A CONFORM TO DESCRIPTION, TESTING, INSPECTION
AND SAMPLES 3,000,000 900,000 1,800,000 1,350,000 300,000 2,250,000
STATUTORY OBLIGATIONS, NOTICES,
1/3B FEES/CHARGES, LOCAL REGULATIONS AND BYE-
LAWS
1/3C SITE SUPERVISION, ATTENDANCE AND MEETINGS

1/4A TRANSPORT TO AND FROM SITES


1/4B WORKING HOURS AND FAIR WAGES
SECURITY OF THE WORKS, EMPLOYEES AND THE
1/4C
PUBLIC
1/4D PROGRAMME OF WORKS

1/5A OVERTIME WORK 1,500,000 450,000 900,000 675,000 150,000 1,125,000


1/5B WATER FOR THE WORKS
1/5C LIGHTING AND ELECTRICITY FOR THE WORKS
1/5D TEMPORARY WORKS AND BUILDINGS 500,000 150,000 300,000 225,000 50,000 375,000

1/6B COMMUNICATION
1/6C HEALTH, SAFETY AND SANITATION

1/7A SIGN BOARDS


1/7B SITE RECORDS
1/7C OPERATING AND MAINTENANCE MANNUAL
1/7D TRAINING
1/7E TAXES

TOTAL CARRIED TO GENERAL SUMMARY 5,000,000 2,250,000 500,000 3,750,000

13
Appendix 7: Abstract for the substructure of the Proposed Health Centre
Development
                 
   
  PROPOSED HEALTHY CENTRE DEVELOPMENT  
   
  LABARATORY, DISPENSARY AND ANTENATAL  
   
   
  SUB STRUCTURE  
   
ITE UNI TIMESING/
M DESCRIPTION T DIMENSION SQUARING
      A B C D    
           
           
A Clear site of bushes, shrubs m2  
undergrowth and the like    
including grabbing their roots
  Add:   1 1 1 392.7 392.7 393
  Deduct:   1 1 1 0 0 0
          393
           
           
B Excavate vegetable soil m2  
average 150mm thick starting
from existing ground level to
   
be preserved in temporary
heaps approximately 300m
from site.
  Add:   1 1 1 392.7 392.7 393
  Deduct:   1 1 1 0 0 0
          393
           
           
C Excavate to reduce levels m3  
starting from the stripped
level average 350mm thick to
   
be preserved in temporary
heaps approximately 300m
from site
137.4
137
  Add:   1 1 1 137.44 4

14
  Deduct:   1 1 1 0 0 0
          137
           
D Excavate for trenches not m3  
exceeding 1.5m deep starting
from existing ground level    
and backfilling of excavated
materials.
  Add:   1 1 1 79.65 79.65 80
      1 1 1 72.93 72.93 73
          153
  Deduct:   1 1 1 0 0 0
          153
           
E Anti-termite treatment to the m2  
sides and bottoms of trench
and pit excavations, tops of
hardcore and tops of    
foundation walls at a rate of
3 litres / m2 or specified by
the manufacturer.
729.8
730
  Add:   1 1 1 729.81 1
  Deduct:   1 1 1 0 0 0
          730
           
F Keep all excavation free Item  
from water except spring or    
running water.
  Add:   1 1 1 1 1 1
  Deduct:   1 1 1 0 0 0
          1
           
G Planking and strutting to Item  
uphold the vertical sides of    
excavation.
           
  Add:   1 1 1 1 1 1
  Deduct:   1 1 1 0 0 0
          1
           
H 50mm thick insitu plain m3  
concrete mix (1:4:8) in    
blinding
  Add:   1 1 1 53.1 53.1 53
  Deduct:   1 1 1 0 0 0

15
          53
           
I In situ plain concrete mix m3  
grade 20 1:2:4 in strip    
footing and concrete bed
           
  Add:   1 1 1 10.62 10.62 11
      1 1 1 7.29 7.29 7
299.3
299
      1 1 1 299.38 8
  Deduct:   1 1 1 0 0 0
          317
           
J 200mm thick solid concrete m2  
block walling to BS…….
bedded and jointed in cement    
sand mortar mix ratio (1:4) in
a stretcher bond.
           
           
  Add:   1 1 1 35.4 35.4 35
  Deduct:   1 1 1 0 0 0
          35
           
           
K 150mm thick solid concrete m2  
block walling to BS…….
bedded and jointed in cement    
sand mortar mix ratio (1:4) in
a stretcher bond.
           
