Proyek Pembangunan

PEMBANGUNAN BANGUNAN UTILITAS


TEMPORARY UTILITY BUILDING
EKA HOSPITAL - BSD

LAPORAN PROGRESS MINGGUAN


MINGGU KE - 12
PERIODE : 31 Oktober s/d 06 Nopember 2022

PAKET PEKERJAAN :

STRUKTUR, ARSITEKTUR & ELEKTRIKAL

PEMBANGUNAN BANGUNAN UTILITAS EKA HOSPITAL

PEMBERI TUGAS :
PT. PELITA RELIENCE INTERNATIONAL HOSPITAL

KONTRAKTOR :
PT. SURYA BANGUN PERSADA INDAH
Project No. P-EKABSD-19
Document
EKA HOSPITAL P-EKBSD-19-SBPI-PGR-0012
No.
Revision No. 0

WEEKLY PROGRESS Page 1 of 18


REPORT TEMPLATE Issue Date 8Nopember 06, 2022

TEMPORARY UTILITY BUILDING


(ARCHITECTURE, STRUCTURE & ELECTRIKAL)

WEEKLY PROGRESS REPORT TEMPLATE

31 Oktober 2022 3 06 Nopember 2022

06 Nopember,
0 Issued for Information PT. SBPI PT.PRIH PT.PRIH
2022

Date Revision Description Prepared Checked Approved


Project No. P-EKABSD-19
Document
EKA HOSPITAL P-EKBSD-19-SBPI-PGR-0012
No.
Revision No. 0

WEEKLY PROGRESS Page 2 of 18


REPORT TEMPLATE Issue Date 8Nopember 06, 2022

Date Revision Description of Revition Prepared Checked Approved

(function affected, modified sections)

06 Nopember 0 Issued for Information PT. SBPI


2022

PT. SBPI QC Eka Hostpital BSD

Nikmatus .S .................................. ................................


Admin Project
Project No. P-EKABSD-19
Document
EKA HOSPITAL P-EKBSD-19-SBPI-PGR-0012
No.
Revision No. 0

WEEKLY PROGRESS Page 3 of 18


REPORT TEMPLATE Issue Date 8Nopember 06, 2022

TABLE OF CONTENTS

1 EXECUTIVE SUMMARY
1.1 DESCRIPTION OF THE PROJECT STATUS
1.2 CURRENT CUMULATIVE SUMMARY PROGRESS
1.3 RECENT TIME LINE
2 PROJECT PROGRESS
2.1 DETAIL ENGINEERING PROGRESS CHART
2.2 SUMMARY ENGINEERING TABLE
2.3 ENGINEERING ACTIVITIES PLAN NEXT WEEK
3 ENGINEERING STATUS
3.1 STATUS MONITORING APPROVAL MATERIAL
3.2 STATUS MONITORING SHOP DRAWING
4 ATTACHMENTS
4.1 TOTAL ENGINEERING S-CURVE
4.2 ACTUAL ENGINEERING S-CURVE
5 DOKUMENTASI
Project No. P-EKABSD-19
Document
EKA HOSPITAL P-EKBSD-19-SBPI-PGR-0012
No.
Revision No. 0

WEEKLY PROGRESS Page 4 of 18


REPORT TEMPLATE Issue Date 8Nopember 06, 2022

1. EXECUTIVE SUMMARY
1.1 Deskripsi Tentang Proyek
Pengerjaan Temporary Bangunan Utility Eka Hospital BSD

1.2 Lokasi Proyek


Central Business District Lot. IX, Jl. Boulevard BSD Tim, Lengkong Gudang, Kec. Serpong, Kota Tangerang
Selatan
Project No. P-EKABSD-19
Document
EKA HOSPITAL P-EKBSD-19-SBPI-PGR-0012
No.
Revision No. 0

WEEKLY PROGRESS Page 5 of 18


REPORT TEMPLATE Issue Date 8Nopember 06, 2022

1.3 Progress Kumulatif Proyek


Untuk progress kerja tanggal 31 Oktober 3 06 Nopember yaitu 98.71%

÷ Pekerjaan Pengecatan
÷ Pekerjaan Pengaspalan jalan
÷ Pekerjaan Pemasngan Pagar BRC
÷ Pekerjaan Pemasangan Paving
÷ Pekerjaan Pemasangan Kansteen
÷ Pekerjaan Pembersihan Area
Project No. P-EKABSD-09
EKA HOSPITAL
Document No. P-EKBSD-09-SBPI-PGR-0012
Revision No. 0
WEEKLY PROGRESS REPORT TEMPLATE Page of 18
Issue Date Nopember 06, 2022

2. PROJECT PROGRESS
2.1 Detail Engineering Progress Chart

Proyek Pembangunan
PEMBANGUNAN BANGUNAN UTILITAS
TEMPORARY UTILITY BUILDING
EKA HOSPITAL - BSD
Paket Pekerjaan : Pemberi Tugas :
STRUKTUR, ARSITEKTUR & MELEKTRIKAL Minggu ke : 12 PT. PELITA RELIENCE INTERNATIONAL HOSPITAL

Bulan : NOPEMBER 2022 Kontraktor Pelaksana :


TEMPORARY UTILITY BUILDING
Periode Tgl. : 31 Okt s/d 06 Nov 2022 PT. SURYA BANGUN PERSADA INDAH

Instruksi Pelaksanaan Pekerjaan ( IPP ) : Mulai Pelaksanaan : 16 Agustus 2022.


011/PKS-UMUM/PRIH/SBPI/BSD/VI/2022 Waktu Pelaksanaan : 90 Hari Kalender
Waktu Terpakai : 83 Hari Kalender
Nilai Kontrak : Sisa Waktu : 7 Hari Kalender
Rp. 3.794.000.000,- ( excl.. PPn ) Serah Terima I : 14 November 2022.

s/d MINGGU LALU MINGGU INI s/d MINGGU INI


BOBOT
NO URAIAN PEKERJAAN SAT VOL. PRESTASI BOBOT PRESTASI BOBOT PRESTASI BOBOT
( % ) (%) (%) (%) (%) (%) (%)

I. PEK. PRELIMINERY / PERSIAPAN 13,128 88,50 11,62 7,26 0,95 95,75 12,57
Catatan Harga ( Pricing Notes ) :

A. This contract is Lump Sum Fixed Price, except where provisional or "Provisional
Sum" is stated. The Contractor is obliged to recalculate the work volume and
check the units made by the Quantity Surveyor and if according to the
Contractor's calculations the volume and or units are not appropriate or there are
work items that have not been listed, the Contractor may change or add to the
special attachments made for additional or less work.

B. The Contractor must have considered including all costs of work expenses and
there will be no claim at a later date against the Employer, if the list of job
descriptions is deemed incomplete.

C. All works that are not listed here are considered included in the offer and all risks
both regarding price escalation, miscalculation of the volume and price submitted
are the responsibility of the Contractor.

1 Proyek Manajemen dan Biaya Administrasi Lapangan Ls 1,00 7,3197 85,00 6,22 10,00 0,73 95,00 6,95
Biaya - biaya untuk mengadakan staf dilapangan yang akan mengelola pelaksanaan pekerjaan, semua biaya
administrasi dan biaya mengurus segala hal yang berhubungan dengan tanggung jawabnya terhadap
kontrak ini .

