PAKET PEKERJAAN :
PEMBERI TUGAS :
PT. PELITA RELIENCE INTERNATIONAL HOSPITAL
KONTRAKTOR :
PT. SURYA BANGUN PERSADA INDAH
Project No. P-EKABSD-19
Document
EKA HOSPITAL P-EKBSD-19-SBPI-PGR-0012
No.
Revision No. 0
06 Nopember,
0 Issued for Information PT. SBPI PT.PRIH PT.PRIH
2022
TABLE OF CONTENTS
1 EXECUTIVE SUMMARY
1.1 DESCRIPTION OF THE PROJECT STATUS
1.2 CURRENT CUMULATIVE SUMMARY PROGRESS
1.3 RECENT TIME LINE
2 PROJECT PROGRESS
2.1 DETAIL ENGINEERING PROGRESS CHART
2.2 SUMMARY ENGINEERING TABLE
2.3 ENGINEERING ACTIVITIES PLAN NEXT WEEK
3 ENGINEERING STATUS
3.1 STATUS MONITORING APPROVAL MATERIAL
3.2 STATUS MONITORING SHOP DRAWING
4 ATTACHMENTS
4.1 TOTAL ENGINEERING S-CURVE
4.2 ACTUAL ENGINEERING S-CURVE
5 DOKUMENTASI
Project No. P-EKABSD-19
Document
EKA HOSPITAL P-EKBSD-19-SBPI-PGR-0012
No.
Revision No. 0
1. EXECUTIVE SUMMARY
1.1 Deskripsi Tentang Proyek
Pengerjaan Temporary Bangunan Utility Eka Hospital BSD
÷ Pekerjaan Pengecatan
÷ Pekerjaan Pengaspalan jalan
÷ Pekerjaan Pemasngan Pagar BRC
÷ Pekerjaan Pemasangan Paving
÷ Pekerjaan Pemasangan Kansteen
÷ Pekerjaan Pembersihan Area
Project No. P-EKABSD-09
EKA HOSPITAL
Document No. P-EKBSD-09-SBPI-PGR-0012
Revision No. 0
WEEKLY PROGRESS REPORT TEMPLATE Page of 18
Issue Date Nopember 06, 2022
2. PROJECT PROGRESS
2.1 Detail Engineering Progress Chart
Proyek Pembangunan
PEMBANGUNAN BANGUNAN UTILITAS
TEMPORARY UTILITY BUILDING
EKA HOSPITAL - BSD
Paket Pekerjaan : Pemberi Tugas :
STRUKTUR, ARSITEKTUR & MELEKTRIKAL Minggu ke : 12 PT. PELITA RELIENCE INTERNATIONAL HOSPITAL
I. PEK. PRELIMINERY / PERSIAPAN 13,128 88,50 11,62 7,26 0,95 95,75 12,57
Catatan Harga ( Pricing Notes ) :
A. This contract is Lump Sum Fixed Price, except where provisional or "Provisional
Sum" is stated. The Contractor is obliged to recalculate the work volume and
check the units made by the Quantity Surveyor and if according to the
Contractor's calculations the volume and or units are not appropriate or there are
work items that have not been listed, the Contractor may change or add to the
special attachments made for additional or less work.
B. The Contractor must have considered including all costs of work expenses and
there will be no claim at a later date against the Employer, if the list of job
descriptions is deemed incomplete.
C. All works that are not listed here are considered included in the offer and all risks
both regarding price escalation, miscalculation of the volume and price submitted
are the responsibility of the Contractor.
1 Proyek Manajemen dan Biaya Administrasi Lapangan Ls 1,00 7,3197 85,00 6,22 10,00 0,73 95,00 6,95
Biaya - biaya untuk mengadakan staf dilapangan yang akan mengelola pelaksanaan pekerjaan, semua biaya
administrasi dan biaya mengurus segala hal yang berhubungan dengan tanggung jawabnya terhadap
kontrak ini .
2 Peralatan dan Perlengkapan Kerja Ls 1,00 0,6570 85,00 0,56 10,00 0,07 95,00 0,62
Pengadaan peralatan dan perlengkapan kerja yang lengkap untuk kelancaran pelaksanaan pekerjaan
sebagaimana yang dimaksud didalam Dokumen Kontrak, termasuk biaya ijin pemasukan peralatan kedalam
lokasi proyek, pemeliharaan dan pemindahan dari satu tempat ke tempat lainnya didalam lokasi pekerjaan
serta mengeluarkannya setelah penyelesaian pekerjaan.