  Add:   1 1 1 43.21 43.21 43
  Deduct:   1 1 1 0 0 0
          43
           
L Murrum filling m3      
  Add   1 1 1 38.94 38.94 39
      1 1 1 35.65 35.65 36
  Deduct:   1 1 1 0 0 0
          75
           
M Bitumen hessian base dump m  
proof course to BS 743 type    
A
           
  Add   1 1 1 88.5 88.5 89

16
    104.8
105
  1 1 1 104.87 7
  Deduct:   1 1 1 0 0 0
          193
           
           
N Backfilling in making up m3  
levels; depositing and    
compacting in layers.
           
  Add   1 1 1 79.65 79.65 80
      1 1 1 72.93 72.93 73
  Deduct:   1 1 1 0 0 0
          153
           
O load and cart away surplus m3  
   
excavated materials from site
           
  Add   1 1 1 5.09 5.09 5
      1 1 1 17.91 17.91 18
      1 1 1 78.61 78.61 79
  Deduct:   1 1 1 0 0 0
          102
           
P 200mm thick hardcore bed in m2  
natural stone hand packed
   
under floors and well
compacted
           
Add   265.4
265
  1 1 1 265.47 7
  Deduct:   1 1 1 0 0 0
          265
           
Q 50mm thick sand blinding m2  
   
laid onto surfaces of hardcore
           
  Add   1 1 1 13.27 13.27 13
  Deduct:   1 1 1 0 0 0
          13
           
R 1000-gauge polythene damp m2  
proof membrane laid
horizontally on top of the    
sand blinding with 150mm
laps

17
           
Add   265.4
265
  1 1 1 265.47 7
  Deduct:   1 1 1 0 0 0
          265
           
S Fabric mesh; to BS 4483; Ref m2  
A142; weight 2.22kg/m2 laid    
on floor slab
           
Add   299.3
299
  1 1 1 299.38 8
  Deduct:   1 1 1 0 0 0
          299
           
T Wrought formwork to edges m  
of beds, roads, footpaths,
pavings, and the like over    
75mm not exceeding 150mm
wide
           
  Add   1 1 1 89.32 89.32 89
  Deduct:   1 1 1 0 0 0
          89
                 

18
Appendix 8: Bill of Quantities for Substructure of Proposed Health Centre
Development
Uni Rate Amount
Item Qty
Description t (Ushs) (Ushs)
       
PROPOSED HEALTH CENTRE
     
DEVELOPMENT
       
       
       
  ELEMENT No. 1    
       
  SUBSTRUCTURE    
       

  SITE PREPARATION; EXCAVATIONS    


AND EARTHWORKS
       
  SITE CLEARANCE    
       
Clear site of bushes, shrubs, undergrowth
A and the like including grabbing up their m2 393 3,520 1,383,360
roots
       
  EXCAVATION    
       
Excavate vegetable soil average 150mm
thick starting from existing ground level to
B m2 393 2,000 786,000
be preserved in temporary heaps
approximately 300m from site.
       

C Excavate to reduce levels starting from the m3 393 10,000 3,930,000


stripped level not exceeding 1.5m deep and
remove from site.
       

D Excavation for trenches not exceeding 1.5m m3 153 10,000 1,530,000


deep commencing from the reduced ground
level
       
  Disposal    
       

19
E Return and well ram filling obtained from
the excavations; filling around foundations
in 150mm thick layers, well compacted
7,
M3 - 000 -
       
F Remove surplus excavated materials from 12,
3
site M   000 -
       
  Disposal of water    
       
G Allow for keeping the whole of the
excavations free from all water including
spring or running water, silt or mud by
pumping or otherwise
Ite 1,000
m ,000
       
  Planking and Strutting    
       
Allow for provision and subsequent removal
H of planking    
and strutting to up-hold and maintain the
  faces of    
excavations Ite 1,000
  m ,000
       
  ANTI TERMITE TREATMENT    
       
Anti-termite treatment to the sides and
bottoms of trench and pit excavations, tops
I of hardcore and top of foundation walls at a
rate of 3 litres / m2 or specified by the
manufacturer. m2 730 2,500 1,825,000
       
           
           
11,454,36
     
Total carried to Collection ’  0
2/1/1

Uni Rate Amount


Item Qty
Description t (Ushs) (Ushs)
       