2 Peralatan dan Perlengkapan Kerja Ls 1,00 0,6570 85,00 0,56 10,00 0,07 95,00 0,62
Pengadaan peralatan dan perlengkapan kerja yang lengkap untuk kelancaran pelaksanaan pekerjaan
sebagaimana yang dimaksud didalam Dokumen Kontrak, termasuk biaya ijin pemasukan peralatan kedalam
lokasi proyek, pemeliharaan dan pemindahan dari satu tempat ke tempat lainnya didalam lokasi pekerjaan
serta mengeluarkannya setelah penyelesaian pekerjaan.

3 Peralatan dan Perlengkapan Keselamatan Kerja serta P3K Ls 1,00 0,0896 85,00 0,08 10,00 0,01 95,00 0,09
Pengadaan topi pengaman (helm), baju hujan, sepatu lapangan, handy talky (HT) sebanyak yang diperlukan
untuk Pemberi Tugas, Pimpinan Proyek dan Konsultan di proyek berikut peralatan P3K. (masing - masing 3
set)

4 Rapat Proyek Ls 1,00 exclude


Mengkoordinasikan semua pemborong yang akan mengikuti rapat berikut pengadaan akomodasi untuk rapat
lapangan termasuk penyediaan konsumsi.

5 Dokumen Kontrak Ls 1,00 0,0264 50,00 0,01 - - 50,00 0,01


Pembuatan dan pencetakan Dokumen Kontrak lengkap dengan gambar-gambar kontrak sebanyak 4 (empat)
set yang terdiri atas 2 (dua) set asli dan 2 (dua) set copy.

6 Pengadaan Gambar
a. Pengadaan gambar-gambar pelaksanaan (construction drawing) sebanyak yang Ls 1,00 exclude
diperlukan untuk keperluan kerja dilapangan termasuk 2 (dua) set keperluan
pengawasan.
b. Pembuatan gambar kerja (shop drawing) berikut perhitungan atau kalkulasi yang Ls 1,00 exclude
terinci sebanyak 2 (dua) set , hingga disetujui Manajemen Konstruksi, Pimpinan
Proyek atau Pemberi Tugas.
c. Pembuatan gambar-gambar terlaksana (as built drawing) sebanyak 1 (satu) set Ls 1,00 0,1054 50,00 0,05 - - 50,00 0,05
kalkir dan 3 (tiga) set cetak biru.

7 Photo - Photo Kemajuan Pekerjaan Ls 1,00 -


Pembuatan photo berwarna atas kemajuan pekerjaan sebanyak 3 (tiga) set setiap bulan hingga masa serah
terima ke-1 (pertama) dan diserahkan kepada Pimpinan Proyek.

8 Contoh - Contoh Bahan Ls 1,00 exclude


Pengadaan contoh-contoh bahan yang dikehendaki oleh Pimpinan Proyek atau Pemberi Tugas harus sesuai
dengan standar dan diambil dengan cara sedemikian rupa sehingga dapat dianggap bahwa bahan atau
pekerjaan tersebutlah yang akan dipakai dalam pelaksanaan pekerjaan nanti dan harus secepatnya
disediakan jika ada instruksi dari Pimpinan Proyek atau Pemberi Tugas.

9 Pemeriksaan dan Pengujian Bahan Ls 1,00 exclude


Pemborong harus memasukkan segala keperluan biaya pengujian berbagai bahan pekerjaan dan pengujian
ulang dari bahan pekerjaan yang tidak memenuhi syarat yang dikehendaki.

RAB - EKA HOSPITAL BSD PT. SBPI Halaman. : 2 - 17


Project No. P-EKABSD-09
EKA HOSPITAL
Document No. P-EKBSD-09-SBPI-PGR-0012
Revision No. 0
WEEKLY PROGRESS REPORT TEMPLATE Page of 18
Issue Date Nopember 06, 2022

2. PROJECT PROGRESS
2.1 Detail Engineering Progress Chart

Proyek Pembangunan
PEMBANGUNAN BANGUNAN UTILITAS
TEMPORARY UTILITY BUILDING
EKA HOSPITAL - BSD
Paket Pekerjaan : Pemberi Tugas :
STRUKTUR, ARSITEKTUR & MELEKTRIKAL Minggu ke : 12 PT. PELITA RELIENCE INTERNATIONAL HOSPITAL

Bulan : NOPEMBER 2022 Kontraktor Pelaksana :


TEMPORARY UTILITY BUILDING
Periode Tgl. : 31 Okt s/d 06 Nov 2022 PT. SURYA BANGUN PERSADA INDAH

Instruksi Pelaksanaan Pekerjaan ( IPP ) : Mulai Pelaksanaan : 16 Agustus 2022.


011/PKS-UMUM/PRIH/SBPI/BSD/VI/2022 Waktu Pelaksanaan : 90 Hari Kalender
Waktu Terpakai : 83 Hari Kalender
Nilai Kontrak : Sisa Waktu : 7 Hari Kalender
Rp. 3.794.000.000,- ( excl.. PPn ) Serah Terima I : 14 November 2022.

s/d MINGGU LALU MINGGU INI s/d MINGGU INI


BOBOT
NO URAIAN PEKERJAAN SAT VOL. PRESTASI BOBOT PRESTASI BOBOT PRESTASI BOBOT
( % ) (%) (%) (%) (%) (%) (%)

10 Direksi Keet Ls 1,00 exclude


Pembuatan Kantor Sementara Direksi atau Pimpinan Proyek selama masa pelaksanaan pekerjaan berikut
pemeliharaannya, kebersihan dan pengadaan peralatan atau perabotannya

11 Kantor Pemborong Lapangan Ls 1,00 0,3664 90,00 0,33 5,00 0,02 95,00 0,35
Pembuatan kantor sementara pemborong di lapangan berikut semua fasilitas yang diperlukan termasuk toilet
untuk para pekerja selama masa pelaksaan pekerjaan berikut pemeliharaan kebersihan didalam lokasi
pekerjaan, pembongkaran bila ada perintah membongkar setelah pekerjaan selesai

12 Gudang Sementara dan Los Kerja Ls 1,00 0,2319 90,00 0,21 5,00 0,01 95,00 0,22
Pengadaan gudang sementara dan los pekerjaan di lapangan berikut pemeliharaannya dan membongkar
setelah pekerjaannya selesai serta memperbaiki, merapihkan dan membersihkannya

13 Pagar Sementara Proyek Ls 1,00 2,2035 100,00 2,20 - - 100,00 2,20


Pembuatan pagar sementara proyek tidak boleh melewati batas - batas lokasi tanah proyek (site) termasuk
pemeliharaannya dan membongkar setelah pekerjaan selesai serta memperbaiki , merapihkan dan
membersihkan kembali sesuai ketentuan lingkungan yang ditetapkan oleh Peraturan Pemerintah Daerah ,
sedangkan ukuran, bentuk , spesifikasi materialnya sesuai dengan yang ditetapkan Pimpinan Proyek atau
Pemberi Tugas.

14 Saluran Sementara Ls 1,00 exclude


Pengadaan saluran sementara untuk mencegah genangan air akibat hujan atau hal lain termasuk
pengadaan pompa untuk mengeringkan air pada lokasi sekitar pekerjaan dan mengalirkan ketempat yang
tidak akan mengganggu kelancaran pekerjaan selama proyek dilaksanakan.

15 Jalan Masuk Ke Tempat Pekerjaan Dan Jalan Sementara Ls 1,00 0,1318 85,00 0,11 10,00 0,01 95,00 0,13
Bilamana diperlukan jalan atau jembatan masuk ketempat lokasi pekerjaan harus diadakan oleh pemborong,
disesuaikan dengan kebutuhan dan kepentingan proyek tersebut. Selama pekerjaan berlangsung
pemborong diharuskan memelihara, memperbaiki segala kerusakan yang diakibatkan dan membersihkannya
kembali.