3 Peralatan dan Perlengkapan Keselamatan Kerja serta P3K Ls 1,00 0,0896 85,00 0,08 10,00 0,01 95,00 0,09
Pengadaan topi pengaman (helm), baju hujan, sepatu lapangan, handy talky (HT) sebanyak yang diperlukan
untuk Pemberi Tugas, Pimpinan Proyek dan Konsultan di proyek berikut peralatan P3K. (masing - masing 3
set)
6 Pengadaan Gambar
a. Pengadaan gambar-gambar pelaksanaan (construction drawing) sebanyak yang Ls 1,00 exclude
diperlukan untuk keperluan kerja dilapangan termasuk 2 (dua) set keperluan
pengawasan.
b. Pembuatan gambar kerja (shop drawing) berikut perhitungan atau kalkulasi yang Ls 1,00 exclude
terinci sebanyak 2 (dua) set , hingga disetujui Manajemen Konstruksi, Pimpinan
Proyek atau Pemberi Tugas.
c. Pembuatan gambar-gambar terlaksana (as built drawing) sebanyak 1 (satu) set Ls 1,00 0,1054 50,00 0,05 - - 50,00 0,05
kalkir dan 3 (tiga) set cetak biru.
2. PROJECT PROGRESS
2.1 Detail Engineering Progress Chart
Proyek Pembangunan
PEMBANGUNAN BANGUNAN UTILITAS
TEMPORARY UTILITY BUILDING
EKA HOSPITAL - BSD
Paket Pekerjaan : Pemberi Tugas :
STRUKTUR, ARSITEKTUR & MELEKTRIKAL Minggu ke : 12 PT. PELITA RELIENCE INTERNATIONAL HOSPITAL
11 Kantor Pemborong Lapangan Ls 1,00 0,3664 90,00 0,33 5,00 0,02 95,00 0,35
Pembuatan kantor sementara pemborong di lapangan berikut semua fasilitas yang diperlukan termasuk toilet
untuk para pekerja selama masa pelaksaan pekerjaan berikut pemeliharaan kebersihan didalam lokasi
pekerjaan, pembongkaran bila ada perintah membongkar setelah pekerjaan selesai
12 Gudang Sementara dan Los Kerja Ls 1,00 0,2319 90,00 0,21 5,00 0,01 95,00 0,22
Pengadaan gudang sementara dan los pekerjaan di lapangan berikut pemeliharaannya dan membongkar
setelah pekerjaannya selesai serta memperbaiki, merapihkan dan membersihkannya
15 Jalan Masuk Ke Tempat Pekerjaan Dan Jalan Sementara Ls 1,00 0,1318 85,00 0,11 10,00 0,01 95,00 0,13
Bilamana diperlukan jalan atau jembatan masuk ketempat lokasi pekerjaan harus diadakan oleh pemborong,
disesuaikan dengan kebutuhan dan kepentingan proyek tersebut. Selama pekerjaan berlangsung
pemborong diharuskan memelihara, memperbaiki segala kerusakan yang diakibatkan dan membersihkannya
kembali.
17 Kebersihan dan Kerapihan Ls 1,00 0,6128 85,00 0,52 10,00 0,06 95,00 0,58
Pemborong harus mengangkut ke luar lokasi proyek semua sampah secara teratur jika sudah bertumpuk
dan pada waktu penyelesaian pekerjaan harus bersih dan rapih. (Catatan :
Dalam pengangkutan keluar proyek tidak boleh mengotori jalan dan prasarana umum).
19 Pemadam Kebakaran Ls 1,00 0,0501 85,00 0,04 10,00 0,01 95,00 0,05
Pengadaan peralatan dan pencegahan terhadap bahaya kebakaran dan yang sesuai dengan anjuran
perusahaan asuransi terhadap pekerjaan dan instalasi pemerintah yang berwenang dan sediakan tenaga-
tenaga yang terlatih untuk maksud diatas .
20 Pengadaan Tenaga Listrik ( biaya Instalasi ) Ls 1,00 0,2596 100,00 0,26 - - 100,00 0,26
Setiap pembangkit tenaga listrik sementara atau penerangan sementara termasuk pemasangan kabel-kabel
dan meteran yang dipergunakan untuk pekerjaan atau pengambilan daya dari sumber atau PLN yang sudah
ada , genset termasuk bahan bakar, maka semua biaya pengadaan dan pemakaian daya selama
pelaksanaan proyek termasuk izin yang diperlukan serta perapihan setelah pekerjaan selesai sudah harus
diperhitungkan oleh pemborong.