  Insitu Plain Concrete in Grade 10    
       
50mm thick blinding under strip
A m2 99 17,500 1,732,500
foundations

20
       
350,00
B m3 17 5,950,000
Strip footing 0
       
  Reinforced Concrete in Grade 25    
       
460,00
C m3 10 4,600,000
Ground beams 0
       
14,582,00
D m2 317 46,000
100mm thick Oversite slab/concrete bed 0
       

  Fabric Mesh; to B.S. 4483; weight 2.22    


kgs per square metre
       
E A142 Fabric laid on floor slab m2
299 12,000 3,588,000
       
  PLINTH WALL    
       
200mm thick solid clay brick walling in
block size….x….x…….mm thick to
F m2 35 45,000 1,593,000
BS……. bedded and jointed in cement sand
mortar mix ratio (1:4) in a stretcher bond.
       
150mm thick solid clay brick walling in
block size….x….x…….mm thick to
G m2 45 33,750 1,518,750
BS……. bedded and jointed in cement sand
mortar mix ratio (1:4) in a stretcher bond.
       
  DAMP PROOF COURSE (DPC)    
       
150mm wide Bitumen hessian base DPC to
H m 193 1,500 289,500
BS 743 type A
       
  MURRAM    
       
300mm thick on formation selected murram
deposited in layers and compacted with 5-
I m3 153 25,000 3,825,000
tonne roller to receive hardcore filling
(measured separately)
       
  Page    
HARDCORE
  Hardcore comprising hard clean stone,    
laterite or broken concrete to pass a 75mm
ring, deposited in layers and consolidated

21
by ramming.
150mm thick filling on consolidated
J murram compacted with 5- tonne roller
(measured separately) m2 265 15,000 3,975,000
       
  SAND BLINDING    
       

K 50mm thick sand blinding laid onto surfaces m2 265 5,000 1,325,000
of hardcore and to receive polythene sheet
       
  DPM    
       

L 1000-gauge polyethene damp proof


membrane laid horizontally on top of sand
blinding with 150mm laps. m2 265 2,500 662,500
       
           
43,641,25
     
Total carried to Collection ’  0
2/1/2

Uni Rate Amount


Item Qty
Description t (Ushs) (Ushs)
       
       
  FORM WORK    
       
Wrought formwork to the edges of beds,
A roads, footpaths and the like over 75mm m 90 2,618 235,575
N.E 150mm wide
       
       
       
       
  Total Carried to Collection   235,575
       
       
  COLLECTION    
       
       
11,454,36
 
Page 2/1/1   0
     

22
43,641,25
 
Page 2/1/2 0
     
  Page 2/1/3 235,575
     
     
     
     
     
     
     
     
     
     
     
     
     
     
     
     
     
     
     
     
     
     
     
       
       
       
       
       
       
       
       
       
       
       
       
           
55,331,18
       
Total to Summary of Elements 5

23
Appendix 9: Valuation for the Proposed Health Centre Development

       
   
   

24
   
  PROPOSED HEALTH CENTRE DEVELOPMENT  
   
  BILLS OF QUANTITIES  
   
  VALUATION No.2  
   
  PREPARED BY:  
   
  WENDY JOAN  
  P.O BOX 8463  
  KAMPALA.  
   
  CHECKED BY:  
  ARCH. BENARD  
  P.O BOX 10899, KAMPALA.  
  SEPTEMBER, 2022.  
   
       

25
CONTRACT VALUATION
Cumm Cummulative
ITEM Rate Amount Qty to Qty
Unit Qty ulative Amount
(Ushs) (Ushs) date Previous
Description Qty
PROPOSED HEALTH CENTRE DEVELOPMENT

ELEMENT No. 1
SUBSTRUCTURE
SITE PREPARATION; EXCAVATIONS AND
EARTHWORKS

SITE CLEARANCE

2/1/1A Clear site of bushes, shrubs, undergrowth and the like including m
2
393 3,520 1,383,360 393 393 1,383,360
grabbing up their roots

EXCAVATION

Excavate vegetable soil average 150mm thick starting from


2
2/1/1B existing ground level to be preserved in temporary heaps m 393 2,000 786,000 393 393 786,000
approximately 300m from site.

Excavate to reduce levels starting from the stripped level not 3


2/1/1C m 393 10,000 3,930,000 35 150 185 1,850,000
exceeding 1.5m deep and remove from site.