16 Papan Nama Proyek Ls 1,00 -


Pemborong harus mengadakan pembuatan dan pemasangan papan nama proyek.(untuk keperluan papan
nama kontraktor sendiri)

17 Kebersihan dan Kerapihan Ls 1,00 0,6128 85,00 0,52 10,00 0,06 95,00 0,58
Pemborong harus mengangkut ke luar lokasi proyek semua sampah secara teratur jika sudah bertumpuk
dan pada waktu penyelesaian pekerjaan harus bersih dan rapih. (Catatan :
Dalam pengangkutan keluar proyek tidak boleh mengotori jalan dan prasarana umum).

18 Penjagaan Proyek Ls 1,00 -


Pemborong bertanggung jawab atas penjagaan , penerangan dan perlindungan terhadap pekerjaan yang
dianggap penting selama masa pelaksanaan kontrak siang dan malam . Pemberi tugas tidak bertanggung
jawab terhadap pemborong dan sub Pemborong atas kehilangan, kerusakan bahan-bahan bangunan,
peralatan atau pekerjaan yang sedang dalam pelaksanaan.

19 Pemadam Kebakaran Ls 1,00 0,0501 85,00 0,04 10,00 0,01 95,00 0,05
Pengadaan peralatan dan pencegahan terhadap bahaya kebakaran dan yang sesuai dengan anjuran
perusahaan asuransi terhadap pekerjaan dan instalasi pemerintah yang berwenang dan sediakan tenaga-
tenaga yang terlatih untuk maksud diatas .

20 Pengadaan Tenaga Listrik ( biaya Instalasi ) Ls 1,00 0,2596 100,00 0,26 - - 100,00 0,26
Setiap pembangkit tenaga listrik sementara atau penerangan sementara termasuk pemasangan kabel-kabel
dan meteran yang dipergunakan untuk pekerjaan atau pengambilan daya dari sumber atau PLN yang sudah
ada , genset termasuk bahan bakar, maka semua biaya pengadaan dan pemakaian daya selama
pelaksanaan proyek termasuk izin yang diperlukan serta perapihan setelah pekerjaan selesai sudah harus
diperhitungkan oleh pemborong.

21 Pengadaan Sumber Air Bersih ( Biaya Instalasi ) Ls 1,00 0,1120 100,00 0,11 - - 100,00 0,11
Pengadaan sumber air bersih sementara untuk air kerja dan keperluan lainnya dari sumber yang ada (sumur
pantek / jet pump, sumur dalam / deep well), termasuk membuat sambungan-sambungan sementara untuk
mengalirkan air dan mencabutnya kembali setelah pekerjaan selesai.

22 Telepon Ls 1,00 0,0659 85,00 0,06 10,00 0,01 95,00 0,06

Pengadaan telepon dan perlengkapannya sesuai kebutuhan termasuk pengurusan permohonan kepada
Perumtel dan pembayaran semua tagihan selama masa pelaksanaan pekerjaan dan menyerahkannya
kepada Pemberi Tugas setelah penyerahan pertama termasuk biaya balik nama kepada Pemberi Tugas.

RAB - EKA HOSPITAL BSD PT. SBPI Halaman. : 3 - 17


Project No. P-EKABSD-09
EKA HOSPITAL
Document No. P-EKBSD-09-SBPI-PGR-0012
Revision No. 0
WEEKLY PROGRESS REPORT TEMPLATE Page of 18
Issue Date Nopember 06, 2022

2. PROJECT PROGRESS
2.1 Detail Engineering Progress Chart

Proyek Pembangunan
PEMBANGUNAN BANGUNAN UTILITAS
TEMPORARY UTILITY BUILDING
EKA HOSPITAL - BSD
Paket Pekerjaan : Pemberi Tugas :
STRUKTUR, ARSITEKTUR & MELEKTRIKAL Minggu ke : 12 PT. PELITA RELIENCE INTERNATIONAL HOSPITAL

Bulan : NOPEMBER 2022 Kontraktor Pelaksana :


TEMPORARY UTILITY BUILDING
Periode Tgl. : 31 Okt s/d 06 Nov 2022 PT. SURYA BANGUN PERSADA INDAH

Instruksi Pelaksanaan Pekerjaan ( IPP ) : Mulai Pelaksanaan : 16 Agustus 2022.


011/PKS-UMUM/PRIH/SBPI/BSD/VI/2022 Waktu Pelaksanaan : 90 Hari Kalender
Waktu Terpakai : 83 Hari Kalender
Nilai Kontrak : Sisa Waktu : 7 Hari Kalender
Rp. 3.794.000.000,- ( excl.. PPn ) Serah Terima I : 14 November 2022.

s/d MINGGU LALU MINGGU INI s/d MINGGU INI


BOBOT
NO URAIAN PEKERJAAN SAT VOL. PRESTASI BOBOT PRESTASI BOBOT PRESTASI BOBOT
( % ) (%) (%) (%) (%) (%) (%)

23 Pengukuran dan Bouwplank Ls 1,00 0,1186 100,00 0,12 - - 100,00 0,12


Penentuan letak titik-titik patok pengukuran dilapangan bersama Pimpinan Proyek dan harus dijaga dari
kerusakan-kerusakan. Setiap titik patok pengukuran yang tidak pada tempatnya lagi atau hilang harus dibuat
lagi, penentuan peil-peil pekerjaan akan diambil dari titik-titik yang teliti. Kesalahan yang timbul dalam
pengambilan ukuran dan perubahan letak atau hilangnya titik-titik patok pengukuran menjadi tanggung jawab
pemborong. Dalam hal ini pemborong harus mengadakan pegawai sebanyak yang diperlukan untuk
membantu Pimpinan Proyek untuk melaksanakan pekerjaan diatas dengan biaya ditanggung pemborong.

24 Kerusakan Dan Kerugian terhadap Bangunan Lain Ls 1,00 -


Semua kerusakan atau kerugian terhadap bangunan atau jaringan instalsi disekitarnya maupun jaringan
instalasi yang sudah ada dari PLN, PAM, Perumgas, PU yang berada di lokasi proyek selama waktu
pelaksanaan menjadi tanggung jawab sepenuhnya pemborong. Berikut pemindahan jaringan instalasi -
jaringan instalasi tersebut diatas juga menjadi tanggung jawab pemborong, jika jaringan tersebut
mengganggu dalam pelaksanaan proyek, termasuk pengurusan izin-izin pada instansi yang bersangkutan.