21 Pengadaan Sumber Air Bersih ( Biaya Instalasi ) Ls 1,00 0,1120 100,00 0,11 - - 100,00 0,11
Pengadaan sumber air bersih sementara untuk air kerja dan keperluan lainnya dari sumber yang ada (sumur
pantek / jet pump, sumur dalam / deep well), termasuk membuat sambungan-sambungan sementara untuk
mengalirkan air dan mencabutnya kembali setelah pekerjaan selesai.
Pengadaan telepon dan perlengkapannya sesuai kebutuhan termasuk pengurusan permohonan kepada
Perumtel dan pembayaran semua tagihan selama masa pelaksanaan pekerjaan dan menyerahkannya
kepada Pemberi Tugas setelah penyerahan pertama termasuk biaya balik nama kepada Pemberi Tugas.
2. PROJECT PROGRESS
2.1 Detail Engineering Progress Chart
Proyek Pembangunan
PEMBANGUNAN BANGUNAN UTILITAS
TEMPORARY UTILITY BUILDING
EKA HOSPITAL - BSD
Paket Pekerjaan : Pemberi Tugas :
STRUKTUR, ARSITEKTUR & MELEKTRIKAL Minggu ke : 12 PT. PELITA RELIENCE INTERNATIONAL HOSPITAL
25 Asuransi
Pemborong atas nama Pemberi Tugas wajib mengasuransikan, sebagai berikut :
a. Asuransi Construction All Risk (CAR) dan Third Party Liability (TPL). Deductible Ls 1,00 -
by kontraktor
b. Asuransi Tenaga Kerja (ASTEK) untuk pekerja dan staff pemborong yang bekerja Ls 1,00 0,1711 85,00 0,15 10,00 0,02 95,00 0,16
pada proyek ini
26 LAIN-LAIN :
a Biaya untuk pembuatan washing bay / cleaning pit untuk membersihkan ban Ls 1,00 0,1318 85,00 0,11 10,00 0,01 95,00 0,13
kendaraan Proyek yang keluar masuk area Proyek, agar tidak mengotori jalan
umum, termasuk pembersihan jalan umum apabila dalam pelaksanaannya tetap
terjadi kendaraan proyek mengotori jalan umum.
b Biaya koordinasi terhadap pihak lain (instansi-instansi, izin lingkungan , ormas) Ls 1,00 0,4744 100,00 0,47 - - 100,00 0,47
selama pelaksanaan proyek berlangsung.
c Land Clearing dan Leveling termasuk sisa - sisa tanah dan puing bekas Ls 1,00 exclude
bongkaran serta Perataan tanah
II. PEK. STRUKTUR 57,810 99,21 57,35 0,02 0,01 99,23 57,36
A. STRUKTUR
3 Tie Beam
a Excavation, back fill and remove excess material out of site m3 43,61 0,1624 100,00 0,16 - - 100,00 0,16
b Soil Compaction m2 52,42 0,0312 100,00 0,03 - - 100,00 0,03
c Gravel 15cm m2 52,42 0,0951 100,00 0,10 - - 100,00 0,10
d Lean concrete 5cm m2 52,42 0,1171 100,00 0,12 - - 100,00 0,12
e Concrete Fc'=30 MPa m3 32,35 1,0214 100,00 1,02 - - 100,00 1,02
f Rebar kg 6.616,51 2,8772 100,00 2,88 - - 100,00 2,88
g Formwork m2 210,15 1,0328 100,00 1,03 - - 100,00 1,03
4 Slab on Ground
a On Soil
- Soil Compaction m2 131,49 0,0783 100,00 0,08 - - 100,00 0,08
- Gravel 15cm m2 131,49 0,2386 100,00 0,24 - - 100,00 0,24
- Lean concrete 5cm m2 131,49 0,2937 100,00 0,29 - - 100,00 0,29
b On Excisting Pavement
- Gravel 4cm m2 527,55 0,2553 95,00 0,24 5,00 0,01 100,00 0,26
- Lean concrete 4cm m2 527,55 1,1784 100,00 1,18 - - 100,00 1,18