Excavation for trenches not exceeding 1.5m deep commencing 3


2/1/1D m 153 10,000 1,530,000 30 25 55 550,000
from the reduced ground level

Total carried to Collection 7,629,360 4,569,360


2/1/1

CONTRACT VALUATION
Cumm Cummulative
Item
Unit QtyRate (Ushs)Amount (Ushs)
Qty to date
Qty Previousulative Amount
Description
Qty

Disposal

2/1/1E Return and well ram filling obtained from the excavations;
filling around foundations in 150mm thick layers, well 50 350,000
compacted M3 - 7,000 - 50

2/1/1F Remove surplus excavated materials from site M3 12,000 - 0 0

Disposal of water

2/1/1G Allow for keeping the whole of the excavations free from all
water including spring or running water, silt or mud by 1 0
pumping or otherwise Item 1,000,000 0.50

Planking and Strutting

2/1/1H Allow for provision and subsquent removal of planking


and strutting to up-hold and maintain the faces of
excavations Item 1,000,000 0.50 1 0
0
ANTI TERMITE TREATMENT

Anti termite treatment to the sides and bottoms of trench and


2/1/1I pit excavations, tops of hardcore and top of foundation walls at 450 1,125,000
2
a rate of 3 litres / m2 or specified by the manufacturer. m 730 2,500 1,825,000 200 250

Total carried to Collection 3,825,000 1,475,000


2/1/2

CONTRACT VALUATION
Cumm Cummulative
Item
Unit QtyRate (Ushs)Amount (Ushs)
Qty to date
Qty Previousulative Amount
Description
Qty

Insitu Plain Concrete in Grade 10

2
2/1/2A 50mm thick blinding under strip foundations m 99 17,500 1,732,500 60 60 1,050,000

3
2/1/2B Strip footing m 17 350,000 5,950,000 5 5 1,750,000

Reinforced Concrete in Grade 25

3
2/1/2C Ground beams m 10 460,000 4,600,000 5 5 2,300,000

2
2/1/2D 100mm thick Oversite slab/concrete bed m 317 46,000 14,582,000 0 0

Fabric Mesh; to B.S. 4483;weight 2.22 kgs per square


metre

2
2/1/2E A142 Fabric laid on floor slab m 299 12,000 3,588,000 0 0

PLINTH WALL

200mm thick solid clay brick walling in block


2
2/1/2F size…..x…..x…….mm thick to BS…….bedded and jointed m 35 45,000 1,593,000 6 6 270,000
in cement sand mortar mix ratio (1:4) in a stretcher bond.

2/1/2G 26

Total carried to Collection 33,564,250 5,707,500


DAMP PROOF COURSE ( DPC)

2/1/2H 150mm wide Bitumen hessian base DPC to BS 743 type A m 193 1,500 289,500 20 20 30,000

MURRAM

300mm thick on formation selected murram deposited in layers


3
2/1/2I and compacted with 5-tonne roller to receive hardcore filling m 153 25,000 3,825,000 0 0
(measured separately)

HARDCORE
Hardcore comprising hard clean stone, laterite or broken
concrete to pass a 75mm ring, deposited in layers and
consolidated by ramming.

2/1/2J 150mm thick filling on consolidated murram compacted with 5- 0 0


2
tonne roller (measured separately) m 265 15,000 3,975,000

SAND BLINDING

50mm thick sand blinding laid onto surfaces of hardcore and 2


2/1/2K m 265 5,000 1,325,000 0 0
to receive polythene sheet

DPM

1000 gauge polyethene damp proof membrane laid horizontally


2/1/2L 2 0 0
on top of sand blinding with 150mm laps. m 265 2,500 662,500

Total carried to Collection 10,077,000 30,000


2/1/4

CONTRACT VALUATION
Cumm Cummulative
Item
Unit QtyRate (Ushs)Amount (Ushs)Qty to date
Qty Previousulative Amount
Description
Qty

FORM WORK

2/1/3A Wrought formwork to the edges of beds , roads, footpaths and m 90 2,618 235,575 0 0
the like over 75mm N.E 150mm wide

Total Carried to Collection 235,575 0

COLLECTION

Page 2/1/1 7,629,360 4,569,360

Page 2/1/2 3,825,000 1,475,000

Page 2/1/3 33,564,250 5,707,500

Page 2/1/4 10,077,000 30,000

Page 2/1/5 235,575 0

Total to Summary of Elements 55,331,185 11,781,860


2/1/5

27
Appendix 10: General Summary of the Proposed Health Centre Development

PROPOSED HEALTH CENTRE DEVELOPMENT

GENERAL SUMMARY
Cummulative
ITEM DESCRIPTION CONTRACT BOQ Amount Paid Amount Payable Amount
AMOUNT Previously To-date Payable (Ushs)