25 Asuransi
Pemborong atas nama Pemberi Tugas wajib mengasuransikan, sebagai berikut :

a. Asuransi Construction All Risk (CAR) dan Third Party Liability (TPL). Deductible Ls 1,00 -
by kontraktor

b. Asuransi Tenaga Kerja (ASTEK) untuk pekerja dan staff pemborong yang bekerja Ls 1,00 0,1711 85,00 0,15 10,00 0,02 95,00 0,16
pada proyek ini

26 LAIN-LAIN :
a Biaya untuk pembuatan washing bay / cleaning pit untuk membersihkan ban Ls 1,00 0,1318 85,00 0,11 10,00 0,01 95,00 0,13
kendaraan Proyek yang keluar masuk area Proyek, agar tidak mengotori jalan
umum, termasuk pembersihan jalan umum apabila dalam pelaksanaannya tetap
terjadi kendaraan proyek mengotori jalan umum.

b Biaya koordinasi terhadap pihak lain (instansi-instansi, izin lingkungan , ormas) Ls 1,00 0,4744 100,00 0,47 - - 100,00 0,47
selama pelaksanaan proyek berlangsung.

c Land Clearing dan Leveling termasuk sisa - sisa tanah dan puing bekas Ls 1,00 exclude
bongkaran serta Perataan tanah

II. PEK. STRUKTUR 57,810 99,21 57,35 0,02 0,01 99,23 57,36
A. STRUKTUR

1 Demolish Excisting m2 1.050,00 2,0327 100,00 2,03 - - 100,00 2,03

2 Foot Foundation incld column Pedestal


a Excavation, back fill and remove excess material out of site m3 93,33 0,3475 100,00 0,35 - - 100,00 0,35
b Soil Compaction m2 54,90 0,0327 100,00 0,03 - - 100,00 0,03
c Gravel 15cm m2 54,90 0,0996 100,00 0,10 - - 100,00 0,10
d Lean concrete 5cm m2 54,90 0,1226 100,00 0,12 - - 100,00 0,12
e Concrete Fc'=30 MPa m3 16,65 0,5258 100,00 0,53 - - 100,00 0,53
f Rebar kg 2.215,98 0,9636 100,00 0,96 - - 100,00 0,96
g Formwork m2 56,00 0,2752 100,00 0,28 - - 100,00 0,28

3 Tie Beam
a Excavation, back fill and remove excess material out of site m3 43,61 0,1624 100,00 0,16 - - 100,00 0,16
b Soil Compaction m2 52,42 0,0312 100,00 0,03 - - 100,00 0,03
c Gravel 15cm m2 52,42 0,0951 100,00 0,10 - - 100,00 0,10
d Lean concrete 5cm m2 52,42 0,1171 100,00 0,12 - - 100,00 0,12
e Concrete Fc'=30 MPa m3 32,35 1,0214 100,00 1,02 - - 100,00 1,02
f Rebar kg 6.616,51 2,8772 100,00 2,88 - - 100,00 2,88
g Formwork m2 210,15 1,0328 100,00 1,03 - - 100,00 1,03

4 Slab on Ground
a On Soil
- Soil Compaction m2 131,49 0,0783 100,00 0,08 - - 100,00 0,08
- Gravel 15cm m2 131,49 0,2386 100,00 0,24 - - 100,00 0,24
- Lean concrete 5cm m2 131,49 0,2937 100,00 0,29 - - 100,00 0,29
b On Excisting Pavement
- Gravel 4cm m2 527,55 0,2553 95,00 0,24 5,00 0,01 100,00 0,26
- Lean concrete 4cm m2 527,55 1,1784 100,00 1,18 - - 100,00 1,18
- Concrete Fc'=30 MPa m3 68,63 2,1668 100,00 2,17 - - 100,00 2,17
- Concrete Fc'=20MPa m3 19,80 0,6133 100,00 0,61 - - 100,00 0,61
- Wiremesh M8 -150 (1 layer) m2 -
- Wiremesh M10 -150 (1 layer) m2 112,76 0,4746 100,00 0,47 - - 100,00 0,47
- Wiremesh M5 -150 (1 layer) m2 384,00 0,5843 100,00 0,58 - - 100,00 0,58
- Wiremesh M4-150 (1 layer m2 176,00 0,2174 100,00 0,22 - - 100,00 0,22
- Formwork m2 85,14 0,4184 100,00 0,42 - - 100,00 0,42

RAB - EKA HOSPITAL BSD PT. SBPI Halaman. : 4 - 17


Project No. P-EKABSD-09
EKA HOSPITAL
Document No. P-EKBSD-09-SBPI-PGR-0012
Revision No. 0
WEEKLY PROGRESS REPORT TEMPLATE Page of 18
Issue Date Nopember 06, 2022

2. PROJECT PROGRESS
2.1 Detail Engineering Progress Chart

Proyek Pembangunan
PEMBANGUNAN BANGUNAN UTILITAS
TEMPORARY UTILITY BUILDING
EKA HOSPITAL - BSD
Paket Pekerjaan : Pemberi Tugas :
STRUKTUR, ARSITEKTUR & MELEKTRIKAL Minggu ke : 12 PT. PELITA RELIENCE INTERNATIONAL HOSPITAL

Bulan : NOPEMBER 2022 Kontraktor Pelaksana :


TEMPORARY UTILITY BUILDING
Periode Tgl. : 31 Okt s/d 06 Nov 2022 PT. SURYA BANGUN PERSADA INDAH

Instruksi Pelaksanaan Pekerjaan ( IPP ) : Mulai Pelaksanaan : 16 Agustus 2022.


011/PKS-UMUM/PRIH/SBPI/BSD/VI/2022 Waktu Pelaksanaan : 90 Hari Kalender
Waktu Terpakai : 83 Hari Kalender
Nilai Kontrak : Sisa Waktu : 7 Hari Kalender
Rp. 3.794.000.000,- ( excl.. PPn ) Serah Terima I : 14 November 2022.

s/d MINGGU LALU MINGGU INI s/d MINGGU INI


BOBOT
NO URAIAN PEKERJAAN SAT VOL. PRESTASI BOBOT PRESTASI BOBOT PRESTASI BOBOT
( % ) (%) (%) (%) (%) (%) (%)

5 Steel Structure
a Column SC1 : WF 300.150.6,5.9 kg 1.293,45 1,0914 100,00 1,09 - - 100,00 1,09
b Column SC2 : WF 250.125.6.9 kg 1.461,20 1,2330 100,00 1,23 - - 100,00 1,23
c Girder SG1 : WF 250.125.6.9 kg 385,87 0,3256 100,00 0,33 - - 100,00 0,33
d Girder SG2 : WF 250.125.6.9 kg 3.086,92 2,6048 100,00 2,60 - - 100,00 2,60
e Girder SG3 : WF 200.100.5,5.8 kg 3.499,76 2,9531 100,00 2,95 - - 100,00 2,95
f Girder SG4 : WF 150x75x5x7 kg -
g Purlin : CNP 125.50.20.3,2 kg 3.836,15 3,2370 100,00 3,24 - - 100,00 3,24
h Listplank frame : CNP 100.50.20.3,2 kg 582,38 0,4914 100,00 0,49 - - 100,00 0,49
i Wind bracing : Dia 16mm kg 362,36 0,3058 100,00 0,31 - - 100,00 0,31
j Turnbuckle dia 16 no 28,00 0,0834 100,00 0,08 - - 100,00 0,08
k Sagrod : dia 12 mm incld bolt kg 193,04 0,1629 100,00 0,16 - - 100,00 0,16
l Plate kg 1.719,26 1,4507 100,00 1,45 - - 100,00 1,45
m Bolt ls 1,00 0,6970 100,00 0,70 - - 100,00 0,70
n Anchorage Bolt L=1000MM + Double bolt no 72,00 0,9650 100,00 0,96 - - 100,00 0,96
o Grouting 500x500, 50mm thk no 18,00 0,1005 100,00 0,10 - - 100,00 0,10
p Zincromate + Finish Paint no 14.508,11 1,5124 100,00 1,51 - - 100,00 1,51