- Concrete Fc'=30 MPa m3 68,63 2,1668 100,00 2,17 - - 100,00 2,17
- Concrete Fc'=20MPa m3 19,80 0,6133 100,00 0,61 - - 100,00 0,61
- Wiremesh M8 -150 (1 layer) m2 -
- Wiremesh M10 -150 (1 layer) m2 112,76 0,4746 100,00 0,47 - - 100,00 0,47
- Wiremesh M5 -150 (1 layer) m2 384,00 0,5843 100,00 0,58 - - 100,00 0,58
- Wiremesh M4-150 (1 layer m2 176,00 0,2174 100,00 0,22 - - 100,00 0,22
- Formwork m2 85,14 0,4184 100,00 0,42 - - 100,00 0,42
2. PROJECT PROGRESS
2.1 Detail Engineering Progress Chart
Proyek Pembangunan
PEMBANGUNAN BANGUNAN UTILITAS
TEMPORARY UTILITY BUILDING
EKA HOSPITAL - BSD
Paket Pekerjaan : Pemberi Tugas :
STRUKTUR, ARSITEKTUR & MELEKTRIKAL Minggu ke : 12 PT. PELITA RELIENCE INTERNATIONAL HOSPITAL
5 Steel Structure
a Column SC1 : WF 300.150.6,5.9 kg 1.293,45 1,0914 100,00 1,09 - - 100,00 1,09
b Column SC2 : WF 250.125.6.9 kg 1.461,20 1,2330 100,00 1,23 - - 100,00 1,23
c Girder SG1 : WF 250.125.6.9 kg 385,87 0,3256 100,00 0,33 - - 100,00 0,33
d Girder SG2 : WF 250.125.6.9 kg 3.086,92 2,6048 100,00 2,60 - - 100,00 2,60
e Girder SG3 : WF 200.100.5,5.8 kg 3.499,76 2,9531 100,00 2,95 - - 100,00 2,95
f Girder SG4 : WF 150x75x5x7 kg -
g Purlin : CNP 125.50.20.3,2 kg 3.836,15 3,2370 100,00 3,24 - - 100,00 3,24
h Listplank frame : CNP 100.50.20.3,2 kg 582,38 0,4914 100,00 0,49 - - 100,00 0,49
i Wind bracing : Dia 16mm kg 362,36 0,3058 100,00 0,31 - - 100,00 0,31
j Turnbuckle dia 16 no 28,00 0,0834 100,00 0,08 - - 100,00 0,08
k Sagrod : dia 12 mm incld bolt kg 193,04 0,1629 100,00 0,16 - - 100,00 0,16
l Plate kg 1.719,26 1,4507 100,00 1,45 - - 100,00 1,45
m Bolt ls 1,00 0,6970 100,00 0,70 - - 100,00 0,70
n Anchorage Bolt L=1000MM + Double bolt no 72,00 0,9650 100,00 0,96 - - 100,00 0,96
o Grouting 500x500, 50mm thk no 18,00 0,1005 100,00 0,10 - - 100,00 0,10
p Zincromate + Finish Paint no 14.508,11 1,5124 100,00 1,51 - - 100,00 1,51
6 Roofing
a Metal Roof type Trimdeck TCT 0,45mm m2 632,51 3,2679 100,00 3,27 - - 100,00 3,27
b Roof Cap m1 44,70 0,2330 100,00 0,23 - - 100,00 0,23
c Insulation (rockwool densiti 60 kg/m2 + wiremesh + 2 layer Alm Foil) m2 -
d Fiber Gutter 400x300 mm incld frame (prov qty ) m1 -
e GRC Listplank W=500mm m1 131,85 0,3995 100,00 0,40 - - 100,00 0,40
B MISCELLANEOUS
1 MEP FOUNDATION
a. Watertank Foundation
Slab on Ground ( S30 )
- Excavation, back fill and remove excess material out of site m3 94,39 0,3514 100,00 0,35 - - 100,00 0,35
- Soil Compaction m2 111,05 0,0662 100,00 0,07 - - 100,00 0,07
- Gravel 15cm m2
- Gravel 50cm m2 111,05 0,6719 100,00 0,67 - - 100,00 0,67
- Lean concrete 5cm m2 111,05 0,2481 100,00 0,25 - - 100,00 0,25
- Concrete Fc'=30 MPa m3 33,32 1,0518 100,00 1,05 - - 100,00 1,05
- Rebar kg 3.613,91 1,5715 100,00 1,57 - - 100,00 1,57
- Formwork m2 10,50 0,0516 100,00 0,05 - - 100,00 0,05
c Genset Foundation ( 2 unit @ 2500 mm x 6250 mm) h = 70 cm m2 31,25 4,0860 100,00 4,09 - - 100,00 4,09