1 Preliminaries 5,000,000 3,750,000 3,750,000

2 Toilet Block 55,331,185 11,781,860 11,781,860

60,331,185 15,531,860
Add: Contingecy 5% 3,016,559

63,347,744 15,531,860
Less: Retention 10% 1,553,186

13,978,674
Add: VAT 18% 11,402,594 2,516,161
16,494,835
Less: Previous Payments (Certificate No. 1) 7,321,810

TOTAL COST ESTIMATE SHS. 74,750,338 9,173,025

7th October 2022

28
Appendix 11: Interim certificate for Proposed Health Centre development
INTERIM CERTIFICATE OF PAYMENT
PROPOSED HEALTH CENTRE DEVELOPMENT
VALUATION No. 2
Date: 07th, October, 2022
S.NO. PARTICULARS AMOUNT USHS.

Employer UGANDA MARTYRS NAMUGONGO S.S


Contractor JULIO ENGINEERING LTD
Procurement Reference Number HEALTH CENTRE DEVELOPMENT
Start Date 01st June, 2022
Completion Date 31st October, 2022

1 Contract Sum with VAT 65,290,798


Contract Sum without VAT 55,331,185

2 Revised Contract Sum NIL


3 Retention Limit with VAT - 5% 3,264,540
Retention Limit without VAT 2,766,559
4 Advance Payment (10% of 1) with VAT NIL
Advance Payment (10% of 1) without VAT NIL
5 15,531,860
6 Materials on Site N/A
Add: Variation Orders NIL
7 Add: Advance Payment NIL
8 Gross Value of Workdone without VAT (5,6, 7 & 8) 15,531,860
Less: Retention (10% of 15,531,860 ) without VAT -1,553,186
Less: Previously Certified - includes Advance Payment - without VAT -6,204,924

9 Amount as per this Valuation No. 2 7,773,750


10 Add: VAT (18%) 1,399,275
11 AMOUNT DUE TO CONTRACTOR 9,173,025

CERTIFIED: APPROVED:
…………………………………………….. ……………………………………
PROJECT QUANTITY SURVEYOR PROJECT ARCHITECT

STATEMENT FOR ARCHITECT’S/ENGINEER’S CERTIFICATE


Archite ct/Engine e r: ARCHITECT BENARD
Contract for: PROPOSED HEALTH CENTRE DEVELOPMENT
Contractor: JULIO ENGINEERING LTD
Amount of Contract Ug.Shs . 65,290,798
Estimated Final Amount: U.Shs. As revised by extra and omissions (approximate only)
Project Commencement Date: 1st Fe bruary, 2021 Date for completion: 31s t Octobe r, 2022
Maintenance Period: a) Building works - 6 MONTHS Retention Limit: 3,264,540 (Vat Incl.)
b) Engineering Services Advance Payment: NIL
STATEMENT FOR INTERIM CERTIFICATE NO. 02 (TWO)
U. Shs. U. Shs. Cts
Gross amount of Contractor’s Work done … … 15,531,860 0
Nominated Sub-Contractors NIL -
Materials on Site … … … … … N/A 0
Add: Extras/Variation Orders (V.O) NIL 0
15,531,860
Add: Advance payment: NIL NIL
15,531,860 0
Discount: … … … … … … … N/A -
15,531,860 0
Le ss : Retention 15,531,860
10% of Limit -3,264,540 1,553,186 0
13,978,674 0

13,978,674
De duct: Amount previously certified without VAT (1...…).
De tails of Pre vious Payme nts without VAT
Ce rt. No. Shs . cts . Ce rt. No. Shs. cts.
Advance NIL Total b/f 6,204,924
1 6,204,924

Total c/f 6,204,924 T otal 6,204,924 6,204,924 0


7,773,750

Add: VAT (18%) 1,399,275 0

Amount of Ce rtificate No. 02 (TWO) 9,173,025 0

I/We hereby certify the amount of payment by the Employer to the Contractor on this Certificate is Ug shs 9,173,025
(Nine Million One Hundred Seventy Three Thousand Twenty Five only).

Date: ………..
To be Signed by: Signed………………………………………………………….
Or for the Insurer named above. Official Stamp.

Co p y: Co n tr acto r Q.S Fi l e

29
30

You might also like