6 Roofing
a Metal Roof type Trimdeck TCT 0,45mm m2 632,51 3,2679 100,00 3,27 - - 100,00 3,27
b Roof Cap m1 44,70 0,2330 100,00 0,23 - - 100,00 0,23
c Insulation (rockwool densiti 60 kg/m2 + wiremesh + 2 layer Alm Foil) m2 -
d Fiber Gutter 400x300 mm incld frame (prov qty ) m1 -
e GRC Listplank W=500mm m1 131,85 0,3995 100,00 0,40 - - 100,00 0,40

B MISCELLANEOUS

1 MEP FOUNDATION
a. Watertank Foundation
Slab on Ground ( S30 )
- Excavation, back fill and remove excess material out of site m3 94,39 0,3514 100,00 0,35 - - 100,00 0,35
- Soil Compaction m2 111,05 0,0662 100,00 0,07 - - 100,00 0,07
- Gravel 15cm m2
- Gravel 50cm m2 111,05 0,6719 100,00 0,67 - - 100,00 0,67
- Lean concrete 5cm m2 111,05 0,2481 100,00 0,25 - - 100,00 0,25
- Concrete Fc'=30 MPa m3 33,32 1,0518 100,00 1,05 - - 100,00 1,05
- Rebar kg 3.613,91 1,5715 100,00 1,57 - - 100,00 1,57
- Formwork m2 10,50 0,0516 100,00 0,05 - - 100,00 0,05

b. Grid foundation (W25)


- Concrete Fc'=30 MPa m3 14,59 0,4605 100,00 0,46 - - 100,00 0,46
- Rebar kg 3.276,29 1,4247 100,00 1,42 - - 100,00 1,42
- Formwork m2 116,70 0,5735 100,00 0,57 - - 100,00 0,57

c Genset Foundation ( 2 unit @ 2500 mm x 6250 mm) h = 70 cm m2 31,25 4,0860 100,00 4,09 - - 100,00 4,09

d Panel / Trafo Foundation H = 20 cm ( SG20 ) m2 68,20 1,8484 100,00 1,85 - - 100,00 1,85

e Pump Foundation H = 20 cm ( SG20 ) m2 4,50 0,1220 100,00 0,12 - - 100,00 0,12

f Strip Foundation for Panel TM Foundation 1 m High ( detail W 25 ) m2 7,70 1,0756 100,00 1,08 - - 100,00 1,08

g Cable Tranch ( provisional ) ( Outer Size 1,8 m x 1,3 m ) m1 10,00 2,1332 100,00 2,13 - - 100,00 2,13

2 OTHER AREA
a Weekly Tank - Platform 4,5 x 9 x 0,25 no 1,00 3,4117 100,00 3,41 - - 100,00 3,41
b Box Control Size 600 x 600 x 400 mm (FIber optic, sound sistem ) include cover no 2,00 0,8447 100,00 0,84 - - 100,00 0,84
c Sewage Pit 2300 x 2300 x 1800 mm incld cover and mainhole no -
d Demolish Existing Toilet ( due to cable power line ) no 1,00 0,4468 - - - -

III. PEK. ARSITEKTUR 14,234 91,32 13,00 7,28 1,04 98,60 14,03
1. Demolition Works &....... ( not Applicable )

2. Interiors Partitions & Masonry


Lightweight concrete blockwork with mortar including reinforced concrete practical columns
and beams as specified.

a. 120mm thick block wall inc practical columns.


- 1st Floor m2 790,79 4,1866 100,00 4,19 - - 100,00 4,19

RAB - EKA HOSPITAL BSD PT. SBPI Halaman. : 5 - 17


Project No. P-EKABSD-09
EKA HOSPITAL
Document No. P-EKBSD-09-SBPI-PGR-0012
Revision No. 0
WEEKLY PROGRESS REPORT TEMPLATE Page of 18
Issue Date Nopember 06, 2022

2. PROJECT PROGRESS
2.1 Detail Engineering Progress Chart

Proyek Pembangunan
PEMBANGUNAN BANGUNAN UTILITAS
TEMPORARY UTILITY BUILDING
EKA HOSPITAL - BSD
Paket Pekerjaan : Pemberi Tugas :
STRUKTUR, ARSITEKTUR & MELEKTRIKAL Minggu ke : 12 PT. PELITA RELIENCE INTERNATIONAL HOSPITAL

Bulan : NOPEMBER 2022 Kontraktor Pelaksana :


TEMPORARY UTILITY BUILDING
Periode Tgl. : 31 Okt s/d 06 Nov 2022 PT. SURYA BANGUN PERSADA INDAH

Instruksi Pelaksanaan Pekerjaan ( IPP ) : Mulai Pelaksanaan : 16 Agustus 2022.


011/PKS-UMUM/PRIH/SBPI/BSD/VI/2022 Waktu Pelaksanaan : 90 Hari Kalender
Waktu Terpakai : 83 Hari Kalender
Nilai Kontrak : Sisa Waktu : 7 Hari Kalender
Rp. 3.794.000.000,- ( excl.. PPn ) Serah Terima I : 14 November 2022.

s/d MINGGU LALU MINGGU INI s/d MINGGU INI


BOBOT
NO URAIAN PEKERJAAN SAT VOL. PRESTASI BOBOT PRESTASI BOBOT PRESTASI BOBOT
( % ) (%) (%) (%) (%) (%) (%)

b. Plaster and render, ex Mortar Utama, AM, or equal


- 1st Floor m2 1.160,73 2,8605 100,00 2,86 - - 100,00 2,86

c. Plaster (only) without render, ex Mortar Utama, AM, or equal


- 1st Floor (R Genset) m2 281,92 0,5458 100,00 0,55 - - 100,00 0,55

3. Ceilling, Wall & Floor Finishes

a. Ceiling Finishes
1 9mm Gypsum board suspended ceilings including suspension system; metal furring
framing and supports and all associated work, all necessary metal angle and stop beads,
and cutting holes for lighting fixtures, speaker, etc.
- 1st Floor m2 -

2 6mm Calsiboard suspended ceilings including suspension system; metal furring


framing and supports and all associated work, all necessary metal angle and stop
beads, and cutting holes for lighting fixtures, speaker, etc.
- external under roof m2 -

3 Prepare and apply approved emulsion paint finish as specified on drawings and
specification,to gypsum ceiling
- 1st Floor m2 -

b. Wall Finishes
1 Prepare and apply approved emulsion paint finish as specified on drawings and
specification,to plastered dan gypsum walls;
- 1st Floor m2 592,84 0,5562 55,00 0,31 40,00 0,22 95,00 0,53

2 Prepare and apply approved Weathershield paint finish as specified on drawings


and specification,to plastered wall
- to external wall m2 567,89 0,6850 75,00 0,51 - - 75,00 0,51

c. Floor Finishes
1 Ceramic tile 300 x 300 mm ex Roman or equal, set in pattern, bedded, jointed on
and pointed with white or coloured cement; all in accordance with the
specification and as shown on drawings;
- 1st Floor (Logistic) m2 70,49 0,5973 100,00 0,60 - - 100,00 0,60

2 Trowelled Finish (apply to structure Surface)


- 1st Floor (to MEP room & outdoor area) m2 659,04 0,6870 100,00 0,69 - - 100,00 0,69

4. Doors & Windows

a. Door
Supply and install steel doors including frames,all necessary components, fixing,
accessories, consumables ironmongeries, all complete as specified in the drawings and
specification
1 TYPE SD 1 (Overall size 2100 x 2450mm)
- 1st Floor (soundproof) no 1,00 0,4597 100,00 0,46 - - 100,00 0,46
2 TYPE SD 2 (Overall size 2100 x 2150mm)
- 1st Floor no 5,00 1,6809 100,00 1,68 - - 100,00 1,68