d Panel / Trafo Foundation H = 20 cm ( SG20 ) m2 68,20 1,8484 100,00 1,85 - - 100,00 1,85
f Strip Foundation for Panel TM Foundation 1 m High ( detail W 25 ) m2 7,70 1,0756 100,00 1,08 - - 100,00 1,08
g Cable Tranch ( provisional ) ( Outer Size 1,8 m x 1,3 m ) m1 10,00 2,1332 100,00 2,13 - - 100,00 2,13
2 OTHER AREA
a Weekly Tank - Platform 4,5 x 9 x 0,25 no 1,00 3,4117 100,00 3,41 - - 100,00 3,41
b Box Control Size 600 x 600 x 400 mm (FIber optic, sound sistem ) include cover no 2,00 0,8447 100,00 0,84 - - 100,00 0,84
c Sewage Pit 2300 x 2300 x 1800 mm incld cover and mainhole no -
d Demolish Existing Toilet ( due to cable power line ) no 1,00 0,4468 - - - -
III. PEK. ARSITEKTUR 14,234 91,32 13,00 7,28 1,04 98,60 14,03
1. Demolition Works &....... ( not Applicable )
2. PROJECT PROGRESS
2.1 Detail Engineering Progress Chart
Proyek Pembangunan
PEMBANGUNAN BANGUNAN UTILITAS
TEMPORARY UTILITY BUILDING
EKA HOSPITAL - BSD
Paket Pekerjaan : Pemberi Tugas :
STRUKTUR, ARSITEKTUR & MELEKTRIKAL Minggu ke : 12 PT. PELITA RELIENCE INTERNATIONAL HOSPITAL
a. Ceiling Finishes
1 9mm Gypsum board suspended ceilings including suspension system; metal furring
framing and supports and all associated work, all necessary metal angle and stop beads,
and cutting holes for lighting fixtures, speaker, etc.
- 1st Floor m2 -
3 Prepare and apply approved emulsion paint finish as specified on drawings and
specification,to gypsum ceiling
- 1st Floor m2 -
b. Wall Finishes
1 Prepare and apply approved emulsion paint finish as specified on drawings and
specification,to plastered dan gypsum walls;
- 1st Floor m2 592,84 0,5562 55,00 0,31 40,00 0,22 95,00 0,53
c. Floor Finishes
1 Ceramic tile 300 x 300 mm ex Roman or equal, set in pattern, bedded, jointed on
and pointed with white or coloured cement; all in accordance with the
specification and as shown on drawings;
- 1st Floor (Logistic) m2 70,49 0,5973 100,00 0,60 - - 100,00 0,60
a. Door
Supply and install steel doors including frames,all necessary components, fixing,
accessories, consumables ironmongeries, all complete as specified in the drawings and
specification
1 TYPE SD 1 (Overall size 2100 x 2450mm)
- 1st Floor (soundproof) no 1,00 0,4597 100,00 0,46 - - 100,00 0,46
2 TYPE SD 2 (Overall size 2100 x 2150mm)
- 1st Floor no 5,00 1,6809 100,00 1,68 - - 100,00 1,68
a. Windows
1 TYPE W1 (Overall size 800x1450mm)
- 1st Floor no 1,00 0,0605 100,00 0,06 - - 100,00 0,06
7. Miscellaneous
b. Concrete canopy
- Size 2300 x 1100mm unit 5,00 0,3617 95,00 0,34 5,00 0,02 100,00 0,36
- Size 1000 x 500mm unit 1,00 0,0298 95,00 0,03 5,00 0,00 100,00 0,03
2. PROJECT PROGRESS
2.1 Detail Engineering Progress Chart
Proyek Pembangunan
PEMBANGUNAN BANGUNAN UTILITAS
TEMPORARY UTILITY BUILDING
EKA HOSPITAL - BSD
Paket Pekerjaan : Pemberi Tugas :