5. WIndows & Louvers

a. Windows
1 TYPE W1 (Overall size 800x1450mm)
- 1st Floor no 1,00 0,0605 100,00 0,06 - - 100,00 0,06

b. Aluminum Louver&.......( Deleted incl. Genset )


1 TYPE GR1 (Overall size 2805x2150mm)
- 1st Floor no -
2 TYPE GR2 (Overall size 5550x2150mm)
- 1st Floor no -
3 TYPE GR3 (Overall size 5550x1250mm)
- 1st Floor no -

6. Sanitary &....... ( not Applicable )

7. Miscellaneous

a. BRC fence H=2000mm including BRC door


- to Watertank m1 36,40 0,6071 100,00 0,61 - - 100,00 0,61
- to trafo panel m1 6,50 0,1084 20,00 0,02 80,00 0,09 100,00 0,11
- to Weekly tank m1 30,00 0,5004 20,00 0,10 80,00 0,40 100,00 0,50

b. Concrete canopy
- Size 2300 x 1100mm unit 5,00 0,3617 95,00 0,34 5,00 0,02 100,00 0,36
- Size 1000 x 500mm unit 1,00 0,0298 95,00 0,03 5,00 0,00 100,00 0,03

RAB - EKA HOSPITAL BSD PT. SBPI Halaman. : 6 - 17


Project No. P-EKABSD-09
EKA HOSPITAL
Document No. P-EKBSD-09-SBPI-PGR-0012
Revision No. 0
WEEKLY PROGRESS REPORT TEMPLATE Page of 18
Issue Date Nopember 06, 2022

2. PROJECT PROGRESS
2.1 Detail Engineering Progress Chart

Proyek Pembangunan
PEMBANGUNAN BANGUNAN UTILITAS
TEMPORARY UTILITY BUILDING
EKA HOSPITAL - BSD
Paket Pekerjaan : Pemberi Tugas :
STRUKTUR, ARSITEKTUR & MELEKTRIKAL Minggu ke : 12 PT. PELITA RELIENCE INTERNATIONAL HOSPITAL

Bulan : NOPEMBER 2022 Kontraktor Pelaksana :


TEMPORARY UTILITY BUILDING
Periode Tgl. : 31 Okt s/d 06 Nov 2022 PT. SURYA BANGUN PERSADA INDAH

Instruksi Pelaksanaan Pekerjaan ( IPP ) : Mulai Pelaksanaan : 16 Agustus 2022.


011/PKS-UMUM/PRIH/SBPI/BSD/VI/2022 Waktu Pelaksanaan : 90 Hari Kalender
Waktu Terpakai : 83 Hari Kalender
Nilai Kontrak : Sisa Waktu : 7 Hari Kalender
Rp. 3.794.000.000,- ( excl.. PPn ) Serah Terima I : 14 November 2022.

s/d MINGGU LALU MINGGU INI s/d MINGGU INI


BOBOT
NO URAIAN PEKERJAAN SAT VOL. PRESTASI BOBOT PRESTASI BOBOT PRESTASI BOBOT
( % ) (%) (%) (%) (%) (%) (%)

c. Concrete Curb h = 150 mm ( existing material ) m1 142,00 0,3066 - 100,00 0,31 100,00 0,31

d. Perkuatan Kolom / Balok Praktis untuk AC m1 -

e. Vertical Garden
- Wiremesh Screen w/ steel hollow frame finish paint m2 -
- Planter Box m1 -
- Vines/"Tanaman Rambat alamanda" incld soil and fertilizer m1 -

IV. EKSTERNAL WORKS 9,197 81,65 7,51 18,35 1,69 100,00 9,20
1. DRAINAGE SYSTEM ( TEMPORARY BUILDING )
Supply and Install drainage system including excavation, sandbed, back fill and restore
the pavement or existing area to original condition
a. Drainage RCP dia 400mm m1 64,86 1,0303 100,00 1,03 - - 100,00 1,03
b. Control Box type BK2 no 8,00 1,8980 100,00 1,90 - - 100,00 1,90

2. ADDITIONAL PARKING
Existing Parking area
a. Land Clearing (including paving, asplalt, vegetation (tress, shrups), etc) m2 227,50 0,3388 100,00 0,34 - - 100,00 0,34
b. Demolish Toilet ls -
c. Excavation m3 386,75 1,4399 100,00 1,44 - - 100,00 1,44
d. Soil compaction (CBR > 6%) m2 227,50 0,1694 100,00 0,17 - - 100,00 0,17
e. Subbase : crushed stone class B CBR >35% h=250 mm m2 227,50 0,9486 100,00 0,95 - - 100,00 0,95
f. Base Course : crushed stone class A CBR >90% h=150 mm m2 227,50 0,9130 95,00 0,87 5,00 0,05 100,00 0,91
g. Aspalt (Tackcoat + ATB 70mm + ACWC 50mm) m2 227,50 2,3377 30,00 0,70 70,00 1,64 100,00 2,34
h. Cansteen + Paint (Existing cansteen) m1 43,00 0,1217 95,00 0,12 5,00 0,01 100,00 0,12

V. PEK. ELEKTRIKAL 5,631 98,44 5,54 - - 98,44 5,54


1. ELECTRICITY
New Power House Building
a. Earthworks
- Excavation and remove surplus spoil material from site m3 19,17 0,0714 100,00 0,07 - - 100,00 0,07
- Lean concrete 5 cm m3 1,83 0,0041 100,00 0,00 - - 100,00 0,00
- Sand layer 10 mm m3 3,65 0,0321 100,00 0,03 - - 100,00 0,03
- Stoneworks fondation m3 15,87 0,4019 100,00 0,40 - - 100,00 0,40
- Backfill m3 5,75 0,0111 100,00 0,01 - - 100,00 0,01

b. Concrete Works
- Concrete Rabat at outside builidng m3 1,30 0,0409 100,00 0,04 - - 100,00 0,04
- Slab Concrete inside m3 2,20 0,3604 100,00 0,36 - - 100,00 0,36
- Sloof concrete m3 0,71 0,1365 100,00 0,14 - - 100,00 0,14
- Concrete Column m3 2,01 0,3597 100,00 0,36 - - 100,00 0,36
- Concrete Beam incld listplank m3 2,07 0,4316 100,00 0,43 - - 100,00 0,43
- Slab Concrete at top m3 3,59 0,5882 100,00 0,59 - - 100,00 0,59
- Cable Trunk m3 3,22 0,5268 100,00 0,53 - - 100,00 0,53
- Manhole Cover - Chequered plate including frame ls 1,00 0,0283 - - - -

c. Finishing
- Wall Partition by red block m2 57,31 0,3585 100,00 0,36 - - 100,00 0,36
- Plaster & Skim coat m2 128,67 0,4024 100,00 0,40 - - 100,00 0,40
Painting
- External paint m2 49,15 0,0461 100,00 0,05 - - 100,00 0,05
- Internal paint m2 79,52 0,0959 100,00 0,10 - - 100,00 0,10

d. Door & Windows


- Double Steel doors 1800 x 2800 mm no 1,00 0,5254 100,00 0,53 - - 100,00 0,53
- Windows Steel grill 1800 x 600 mm no 4,00 0,5147 100,00 0,51 - - 100,00 0,51
- Windows Steel grill 1250 x 600 mm no 1,00 0,0894 100,00 0,09 - - 100,00 0,09
- Windows Steel grill 900 x 600 mm no 2,00 0,1287 100,00 0,13 - - 100,00 0,13

e. Roof Finish
- Plaster & Skim coat m2 19,36 0,0605 100,00 0,06 - - 100,00 0,06

f. MEP WORK
- Pipa Drain 2,5" PVC m 32,00 0,1470 100,00 0,15 - - 100,00 0,15
- Sparing MEP (dia 1", 3", 6" etc) ls 1,00 0,1489 100,00 0,15 - - 100,00 0,15
- Lighting LED TL Balk 1x36 incld instaltion NYM 3x2,5 mm with pvc conduif no 4,00 0,0596 100,00 0,06 - - 100,00 0,06
- Double Switch no 1,00 0,0019 100,00 0,00 - - 100,00 0,00
- Grounding sparing / sleeve no 3,00 by Others

RAB - EKA HOSPITAL BSD PT. SBPI Halaman. : 7 - 17


Project No. P-EKABSD-09
EKA HOSPITAL
Document No. P-EKBSD-09-SBPI-PGR-0012
Revision No. 0
WEEKLY PROGRESS REPORT TEMPLATE Page of 18
Issue Date Nopember 06, 2022

2. PROJECT PROGRESS
2.1 Detail Engineering Progress Chart

Proyek Pembangunan
PEMBANGUNAN BANGUNAN UTILITAS
TEMPORARY UTILITY BUILDING
EKA HOSPITAL - BSD
Paket Pekerjaan : Pemberi Tugas :
STRUKTUR, ARSITEKTUR & MELEKTRIKAL Minggu ke : 12 PT. PELITA RELIENCE INTERNATIONAL HOSPITAL

Bulan : NOPEMBER 2022 Kontraktor Pelaksana :


TEMPORARY UTILITY BUILDING
Periode Tgl. : 31 Okt s/d 06 Nov 2022 PT. SURYA BANGUN PERSADA INDAH

Instruksi Pelaksanaan Pekerjaan ( IPP ) : Mulai Pelaksanaan : 16 Agustus 2022.


011/PKS-UMUM/PRIH/SBPI/BSD/VI/2022 Waktu Pelaksanaan : 90 Hari Kalender
Waktu Terpakai : 83 Hari Kalender
Nilai Kontrak : Sisa Waktu : 7 Hari Kalender
Rp. 3.794.000.000,- ( excl.. PPn ) Serah Terima I : 14 November 2022.

s/d MINGGU LALU MINGGU INI s/d MINGGU INI


BOBOT
NO URAIAN PEKERJAAN SAT VOL. PRESTASI BOBOT PRESTASI BOBOT PRESTASI BOBOT
( % ) (%) (%) (%) (%) (%) (%)

2. WATER CONNECTION
a. Relocation
- Relocation By PDAM ls 1,00 by Others
- Collection Tank PDAM 20m3 (size 4500x2500x4450) incld cover and mainhole no 1,00 Deleted
- PDAM meter box no 1,00 0,0596 - - - -

GRAND TOTAL 100,00 95,02 95,02 3,69 3,69 98,71 98,71

Mengetahui : Dibuat oleh :


Pemberi Tugas - Pemilik Kontraktor Pelaksana
PT. PELITA RELIENCE INTERNATIONAL HOSPITAL PT. SURYA BANGUN PERSADA INDAH

WANDI HIDAYAT HENRY GAUTAMA A P


Project Manager Project Manager

RAB - EKA HOSPITAL BSD PT. SBPI Halaman. : 8 - 17


RAB - EKA HOSPITAL BSD PT. SBPI Halaman. : 9 - 17
RAB - EKA HOSPITAL BSD PT. SBPI Halaman. : 10 - 17
RAB - EKA HOSPITAL BSD PT. SBPI Halaman. : 11 - 17
RAB - EKA HOSPITAL BSD PT. SBPI Halaman. : 12 - 17
RAB - EKA HOSPITAL BSD PT. SBPI Halaman. : 13 - 17
RAB - EKA HOSPITAL BSD PT. SBPI Halaman. : 14 - 17
RAB - EKA HOSPITAL BSD PT. SBPI Halaman. : 15 - 17
Project No. P-EKABSD
EKA HOSPITAL
Document No. P-EKBSD-09-SBPI-PGR-0012
Revision No. 0
WEEKLY PROGRESS REPORT
Page 11 of 18
TEMPLATE
Issue Date Nopember 06, 2022

2.2 Summary Engineering Table

Proyek Pembangunan
PEMBANGUNAN BANGUNAN UTILITAS
TEMPORARY UTILITY BUILDING
EKA HOSPITAL - BSD
Paket Pekerjaan : Minggu ke : 12 Pemberi Tugas :
STRUKTUR, ARSITEKTUR & ELEKTRIKAL Bulan : NOPEMBER 2022 PT. PELITA RELIENCE INTERNATIONAL HOSPITAL

Periode Tgl. : 31 Okt s/d 06 Nov 2022 Kontraktor Pelaksana :


TEMPORARY UTILITY BUILDING
Progress Rencana : 98,334 % PT. SURYA BANGUN PERSADA INDAH
Progress Actual : 98,709 %
Deviasi : 0,375 %

s/d MINGGU LALU MINGGU INI s/d MINGGU INI


BOBOT
NO URAIAN PEKERJAAN PRESTASI BOBOT PRESTASI BOBOT PRESTASI BOBOT
( % ) (%) (%) (%) (%) (%) (%)

I. PEK. PRELIMINERY / PERSIAPAN 13,13 88,50 11,618 7,26 0,953 95,75 12,571

II. PEK. STRUKTUR 57,81 99,21 57,350 0,02 0,013 99,23 57,363

III. PEK. ARSITEKTUR 14,23 91,32 12,999 11,86 1,688 98,60 14,034

IV. EKSTERNAL WORKS 9,20 81,65 7,509 18,35 1,688 100,00 9,197

V. PEK. ELEKTRIKAL 5,631 98,44 5,544 - - 98,44 5,544

GRAND TOTAL 100,00 95,02 95,0196 4,34 4,3419 98,71 98,7090

Mengetahui : Dibuat oleh :


Pemberi Tugas - Pemilik Kontraktor Pelaksana
PT. PELITA RELIENCE INTERNATIONAL HOSPITAL PT. SURYA BANGUN PERSADA INDAH

WANDI HIDAYAT HENRY GAUTAMA A P


Project Manager Project Manager
Project No. P-EKABSD-09
Document
EKA HOSPITAL P-EKBSD-09-SBPI-PGR-0012
No.
Revision No. 0

WEEKLY PROGRESS Page 12 of 18


REPORT TEMPLATE Issue Date Nopember 06, 2022

2.3 Engineering Activities Plan Next Week

÷ Perapian dan Pembersihan


÷ Demolish Toilet Existing
÷ Pembuatan Box

2.4 Engineering Man Power


÷ Staff PT. SBPI : 5 Orang
÷ Staff Safety Officer : 1 Orang
÷ Pekerja PT.SBPI : 35 Orang
Project No. P-EKABSD-09
Document
EKA HOSPITAL P-EKBSD-09-SBPI-PGR-0012
No.
Revision No. 0