STRUKTUR, ARSITEKTUR & MELEKTRIKAL Minggu ke : 12 PT. PELITA RELIENCE INTERNATIONAL HOSPITAL
c. Concrete Curb h = 150 mm ( existing material ) m1 142,00 0,3066 - 100,00 0,31 100,00 0,31
e. Vertical Garden
- Wiremesh Screen w/ steel hollow frame finish paint m2 -
- Planter Box m1 -
- Vines/"Tanaman Rambat alamanda" incld soil and fertilizer m1 -
IV. EKSTERNAL WORKS 9,197 81,65 7,51 18,35 1,69 100,00 9,20
1. DRAINAGE SYSTEM ( TEMPORARY BUILDING )
Supply and Install drainage system including excavation, sandbed, back fill and restore
the pavement or existing area to original condition
a. Drainage RCP dia 400mm m1 64,86 1,0303 100,00 1,03 - - 100,00 1,03
b. Control Box type BK2 no 8,00 1,8980 100,00 1,90 - - 100,00 1,90
2. ADDITIONAL PARKING
Existing Parking area
a. Land Clearing (including paving, asplalt, vegetation (tress, shrups), etc) m2 227,50 0,3388 100,00 0,34 - - 100,00 0,34
b. Demolish Toilet ls -
c. Excavation m3 386,75 1,4399 100,00 1,44 - - 100,00 1,44
d. Soil compaction (CBR > 6%) m2 227,50 0,1694 100,00 0,17 - - 100,00 0,17
e. Subbase : crushed stone class B CBR >35% h=250 mm m2 227,50 0,9486 100,00 0,95 - - 100,00 0,95
f. Base Course : crushed stone class A CBR >90% h=150 mm m2 227,50 0,9130 95,00 0,87 5,00 0,05 100,00 0,91
g. Aspalt (Tackcoat + ATB 70mm + ACWC 50mm) m2 227,50 2,3377 30,00 0,70 70,00 1,64 100,00 2,34
h. Cansteen + Paint (Existing cansteen) m1 43,00 0,1217 95,00 0,12 5,00 0,01 100,00 0,12
b. Concrete Works
- Concrete Rabat at outside builidng m3 1,30 0,0409 100,00 0,04 - - 100,00 0,04
- Slab Concrete inside m3 2,20 0,3604 100,00 0,36 - - 100,00 0,36
- Sloof concrete m3 0,71 0,1365 100,00 0,14 - - 100,00 0,14
- Concrete Column m3 2,01 0,3597 100,00 0,36 - - 100,00 0,36
- Concrete Beam incld listplank m3 2,07 0,4316 100,00 0,43 - - 100,00 0,43
- Slab Concrete at top m3 3,59 0,5882 100,00 0,59 - - 100,00 0,59
- Cable Trunk m3 3,22 0,5268 100,00 0,53 - - 100,00 0,53
- Manhole Cover - Chequered plate including frame ls 1,00 0,0283 - - - -
c. Finishing
- Wall Partition by red block m2 57,31 0,3585 100,00 0,36 - - 100,00 0,36
- Plaster & Skim coat m2 128,67 0,4024 100,00 0,40 - - 100,00 0,40
Painting
- External paint m2 49,15 0,0461 100,00 0,05 - - 100,00 0,05
- Internal paint m2 79,52 0,0959 100,00 0,10 - - 100,00 0,10
e. Roof Finish
- Plaster & Skim coat m2 19,36 0,0605 100,00 0,06 - - 100,00 0,06
f. MEP WORK
- Pipa Drain 2,5" PVC m 32,00 0,1470 100,00 0,15 - - 100,00 0,15
- Sparing MEP (dia 1", 3", 6" etc) ls 1,00 0,1489 100,00 0,15 - - 100,00 0,15
- Lighting LED TL Balk 1x36 incld instaltion NYM 3x2,5 mm with pvc conduif no 4,00 0,0596 100,00 0,06 - - 100,00 0,06
- Double Switch no 1,00 0,0019 100,00 0,00 - - 100,00 0,00
- Grounding sparing / sleeve no 3,00 by Others
2. PROJECT PROGRESS
2.1 Detail Engineering Progress Chart
Proyek Pembangunan