WEEKLY PROGRESS Page 13 of 18


REPORT TEMPLATE Issue Date Nopember 06, 2022

3. ENGINEERING STATUS
3.1 Status Monitoring Approval Material

Lampiran Terpisah

3.2 Status Monitoring Shop Drawing


Tgl
No. No. Gambar Judul Gambar Status
Pengajuan
Gambar
1 SD-EkaBSD-STR-PLN-001 R01 SHOP DRAWING GARDU PLN 14/09/2022 Review blm
kembali
Gambar
2 SD-EkaBSD-STR-UTILITY-001 LAYOUT HORDING PAGAR 04/08/2022 Review blm
kembali
Gambar
3 SD-EkaBSD-STR-UTILITY DENAH DETAILL UTILITY & GYM 22/08/2022 Review blm
kembali
Gambar
SD-EkaBSD-ARS-UTILITY&
4 DENAH BRICKWALL 14/09/2022 Review blm
GYM-BW
kembali
Gambar
SD-EkaBSD-ARS-UTILITY&
5 DENAH DRYWALL 14/09/2022 Review blm
GYM-PDW
kembali
Gambar
SD-EkaBSD-ARS-UTILITY&
6 DENAH FINISHING UTILITY 14/09/2022 Review blm
GYM-FD
kembali
Project No. P-EKABSD-09
Document
EKA HOSPITAL P-EKBSD-09-SBPI-PGR-0012
No.
Revision No. 0

WEEKLY PROGRESS Page 14 of 18


REPORT TEMPLATE Issue Date Nopember 06, 2022

4. ATTACHMENT
4.1 Total S-Curve Engineering
Project No. P-EKABSD
EKA HOSPITAL
Document No. P-EKBSD-01-SBPI-PGR-012
Revision No. 0
WEEKLY PROGRESS REPORT
Page 16 of 18
TEMPLATE
Issue Date Nopember 06, 2022

4.2 Actual Engineering S-Curve

JADWAL PELAKSANAAN ( TIME SCHEDULE - S CURVE )


WAKTU PELAKSANAAN : 90 HARI (+/- 3 BULAN)
Tanggal 31 Oktober 2022 s/d Tanggal 06 Nopember 2022

KONTRAKTOR PELAKSANA : PT. SURYA BANGUN PERSADA INDAH - SBPI


PAKET PEKERJAAN : STRUKTUR, ARSITEKTUR & M E P
Tahun 2022
S
Bulan AGUSTUS | SEPTEMBER | OKTOBER | NOVEMBER
NO. URAIAN PEKERJAAN BOBOT Bulan Ke 1 2 3
c
a
l
Minggu Ke 1 2 3 4 5 6 7 8 9 10 11 12 13 e
(%) Periode Tgl. 15 - 21 22 - 28 29- 04 05 - 11 12 - 18 19 - 25 26 - 02 03 - 09 10 - 16 17 - 23 24 - 30 31 - 06 07 - 12

I. PEK. PRELIMINERY / PERSIAPAN 13,128 0,13128 0,13128 0,35008 0,35008 0,35008 1,31280 1,31280 1,96920 1,96920 1,64100 1,64100 1,31280 0,65640

II. PEK. STRUKTUR 57,810 0,04065 0,16262 0,67668 1,38678 4,64246 11,47555 13,49689 9,50977 6,83162 6,13183 2,98457 0,47031

A STRUKTUR 37,370
1 DEMOLISH EXCISTING 2,03275 0,04065 0,16262 0,20327 0,20327 0,60982 0,30491 0,30491 0,20327

2 FOOT FOUNDATION incl. COLOUM PEDESTAL 2,36701 0,47340 1,18351 0,71010

3 TIE BEAM 5,33714 1,60114 3,73600

4 SLAB on GROUND 6,51919 1,95576 4,56343

5 STEEL STRUCTURE 17,21385 1,72139 5,16416 6,88554 3,44277

6 ROOFING 3,90035 0,39003 2,34021 1,17010

B MISCELLANEOUS 20,439
1 MEP FOUNDATION 15,73632 0,31473 1,25891 3,14726 4,72090 4,72090 1,57363

2 OTHER AREA 4,70312 0,09406 0,37625 0,94062 1,41094 1,41094 0,47031

III. PEK. ARSITEKTUR 14,234 0,75929 2,27787 3,28971 2,49183 2,47695 2,55509 0,38280

1 DEMOLITION WORKS & STRUCTURAL WORKS 0,00000

2 INTERIORS PARTITIONS & MASONRY 7,59289 0,75929 2,27787 3,03716 1,51858

3 CEILLING, WALL & FLOOR FINISHES 2,52554 0,25255 0,75766 1,01022 0,50511

4 DOORS & WINDOWS 2,14064 0,85626 1,28438

5 WINDOWS & LOUVRE 0,06046 0,02418 0,03628

6 SANITARY 0,00000

7 MISCELLANEOUS 1,91400 0,19140 0,57420 0,76560 0,38280

IV. EXSTERNAL WORKS 9,197 0,41821 1,38000 2,42511 2,46636 1,88071 0,62690

1 DRAINAGE SYSTEM ( TEMPORARY BUILDING ) 2,92826 0,29283 0,87848 1,17130 0,58565

2 ADDITIONAL PARKING 6,26904 0,12538 0,50152 1,25381 1,88071 1,88071 0,62690

V. PEK. ELEKTRIKAL 5,631 0,20822 0,55956 0,74171 1,07924 1,05270 1,09742 0,72519 0,10781 0,05957

A ELECTRICITY 5,572
New Power House Building

a. Earthworks 0,52054 0,20822 0,31233

b. Concrete Works 2,47238 0,24724 0,74171 0,98895 0,49448

c. Finishing 0,90288 0,09029 0,27086 0,36115 0,18058

d. Door & Windows 1,25807 0,25161 0,62904 0,37742

e. Roof Finish 0,06054 0,02422 0,03633


f. MEP Works 0,35743 0,03574 0,10723 0,14297 0,07149

B WATER CONNECTION 0,060


a. Relocation 0,05957 0,05957

TOTAL BOBOT PEKERJAAN ( % ) 100,000

RENCANA / Mgg. ( % ) 0,17194 0,29390 1,02676 1,94508 5,55210 13,53007 16,64822 15,22774 14,56795 13,41496 9,67670 6,27849 1,66610

RENCANA KOMULATIF / Mgg. ( % ) 0,000 0,172 0,466 1,493 3,438 8,990 22,520 39,168 54,396 68,964 82,379 92,055 98,334 100,000

PRESTASI / Mgg. ( % ) 1,96850 1,63108 1,67341 6,13073 22,54023 12,01703 13,46906 14,23397 7,92715 7,71212 5,71629 3,68946 0,00000

PRESTASI KOMULATIF / Mgg. ( % ) 0,000 1,968 3,600 5,273 11,404 33,944 45,961 59,430 73,664 81,591 89,303 95,020 98,709

DEVIASI ( + / - ) / Mgg. ( % ) 1,797 3,134 3,780 7,966 24,954 23,441 20,262 19,268 12,627 6,925 2,964 0,375

Dibuat oleh :
PT. SURYA BANGUN PERSADA INDAH

Ir. HENRY GAUTAMA A P.


Manajer Proyek
Project No. P-EKABSD-09
Document
EKA HOSPITAL P-EKBSD-09-SBPI-PGR-0012
No.
Revision No. 0

WEEKLY PROGRESS Page 17 of 18


REPORT TEMPLATE Issue Date Nopember 06, 2022

5. DOKUMENTASI
5.1 Dokumentasi
Project No. P-EKABSD-09
Document
EKA HOSPITAL P-EKBSD-09-SBPI-PGR-0012
No.
Revision No. 0

WEEKLY PROGRESS Page 18 of 18


REPORT TEMPLATE Issue Date Nopember 06, 2022