PEMBANGUNAN BANGUNAN UTILITAS
TEMPORARY UTILITY BUILDING
EKA HOSPITAL - BSD
Paket Pekerjaan : Pemberi Tugas :
STRUKTUR, ARSITEKTUR & MELEKTRIKAL Minggu ke : 12 PT. PELITA RELIENCE INTERNATIONAL HOSPITAL
2. WATER CONNECTION
a. Relocation
- Relocation By PDAM ls 1,00 by Others
- Collection Tank PDAM 20m3 (size 4500x2500x4450) incld cover and mainhole no 1,00 Deleted
- PDAM meter box no 1,00 0,0596 - - - -
Proyek Pembangunan
PEMBANGUNAN BANGUNAN UTILITAS
TEMPORARY UTILITY BUILDING
EKA HOSPITAL - BSD
Paket Pekerjaan : Minggu ke : 12 Pemberi Tugas :
STRUKTUR, ARSITEKTUR & ELEKTRIKAL Bulan : NOPEMBER 2022 PT. PELITA RELIENCE INTERNATIONAL HOSPITAL
I. PEK. PRELIMINERY / PERSIAPAN 13,13 88,50 11,618 7,26 0,953 95,75 12,571
II. PEK. STRUKTUR 57,81 99,21 57,350 0,02 0,013 99,23 57,363
III. PEK. ARSITEKTUR 14,23 91,32 12,999 11,86 1,688 98,60 14,034
IV. EKSTERNAL WORKS 9,20 81,65 7,509 18,35 1,688 100,00 9,197
3. ENGINEERING STATUS
3.1 Status Monitoring Approval Material
Lampiran Terpisah
4. ATTACHMENT
4.1 Total S-Curve Engineering
Project No. P-EKABSD
EKA HOSPITAL
Document No. P-EKBSD-01-SBPI-PGR-012
Revision No. 0
WEEKLY PROGRESS REPORT
Page 16 of 18
TEMPLATE
Issue Date Nopember 06, 2022
I. PEK. PRELIMINERY / PERSIAPAN 13,128 0,13128 0,13128 0,35008 0,35008 0,35008 1,31280 1,31280 1,96920 1,96920 1,64100 1,64100 1,31280 0,65640
II. PEK. STRUKTUR 57,810 0,04065 0,16262 0,67668 1,38678 4,64246 11,47555 13,49689 9,50977 6,83162 6,13183 2,98457 0,47031
A STRUKTUR 37,370
1 DEMOLISH EXCISTING 2,03275 0,04065 0,16262 0,20327 0,20327 0,60982 0,30491 0,30491 0,20327
B MISCELLANEOUS 20,439
1 MEP FOUNDATION 15,73632 0,31473 1,25891 3,14726 4,72090 4,72090 1,57363
III. PEK. ARSITEKTUR 14,234 0,75929 2,27787 3,28971 2,49183 2,47695 2,55509 0,38280
3 CEILLING, WALL & FLOOR FINISHES 2,52554 0,25255 0,75766 1,01022 0,50511
6 SANITARY 0,00000
IV. EXSTERNAL WORKS 9,197 0,41821 1,38000 2,42511 2,46636 1,88071 0,62690
V. PEK. ELEKTRIKAL 5,631 0,20822 0,55956 0,74171 1,07924 1,05270 1,09742 0,72519 0,10781 0,05957
A ELECTRICITY 5,572
New Power House Building
RENCANA / Mgg. ( % ) 0,17194 0,29390 1,02676 1,94508 5,55210 13,53007 16,64822 15,22774 14,56795 13,41496 9,67670 6,27849 1,66610
RENCANA KOMULATIF / Mgg. ( % ) 0,000 0,172 0,466 1,493 3,438 8,990 22,520 39,168 54,396 68,964 82,379 92,055 98,334 100,000
PRESTASI / Mgg. ( % ) 1,96850 1,63108 1,67341 6,13073 22,54023 12,01703 13,46906 14,23397 7,92715 7,71212 5,71629 3,68946 0,00000
PRESTASI KOMULATIF / Mgg. ( % ) 0,000 1,968 3,600 5,273 11,404 33,944 45,961 59,430 73,664 81,591 89,303 95,020 98,709
DEVIASI ( + / - ) / Mgg. ( % ) 1,797 3,134 3,780 7,966 24,954 23,441 20,262 19,268 12,627 6,925 2,964 0,375
Dibuat oleh :
PT. SURYA BANGUN PERSADA INDAH
5. DOKUMENTASI
5.1 Dokumentasi
Project No. P-EKABSD-09
Document
EKA HOSPITAL P-EKBSD-09-SBPI-PGR-0012
No.
Revision No. 0